MONTHYEARML23187A0462023-07-0606 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000237/2023004 ML23087A0852023-03-28028 March 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information IR 05000237/20220062023-03-0101 March 2023 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2022006 and 05000249/2022006) ML23037A9192023-02-0707 February 2023 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000237/2023011 and 05000249/2023011 ML22318A1842022-11-15015 November 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000237/2023401; 05000249/2023401 ML22306A2172022-11-0202 November 2022 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Dresden Nuclear Power Station, Units 2 and 3 IR 05000237/20220052022-08-22022 August 2022 Updated Inspection Plan for Dresden Nuclear Power Station (Report 05000237/2022005; 05000249/2022005) ML22068A0862022-03-0909 March 2022 Reissue Dresden Nuclear Power Station, Units 2 and 3 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests, and Experiments) Baseline Inspection ML22062B0522022-03-0404 March 2022 Information Request for an Triennial 10 CFR 50.59 (Evaluation of Changes, Tests, and Experiments) Baseline Inspection IR 05000237/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000237/2021006 and 05000249/2021006) ML22027A3592022-01-26026 January 2022 U1: CY2022 Inspection Plan, Docket No. 05000010, License No. DPR-2 IR 05000237/20220102021-12-21021 December 2021 Notification of NRC DBAI (Programs) and Initial RFI Inspection Report 05000237/2022010 05000249/2022010 ML21265A2262021-09-22022 September 2021 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000237/2021004 05000249/2021004 IR 05000237/20210052021-09-0101 September 2021 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3, Report 05000237/2021005 and 05000249/2021005 ML21096A1752021-04-0606 April 2021 Notification of NRC Fire Protection Team Inspection Request for Information: Inspection Report 05000237/2021011; 05000249/2021011 IR 05000237/20200062021-03-0404 March 2021 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2020006 and 05000249/2020006) ML20337A4242020-12-0202 December 2020 Information Request for the Cyber-Security Full Implementation Inspection, Notification to Perform Inspection 05000237/2021401 and 05000249/2021401 ML20302A4602020-10-28028 October 2020 Request for Information for an NRC Triennial Baseline Deisgn Bases Assurance Inspection (Team): Inspection Report 05000237/2021010; 05000249/202101 IR 05000237/20200052020-09-0101 September 2020 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2020005 and 05000249/2020005) IR 05000237/20190062020-03-0303 March 2020 Annual Assessment Letter for Dresden, Units 2 and 3 (Report 05000237/2019006 and 05000249/2019006, 05000237/2019006 and 05000249/2019006) ML19290G5152019-10-15015 October 2019 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Dresden Nuclear Power Station, Units 2 and 3 IR 05000237/20190052019-08-28028 August 2019 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2019005 and 05000249/2019005) ML19136A1852019-05-15015 May 2019 Byron Station, Clinton Power Station, Dresden Nuclear Power Station, LaSalle County Station, and Quad Cities Nuclear Power Station-Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency IR 05000237/20180062019-03-0404 March 2019 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2018006 and 05000249/2018006) ML19008A3912019-01-0707 January 2019 Initial Information Request (Part 2) for the Upcoming Phase IV License Renewal Inspection, Dated 01/07/19 (DRS-J. Corujo-Sandin) IR 05000237/20180052018-08-28028 August 2018 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2018005 and 05000249/2018005) IR 05000237/20170062018-03-0202 March 2018 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2017006 and 05000249/2017006) IR 05000237/20170112018-01-0202 January 2018 NRC Temporary Instruction 2515/191, Mitigation Strategies, Spent Fuel Pool Instrumentation and Emergency Preparedness Inspection Report 05000237/2017011 and 05000249/2017011 ML17354B0352017-12-20020 December 2017 U1: CY2018 Master Inspection Plan IR 05000237/20170052017-08-28028 August 2017 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2017005 and 05000249/2017005) ML17240A2672017-08-25025 August 2017 Information Request to Support Upcoming Temporary Instruction 2515/191 Inspection at Dresden, Units 2 and 3 ML17236A0742017-08-23023 August 2017 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000237/2017004; 05000249/2017004 IR 05000237/20160062017-03-0101 March 2017 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2016006 and 05000249/2016006) ML16351A1072016-12-15015 December 2016 Master Inspection Plan - Calendar Year 2017 IR 05000237/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3,(Report 05000237/2016005; 05000249/2016005) ML16242A0712016-08-26026 August 2016 Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information 05000237/2017007; 05000249/2017007 ML16070A1102016-03-0909 March 2016 Request for Information for an NRC Pilot Design Bases Inspection on the Implementation of the Environmental Qualification Program Inspection Report 05000237/2016009; 05000249/2016009 IR 05000237/20150062016-03-0202 March 2016 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Inspection Report 05000237/2015006 and 05000249/2015006) ML16011A4852016-01-11011 January 2016 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Dresden Nuclear Power Station, Units 2 and 3 ML15357A1282015-12-21021 December 2015 Master Inspection Plan - Calendar Year 2016 ML15322A3722015-11-18018 November 2015 IR 05000237/2016008; 05000249/2016008 February 8 - 12, 2016; and February 22 - 26, 2016, Dresden Nuclear Power Station, Units 2 and 3; Request for Information for an NRC Pilot Component Design Bases Inspection IR 05000237/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2015005; 05000249/2015005) IR 05000237/20140012015-03-0404 March 2015 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3, (Report 05000237/2014001; 05000249/2014001) IR 05000237/20130012014-03-0404 March 2014 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2013001; 05000249/2013001) ML14003A2832014-01-0303 January 2014 Fire Protection Request for Information ML13308B2322013-11-0404 November 2013 Ltr 11/4/13 Dresden, Unit 2 and 3, Notification to Perform an Inspection of Temporary Instruction 2201/004, Inspection of Implementation of Interim Cyber Security Milestone 1-7 and Request for Information IR 05000237-14-405; 05000249-144-40 ML13301A7352013-10-28028 October 2013 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Dresden Nuclear Power Station, Units 2 and 3 ML13246A2172013-09-0303 September 2013 2013 Dresden MOC Letter Combined IR 05000237/20120012013-03-0404 March 2013 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2012001 and 05000249/2012001) ML12277A1872012-10-0303 October 2012 ISI Request for Information 2023-07-06
[Table view] Category:Letter
MONTHYEARIR 05000237/20230042024-02-0202 February 2024 Integrated Inspection Report 05000237/2023004 and 05000249/2023004 IR 05000010/20230012024-01-17017 January 2024 NRC Inspection Report 05000010/2023001 (Drss) ML23354A2812024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0031 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 RS-23-121, Sixth Ten-Year Interval Inservice Testing Program2023-11-30030 November 2023 Sixth Ten-Year Interval Inservice Testing Program SVPLTR 23-0037, Core Operating Limits Report for Cycle 292023-11-29029 November 2023 Core Operating Limits Report for Cycle 29 RS-23-119, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums RS-23-107, Relief Request I5R-22, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2023-11-0808 November 2023 Relief Request I5R-22, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval RS-23-102, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-16016 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23285A2342023-10-13013 October 2023 Confirmation of Initial License Examination RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans ML23279A0712023-10-0606 October 2023 Response to NRC Dresden Nuclear Power Station, Units 2 and 3 - Comprehensive Engineering Team Inspection Report 05000237/2023011 and 05000249/2023011 ML23269A0662023-09-28028 September 2023 Proposed Alternative Request RV-23H Associated with the Sixth 10-Year Inservice Testing Interval ML23265A1322023-09-27027 September 2023 Proposed Alternative Request RV-03 Associated with the Sixth 10-Year Inservice Testing Interval ML23205A1362023-09-20020 September 2023 Proposed Alternative Request RV-02D Associated with the Sixth IST Interval IR 05000237/20230112023-09-0606 September 2023 Comprehensive Engineering Team Inspection Report 05000237/2023011 and 05000249/2023011 RS-23-071, Application to Adopt TSTF-564, Safety Limit MCPR2023-08-30030 August 2023 Application to Adopt TSTF-564, Safety Limit MCPR RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs IR 05000237/20234022023-08-29029 August 2023 Security Baseline Inspection Report 05000237/2023402 and 05000249/2023402 IR 05000237/20230022023-08-0808 August 2023 Integrated Inspection Report 05000237/2023002 and 05000249/2023002 ML23212A9892023-08-0303 August 2023 Subsequent License Renewal Application Public Meeting Summary of Pre-Submittal Meeting ML23174A1502023-08-0303 August 2023 Issuance of Amendment Nos. 282 and 275 Control Rod Scram Times ML23193A0052023-07-28028 July 2023 Subsequent License Renewal Application Public Meeting Summary of Pre-Submittal Meeting ML23192A6292023-07-11011 July 2023 Correction Letter - Issuance of Amendment Nos. 281 and 274 Regarding Transition to GNF3 Fuel (EPID L-2022-LLA-0121) (Non-Proprietary) ML23144A3142023-07-0606 July 2023 Issuance of Amendment Nos. 281 and 274 Transition to GNF3 Fuel (EPID L-2022-LLA-0121) - Nonproprietary ML23187A0462023-07-0606 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000237/2023004 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III SVPLTR 23-0021, Registration of Use of Casks to Store Spent Fuel2023-06-20020 June 2023 Registration of Use of Casks to Store Spent Fuel RS-23-078, Supplement to License Amendment Request to Revise Technical Specification 3.1.4, Control Rod Scram Times2023-06-16016 June 2023 Supplement to License Amendment Request to Revise Technical Specification 3.1.4, Control Rod Scram Times RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000237/20233012023-05-30030 May 2023 NRC Initial License Examination Report 05000237/2023301; 05000249/2023301 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23132A0932023-05-17017 May 2023 Information Meeting (Public Open House) with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Dresden Power Station, Units 2 and 3 RS-23-070, Supplement to License Amendment Request Regarding Transition to GNF3 Fuel2023-05-16016 May 2023 Supplement to License Amendment Request Regarding Transition to GNF3 Fuel SVPLTR 23-0018, Submittal of 2022 Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Submittal of 2022 Annual Radiological Environmental Operating Report IR 05000237/20230012023-05-0404 May 2023 Integrated Inspection Report 05000237/2023001 and 05000249/2023001 SVPLTR 23-0019, ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1)2023-05-0101 May 2023 ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1) ML23118A3472023-05-0101 May 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Correction of Amendment No. 193 Adoption of TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration EPID L-2022-LLA-0143 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI IR 05000237/20234012023-04-26026 April 2023 Cyber Security Inspection Report 05000237/2023401 and 05000249/2023401 ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration IR 05000237/20235012023-04-21021 April 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000237/2023501 and 05000249/2023501 ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection RS-23-057, Supplement to License Amendment Request Regarding Transition to GNF3 Fuel2023-04-17017 April 2023 Supplement to License Amendment Request Regarding Transition to GNF3 Fuel SVPLTR 23-0014, Annual Dose Report for 20222023-04-15015 April 2023 Annual Dose Report for 2022 ML23088A2242023-04-0505 April 2023 Regulatory Audit Report Regarding License Amendment Request to Transition to GNF3 Fuel ML23087A0482023-03-28028 March 2023 Operator Licensing Examination Approval - Dresden Nuclear Power Station, April 2023 2024-02-02
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 September 2, 2008 Mr. Charles G. Pardee Chief Nuclear Officer and Senior Vice President Exelon Generation Company, LLC 4300 Winfield Road Warrenville IL 60555
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
DRESDEN NUCLEAR POWER STATION
Dear Mr. Pardee:
On August 14, 2008, the NRC staff completed its performance review of the Dresden Nuclear Power Station for the first half of the calendar year 2008 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous 12 months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as Official Use Only -Security Information will include the security cornerstone review and resultant inspection plan.
Plant performance for both Dresden Units 2 and 3 during the assessment period was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections of Units 2 and 3.
The enclosed inspection plan details the inspections, less those related to security, scheduled through December 31, 2009. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite.
Routine resident inspections are not listed due to their ongoing and continuous nature.
Additional inspections scheduled include: engineering modifications/50.59, license renewal, independent spent fuel storage installation, and initial license examination. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public
C. Pardee Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 630-829-9703 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Mark A. Ring, Chief Projects Branch 1 Division of Reactor Projects Docket Nos. 50-237; 50-249;72-037 License Nos. DPR-19; DPR-25
Enclosure:
Dresden Inspection/Activity Plan DISTRIBUTION:
See next page
Letter to C. Pardee from M. Ring dated September 2, 2008
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
DRESDEN NUCLEAR POWER STATION cc w/encl: Site Vice President - Dresden Nuclear Power Station Plant Manager - Dresden Nuclear Power Station Regulatory Assurance Manager - Dresden Nuclear Power Station Chief Operating Officer and Senior Vice President Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden, and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General J. Klinger, State Liaison Officer, Illinois Emergency Management Agency Chairman, Illinois Commerce Commission Will County Executive Will County Sheriff Director, Will County Emergency Management Agency Mayor of Joliet City Manager of Joliet Kendall County Board Chairman Kendall County Sheriff Grundy County Board Chairman Grundy County Sheriff Grundy County Emergency Management Agency Mayor of Morris Minooka Village President Mayor of Coal City Mayor of Carbon Hill Mayor of Diamond Mayor of Braidwood Mayor of Wilmington Channahon Village President Channahon Village Administrator Mayor of Shorewood Shorewood Village Administrator Mayor of Elwood G. Mortensen, INPO
C. Pardee Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 630-829-9703 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Mark A. Ring, Chief Projects Branch 1 Division of Reactor Projects Docket Nos. 50-237; 50-249;72-037 License Nos. DPR-19; DPR-25
Enclosure:
Dresden Inspection/Activity Plan DISTRIBUTION:
See next page DOCUMENT NAME: G:\1-SECY\2008 MID-CYCLE FINAL LETTERS\DRESDEN MOC LETTER 2008.DOC G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" =
Copy with attach/encl "N" = No copy OFFICE RIII E RIII RIII RIII NAME MRing:cms DATE 8/27/08 OFFICIAL RECORD COPY
Letter to C. Pardee from M. Ring dated September 2, 2008
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
DRESDEN NUCLEAR POWER STATION DISTRIBUTION:
Tamara Bloomer RidsNrrDorlLpl3-2 RidsNrrPMDresden Resource RidsNrrDirslpab Resource James Caldwell Mark Satorius Kenneth Obrien Jared Heck Allan Barker DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports@nrc.gov
Dresden Inspection / Activity Plan 09/01/2008 - 12/31/2009 No. of Staff Planned Dates Inspection Inspection Activity Title on Site Start End Type TI - TEMPORARY INSTRUCTION 2515/171 2 IP 2515/171 Verification of Site Specific Implementation Of B.5.b Phase 2 & 3 Mitigating Strategies 10/20/2008 10/24/2008 Generic Safety Inspectio BI ENG - ENGINEERING INSERVICE INSPECTION 1 IP 7111108G Inservice Inspection Activities - BWR 11/03/2008 11/21/2008 Baseline Inspections BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 7112101 Access Control to Radiologically Significant Areas 11/10/2008 11/14/2008 Baseline Inspections IP 7112102 ALARA Planning and Controls 11/10/2008 11/14/2008 Baseline Inspections IP 71151-OR01 Occupational Exposure Control Effectiveness 11/10/2008 11/14/2008 Baseline Inspections BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 7112202 Radioactive Material Processing and Transportation 02/09/2009 02/13/2009 Baseline Inspections FY 2009 - DRESDEN INIT PREP FEB/2009 3 W90196 OL - INITIAL EXAM - MARCH 2009 - DRES 02/16/2009 02/20/2009 Not Applicable ISFSI - ISFSI - ROUTINE LOADING 1 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants 03/01/2009 06/30/2009 Other Routine BI EP - EP EXERCISE INSPECTION / PI VERIFICATION 1 IP 7111401 Exercise Evaluation 03/23/2009 03/27/2009 EP Baseline Inspection IP 71151-EP01 Drill/Exercise Performance 03/23/2009 03/27/2009 Baseline Inspections IP 71151-EP02 ERO Drill Participation 03/23/2009 03/27/2009 Baseline Inspections IP 71151-EP03 Alert & Notification System 03/23/2009 03/27/2009 Baseline Inspections OL EXAM - DRESDEN INITIAL LICENSE EXAMINATION 3 W90196 OL - INITIAL EXAM - MARCH 2009 - DRES 03/09/2009 03/20/2009 Not Applicable BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 7112101 Access Control to Radiologically Significant Areas 04/27/2009 05/01/2009 Baseline Inspections IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 04/27/2009 05/01/2009 Baseline Inspections IP 71151-BI01 Reactor Coolant System Activity 04/27/2009 05/01/2009 Baseline Inspections BI ENG - ENGINEERING MODIFICATIONS / 50.59 INSP. 3 IP 7111117B Evaluations of Changes, Tests, or Experiments & Permanent Plant Modifications 05/18/2009 06/05/2009 Baseline Inspections BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 2515/173 Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative 08/04/2009 08/14/2009 Generic Safety Inspectio IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 08/04/2009 08/14/2009 Baseline Inspections IP 71151-PR01 RETS/ODCM Radiological Effluent 08/04/2009 08/14/2009 Baseline Inspections RENEWAL - POST-LICENSE RENEWAL INSPECTION 5 IP 71003 Post-Approval Site Inspection for License Renewal 10/05/2009 10/23/2009 License Renewal Inspec BI ENG - ENGINEERING INSERVICE INSPECTION 1 IP 7111108G Inservice Inspection Activities - BWR 11/09/2009 11/13/2009 Baseline Inspections
Dresden Inspection / Activity Plan 09/01/2008 - 12/31/2009 No. of Staff Planned Dates Inspection Inspection Activity Title on Site Start End Type RENEWAL - POST LIC RENEWAL INSPECTION 2 IP 71003 Post-Approval Site Inspection for License Renewal 11/09/2009 11/20/2009 License Renewal Inspec BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 7112101 Access Control to Radiologically Significant Areas 11/16/2009 11/20/2009 Baseline Inspections IP 7112102 ALARA Planning and Controls 11/16/2009 11/20/2009 Baseline Inspections IP 71151-OR01 Occupational Exposure Control Effectiveness 11/16/2009 11/20/2009 Baseline Inspections