ML082310359

From kanterella
Jump to navigation Jump to search
Notification of Inspection and Request for Information
ML082310359
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 08/18/2008
From: Hopper G
NRC/RGN-II/DRS/EB3
To: Tynan T
Southern Nuclear Operating Co
References
Download: ML082310359 (11)


Text

August 18, 2008 Mr. Tom E. Tynan Vice President Southern Nuclear Operating Company, Inc.

Vogtle Electric Generating Plant 7821 River Road Waynesboro, GA 30830

SUBJECT:

VOGTLE UNIT 2 - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION

Dear Mr. Tynan:

From September 22 to October 3, 2008, the NRC will perform the baseline in-service inspection (ISI) at the Vogtle Nuclear Plant, Unit 2 (NRC Inspection Procedure 71111.08). Experience has shown that this inspection is resource intensive both for the NRC inspectors and your staff. In order to minimize the impact to your on-site resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. These documents have been divided into two groups. The first group (section A of the enclosure) identifies information to be provided prior to the inspection to ensure that the inspectors are adequately prepared.

The second group (section B of the enclosure) identifies the information the inspectors will need upon arrival at the site. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection.

We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Mukut Sharma of your organization. Our inspection dates are subject to change based on your updated schedule of outage activities. If there are any questions about this inspection or the material requested, please contact the lead inspector Cecil Fletcher at (404) 562-4973 (Cecil.Fletcher@nrc.gov) or Eric Michel at (404) 562-4555 (Eric.Michel@nrc.gov).

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).

SNC, INC. 2 ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

George T. Hopper, Chief Engineering Branch 3 Division of Reactor Safety Docket No. 50-425 License No. NPF-81 Enclosure (cc w/encl - See page 3)

SNC, INC. 3 cc w/encl: Mr. N. Holcomb N. J. Stringfellow Commissioner Manager Department of Natural Resources Licensing Electronic Mail Distribution Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Dr. Carol Couch Director Jeffrey T. Gasser Environmental Protection Executive Vice President Department of Natural Resources Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution Cynthia Sanders L. Mike Stinson Program Manager Vice President Radioactive Materials Program Fleet Operations Support Department of Natural Resources Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution Jim Sommerville Michael A. MacFarlane (Acting) Chief Southern Nuclear Operating Company, Inc. Environmental Protection Division 40 Inverness Center Parkway Department of Natural Resources P.O. Box 1295 Electronic Mail Distribution Birmingham, AL 35201-1295 Mr. Steven M. Jackson David H. Jones Senior Engineer - Power Supply Vice President Municipal Electric Authority of Georgia Engineering Electronic Mail Distribution Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Mr. Reece McAlister Executive Secretary Bob Masse Georgia Public Service Commission Resident Manager Electronic Mail Distribution Vogtle Electric Generating Plant Oglethorpe Power Corporation Office of the Attorney General Electronic Mail Distribution Electronic Mail Distribution Moanica Caston M. Stanford Blanton, Esq.

Vice President and General Counsel Balch and Bingham Law Firm Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution Office of the County Commissioner Resident Manager Burke County Commission Oglethorpe Power Corporation Electronic Mail Distribution Alvin W. Vogtle Nuclear Plant 7821 River Road Arthur H. Domby, Esq.

Waynesboro, GA 30830 Troutman Sanders Electronic Mail Distribution Laurence Bergen Oglethorpe Power Corporation Electronic Mail Distribution

SNC, INC. 4 cc: w/encl Director Consumers' Utility Counsel Division Governors Office of Consumer Affairs 2 M. L. King, Jr. Drive Plaza Level East; Suite 356 Atlanta, GA 30334-4600 Senior Resident Inspector Southern Nuclear Operating Company, Inc.

Vogtle Electric Generating Plant U.S. NRC 7821 River Road Waynesboro, GA 30830 Susan E. Jenkins Director, Division of Waste Management Bureau of Land and Waste Management S.C. Department of Health and Environmental Control Electronic Mail Distribution

SNC, INC. 5 Letter to Tom E. Tynan from George Hopper dated August 18, 2008

SUBJECT:

VOGTLE - NRC INTEGRATED INSPECTION REPORT 05000424/2008 AND 05000425/2008 Distribution w/encl:

RIDSNRRDIRS PUBLIC Richard Jervey, NRR

August 18, 2008 Mr. Tom E. Tynan Vice President Southern Nuclear Operating Company, Inc.

Vogtle Electric Generating Plant 7821 River Road Waynesboro, GA 30830

SUBJECT:

VOGTLE UNIT 2 - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION

Dear Mr. Tynan:

From September 22 to October 3, 2008, the NRC will perform the baseline in-service inspection (ISI) at the Vogtle Nuclear Plant, Unit 2 (NRC Inspection Procedure 71111.08). Experience has shown that this inspection is resource intensive both for the NRC inspectors and your staff. In order to minimize the impact to your on-site resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. These documents have been divided into two groups. The first group (Section A of the enclosure) identifies information to be provided prior to the inspection to ensure that the inspectors are adequately prepared.

The second group (section B of the enclosure) identifies the information the inspectors will need upon arrival at the site. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection.

We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Mukut Sharma of your organization. Our inspection dates are subject to change based on your updated schedule of outage activities. If there are any questions about this inspection or the material requested, please contact the lead inspector Cecil Fletcher at (404) 562-4973 (Cecil.Fletcher@nrc.gov) or Eric Michel at (404) 562-4555 (Eric.Michel@nrc.gov).

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).

_________________________ XG SUNSI REVIEW COMPLETE OFFICE RII-DRS RII-DRS RII-DRS RII:DRP SIGNATURE /RA/ /RA/ /RA/ /RA/

NAME Cecil Fletcher Eric Michel George Hopper Scott Shaeffer DATE 08/07/08 08/11/08 08/11/2008 08/11/08 8/ /2008 8/ /2008 8/ /2008 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

INSERVICE INSPECTION DOCUMENT REQUEST Inspection Dates: September 22 to October 3, 2008 Inspection Procedures: IP 71111.08 In-service Inspection (ISI) Activities Inspectors: Cecil Fletcher, Reactor Inspector (Lead Inspector - ISI)

Eric Michel, Senior Reactor Inspector (Inspector - SGISI)

A. Information Requested for the In-Office Preparation Week The following information should be sent to the Region II office in hard copy or electronic format (CD preferred), in care of Cecil Fletcher by September 10, 2008 to facilitate the selection of specific items that will be reviewed during the onsite inspection week. The inspector will select specific items from the information requested below and then request from your staff additional documents needed during the onsite inspection week (section B of this enclosure). We ask that the specific items selected from the lists be available and ready for review on the first day of inspection. *Please provide requested documentation electronically if possible. If requested documents are large and only hard copy formats are available, please inform the inspector(s), and provide subject documentation during the first day of the onsite inspection. If you have any questions regarding this information request, please call the inspector as soon as possible.

A.1 ISI / Welding Programs and Schedule Information a) A detailed schedule (including preliminary dates) of:

i) Nondestructive examinations (NDEs) planned for Class 1 & 2 systems and containment, performed as part of your ASME Section XI, (and/or Risk Informed Program) during the upcoming outage.

Provide a status summary of the NDE inspection activities versus the required inspection period percentages for this Interval by category per ASME Section XI, IWX-2400 (do not provide separately if other documentation requested contains this information).

ii) Reactor pressure vessel head (RPVH) examinations planned for the upcoming outage.

iii) Examinations planned for Alloy 82/182/600 components that are not included in the Section XI scope (MRP-126 and MRP-139).

iv) Examinations planned as part of your Boric Acid Corrosion Control Program (Mode 3 walkdowns, bolted connection walkdowns, etc.).

Enclosure

2 v) Welding activities that are scheduled to be completed during the upcoming outage (ASME Class 1, 2, or 3 structures, systems, or components (SSCs).

b) A copy of ASME Section XI Code Relief Requests and associated NRC Safety Evaluations applicable to the examinations and welding identified above.

c) A list of NDE reports (ultrasonic, radiography, magnetic particle, dye penetrant, visual VT-1, VT-2, and VT-3) which have identified recordable indications (geometric or flaw) on Code Class 1 & 2 systems since the beginning of the last refueling outage. This should include the previousSection XI pressure test(s) conducted during start up and any evaluations associated with the results of the pressure tests. Also, include in the list the NDE reports with recorded indications in the RPVH penetration nozzles which have been accepted for continued service. The list of NDE reports should include a brief description of the SSC where the recordable indication was identified.

d) A list with a brief description (e.g. system, material, pipe size, weld number, and NDE performed) of the welds in Code Class 1 and 2 systems which have been fabricated due to component repair/replacement activities since the beginning of the last refueling outage, or are planned to be fabricated this refueling outage.

e) If reactor vessel weld examinations required by the ASME Code are scheduled to occur during the upcoming outage, provide a detailed description of the welds to be examined, and the extent of the planned examination. Please also provide reference numbers for applicable procedures that will be used to conduct these examinations.

f) Copy of any 10 CFR Part 21 reports applicable to your SSCs within the scope of Section XI of the ASME Code that have been identified since the beginning of the last refueling outage.

g) A list of any temporary non-code repairs in service (e.g. pinhole leaks repaired under code case N-513-2 or Generic Letter 90-05).

h) Please provide copies of the most recent self assessments for the ISI, Welding, and Alloy 600 Programs.

A.2 Reactor Pressure Vessel Head (RPVH) a) Provide the detailed scope of the planned NDE of the reactor vessel head which identifies the types of NDE methods to be used on each specific part of the vessel head to fulfill NRC commitments made in response to NRC Bulletin 2002-02 and NRC Order EA-03-009. Also, include examination scope expansion criteria and planned expansion sample sizes if relevant indications are identified.

(If applicable)

Enclosure

3 b) A list of the standards and/or requirements that will be used to evaluate indications identified during NDE of the reactor vessel head (e.g. the specific industry or procedural standards which will be used to evaluate potential leakage and/or flaw indications).

A.3 Boric Acid Corrosion Control Program (BACCP) a) Copy of the procedures that govern the scope, equipment and implementation of the inspections required to identify boric acid leakage and the procedures for boric acid leakage/corrosion evaluation.

b) Please provide a list of leaks (including code class of the components) that have been identified since the last refueling outage and associated corrective action documentation. If during the last cycle, the Unit was shutdown, please provide documentation of containment walk-down inspections performed as part of the BACCP.

c) Please provide a copy of the most recent self-assessment performed for the BACCP.

A.4 Steam Generator (SG) Inspections a) A detailed schedule of SG tube inspection, data analyses, and repair activities for the upcoming outage.

ii) SG secondary side inspection activities for the upcoming outage.

b) Please provide a copy of your SG ISI Inspection Program and Plan. Please include a copy of the Operational Assessment from last outage, and a copy of the following documents as they become available:

i) Degradation Assessment ii) Condition Monitoring Assessment c) A list of known deviations from the Standard Technical Specifications for the SGMP.

d) Copy of SG training documentation given to vendors performing eddy current (ET) testing of the SGs during the upcoming outage.

e) Copy of SG Eddy Current Data Analyst Guidelines, and Site Validated Eddy Current Technique.

f) A copy of your EPRI Appendix H written program (see App. H.1.c).

Enclosure

4 g) Identify and quantify any SG tube leakage experienced during the previous operating cycle. Also provide documentation identifying which SG was leaking and corrective actions completed or planned for this condition. (If applicable) h) Provide past history of the condition and issues pertaining to the secondary side of the steam generators (including items such as loose parts, fouling, top of tube sheet condition, crud removal amounts, etc.)

i) Please provide copies of your most recent self assessments of the SG monitoring, loose parts monitoring, and secondary side water chemistry control programs.

j) Please indicate where the primary, secondary, and resolution analyses are scheduled to take place.

k) Please provide a summary of the scope of the SG ISI examinations, including examination methods such as Bobbin, Rotating Pancake, or Plus Points, and the percentage of tubes to be examined. Do not provide these documents separately if already included in other information requested.

A.5 Additional information related to all ISI activities a) A list with a brief description of ISI, BACCP, and SG ISI related issues (e.g.,

condition reports) entered into your corrective action program since the beginning of the last refueling outage (for Unit 2). For example, a list based upon data base searches using key words related to piping or SG tube degradation such as: ISI, ASME Code,Section XI, NDE, cracks, wear, thinning, leakage, rust, corrosion, boric acid, or errors in piping/SG tube examinations.

b) Please provide names and phone numbers for the following program leads:

ISI contacts (Examination, planning)

Containment Exams RPVH Exams Snubbers and Supports Repair and Replacement Program Manager Licensing Contact Site Welding Engineer Boric Acid Corrosion Control Program SG Inspection Activities (site lead and vendor contact)

B. Information to be provided on-site to the inspector at the entrance meeting (September 29, 2008):

B.1 ISI / Welding Programs and Schedule Information a) Updated schedules for ISI/NDE activities, including SG ISI, planned welding activities, and schedule showing contingency repair plans, if available.

b) For ASME Class 1 and 2 welds selected by the inspector from the lists provided from section A of this enclosure, please provide copies of the following documentation for each subject weld:

Enclosure

5 i) Weld data sheet ii) Weld traveler ii) Weld configuration and system location iii) Applicable Code Edition and Addenda for weldment iv) Applicable Code Edition and Addenda for welding procedures v) Applicable weld procedures (WPS) used to fabricate the welds vi) Copies of procedure qualification records (PQRs) supporting the WPS from B.1.b.v vii) Copies of mechanical test reports identified in the PQRs above viii) Copies of the nonconformance reports for the selected welds (If applicable) ix) Radiographs of the selected welds and access to equipment to allow viewing radiographs (if RT was performed) x) Copies of the pre-service examination records for the selected welds.

xi) Copies of welder performance qualifications records applicable to WPS, including documentation that welder maintained proficiency in the applicable welding processes specified in the WPS (At least six months prior to date subject work) xii) Copies of NDE personnel qualifications (VT, PT, UT, RT) As applicable c) For the ISI related corrective action issues selected by the inspector from Section A of this enclosure, provide a copy of the corrective actions and supporting documentation.

d) For the NDE reports with recordable indications on Code Class 1 & 2 systems selected by the inspector from Section A above, provide a copy of the examination records, examiner qualification records, and associated corrective action documents.

e) A copy of (or ready access to) most current revision of the ISI Program Manual and Plan for the current Interval.

f) For the NDEs selected by the inspector from section A of this enclosure, provide copy of the NDE procedures used to perform the examinations (including calibration and flaw characterization/sizing procedures). For ultrasonic examination procedures qualified in accordance with ASME Code,Section XI, Appendix VIII, provide documentation supporting the procedure qualification (e.g., the EPRI performance demonstration qualification summary sheets). Also, include documentation of the specific equipment to be used (e.g., ultrasonic unit, cables, and transducers including serial numbers) and NDE personnel qualification records.

B.2 Reactor Pressure Vessel Head (RPVH) a) Provide the NDE personnel qualification records for the examiners who will perform examinations of the RPVH.

b) Provide drawings showing the following: (If a visual examination is planned for the upcoming refueling outage) i) RPVH and CRDM nozzle configurations Enclosure

6 ii) RPVH insulation configuration The drawings listed above should include fabrication drawings for the nozzle attachment welds as applicable.

c) Copy of NDE reports from the last RPVH examination.

d) Copy of evaluation or calculation demonstrating that the scope of the visual examination of the upper head will meet the 95% minimum coverage required by NRC Order EA-03-009 (If a visual examination is planned for the upcoming refueling outage).

e) Provide a copy of the procedures that will be used to identify the source of any boric acid deposits identified on the RPVH. If no explicit procedures exist which govern this activity, provide a description of the process to be followed including personnel responsibilities and expectations.

f) Provide a copy of the updated calculation of effective degradation years (EDY) for the RPVH susceptibility ranking.

g) Provide copy of the vendor qualification report(s) that demonstrates the detection capability of the NDE equipment used for the RPVH examinations. Also, identify any changes in equipment configurations used for the RPVH examinations which differ from that used in the vendor qualification report(s).

B.3 Boric Acid Corrosion Control Program (BACCP) a) Please provide boric acid walk down inspection results, an updated list of boric acid leaks identified so far this outage, associated corrective action documentation, and overall status of planned boric acid inspections.

b) Please provide any engineering evaluations completed for boric acid leaks identified since the end of the last refueling outage. Please include a status of corrective actions to repair and/or clean these boric acid leaks. Please specify which known leaks, if any, have remained in service or will remain in service as active leaks.

B.4 Steam Generator (SG) Inspections a) Copies of the site specific acquisition and analysis Examination Technique Specification Sheets (ETSS).

b) Copy of the guidance to be followed if a loose part or foreign material is identified in the SGs.

c) Please provide a copy of the ET procedures used to perform the SG ISI (specifically calibration and flaw characterization/sizing procedures, etc.). Also include documentation for the specific equipment to be used.

Enclosure

7 d) Please provide copies of your responses to NRC and industry operating experience communications such as Generic Letters, Information Notices, etc. as applicable to SG inspections. Do not provide these documents separately if already included in other information requested such as the degradation assessment.

e) List of corrective action documents generated by the vendor and/or site with respect to SG inspection activities.

B.5 Codes and Standards a) Ready access to: (i.e. copies provided to the inspector to use for the duration of the inspection at the on-site inspection location, or room number and location where available) i) Applicable editions of the ASME Code (Sections V, IX and XI) for the in-service inspection program and the repair/replacement program.

ii) EPRI and industry standards referenced in your procedures.

Inspector Contact Information:

Cecil Fletcher Eric Michel Reactor Inspector Senior Reactor Inspector 404-562-4973 404-562-4555 Cecil.Fletcher@nrc.gov eric.michel@nrc.gov Mailing Address:

US NRC Region 2 Attn: Eric Michel 61 Forsyth Street SW, Suite 23T85 Atlanta, GA 30303 Enclosure