May 21, 2008 Mr. M. R. Blevins Executive Vice President
& Chief Nuclear Officer Luminant Generation Company LLC ATTN: Regulatory Affairs P. O. Box 1002 Glen Rose, TX 76043
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION, UNITS 1 AND 2 -
WITHDRAWAL OF LICENSE AMENDMENT REQUEST 06-009, REVISION TO TECHNICAL SPECIFICATION 3.8.1, AC SOURCES - OPERATING, EXTENSION OF COMPLETION TIMES FOR DIESEL GENERATORS (TAC NOS. MD4066 AND MD4067)
Dear Mr. Blevins:
By [[letter::CPSES-200700130, License Amendment Request (LAR)06-009, Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times for Diesel Generators|letter dated January 18, 2007]], as supplemented by letters dated November 15 and November 28, 2007, TXU Generation Company LP (subsequently renamed as Luminant Generation Company LLC, the licensee) applied for an amendment to the Comanche Peak Steam Electric Station, Units 1 and 2, Facility Operating License Nos. NPF-87 and NPF-89, respectively. The proposed change would have modified the facility technical specifications (TSs) pertaining to TS 3.8.1 to extend the 72-hour completion time for one inoperable diesel generator to 14 days, provided an alternate AC [alternating current] power source was available.
Subsequently, by [[letter::CP-200800183, Withdrawal of License Amendment Request (LAR)06-009, Revision to Technical Specification 3.8.1, AC Sources - Operating, Extension of Completion Times for Diesel Generators|letter dated January 30, 2008]], you withdrew the amendment request.
The Commission has filed the enclosed Notice of Withdrawal of Application for Amendment to Facility Operating Licenses with the Office of the Federal Register for publication.
Sincerely,
/RA/
Balwant K. Singal, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-445 and 50-446
Enclosure:
Notice of Withdrawal cc w/encl: See next page
May 21, 2008 Mr. M. R. Blevins Executive Vice President
& Chief Nuclear Officer Luminant Generation Company LLC ATTN: Regulatory Affairs P. O. Box 1002 Glen Rose, TX 76043
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION, UNITS 1 AND 2 -
WITHDRAWAL OF LICENSE AMENDMENT REQUEST 06-009, REVISION TO TECHNICAL SPECIFICATION 3.8.1, AC SOURCES - OPERATING, EXTENSION OF COMPLETION TIMES FOR DIESEL GENERATORS (TAC NOS. MD4066 AND MD4067)
Dear Mr. Blevins:
By [[letter::CPSES-200700130, License Amendment Request (LAR)06-009, Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times for Diesel Generators|letter dated January 18, 2007]], as supplemented by letters dated November 15 and November 28, 2007, TXU Generation Company LP (subsequently renamed as Luminant Generation Company LLC, the licensee) applied for an amendment to the Comanche Peak Steam Electric Station, Units 1 and 2, Facility Operating License Nos. NPF-87 and NPF-89, respectively. The proposed change would have modified the facility technical specifications (TSs) pertaining to TS 3.8.1 to extend the 72-hour completion time for one inoperable diesel generator to 14 days, provided an alternate AC [alternating current] power source was available.
Subsequently, by [[letter::CP-200800183, Withdrawal of License Amendment Request (LAR)06-009, Revision to Technical Specification 3.8.1, AC Sources - Operating, Extension of Completion Times for Diesel Generators|letter dated January 30, 2008]], you withdrew the amendment request.
The Commission has filed the enclosed Notice of Withdrawal of Application for Amendment to Facility Operating Licenses with the Office of the Federal Register for publication.
Sincerely,
/RA/
Balwant K. Singal, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-445 and 50-446
Enclosure:
Notice of Withdrawal cc w/encl: See next page DISTRIBUTION:
PUBLIC LPLIV Reading RidsAcrsAcnw_MailCTR Resource RidsNrrDorlLpl4 Resource RidsNrrPMBSingal Resource RidsNrrLAJBurkhardt Resource RidsOgcRp Resource RidsRgn4MailCenter Resource ADAMS Accession No: ML081290462
- NLO w/comments OFFICE NRR/LPL4/PM NRR/LPL4/LA OGC NRR/LPL4/BC NAME BSingal JBurkhardt AHodgdon*
THiltz DATE 5/12/08 5/12/08 5/20/08 5/21/08 OFFICIAL AGENCY RECORD
Comanche Peak Steam Electric Station (10/2007) cc:
Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 2159 Glen Rose, TX 76403-2159 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011 Mr. Fred W. Madden, Director Regulatory Affairs Luminant Generation Company LLC P.O. Box 1002 Glen Rose, TX 76043 Timothy P. Matthews, Esq.
Morgan Lewis 1111 Pennsylvania Avenue, NW Washington, DC 20004 County Judge P.O. Box 851 Glen Rose, TX 76043 Environmental and Natural Resources Policy Director Office of the Governor P.O. Box 12428 Austin, TX 78711-3189 Mr. Richard A. Ratliff, Chief Bureau of Radiation Control Texas Department of Health 1100 West 49th Street Austin, TX 78756-3189 Mr. Brian Almon Public Utility Commission William B. Travis Building P.O. Box 13326 1701 North Congress Avenue Austin, TX 78701-3326 Ms. Susan M. Jablonski Office of Permitting, Remediation and Registration Texas Commission on Environmental Quality MC-122 P.O. Box 13087 Austin, TX 78711-3087 Anthony P. Jones Chief Boiler Inspector Texas Department of Licensing and Regulation Boiler Division E.O. Thompson State Office Building P.O. Box 12157 Austin, TX 78711
7590-01-P UNITED STATES NUCLEAR REGULATORY COMMISSION LUMINANT GENERATION COMPANY LLC DOCKET NOS. 50-445 AND 50-446 NOTICE OF WITHDRAWAL OF APPLICATION FOR AMENDMENT TO FACILITY OPERATING LICENSES The U.S. Nuclear Regulatory Commission (NRC, the Commission) has granted the request of Luminant Generation Company LLC (the licensee) to withdraw its January 18, 2007, application for an amendment to Facility Operating License Nos. NPF-87 and NPF-89 for the Comanche Peak Steam Electric Station, Units 1 and 2, located in Hood County, Texas.
The proposed amendment would have revised Technical Specification 3.8.1 to extend the 72-hour completion time for one inoperable diesel generator to 14 days, provided an alternate AC [alternating current] power source was available.
The Commission had previously issued a Notice of Consideration of Issuance of Amendment to Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing, published in the FEDERAL REGISTER on April 10, 2007 (72 FR 17952). However, by [[letter::CP-200800183, Withdrawal of License Amendment Request (LAR)06-009, Revision to Technical Specification 3.8.1, AC Sources - Operating, Extension of Completion Times for Diesel Generators|letter dated January 30, 2008]], the licensee withdrew the proposed change.
For further details with respect to this action, see the application for amendment dated January 18, 2007 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML070230493), and the licensee's [[letter::CP-200800183, Withdrawal of License Amendment Request (LAR)06-009, Revision to Technical Specification 3.8.1, AC Sources - Operating, Extension of Completion Times for Diesel Generators|letter dated January 30, 2008]] (ADAMS Accession No. ML080390310), which withdrew the application for license amendment.
Documents may be examined, and/or copied for a fee, at the NRC=s Public Document Room
(PDR), located at One White Flint North, Public File Area O1 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records are accessible electronically from the ADAMS Public Electronic Reading Room on the internet at the NRC Web site, http://www.nrc.gov/reading-rm.html. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS should contact the NRC PDR Reference staff by telephone at 1-800-397-4209, or 301-415-4737 or by email to pdr@nrc.gov.
Dated at Rockville, Maryland, this 21st day of May, 2008.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
Balwant K. Singal, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation