May 13, 2008 LICENSEE: Southern Nuclear Operating Company, Inc.
FACILITY: Vogtle Electric Generating Plant, Units 1 and 2
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON APRIL 17, 2008, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND SOUTHERN NUCLEAR OPERATING COMPANY, INC., CONCERNING REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory and representatives of Southern Nuclear Operating Company, Inc., held a telephone conference call on April 17, 2008, to discuss and clarify the staffs request for additional information (RAI) concerning the Vogtle Electric Generating Plant, Units 1 and 2, license renewal application. The telephone conference call was useful in clarifying the intent of the staffs RAIs. provides a listing of the participants. Enclosure 2 contains a summary of the discussions and a listing of the RAIs discussed with the applicant, including a brief description on the status of the items.
The applicant had an opportunity to comment on this summary.
/RA/
Donnie J. Ashley, Sr. Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-424 and 50-425
Enclosures:
As stated cc w/encls: See next page
ML081290027 OFFICE LA:DLR PM:RPB1:DLR BC:RPB1:DLR NAME IKing DAshley LLund DATE 5/ 9 /08 5/ 9 /08 5/ 13 /08
TELEPHONE CONFERENCE CALL VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS APRIL 17, 2008 PARTICIPANTS AFFILIATIONS Donnie Ashley U.S. Nuclear Regulatory Commission (NRC)
Edward Smith NRC Chalmer Myer Southern Nuclear Operating Company, Inc Louis Bohn SNOC ENCLOSURE 1
SUMMARY
OF TELEPHONE CONFERENCE VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION APRIL 17, 2008 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Southern Nuclear Operating Company, Inc., held a telephone conference call on April 17, 2008, to discuss and clarify the applicants responses to previous requests for additional information (RAI) concerning the Vogtle Electric Generating Plant (VEGP), Units 1 and 2, license renewal application (LRA).
These questions are focused on the scoping and screening section of the LRA.
In RAI 2.3.3.20-4, we requested that the applicant provide additional information explaining which tank vents on the LRA drawings do or do not have the tank vent screen component that is listed as item 36 in LRA Table 2.3.3.20. The applicants response stated that ...Since the vents for both tanks provide the same function, it is assumed that screen covers were installed on the diesel fuel day tank vents as well. We will accept this response by stating that there are screen vents on the diesel fuel day tanks - thereby committing the applicant to having an aging management review for them. If it turns out that there are no screens, then the applicant should advise us and we will modify the response.
In RAI 2.3.3.23-3, we requested that the applicant provide additional information to verify that the continuation of pipeline 097-2 from LRA drawings 1X4LD179-2 and 2X4LD179-2 had been made to the correct drawings and locations and to provide the drawings. The applicant stated that the pipeline continues to P&ID AX4DB124-2 and shows the point where the license renewal boundary ends at the Auxiliary Building to Radwaste Transfer Tunnel Boundary. The applicant further stated that 1X4LD179-2 and 2X4LD179-2 ...should have been revised to include the Auxiliary Building to Radwaste Transfer Tunnel Boundary for clarity. Since X4LD179-2 and 2X4LD179-2 were not revised to show the boundary and AX4DB124-2 was not provided for our review, we are unable to confirm that there are no new component types within the boundary for which the drawing was not provided. The applicant confirmed that there are no new component types within the boundary discussed.
In RAI2.3.4.4, we requested additional information justifying the boundary locations for line 153-10" at HV5103. The applicants response referred to 1302-153-10" and 1302-010-10".
There is some confusion regarding which line is being referred to. We can find no 1302-153-10". According to drawing 1(2)X4LD161-1, the line from HV5103 is 1305-153-10."
The applicant stated that 1302-153-10" was mislabeled and should have been 1305-153-10".
Enclosure 2
Letter to Southern Nuclear from D. Ashley, dated May 13, 2008 DISTRIBUTION:
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON APRIL 17, 2008, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND SOUTHERN NUCLEAR OPERATING COMPANY, INC., CONCERNING REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION HARD COPY:
DLR RF E-MAIL:
PUBLIC SSmith (srs3)
SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSrxb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter
DAshley JPLeous SLingam CJulian, RII GMcCoy, RII
Vogtle Electric Generating Plant, Units 1 and 2 cc:
Mr. Tom E. Tynan Mr. Laurence Bergen Vice President - Vogtle Oglethorpe Power Corporation Vogtle Electric Generating Plant 2100 East Exchange Place 7821 River Road P.O. Box 1349 Waynesboro, GA 30830 Tucker, GA 30085-1349 Mr. N. J. Stringfellow Arthur H. Domby, Esquire Manager, Licensing Troutman Sanders Southern Nuclear Operating Company, Inc. Nations Bank Plaza P.O. Box 1295 600 Peachtree Street, NE Birmingham, AL 35201-1295 Suite 5200 Atlanta, GA 30308-2216 Mr. Jeffrey T. Gasser Executive Vice President Resident Inspector Southern Nuclear Operating Company, Inc. Vogtle Plant P.O. Box 1295 8805 River Road Birmingham, AL 35201-1295 Waynesboro, GA 30830 Mr. Steven M. Jackson Office of the County Commissioner Senior Engineer - Power Supply Burke County Commission Municipal Electric Authority of Georgia Waynesboro, GA 30830 1470 Riveredge Parkway, NW Atlanta, GA 30328-4684 Mr. Stanford M. Blanton, Esq.
Balch & Bingham, LLP Mr. Reece McAlister P.O. Box 306 Executive Secretary Birmingham, AL 35201 Georgia Public Service Commission 244 Washington Street, SW Ms. Moanica M. Caston Atlanta, GA 30334 Vice President and General Counsel Southern Nuclear Operating Company, Inc.
Mr. Harold Reheis, Director 40 Inverness Center Parkway Department of Natural Resources P.O. Box 1295 205 Butler Street, SE, Suite 1252 Birmingham, AL 35201-1295 Atlanta, GA 30334 Chalmer R. Myer Attorney General Southern Nuclear Operating Company, Inc.
Law Department 40 Inverness Center Parkway 132 Judicial Building P.O. Box 1295 Atlanta, GA 30334 Birmingham, AL 35201-1295