Notification of Inspection of the Implementation of B.5.b Phase 2 and 3 Mitigating Strategies Using Temporary Instruction 2515/171
ML082140560
Person / Time
Site: McGuire, Mcguire  Duke Energy icon.png
Issue date: 08/01/2008
From: Steven Rose
NRC/RGN-II/DRP/RPB1
To: Brandi Hamilton
Duke Energy Carolinas, Duke Power Co
References
Download: ML082140560 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II SAM NUNN ATLANTA FEDERAL CENTER 61 FORSYTH STREET, SW, SUITE 23T85 ATLANTA, GEORGIA 30303-8931 August 1, 2008 Mr. Bruce Hamilton Vice President Duke Power Company, LLC d/b/a Duke Energy Carolinas, LLC McGuire Nuclear Station 12700 Hagers Ferry Road Huntersville, NC 28078-8985

SUBJECT:

MCGUIRE NUCLEAR STATION - NOTIFICATION OF INSPECTION OF THE IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITIGATING STRATEGIES USING TEMPORARY INSTRUCTION 2515/171

Dear Mr. Hamilton:

The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC) staff will conduct an inspection at the McGuire Nuclear Station the week of November 3, 2008. The inspection team will be led by Norman Merriweather, senior reactor inspector. The team will be composed of an inspector from Region II, an NRR inspector/contractor, and the team leader. The inspection will be conducted in accordance with NRC Temporary Instruction 2515/171, Verification of Site Specific Implementation of B.5.b Phase 2 and 3 Mitigation Strategies.

In order for the NRC to adequately prepare for this inspection, please furnish the documents listed in Enclosure 1 to the NRC team lead (Norman Merriweather) at least two weeks prior to the planned on-site inspection. Please have available on-site at the beginning of the inspection the documents listed in Enclosure 2. Kay Crane, of your staff, has been advised of this request and other inspection team support needs.

This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018, which expires on June 30, 2009.

DEC 2

Your cooperation and support during this inspection will be appreciated. If you have any questions regarding this inspection, please contact Norman Merriweather at (404) 562-4627, or me at (404) 562-4609.

Sincerely,

/RA/

Steven D. Rose, Acting Chief Reactor Projects Branch 1 Division of Reactor Projects Docket No.:

50-369, 50-370 License No.: NPF-9, 17

Enclosures:

1.

Documentation Requested Prior to the Inspection

2.

Arrangements/Documents Requested to be Available Onsite During the Inspection Week

X SUNSI REVIEW /SDR/

OFFICE RII:DRS RII:DRP SIGNATURE NXM /RA/

SDR /RA/

NAME NMerriweather SRose DATE 07/29/2008 08/01/2008 E-MAIL COPY?

YES NO YES NO YES NO YES NO YES NO YES NO YES NO

DEC 3

cc w/encl:

Bruce Hamilton Vice President McGuire Nuclear Station Duke Power Company, LLC d/b/a Duke Energy Carolinas, LLC Electronic Mail Distribution Steven D. Capps Engineering Manager Duke Power Company, LLC d/b/a Duke Energy Carolinas, LLC Electronic Mail Distribution Scotty L. Bradshaw Training Manager Duke Power Company, LLC d/b/a Duke Energy Carolinas, LLC Electronic Mail Distribution Kenneth L. Ashe Regulatory Compliance Manager Duke Power Company, LLC d/b/a Duke Energy Carolinas, LLC Electronic Mail Distribution R. L. Gill, Jr.

Manager Nuclear Regulatory Issues & Industry Affairs Duke Power Company, LLC d/b/a Duke Energy Carolinas, LLC Electronic Mail Distribution Lisa F. Vaughn Associate General Counsel Duke Energy Corporation 526 South Church Street-EC07H Charlotte, NC 28202 Kathryn B. Nolan Senior Counsel Duke Energy Corporation 526 South Church Street-EC07H Charlotte, NC 28202 David A. Repka Winston Strawn LLP Electronic Mail Distribution County Manager of Mecklenburg County 720 East Fourth Street Charlotte, NC 28202 Beverly O. Hall Chief, Radiation Protection Section Department of Environmental Health N.C. Department of Environmental Commerce & Natural Resources Electronic Mail Distribution Dhiaa M. Jamil Group Executive and Chief Nuclear Officer Duke Energy Carolinas, LLC Electronic Mail Distribution

DEC 4

Letter to Bruce Hamilton from Steven D. Rose dated August 1, 2008

SUBJECT:

MCGUIRE NUCLEAR STATION - NOTIFICATION OF INSPECTION OF THE IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITIGATING STRATEGIES USING TEMPORARY INSTRUCTION 2515/171 Distribution w/encl:

C. Evans, RII L. Slack, RII OE Mail RIDSNRRDIRS PUBLIC J. Stang, NRR

DOCUMENTATION REQUESTED PRIOR TO THE INSPECTION Please provide the items below two weeks prior to the onsite inspection week. For any items below not supplied prior to the onsite inspection week, please have the item available at the start of the onsite inspection. Please provide as much as possible in electronic format. You are reminded to properly identify and handle all Official Use Only-Security-Related Information and/or Proprietary Information in accordance with current guidance.

1.

Copies of procedures/guidelines that were revised or generated to implement the mitigation strategies. These could be Extensive Damage Mitigation Guidelines (EDMGs), SAMGs, EOPs, AOPs, etc;

2.

A matrix that shows the correlation between the mitigation strategies identified in NEI 06-12 and the site-specific procedures or guidelines used to implement the strategy;

3.

Engineering evaluations/calculations that were used to verify engineering bases for the mitigation strategies;

4.

Simplified flow diagrams for systems relied upon in the mitigation strategies; (These diagrams could be the type used for training.);

5.

Simplified drawings/descriptions of modifications that were made to plant systems to implement the mitigation strategies; and

6.

Electrical one line diagrams credited or revised to implement the mitigation strategies.

ARRANGEMENTS/DOCUMENTS REQUESTED TO BE AVAILABLE ONSITE DURING THE INSPECTION WEEK

1.

Provide a conference room to accommodate up to four (4) NRC staff. Preferably this would be outside the protected area.

2.

Site B.5.b contact person(s) should be available for the week.

3.

B.5.b engineering persons(s) should be on call for questions about any engineering calculations.

4.

Appropriate Operations staff should be available, as needed, for plant walkdowns throughout the week.

5.

Modification packages for any plant modifications performed as a result of B.5.b

6.

Detailed drawings (e.g., P&IDs) of systems used to implement mitigating strategies

7.

Copies of procedures/guidelines that were revised or generated to implement the mitigation strategies - these could be Extensive Damage Mitigation Guidelines (EDMGs),

SAMGs, EOPs, AOPs, etc. This is the same as Item 1 to Enclosure 1, except that hard copies of these procedures/guidelines should be made available for each member of the inspection team.

8.

Copies of procedures used to inventory equipment used in the mitigation strategies (e.g.,

hoses, fittings, pumps, etc.).

9.

Training records/ training matrix/ lesson plans related to B.5.b

10.

Copies of Memoranda of Understanding (MOUs) with local fire departments or other emergency services that are required to implement any mitigating strategies

11.

Copies of any evaluations performed to document that enough equipment is available to implement the mitigating strategies (e.g., enough fire hose or electrical cable is available based on a plant walkdown or review of drawings)

12.

You are reminded to properly identify and handle all Official Use Only - Security-Related Information and/or Proprietary Information in accordance with current guidance.