May 2, 2008

Richard M. Rosenblum

Senior Vice President and

Chief Nuclear Officer

Southern California Edison Company

San Onofre Nuclear Generating Station

P.O. Box 128

San Clemente, CA 92674-0128

SUBJECT:

SAN ONOFRE NUCLEAR GENERATING STATION, UNITS 2 AND 3 -

NOTIFICATION OF NRC INITIAL OPERATOR LICENSING EXAMINATION

05000361/2008301; 05000362/2008301

Dear Mr. Rosenblum:

In a telephone conversation on April 23, 2008 between Messrs. Bill Arbor, Initial Operator

Training Supervisor and Steve Garchow, Chief Examiner, arrangements were made for the

administration of licensing examinations at San Onofre Nuclear Generating Station during the

weeks of September 22 and September 29, 2008.

As agreed during the telephone conversation, your staff will prepare the examinations based on

the guidelines in NUREG-1021, Operator Licensing Examination Standards for Power

Reactors, Revision 9, Supplement 1, and NUREG-1122, Knowledge and Abilities Catalog for

Nuclear Power Plant Operators, Revision 2, Supplement 1. The NRCs regional office will

discuss with your staff any changes that might be necessary before the examinations are

administered.

To meet the above schedule, it will be necessary for your staff to furnish the examination

outlines by July 6, 2008. The written examinations, operating tests, and supporting reference

materials identified in Attachment 3 to ES-201 will be due by August 5, 2008. Pursuant to

Title 10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an

authorized representative of the facility licensee shall approve the outlines, examinations, and

tests before they are submitted to the NRC for review and approval. All materials shall be

complete and ready-to-use. We request that any personal, proprietary, sensitive unclassified, or

safeguards information in your response be contained in a separate enclosure and appropriately

marked. Any delay in receiving the required examination and reference materials, or the

submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled.

In addition, your support for on-site validation of the examinations is required during the week of

August 25, 2008.

UNITED STATES

NUCLEAR REGULATORY COMMISSION

R E GI ON I V

612 EAST LAMAR BLVD, SUITE 400

ARLINGTON, TEXAS 76011-4125

Southern California Edison Company

- 2 -

In order to conduct the requested written examinations and operating tests, it will be necessary

for your staff to provide adequate space and accommodations in accordance with ES-402, and

to make the simulation facility available on the dates noted above. In accordance with ES-302,

your staff should retain the original simulator performance data (e.g., system pressures,

temperatures, and levels) generated during the dynamic operating tests until the examination

results are final.

Appendix E to NUREG-1021 contains a number of NRC policies and guidelines that will be in

effect while the written examinations and operating tests are being administered.

To permit timely NRC review and evaluation, your staff should submit preliminary reactor

operator and senior operator license applications (Office of Management and Budget (OMB)

approval number 3150-0090), medical certifications (OMB approval number 3150-0024), and

waiver requests (if any)(OMB approval number 3150-0090) at least 30 days before the first

examination date. If the applications are not received at least 30 days before the examination

date, a postponement may be necessary. Signed applications certifying that all training has

been completed should be submitted at least 14 days before the first examination date.

This letter contains information collections that are subject to the Paperwork Reduction

Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB,

under approval number 3150-0018, which expires on June 30, 2009. The public reporting

burden for this collection of information is estimated to average 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> per response, including

the time for reviewing instructions, gathering and maintaining the data needed, and completing

and reviewing the collection of information. Send comments on any aspect of this collection of

information, including suggestions for reducing the burden, to the Information and Records

Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington,

DC 20555-0001, or by Internet electronic mail to Margie.Janney@nrc.gov; and to the Desk

Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of

Management and Budget, Washington, DC 20503.

The NRC may neither conduct nor sponsor, and a person is not required to respond to, an

information collection, unless it displays a currently valid OMB control number.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosures will be available electronically for public inspection in the NRCs Public Document

Room or from the Publicly Available Records (PARS) component of the NRCs Agencywide

Documents Access and Management System (ADAMS). ADAMS is accessible from the

electronic Reading Room page of the NRCs public Web site at http://www.nrc.gov/reading-

rm/adams.html.

Southern California Edison Company

- 3 -

Thank you for your cooperation in this matter. Mr. Arbor has been advised of the policies and

guidelines referenced in this letter. If you have any questions regarding the NRCs examination

procedures and guidelines, please contact Mr. Mark Haire at (817-860-8117, or myself at

817-860-8159.

Sincerely,

/RA/

Ryan E. Lantz, Chief

Operations Branch

Division of Reactor Safety

Dockets: 50-361; 50-362

Licenses: NPF-10; NPF-15

DISTRIBUTION:

Mr. Ross T. Ridenoure

Vice President and Site Manager

Southern California Edison Company

San Onofre Nuclear Generating Station

P.O. Box 128

San Clemente, CA 92674-0128

Chairman, Board of Supervisors

County of San Diego

1600 Pacific Highway, Room 335

San Diego, CA 92101

Gary L. Nolff

Assistant Director-Resources

City of Riverside

3900 Main Street

Riverside, CA 92522

Mark L. Parsons

Deputy City Attorney

City of Riverside

3900 Main Street

Riverside, CA 92522

Dr. David Spath, Chief

Division of Drinking Water and

Environmental Management

California Department of Health Services

850 Marina Parkway, Bldg P, 2nd Floor

Richmond, CA 94804

Michael J. DeMarco

San Onofre Liaison

San Diego Gas & Electric Company

8315 Century Park Ct. CP21G

San Diego, CA 92123-1548

Director, Radiological Health Branch

State Department of Health Services

P.O. Box 997414 (MS 7610)

Sacramento, CA 95899-7414

Mayor

City of San Clemente

100 Avenida Presidio

San Clemente, CA 92672

James D. Boyd, Commissioner

California Energy Commission

1516 Ninth Street (MS 34)

Sacramento, CA 95814

Southern California Edison Company

- 3 -

Douglas K. Porter, Esq.

Southern California Edison Company

2244 Walnut Grove Avenue

Rosemead, CA 91770

A. Edward Scherer

Southern California Edison Company

San Onofre Nuclear Generating Station

P.O. Box 128

San Clemente, CA 92674-0128

Mr. Steve Hsu

Department of Health Services

Radiologic Health Branch

MS 7610, P.O. Box 997414

Sacramento, CA 95899-7414

Mr. James T. Reilly

Southern California Edison Company

San Onofre Nuclear Generating Station

P.O. Box 128

San Clemente, CA 92674-0128

Chief, Radiological Emergency

Preparedness Section

National Preparedness Directorate

Technological Hazards Division

Department of Homeland Security

1111 Broadway, Suite 1200

Oakland, CA 94607-4052

Southern California Edison Company

- 3 -

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov)

DRP Director (Dwight.Chamberlain@nrc.gov)

DRS Director (Roy.Caniano@nrc.gov)

DRS Deputy Director (Troy.Pruett@nrc.gov)

Senior Resident Inspector (Clyde.Osterholtz@nrc.gov)

Branch Chief, DRP/D (Michael.Hay@nrc.gov)

Senior Project Engineer, DRP/D (Greg.Werner@nrc.gov)

Senior Project Engineer, DRP/D (Geoff.Miller@nrc.gov)

Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

DRS STA (Dale.Powers@nrc.gov)

J. Adams, OEDO RIV Coordinator (John.Adams@nrc.gov)

ROPreports Resource

SO Site Secretary (Heather.Hutchinson@nrc.gov))

SUNSI Review Completed: __Y____ADAMS: 7 Yes

No Initials: __SMG____

7 Publicly Available Non-Publicly Available Sensitive 7 Non-Sensitive

SOE

C:OB

SMGarchow

RELantz

/RA/

/RA/

4/28/08

5/2/08

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax