UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II SAM NUNN ATLANTA FEDERAL CENTER 61 FORSYTH STREET, SW, SUITE 23T85 ATLANTA, GEORGIA 30303-8931 May 6, 2008 Mr. Robert J. Duncan, II Vice President Carolina Power & Light Company Shearon Harris Nuclear Power Plant P.O. Box 165, Mail Code: Zone 1 New Hill, NC 27562-0165
SUBJECT:
SHEARON HARRIS NUCLEAR PLANT - NOTIFICATION OF INSPECTION OF THE IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITIGATING STRATEGIES USING TEMPORARY INSTRUCTION 2515/171
Dear Mr. Duncan:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC) staff will conduct an inspection at Shearon Harris Nuclear Plant the week of June 2, 2008. The inspection team will be led by Rodney Fanner from the NRC Region II office. The team will be composed of the resident inspector, an NRR inspector/contractor, and the team leader. The inspection will be conducted in accordance with NRC Temporary Instruction 2515/171, Verification of Site Specific Implementation of B.5.b Phase 2 and 3 Mitigation Strategies.
In order for the NRC to adequately prepare for this inspection, please furnish the documents listed in Enclosure 1 to the NRC team lead, resident inspector, and NRR inspector (one copy each) at least two weeks prior to the planned on-site inspection.
Please have available on-site at the beginning of the inspection the documents listed in. Mike Wallace, of your staff, has been advised of this request and other inspection team support needs, including the names and addresses of the inspectors assigned to this inspection.
This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018, which expires on June 30, 2009.
CP&L 2
Your cooperation and support during this inspection will be appreciated. If you have any questions regarding this inspection, please contact Rodney Fanner at 404-562-4638, or me at 404-562-6326.
Sincerely,
/RA/
Steven J. Vias, Chief Technical Support Branch Division of Reactor Projects Docket No. 50-400 License No. NPF-63
Enclosures:
- 1.
Documentation Requested Prior to the Inspection
- 2.
Arrangements/Documents Requested to be Available Onsite During the Inspection Week
OFFICE RII:DRP RII:DRP SIGNATURE RJF2 JSV NAME RFanner SVias DATE 05/06/2008 05/06/2008 05/ /2008 05/ 2008 05/ /2008 05/ /2008 05/ /2008 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO YES NO
CP&L 3
cc w/encl:
Paul Fulford Manager Performance Evaluation and Regulatory Affairs PEB5 Carolina Power & Light Company Electronic Mail Distribution Chris L. Burton Director Site Operations Carolina Power & Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution J. Wayne Guganious Training Manager Harris Progress Energy Carolinas, Inc.
Electronic Mail Distribution Thomas J. Natale Manager Support Services Shearon Harris Nuclear Power Plant Electronic Mail Distribution David H. Corlett Supervisor Licensing/Regualtory Programs Carolina Power & Light Company Electronic Mail Distribution David T. Conley Associate General Counsel Legal Dept.
Progress Energy Service Company, LLC Electronic Mail Distribution John H. O'Neill, Jr.
Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washington, DC 20037-1128 Beverly Hall, Chief Radiation Protection Section N.C. Department of Environmental Commerce & Natural Resources Electronic Mail Distribution Public Service Commission State of South Carolina P.O. Box 11649 Columbia, SC 29211 Chairman North Carolina Utilities Commission Electronic Mail Distribution Robert P. Gruber Executive Director Public Staff - NCUC 4326 Mail Service Center Raleigh, NC 27699-4326 Herb Council Chair Board of County Commissioners of Wake County P.O. Box 550 Raleigh, NC 27602 Tommy Emerson Chair Board of County Commissioners of Chatham County 186 Emerson Road Siler City, NC 27344 Kelvin Henderson Plant General Manager Carolina Power and Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution Senior Resident Inspector Carolina Power and Light Company Shearon Harris Nuclear Power Plant U.S. NRC 5421 Shearon Harris Rd New Hill, NC 27562-9998
CP&L 4
Letter to Robert J. Duncan, II from Steven J. Vias dated May 06, 2008
SUBJECT:
SHEARON HARRIS NUCLEAR PLANT - NOTIFICATION OF INSPECTION OF THE IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITIGATING STRATEGIES USING TEMPORARY INSTRUCTION 2515/171 Distribution w/encl:
C. Evans, RII L. Slack, RII OE Mail RIDSNRRDIRS PUBLIC D. Nelson, NRR
DOCUMENTATION REQUESTED PRIOR TO THE INSPECTION Please provide the items below two weeks prior to the onsite inspection week. For any items below not supplied prior to the onsite inspection week, please have the item available at the start of the onsite inspection. Please provide as much as possible in electronic format. You are reminded to properly identify and handle all Official Use Only-Security-Related Information and/or Proprietary Information in accordance with current guidance.
- 1.
Copies of procedures/guidelines that were revised or generated to implement the mitigation strategies. These could be Extensive Damage Mitigation Guidelines (EDMGs), SAMGs, EOPs, AOPs, etc;
- 2.
A matrix that shows the correlation between the mitigation strategies identified in NEI 06-12 and the site-specific procedures or guidelines used to implement the strategy;
- 3.
Engineering evaluations/calculations that were used to verify engineering bases for the mitigation strategies;
- 4. Simplified flow diagrams for systems relied upon in the mitigation strategies; (These diagrams could be the type used for training.);
- 5. Simplified drawings/descriptions of modifications that were made to plant systems to implement the mitigation strategies; and
- 6. Electrical one line diagrams credited or revised to implement the mitigation strategies.
ARRANGEMENTS/DOCUMENTS REQUESTED TO BE AVAILABLE ONSITE DURING THE INSPECTION WEEK
- 1.
Provide a conference room to accommodate up to four (4) NRC staff. Preferably this would be outside the protected area.
- 2.
Site B.5.b contact person(s) should be available for the week.
- 3.
B.5.b engineering persons(s) should be on call for questions about any engineering calculations.
- 4.
Appropriate Operations staff should be available, as needed, for plant walkdowns throughout the week.
- 5.
Modification packages for any plant modifications performed as a result of B.5.b
- 6.
Detailed drawings (e.g., P&IDs) of systems used to implement mitigating strategies
- 7.
Copies of procedures/guidelines that were revised or generated to implement the mitigation strategies - these could be Extensive Damage Mitigation Guidelines (EDMGs), SAMGs, EOPs, AOPs, etc. This is the same as Item 1 to Enclosure 1, except that hard copies of these procedures/guidelines should be made available for each member of the inspection team.
- 8.
Copies of procedures used to inventory equipment used in the mitigation strategies (e.g., hoses, fittings, pumps, etc.).
- 9.
Training records/ training matrix/ lesson plans related to B.5.b
- 10.
Copies of Memoranda of Understanding (MOUs) with local fire departments or other emergency services that are required to implement any mitigating strategies
- 11.
Copies of any evaluations performed to document that enough equipment is available to implement the mitigating strategies (e.g., enough fire hose or electrical cable is available based on a plant walkdown or review of drawings)
- 12.
You are reminded to properly identify and handle all Official Use Only - Security-Related Information and/or Proprietary Information in accordance with current guidance.