MONTHYEARIR 05000373/20230042024-01-24024 January 2024 County Station - Integrated Inspection Report 05000373/2023004 and 05000374/2023004 ML24024A1332024-01-24024 January 2024 Confirmation of Initial License Examination IR 05000373/20230122024-01-18018 January 2024 County Station - Biennial Problem Identification and Resolution Inspection Report 05000373/2023012 and 05000374/2023012 ML23354A2902024-01-0505 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0028 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23360A6082023-12-27027 December 2023 County Station Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000373/2024010 and 05000374/2024010 ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums RS-23-120, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information IR 05000373/20230032023-11-0909 November 2023 County Station Integrated Inspection Report 05000373/2023003, 05000374/2023003, and 07200070/2023001 ML23286A2602023-11-0808 November 2023 Issuance of Amendment Nos. 260 and 245 to Renewed Facility Operating Licenses Relocation of Pressure and Temperature Limit Curves to the Pressure Temperature Report IR 05000373/20234012023-11-0707 November 2023 County Station Security Baseline Inspection Report 05000373/2023401 and 05000374/2023401 RS-23-103, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-13013 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans IR 05000374/20230102023-10-11011 October 2023 NRC Inspection Report 05000374/2023010 IR 05000373/20233012023-09-15015 September 2023 Errata to NRC Initial License Examination Report 05000373/2023301; 05000374/2023301 RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor ML23212A9012023-08-0303 August 2023 Regulatory Audit Report to Support the Review of the Amendments to Relocation of the Pressure Temperature Limit Curves to the Pressure and Temperature Limits Report IR 05000373/20230022023-08-0101 August 2023 County Station - Integrated Inspection Report 05000373/2023002 and 05000374/2023002 ML23208A3182023-07-27027 July 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI RS-23-084, Response to Request for Additional Information Regarding the Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis2023-07-24024 July 2023 Response to Request for Additional Information Regarding the Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis ML23192A5272023-07-12012 July 2023 NRC Initial License Examination Report 05000373/2023301; 05000374/2023301 ML23186A2062023-07-0606 July 2023 Information Request for a NRC Post-Approval Site Inspection for License Renewal 05000374/2023010 ML23181A1502023-06-30030 June 2023 Combined Response to Request for Additional Information and Supplemental Information in Support of LAR to Relocate Pressure and Temperature Limit Curves to the Pressure and Temperature Limits Report ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III IR 05000373/20230112023-06-26026 June 2023 County Station - Quadrennial Fire Protection Team Inspection Report 05000373/2023011 and 05000374/2023011 RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23167A0352023-06-16016 June 2023 Registration of Use of Cask to Store Spent Fuel ML23171A9562023-06-12012 June 2023 Post Exam Ltr RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling IR 05000373/20230012023-05-10010 May 2023 County Station - Integrated Inspection Report 05000373/2023001 and 05000374/2023001 ML23123A2202023-05-0303 May 2023 Relief Request I4R-14 for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection ML23118A3472023-05-0101 May 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Correction of Amendment No. 193 Adoption of TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration EPID L-2022-LLA-0143 ML23121A1612023-05-0101 May 2023 Information Meeting (Open House) with a Question-and-Answer Session to Discuss NRC 2022 End-of-Cycle Plant Performance Assessment of LaSalle County Station, Units 1 and 2 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23107A1822023-04-18018 April 2023 Operator Licensing Examination Approval Lasalle County Station, May 2023 RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23073A2182023-03-22022 March 2023 Issuance of Amendment No. 258 to Renewed Facility Operating Licenses Exigent Amendment to Revise Design Basis Related to Seismic Requirements RS-23-048, Exigent Amendment Request to Revise Design Basis Related to Seismic Requirements2023-03-0707 March 2023 Exigent Amendment Request to Revise Design Basis Related to Seismic Requirements ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 IR 05000373/20220062023-03-0101 March 2023 Annual Assessment Letter for LaSalle County Station, Units 1 and 2 (Report 05000373/2022006 and 05000374/2022006) RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-037, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for LaSalle County Station2023-02-22022 February 2023 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for LaSalle County Station ML23024A1372023-02-0303 February 2023 Request for Withholding Information from Public Disclosure for LaSalle County Station, Unit Nos. 1 and 2 ML23031A1972023-01-31031 January 2023 Notification of NRC Fire Protection Team Inspection Request for Information, Inspection Report Nos. 05000373/2023011 and 05000374/2023011 IR 05000373/20220042023-01-31031 January 2023 County Station - Integrated Inspection Report 05000373/2022004 and 05000374/2022004 RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 2024-01-05
[Table view] Category:Safety Evaluation
MONTHYEARML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23286A2602023-11-0808 November 2023 Issuance of Amendment Nos. 260 and 245 to Renewed Facility Operating Licenses Relocation of Pressure and Temperature Limit Curves to the Pressure Temperature Report ML23262B4442023-09-26026 September 2023 Authorization and Safety Evaluation for Alternative Request No. I4R-14 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration ML23073A2182023-03-22022 March 2023 Issuance of Amendment No. 258 to Renewed Facility Operating Licenses Exigent Amendment to Revise Design Basis Related to Seismic Requirements ML22341A2222022-12-28028 December 2022 Issuance of Amendment Nos. 257 and 243 to Renewed Facility Operating Licenses New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies and Changes to Core Operating Limits Report ML22293B8052022-11-30030 November 2022 Constellation Energy Generation, Llc_Fleet - Request to Authorize Use Honeywell Mururoa V4F1 R Supplied Air Suits ML22194A9152022-07-15015 July 2022 Proposed Alternative I4-R13 for Repair of Recirculation Flow Control Valves ML22090A0862022-04-29029 April 2022 Amendments to Adopt TSTF-541,Rev.2,Add Exceptions to Surveillance Requirements for Valves,Dampers Locked in Actuated Position ML22094A0012022-04-15015 April 2022 Constellation Energy Generation, LLC - Proposed Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles (Epids L-2021-LLR-0057 and L-2021-LLR-0058) ML21362A7212022-02-0404 February 2022 Issuance of Amendment Nos. 255 and 241 Revision to Technical Specifications to Incorporate Licensing Topical Report NEDE-33885P-A, Revision 1, GNF CRDA Application Methodology ML21347A0382022-01-13013 January 2022 Issuance of Amendments to Revise Reactor Coolant Leakage Requirements ML21307A3422021-12-0707 December 2021 Issuance of Amendments to Adopt Reactor Pressure Vessel Water Inventory Control Enhancements (EPIDs L-2020-LLA-0253 and L-2020-LLA-0254) ML21277A2482021-11-16016 November 2021 Letter with Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (Public Version) ML21280A0782021-10-27027 October 2021 Proposed Alternative to Use of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Case N-893 (Epids L-2020-LLR-0147 and L-2020-LLR-0148) ML21162A0692021-09-0707 September 2021 Issuance of Amendment Nos. Xxx and Yyy Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2 ML21230A2062021-09-0303 September 2021 Proposed Alternative to Use ASME OM Code Case OMN-28 ML21216A2202021-08-0505 August 2021 Proposed Alternative to Eliminate Certain Documentation Requirements for Pressure Retaining Bolting ML21188A0192021-07-28028 July 2021 Proposed Alternative I4R-12, Revision 2 from Code Surface Examinations Requirements of the ASME Code for Valves 2B33 F60A and 2B33 F60B Repairs ML21158A2282021-07-13013 July 2021 Issuance of Amendments to Renewed Facility Operating Licenses a License Amendment to Technical Specification 3.7.3, Ultimate Heat Sink ML21166A1682021-06-25025 June 2021 ML21082A4222021-05-27027 May 2021 Issuance of Amendment Nos. 249 and 235 to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML21033A5302021-04-0101 April 2021 Issuance of Amendments to Adopt Technical Specifications Task Force TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems ML21013A0052021-02-0404 February 2021 Issuance of Amendments to Adopt Technical Specifications Task Traveler TSTF-568, Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2 ML21028A6732021-02-0303 February 2021 Request to Use a Provision of Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI (EPID L-2020-LLR-011 ML20287A1302020-11-0505 November 2020 Review of Quality Assurance Program Changes ML20269A2002020-09-30030 September 2020 Request to Use a Provision of Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI (EPID L2020-LLR-0117 ML20153A8042020-07-31031 July 2020 Co. - Issuance of Amendments Revising Emergency Action RA3 ML20141L6362020-07-10010 July 2020 Issuance of Amendments Based on TSTF-427,Allowance for Nontechnical Specification Barrier Degradation on Supported System Operability,Rev 2 ML20134H9402020-07-0808 July 2020 Issuance of Amendments Revising the High Radiation Area Administrative Controls ML20113F0412020-04-30030 April 2020 Proposed Alternative to the Submittal Schedule for Certain Reports (COVID-19) ML20021A0702020-04-0606 April 2020 Issuance of Amendments to Delete License Conditions for Decommissioning Trusts ML19331A7252020-02-14014 February 2020 Issuance of Amendments Revising Emergency Action Levels ML20028E3992020-02-0404 February 2020 Proposed Alternative to Use ASME Code Case N-879 ML19269C5342019-09-27027 September 2019 Proposed Alternative to Use Encoded Phased Array Ultrasonic Examination Techniques ML19217A3062019-09-10010 September 2019 Relief Request RV-03, Relief from the Requirements of the ASME Code Related to Pressure Isolation Valve Testing Frequency ML19218A3652019-08-29029 August 2019 Safety Evaluation Regarding Implementation of Hardened Containment Vents Capable of Operation Under Severe Accident Conditions Related to Order EA-13-109 ML19176A0332019-08-28028 August 2019 Issuance of Amendments to Adopt TSTF-564, Safety Limit MCPR ML19192A2442019-07-18018 July 2019 Proposed Alternative to Use ASME Code Cases N-878 and N-880 ML19121A5052019-06-24024 June 2019 Issuance of Amendments to Renewed Facility Operating Licenses Removal of Operating Mode Restrictions for Performing Surveillance Testing of the Division 3 Battery and High Pressure Core Spray Diesel Generator ML19121A3172019-05-20020 May 2019 Relief Request 13R-15, Relief from the Requirements of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel (B&Pv) Code, Section X1, Rules for Inservice Inspection (EPID-L-2018-LLR-0123) ML19098A0342019-04-30030 April 2019 Units 1 and 2; Limerick, Units 1 and 2; Peach Bottom, Units 2 and 3, and Quad Cities, Units 1 and 2 - Revision to Approved Alternative to Use BWR Vessel and Internal Proj Guidelins ML19036A5862019-03-21021 March 2019 Issuance of Amendments to Revise the Emergency Response Organization Staffing Requirements ML19025A2882019-02-14014 February 2019 Issuance of Amendments to Renewed Facility Operating Licenses Revision of Technical Specifications to Adopt TSTF-334-A ML18304A3652019-01-16016 January 2019 2. Issuance of Amendments to Revise the Average Power Range Monitor Requirements ML18311A2652019-01-0202 January 2019 Issuance of Amendments Nos. 233 and 219 to Renewed Facility Operating Licenses License Amendment Request for Temporary Extensions to Technical Specifications ML18278A0302018-12-19019 December 2018 Issuance of Amendments 232, 218 to Renewed Facility Operating Licenses Request to Revise the Technical Specifications Surveillance Requirement to Revise the Lower Setpoint Tolerance for Safety/Relief Valves ML18254A3672018-10-29029 October 2018 County 1 & 2; and Quad Cities 1 & 2 - Issuance of Amendments 220, 259, 252, 231, 217, 271 and 266 to Revise Technical Specification Requirements for Inoperable Snubbers ML18226A2022018-10-15015 October 2018 Issuance of Amendments to Renewed Facility Operating Licenses Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control 2023-09-26
[Table view] |
Text
May 28, 2008 Mr. Charles G. Pardee Chief Nuclear Officer and Senior Vice President Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
LASALLE COUNTY STATION, UNITS 1 AND 2 - RELIEF REQUEST FOR I3R-11 FOR THE THIRD TEN-YEAR INSERVICE INSPECTION INTERVAL (TAC NOS. MD5469 AND MD5470)
Dear Mr. Pardee:
By letter to the Nuclear Regulatory Commission (NRC), dated April 30, 2007, as supplemented by letters dated July 20, 2007, and March 6, 2008, Exelon Generation Company LLC (the licensee), submitted inservice inspection (ISI) Relief Request (RR) I3R-11, Revision 1, for NRC approval at LaSalle County Station (LSCS), Units 1 and 2. Specifically, the licensee proposed an alternative to certain requirements in the American Society of Mechanical Engineers Boiler and Pressure Vessel Code for the system leakage test of the unit cross-tie piping of the hydrogen recombiner system for the third 10-year inspection interval for LSCS.
The NRC staff has completed its review of RR 13R-11 and is providing the attached safety evaluation (SE). The additional RRs contained in the licensees April 30, 2007, letter are not evaluated in the attached SE and are addressed, separately. Pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 50.55(a)(3)(ii), the licensees proposed alternative is acceptable on the basis that complying with the specified requirements results in hardship without a compensating increase in the level of quality and safety.
The LSCS third 10-year ISI interval started on October 1, 2007. The RR is authorized for the third 10-year interval, which will end September 30, 2017.
Sincerely,
/RA/
Russell Gibbs, Chief Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-373 and 50-374
Enclosure:
Safety Evaluation cc w/encls: See next page
Mr. Charles G. Pardee May 28, 2008 Chief Nuclear Officer and Senior Vice President Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
LASALLE COUNTY STATION, UNITS 1 AND 2 - RELIEF REQUEST FOR I3R-11 FOR THE THIRD TEN-YEAR INSERVICE INSPECTION INTERVAL (TAC NOS. MD5469 AND MD5470)
Dear Mr. Pardee:
By letter to the Nuclear Regulatory Commission (NRC), dated April 30, 2007, as supplemented by letters dated July 20, 2007, and March 6, 2008, Exelon Generation Company LLC (the licensee), submitted inservice inspection (ISI) Relief Request (RR) I3R-11, Revision 1, for NRC approval at LaSalle County Station (LSCS), Units 1 and 2. Specifically, the licensee proposed an alternative to certain requirements in the American Society of Mechanical Engineers Boiler and Pressure Vessel Code for the system leakage test of the unit cross-tie piping of the hydrogen recombiner system for the third 10-year inspection interval for LSCS.
The NRC staff has completed its review of RR 13R-11 and is providing the attached safety evaluation (SE). The additional RRs contained in the licensees April 30, 2007, letter are not evaluated in the attached SE and are addressed, separately. Pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 50.55(a)(3)(ii), the licensees proposed alternative is acceptable on the basis that complying with the specified requirements results in hardship without a compensating increase in the level of quality and safety.
The LSCS third 10-year ISI interval started on October 1, 2007. The RR is authorized for the third 10-year interval, which will end September 30, 2017.
Sincerely,
/RA/
Russell Gibbs, Chief Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-373, 50-374
Enclosure:
Safety Evaluation cc w/encls: See Next page DISTRIBUTION:
PUBLIC LPL3-2 R/F RidsNrrDorlLpl3-2 RidsRgn3MailCenter RidsNrrDciCnpb RidsNrrLAEWhitt RidsNrrPMSSands RidsNrrOd RidsAcrsAcnw&mMailCenter RidsOgcRp JAdams, EDO Region III Adams Accession No.: ML081190470 *SE Dated *NLO w/changes NRR-028 OFFICE LPL3-2/PM LPL3-2/LA DCI/CNPB OGC
- LPL3-2/BC NAME SSands EWhitt TChan* JBiggins RGibbs DATE 05 /8/08 05 /8/08 03 / 24 /08 05 / 2 /08 05 /28/08 OFFICIAL RECORD COPY
LaSalle County Station, Units 1 and 2 cc:
Corporate Distribution Exelon Generation Company, LLC Via e-mail LaSalle Distribution Exelon Generation Company, LLC Via e-mail LaSalle Resident Inspector U.S. Nuclear Regulatory Commission Via e-mail Phillip P. Steptoe, Esquire Sidley and Austin Via e-mail Assistant Attorney General Chicago, IL 60603 Via e-mail Chairman LaSalle County Board Via e-mail Attorney General Via e-mail Chairman Illinois Commerce Commission Via e-mail Illinois Emergency Management Agency Division of Disaster Assistance &
Preparedness Via e-mail Robert Cushing, Chief, Public Utilities Division Illinois Attorney General's Office 100 W. Randolph Street Chicago, IL 60601
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION INSERVICE INSPECTION RELIEF REQUEST I3R-11, REVISION 1 THIRD TEN-YEAR INSPECTION INTERVAL EXELON GENERATION COMPANY, LLC LASALLE COUNTY STATION, UNITS 1 AND 2 DOCKET NOS. 50-373 and 50-374
1.0 INTRODUCTION
By letter to the Nuclear Regulatory Commission (NRC, the Commission), dated April 30, 2007 (Agencywide Documents Management System (ADAMS), Accession No. ML071280395), as supplemented by letters dated July 20, 2007, and March 6, 2008 (ADAMS Accession Nos.
ML072080475 and ML080670036, respectively), Exelon Generation Company LLC (the licensee), submitted inservice inspection (ISI) Relief Request (RR) I3R-11, Revision 1, for NRC approval at LaSalle County Station, Units 1 and 2 (LSCS). Specifically, the licensee proposed an alternative to certain requirements in the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code) for the system leakage test of the unit cross-tie piping of the hydrogen recombiner system for the third 10-year inspection interval for LSCS.
Relief is requested for the third 10-year ISI interval for LSCS, which began on October 1, 2007 and concludes on September 30, 2017.
2.0 REGULATORY EVALUATION
As specified in Title 10 of the Code of Federal Regulations (10 CFR) Section 50.55a(g), ISI of nuclear power plant components shall be performed in accordance with the requirements of ASME Code,Section XI, except where specific written relief has been granted by the Commission pursuant to 10 CFR 50.55a(g)(6)(i). As stated in 10 CFR 50.55a(g)(5)(iii), if the licensee has determined that conformance with certain ASME Code requirements is impractical for its facility, the licensee shall notify the Commission and submit, as specified in 10 CFR 50.4, information to support the determinations. Pursuant to 10 CFR 50.55a(a)(3), alternatives to the requirements of paragraph (g) may be used, when authorized by the NRC, if (i) the proposed alternatives would provide an acceptable level of quality and safety, or (ii) compliance with the specified requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety The information provided by the licensee in support of its RR has been evaluated by the NRC staff, and the bases for disposition are documented below.
3.0 TECHNICAL EVALUATION
3.1 Components for Which Relief is Requested:
Reference:
IWC-2500, Table IWC-2500-1
- Examination Category: C-H
Description:
Hydrogen Recombiner System Piping
- Component Number: HG Unit Cross-Tie Piping
3.3 Applicable ASME Code Requirements Table IWC-2500-1, Examination Category C-H, Item Number C7.10, requires all Class 2 pressure retaining components be subject to a system leakage test with a VT-2 visual examination in accordance with IWC-5220. This pressure test is to be conducted once each inspection period.
IWC-5210(b)(2) requires the test procedure to include methods for detection and location of through-wall leakage from the components of the system tested when the pressurizing medium is gas.
3.4 Reason for Request Relief is requested from the system pressure test requirements of IWC-5221 and the periodicity requirements of Table IWC-2500-1, as well as the requirements of IWC-5210(b)(2) as applied to the cross-tie piping of the hydrogen recombiner system, as depicted on page 4 in Figure I3R-11.1 of the licensees July 20, 2007, submittal and as defined in the above component numbers. Air is used as the pressurizing medium for the hydrogen recombiner system because the system contains air during normal operation. The application of a leak detection solution (e.g., soap bubble solution) to the surface of the piping would be necessary per IWC-5210(b)(2) in order to allow for the detection and location of potential through-wall air leakage. To access the surface of the cross-tie piping, scaffolding is required because there are long runs of piping located approximately 30 feet overhead. An estimated 600 person-hours and accumulated dose of 1.25 rem (roentgen equivalent man) would be required to erect scaffolding and perform a leakage test of cross tie piping. Furthermore, a significant amount of scaffolding would have to be erected around several sensitive instrument racks and systems on both units that, if jarred, could result in a unit trip or other challenges to the operators.
Alternatively, LSCS will challenge the unit cross-tie piping to provide assurance of its structural integrity by performing pressure test at peak accident pressure and applying a soap bubble solution to all pipe welds once per Inspection Interval. Necessary scaffolding will be erected and leak detection solution will be applied to the surface of the unit cross-tie piping to the extent required by IWC-5210(b)(2) if through wall leakage is detected during pressure testing of accessible components and associated piping, which is performed once every inspection period, or if through wall leakage is detected during pressure testing unit cross tie piping welds.
The condition of the accessible components as determined by pressure testing of the accessible components once every inspection period in accordance with the Section XI rules would be indicative of that of the inaccessible components. Both the accessible and inaccessible components are designed/constructed to the same requirements and are subject to similar operating conditions. Additionally, the hydrogen recombiners, including the unit cross-tie piping, are functionally tested every refuel outage to verify system temperature, pressure, and flow requirements to further ensure system operability and structural integrity.
Based on the above discussion, reasonable assurance of the unit cross-tie piping structural integrity is achieved by the performance of the alternate pressure test of piping welds once every ISI interval.
3.5 Proposed Alternative and Basis for Use A pressure test will be performed on the unit cross-tie piping welds, at peak accident pressure, once each inspection interval.
Necessary scaffolding will be erected and leak detection solution will be applied to the surface of the unit cross-tie piping to the extent required by IWC-5210(b)(2) if:
- Through wall leakage is detected during pressure testing of accessible components and associated piping (once per inspection period.) (Remainder of system for which no relief is requested).
OR
- Through wall leakage is detected during pressure testing of unit cross-tie piping welds (once per inspection period).
3.6 Duration of Proposed Alternative Relief is requested for the third 10-year ISI interval LSCS, which began on October 1, 2007 and concludes on September 30, 2017.
4.0 EVALUATION The licensee requested relief from certain ASME Code requirements in performing the system pressure (leakage) test of the unit cross-tie piping, of the hydrogen recombiner system, at LSCS. In performing the system pressure test, air is used as the pressurizing medium and a soap solution will be applied on the piping surface (pressure boundary) for detection and location of leak. The subject RR consists of two parts, one of which pertains to a limited VT-2
examination of the cross-tie piping as the ASME Code requires that 100 percent of the pressure boundary surface be visually examined (VT-2) to detect and locate potential leakage. The relief from 100 percent VT-2 examination of the piping surface is needed because several hundred feet of cross-tie piping are located 30 feet overhead and are inaccessible for examination. To meet the ASME Code requirements, considerable amount of scaffolding is required to be erected in an area with high radiation level and surrounded by several sensitive instrument racks and systems. Therefore, the NRC staff concludes that the erecting of the scaffolding for performing a leakage examination over the entire cross-tie piping surface would impose undue hardship or unusual difficulties on the licensee.
The second part of the relief pertains to the frequency of the examination required by the ASME Code for this piping. The licensee proposed to perform the pressure test at peak accident pressure once per inspection interval and limit the inspection to all pipe welds with the application of soap solution, rather than performing the system pressure test once per inspection period as required by the ASME Code. The licensee will continue to perform a VT-2 visual examination of the accessible portion of this piping that need no scaffolding during each inspection period in accordance with the ASME Code. In addition, the boundary of the surface examination will be extended to cover the inaccessible portion of this piping as required by IWC-5210(b)(2) if through-wall leakage is detected during the system pressure testing of the accessible and inaccessible components and associated piping.
The NRC staff finds that the licensees proposed alternative provides reasonable assurance of structural integrity of the unit cross-tie piping. This is based on the following considerations:
(1) The accessible and inaccessible portions of the piping are made of identical material and size, and are exposed to similar service conditions in terms of stress and temperature.
Therefore, the examination of accessible piping would provide a reasonable indication regarding the condition of the inaccessible portion of the piping.
(2) The welds in a piping system are considered to be the weakest links in the piping system. Therefore, leakage at weld locations is more likely to occur than leakage in the piping base material. Hence, examinations of the piping welds after the system pressure test would provide reasonable assurance of the leak-tight integrity of the entire cross-tie piping.
(3) The pressure in the referenced piping system during most of the plant life is very low.
Furthermore, the piping contains ambient air and the potential for developing any environmentally-assisted cracking is expected to be negligible. Therefore, any gross rupture of the piping due to large undetected cracks is highly unlikely.
(4) The proposed system pressure test for this piping is going to be performed at the peak accident pressure (39.9 psig) which is more conservative than that required by the ASME Code (atmosphere pressure). Therefore, the results of the proposed system pressure test will provide reasonable assurance in demonstrating the structural integrity of the piping.
5.0 CONCLUSION
Based on the above review, the NRC staff concludes that the licensees RR I3R-11 is acceptable. This is based on the consideration that requiring the licensee to perform a Code-required examination would impose an undue hardship or unusual difficulty on the licensee without a compensating increase in the level of quality and safety. In addition, the licensees proposed alternative as discussed above will provide reasonable assurance in the maintenance of the structural integrity of the unit cross-tie piping. Therefore, pursuant to 10 CFR 50.55a(a)(3)(ii), the NRC staff authorizes the use of the proposed alternative for the third 10-year ISI interval of LSCS. All other ASME Code,Section XI, requirements for which relief was not specifically requested and authorized herein by the NRC staff remain applicable, including third party review by the Authorized Nuclear Inservice Inspector.
Principal Contributor: W. Koo, NRR Date: May 28, 2008