Dresden - Mid-Cycle Performance Review and Inspection Plan
ML082460243
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 09/02/2008
From: Ring M
NRC/RGN-III/DRP/B1
To: Pardee C
Exelon Generation Co
References
FOIA/PA-2010-0209
Download: ML082460243 (7)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 September 2, 2008 Mr. Charles G. Pardee Chief Nuclear Officer and Senior Vice President Exelon Generation Company, LLC 4300 Winfield Road Warrenville IL 60555

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

DRESDEN NUCLEAR POWER STATION

Dear Mr. Pardee:

On August 14, 2008, the NRC staff completed its performance review of the Dresden Nuclear Power Station for the first half of the calendar year 2008 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous 12 months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as Official Use Only -Security Information will include the security cornerstone review and resultant inspection plan.

Plant performance for both Dresden Units 2 and 3 during the assessment period was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections of Units 2 and 3.

The enclosed inspection plan details the inspections, less those related to security, scheduled through December 31, 2009. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite.

Routine resident inspections are not listed due to their ongoing and continuous nature.

Additional inspections scheduled include: engineering modifications/50.59, license renewal, independent spent fuel storage installation, and initial license examination. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public

C. Pardee Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 630-829-9703 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Mark A. Ring, Chief Projects Branch 1 Division of Reactor Projects Docket Nos. 50-237; 50-249;72-037 License Nos. DPR-19; DPR-25

Enclosure:

Dresden Inspection/Activity Plan DISTRIBUTION:

See next page

Letter to C. Pardee from M. Ring dated September 2, 2008

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

DRESDEN NUCLEAR POWER STATION cc w/encl: Site Vice President - Dresden Nuclear Power Station Plant Manager - Dresden Nuclear Power Station Regulatory Assurance Manager - Dresden Nuclear Power Station Chief Operating Officer and Senior Vice President Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden, and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General J. Klinger, State Liaison Officer, Illinois Emergency Management Agency Chairman, Illinois Commerce Commission Will County Executive Will County Sheriff Director, Will County Emergency Management Agency Mayor of Joliet City Manager of Joliet Kendall County Board Chairman Kendall County Sheriff Grundy County Board Chairman Grundy County Sheriff Grundy County Emergency Management Agency Mayor of Morris Minooka Village President Mayor of Coal City Mayor of Carbon Hill Mayor of Diamond Mayor of Braidwood Mayor of Wilmington Channahon Village President Channahon Village Administrator Mayor of Shorewood Shorewood Village Administrator Mayor of Elwood G. Mortensen, INPO

C. Pardee Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 630-829-9703 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Mark A. Ring, Chief Projects Branch 1 Division of Reactor Projects Docket Nos. 50-237; 50-249;72-037 License Nos. DPR-19; DPR-25

Enclosure:

Dresden Inspection/Activity Plan DISTRIBUTION:

See next page DOCUMENT NAME: G:\1-SECY\2008 MID-CYCLE FINAL LETTERS\DRESDEN MOC LETTER 2008.DOC G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" =

Copy with attach/encl "N" = No copy OFFICE RIII E RIII RIII RIII NAME MRing:cms DATE 8/27/08 OFFICIAL RECORD COPY

Letter to C. Pardee from M. Ring dated September 2, 2008

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

DRESDEN NUCLEAR POWER STATION DISTRIBUTION:

Tamara Bloomer RidsNrrDorlLpl3-2 RidsNrrPMDresden Resource RidsNrrDirslpab Resource James Caldwell Mark Satorius Kenneth Obrien Jared Heck Allan Barker DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports@nrc.gov

Dresden Inspection / Activity Plan 09/01/2008 - 12/31/2009 No. of Staff Planned Dates Inspection Inspection Activity Title on Site Start End Type TI - TEMPORARY INSTRUCTION 2515/171 2 IP 2515/171 Verification of Site Specific Implementation Of B.5.b Phase 2 & 3 Mitigating Strategies 10/20/2008 10/24/2008 Generic Safety Inspectio BI ENG - ENGINEERING INSERVICE INSPECTION 1 IP 7111108G Inservice Inspection Activities - BWR 11/03/2008 11/21/2008 Baseline Inspections BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 7112101 Access Control to Radiologically Significant Areas 11/10/2008 11/14/2008 Baseline Inspections IP 7112102 ALARA Planning and Controls 11/10/2008 11/14/2008 Baseline Inspections IP 71151-OR01 Occupational Exposure Control Effectiveness 11/10/2008 11/14/2008 Baseline Inspections BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 7112202 Radioactive Material Processing and Transportation 02/09/2009 02/13/2009 Baseline Inspections FY 2009 - DRESDEN INIT PREP FEB/2009 3 W90196 OL - INITIAL EXAM - MARCH 2009 - DRES 02/16/2009 02/20/2009 Not Applicable ISFSI - ISFSI - ROUTINE LOADING 1 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants 03/01/2009 06/30/2009 Other Routine BI EP - EP EXERCISE INSPECTION / PI VERIFICATION 1 IP 7111401 Exercise Evaluation 03/23/2009 03/27/2009 EP Baseline Inspection IP 71151-EP01 Drill/Exercise Performance 03/23/2009 03/27/2009 Baseline Inspections IP 71151-EP02 ERO Drill Participation 03/23/2009 03/27/2009 Baseline Inspections IP 71151-EP03 Alert & Notification System 03/23/2009 03/27/2009 Baseline Inspections OL EXAM - DRESDEN INITIAL LICENSE EXAMINATION 3 W90196 OL - INITIAL EXAM - MARCH 2009 - DRES 03/09/2009 03/20/2009 Not Applicable BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 7112101 Access Control to Radiologically Significant Areas 04/27/2009 05/01/2009 Baseline Inspections IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 04/27/2009 05/01/2009 Baseline Inspections IP 71151-BI01 Reactor Coolant System Activity 04/27/2009 05/01/2009 Baseline Inspections BI ENG - ENGINEERING MODIFICATIONS / 50.59 INSP. 3 IP 7111117B Evaluations of Changes, Tests, or Experiments & Permanent Plant Modifications 05/18/2009 06/05/2009 Baseline Inspections BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 2515/173 Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative 08/04/2009 08/14/2009 Generic Safety Inspectio IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 08/04/2009 08/14/2009 Baseline Inspections IP 71151-PR01 RETS/ODCM Radiological Effluent 08/04/2009 08/14/2009 Baseline Inspections RENEWAL - POST-LICENSE RENEWAL INSPECTION 5 IP 71003 Post-Approval Site Inspection for License Renewal 10/05/2009 10/23/2009 License Renewal Inspec BI ENG - ENGINEERING INSERVICE INSPECTION 1 IP 7111108G Inservice Inspection Activities - BWR 11/09/2009 11/13/2009 Baseline Inspections

Dresden Inspection / Activity Plan 09/01/2008 - 12/31/2009 No. of Staff Planned Dates Inspection Inspection Activity Title on Site Start End Type RENEWAL - POST LIC RENEWAL INSPECTION 2 IP 71003 Post-Approval Site Inspection for License Renewal 11/09/2009 11/20/2009 License Renewal Inspec BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 7112101 Access Control to Radiologically Significant Areas 11/16/2009 11/20/2009 Baseline Inspections IP 7112102 ALARA Planning and Controls 11/16/2009 11/20/2009 Baseline Inspections IP 71151-OR01 Occupational Exposure Control Effectiveness 11/16/2009 11/20/2009 Baseline Inspections