May 5, 2008 LICENSEE:

Exelon Generation Company, LLC FACILITY:

Dresden Nuclear Power Station Units 2 and 3

SUBJECT:

SUMMARY

OF THE APRIL 30, 2008, PUBLIC MEETING TO DISCUSS THE 2007 DRESDEN NUCLEAR POWER STATION UNITS 2 AND 3 END-OF-CYCLE PERFORMANCE ASSESSMENT On April 30, 2008, the Nuclear Regulatory Commission (NRC) held a public meeting at the Grundy County Administration Building in Morris, Illinois. The meeting was between NRC Region III and Exelon Generation Company representatives to discuss the NRCs 2007 End-of-Cycle Assessment of the Dresden Nuclear Power Station Units 2 and 3 safety performance. The results of that assessment were discussed in a letter to the licensee dated March 3, 2008 (ADAMS ML080600255).

The NRC began the meeting with an overview of the NRC and the nuclear industry, the NRCs Reactor Oversight Process (ROP), and national ROP results. This was followed by a summary of the NRCs assessment of Dresden Nuclear Power Station Units 2 and 3 performance in 2007. The NRCs meeting presentation slides can be found in ADAMS at ML081220979. A list of principal meeting attendees can be found in the attached Enclosure.

The licensee then provided an oral response to the NRCs assessment. The licensee concurred with the NRC assessment that Dresden Nuclear Power Station Units 2 and 3 were operated in a manner that preserved the health and safety of the public and the environment.

At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials. Members of the public asked questions that covered how releases of tritium were monitored and tracked from the Dresden Nuclear Power Station, as well as underground pipe construction and clean up efforts from a contaminated spill from 2004 and 2006.

/RA/

Mark Ring, Chief Branch 1 Division of Reactor Projects Docket No. 50-237, 50-249,72-037 License No. DPR-19, DPR-25

Enclosure:

As stated DISTRIBUTION:

See next page

Memo to Exelon Generation Company, LLC from M. Ring dated May 5, 2008

SUBJECT:

SUMMARY

OF THE APRIL 30, 2008, PUBLIC MEETING TO DISCUSS THE 2007 DRESDEN NUCLEAR POWER STATION UNITS 2 AND 3 END-OF-CYCLE PERFORMANCE ASSESSMENT cc w/encl:

Site Vice President - Dresden Nuclear Power Station Plant Manager - Dresden Nuclear Power Station Regulatory Assurance Manager - Dresden Nuclear Power Station Chief Operating Officer and Senior Vice President Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden, and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency J. Klinger, State Liaison Officer Chairman, Illinois Commerce Commission Will County Executive Will County Sheriff Director, Will County Emergency Management Agency Mayor of Joliet City Manager of Joliet Kendall County Board Chairman Kendall County Sheriff Grundy County Board Chairman Grundy County Sheriff Grundy County Emergency Management Agency Mayor of Morris Minooka Village President Mayor of Coal City Mayor of Carbon Hill Mayor of Diamond Mayor of Braidwood Mayor of Wilmington Channahon Village President Channahon Village Administrator Mayor of Shorewood Shorewood Village Administrator Mayor of Elwood G. Mortensen, INPO

May 5, 2008 LICENSEE:

Exelon Generation Company, LLC FACILITY:

Dresden Nuclear Power Station Units 2 and 3

SUBJECT:

SUMMARY

OF THE APRIL 30, 2008, PUBLIC MEETING TO DISCUSS THE 2007 DRESDEN NUCLEAR POWER STATION UNITS 2 AND 3 END-OF-CYCLE PERFORMANCE ASSESSMENT On April 30, 2008, the Nuclear Regulatory Commission (NRC) held a public meeting at the Grundy County Administration Building in Morris, Illinois. The meeting was between NRC Region III and Exelon Generation Company representatives to discuss the NRCs 2007 End-of-Cycle Assessment of the Dresden Nuclear Power Station Units 2 and 3 safety performance. The results of that assessment were discussed in a letter to the licensee dated March 3, 2008 (ADAMS ML080600255).

The NRC began the meeting with an overview of the NRC and the nuclear industry, the NRCs Reactor Oversight Process (ROP), and national ROP results. This was followed by a summary of the NRCs assessment of Dresden Nuclear Power Station Units 2 and 3 performance in 2007. The NRCs meeting presentation slides can be found in ADAMS at ML081220979. A list of principal meeting attendees can be found in the attached Enclosure.

The licensee then provided an oral response to the NRCs assessment. The licensee concurred with the NRC assessment that Dresden Nuclear Power Station Units 2 and 3 were operated in a manner that preserved the health and safety of the public and the environment.

At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials. Members of the public asked questions that covered how releases of tritium were monitored and tracked from the Dresden Nuclear Power Station, as well as underground pipe construction and clean up efforts from a contaminated spill from 2004 and 2006.

/RA/

Mark Ring, Chief Branch 1 Division of Reactor Projects Docket No. 50-237, 50-249,72-037 License No. DPR-19, DPR-25

Enclosure:

As stated DISTRIBUTION:

See next page DOCUMENT NAME: G:\\DRES\\PUBLIC MEETINGS\\DRES

SUMMARY

LETTER 04-30-2008.DOC G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" =

Copy with attach/encl "N" = No copy OFFICE RIII N

RIII E

RIII RIII NAME BCushman:cms MRing DATE 5/2/08 5/5/08 OFFICIAL RECORD COPY

Memo to Exelon Generation Company, LLC from M. Ring dated May 5, 2008

SUBJECT:

SUMMARY

OF THE APRIL 30, 2008, PUBLIC MEETING TO DISCUSS THE 2007 DRESDEN NUCLEAR POWER STATION UNITS 2 AND 3 END-OF-CYCLE PERFORMANCE ASSESSMENT DISTRIBUTION:

TEB RAG1 CXG1 MMT RidsNrrDirslpab JLC1 MAS KGO JKH3 RML2 SRI Dresden DRPIII DRSIII PLB1 TXN

Enclosure PUBLIC MEETING PRINCIPAL ATTENDEES April 30, 2008 Exelon Generation Company, LLC David Wozniak, Site Vice President, Dresden Station Steve Tribuzzi, Public Affairs, Dresden Station Tim Hanley, Plant Manager, Dresden Station Bob Osgood, Public Affairs, Dresden Station James Ellis, Regulatory Assurance Manager, Dresden Station Marshall Murphy, Exelon Corporate Public Affairs Nuclear Regulatory Commission Mark Ring, Branch Chief, Division Reactor Projects Chuck Phillips, Senior Resident Inspector, Dresden Station Daniera Melendez-Colon, Resident Inspector, Dresden Station Steve Ray, Senior Resident Inspector, Braidwood Station Brian Cushman, Reactor Engineer, Division Reactor Projects Karen Gladden, Resident Inspector Office, Dresden Station Viktoria Miltyng, Regional Public Affairs Other Attendees Jim Lutz, Grundy County Emergency Management Agency Alwyn C. Settles, IEMA Joe Cosgrove, Citizen April Geastung, Citizen Frank Barber, Citizen Wanda Alderson, Citizen