& STARS Meeting PVNGS PVNGS & STARS Meeting with NRC June, 2008 1

.1, AGENDA

" Introduction to STARS

" Wolf Creek Model

  • Palo Verde Status

" Other STARS Plants

" Discussion 2

A~.

iv -

PREVIOUS MEETINGS

" November 2004

" October 2005

" May 2006

" September 2007 3

STARS PAM COB

  • Established March 2004
  • Combined utility and contractor staff
  • Perform integrated plant assessments in preparation of LRA's
  • Establish and apply common methodologies & documentation
  • Realize efficiencies and savings 4

A~ STARS iii PAM COB MEMBERS

  • Callaway*
  • Comanche Peak

" Diablo Canyon

° Palo Verde

" San Onofre*

  • Callaway and San Onofre joined the COB January 1, 2008 5

STARS LRA STATUS

" Wolf Creek

- Draft SER issued with Open Items

- ACRS Subcommittee Meeting held March 5th

- SER due July 29th

- ACRS Full Committee Meeting September

- License issue date November 2 1 st

  • Palo Verde

- Draft application issued for review

- Letter to NRC May 15th

- Target submittal ready - 4 th Quarter 2008

  • Plant #3

- Feasibility Study Production began beginning 2008

- Environmental review underway

- Feasibility Study Complete - 4 th Quarter 2009

  • Plant #4

- Readiness Review Completed

- Data transfer and database preparation in progress

- Production begins August 2008

- Target submittal window - 4 th Quarter 2010 6

STARS LETTERS OF INTENT

  • Letters of Intent

-4th Quarter 2008

-4th Quarter 2009

-4th Quarter 2010

- 4 th Quarter 2011

-4th Quarter 2012 3rd Quarter 2013 7

STARS PAM COB ACTIVITIES

'I' WITHIN THE INDUSTRY

- License Renewal Task Force

- Discipline License Renewal Working Groups

  • Peer Reviews & Assessments 9 Benchmarking, Industry Workshops, Audits, RAI Database

STARS APPROACH TO SUBMITTALS

" Wolf Creek sets standard for follow-on plants

- Common methodology, documentation and presentation

" Utilize Common utility and contractor staff

  • Schedule sequential filings to maximize benefits

" Foster station ownership of product

" Maintain cognizance of industry direction, influence key decisions

- Provide timely feedback from predecessor plant and other industry submittals into process

" Make NRC's reviews, audits, and inspections easy

" Established License Renewal Oversight Committee to ensure COB objectives are being met v

A On. WIc~*~

Sept. 25, 2007 NRC Lessons-11/' Learned Meeting - Positives o Wolf Creek application is a good model

  • Enhance; don't rebuild

" Well organized

" Well documented

  • Very good drawings

" Excellent interaction between plant staff & COB staff

" Website access a definite strength

" Q&A Database worked well 10

Sept. 25, 2007 NRC Lessons-Learned Meeting - Recommendations

" Make more environmental docs available on website

  • Be more specific in referencing basis documents (page, section, subsection)
  • Be as timely as possible in submitting amendments I responses - consider partial submittals
  • OE and CAP extremely important; the more, the better

" Follow GALL Rev. 1; Exceptions to NUREG-1801 will require additional review (enhancements are better)

" Continue to monitor other applications and audits

  • Ensure internet access for at least one NRC person during audits / inspections 11

11/1' I

OTHER STARS PLANTS 9 Preparations in Progress 12

PLOL~LK 7LEREDE~

'2' SUR FLAEZHPE Q~IIp6 0 p ii'

~i~T 6 0 13

JPALO VERDE S"Three identical CE System 80 PWRs

  • Located 26 mi west of the Phoenix metropolitan area
  • Licensed power 3990 MWt
  • Zero discharge plant cooled by forced draft low profile cooling towers

° All SGs have been replaced

  • Reactor heads will be replaced in RF15 (10/09, 4/10 and 10/10) 4 I,,+

PALO VERDE STATUS

  • Preparation began March 2006
  • Production work done
  • Completed first LRA draft - April 2008
  • Industry Peer Review - May 2008
  • Second draft now in review by Plant Review Board and Off-Site Safety Review Committee 9 Target Submittal Date - 4th Quarter 2008 15

f4L

-~

APPLICATION OF

!(/1 NUREG-1801 e 39 Aging Management Programs

- 17 programs will be enhanced

- 9 programs with exception

- 9 new programs 9 NUREG-1801 Consistency

- Aging evaluation approximately 952/o consistent with NUREG-1 801

- Two Plant Specific Programs

" Plant specific Njckel Alloy Program

" RCS supplement for Reactor Internals and Nickel Alloy 16

J_ APPLICATION OF 1/LESSONS LEARNED

  • Wolf Creek sets standard for STARS plants
  • Common methodology and documentation
  • Common utility and contractor staff
  • Timely feedback from predecessor plant NRC reviews
  • Industry Participation and Feedback
  • Executive Management Engagement and Site Ownership 17

SPECIFIC ISSUES

  • Station Blackout
  • Consistency with GALL
  • Review and Audit/Inspection Process
  • Other Concerns, Expectation s, Areas to focus on?

18

SUMMARY

  • STARS Approach
  • Industry Participation

" Consistent with NUREG-1 801

" Use of Lessons Learned and NRC Feedback

" Interaction between Plant and NRC staff 19

~U~AI DISCUSSION 20