MONTHYEARL-PI-24-044, Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-10-21021 October 2024 Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program L-PI-24-040, Post-Submittal Package Letter2024-08-23023 August 2024 Post-Submittal Package Letter L-PI-24-036, – Preparation and Scheduling of Operator Licensing Examinations2024-06-28028 June 2024 – Preparation and Scheduling of Operator Licensing Examinations L-PI-24-031, Independent Spent Fuel Storage Installation, Supplement to License Amendment Request to Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2)2024-06-0505 June 2024 Independent Spent Fuel Storage Installation, Supplement to License Amendment Request to Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2) L-PI-24-014, License Amendment Request to Revise the Technical Specification Definition of Reactor Trip System (RTS) Response Time and Apply Response Time Testing to RTS Trip Functions with Time Delay Assumption2024-06-0303 June 2024 License Amendment Request to Revise the Technical Specification Definition of Reactor Trip System (RTS) Response Time and Apply Response Time Testing to RTS Trip Functions with Time Delay Assumption L-PI-24-030, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.12024-05-22022 May 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.1 L-PI-24-012, Independent Spent Fuel Storage Installation - License Amendment Request: Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2)2024-04-0202 April 2024 Independent Spent Fuel Storage Installation - License Amendment Request: Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2) L-PI-24-004, Independent Spent Fuel Storage Installation - Annual Effluent Report, January Through December 20232024-02-29029 February 2024 Independent Spent Fuel Storage Installation - Annual Effluent Report, January Through December 2023 L-PI-24-009, Response to Request for Additional Information Prairie Island Nuclear Generating Plant, Unit 2, Alternative RR-09 Safety Injection System and Volume Control System Category C Check Valve Quarterly Testing2024-02-13013 February 2024 Response to Request for Additional Information Prairie Island Nuclear Generating Plant, Unit 2, Alternative RR-09 Safety Injection System and Volume Control System Category C Check Valve Quarterly Testing L-PI-23-034, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.8, Cooling Water (Cl) System,2024-01-0202 January 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.8, Cooling Water (Cl) System, L-PI-23-035, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report2023-12-20020 December 2023 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report L-PI-23-033, Supplement to License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 32023-12-0505 December 2023 Supplement to License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 3 L-PI-23-027, Revision to 10 CFR 50.55a Requests Nos. 1-RR-5-10 and 2-RR-5-10, Proposed Alternative to Reactor Vessel Inservice Inspection (ISI) Intervals2023-10-0303 October 2023 Revision to 10 CFR 50.55a Requests Nos. 1-RR-5-10 and 2-RR-5-10, Proposed Alternative to Reactor Vessel Inservice Inspection (ISI) Intervals L-PI-23-025, License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 32023-09-28028 September 2023 License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 3 L-PI-23-023, Baffle Former Bolts Alternate Aging Management Strategy2023-09-11011 September 2023 Baffle Former Bolts Alternate Aging Management Strategy L-PI-23-018, License Amendment Request to Revise ISFSI Technical Specification 4.4 to Allow Use of a Code Alternative to ASME Code, NB-5130, Examination of Weld Edge Preparation Surfaces, for the TN-40HT2023-07-14014 July 2023 License Amendment Request to Revise ISFSI Technical Specification 4.4 to Allow Use of a Code Alternative to ASME Code, NB-5130, Examination of Weld Edge Preparation Surfaces, for the TN-40HT L-PI-23-006, License Amendment Request to Revise Technical Specification 3.7.8 Required Actions2023-06-22022 June 2023 License Amendment Request to Revise Technical Specification 3.7.8 Required Actions L-PI-23-016, 2022 10 CFR 50.46 LOCA Annual Report2023-06-14014 June 2023 2022 10 CFR 50.46 LOCA Annual Report L-PI-23-010, Annual Report of Individual Monitoring2023-04-27027 April 2023 Annual Report of Individual Monitoring L-PI-23-007, Supplement to Application to Revise Technical Specification Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)2023-03-28028 March 2023 Supplement to Application to Revise Technical Specification Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) L-PI-23-005, CFR 50.55a Requests Nos. 1-RR-5-15 and 2-RR-5-15, Proposed Use of Subsequent ASME Code Edition and Addenda in Accordance with 10 CFR 50.55a(g)(4)(iv)2023-03-0303 March 2023 CFR 50.55a Requests Nos. 1-RR-5-15 and 2-RR-5-15, Proposed Use of Subsequent ASME Code Edition and Addenda in Accordance with 10 CFR 50.55a(g)(4)(iv) L-PI-23-001, Day Steam Generator Tube Inspection Report2023-01-30030 January 2023 Day Steam Generator Tube Inspection Report L-PI-22-047, Resubmittal of Prairie Island Nuclear Generating Plant (PINGP) 2018 Unit 1 180-Day Steam Generator Tube Inspection Report2022-12-21021 December 2022 Resubmittal of Prairie Island Nuclear Generating Plant (PINGP) 2018 Unit 1 180-Day Steam Generator Tube Inspection Report L-PI-22-020, Application to Revise Technical Specification Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)2022-12-0202 December 2022 Application to Revise Technical Specification Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) L-PI-22-040, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2022-10-0606 October 2022 Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections L-PI-22-037, Updated Approach for Prairie Island Unit 1 and Unit 2 Baffle Former Bolts2022-09-20020 September 2022 Updated Approach for Prairie Island Unit 1 and Unit 2 Baffle Former Bolts L-PI-22-032, CFR 50.46 LOCA Annual Report2022-06-16016 June 2022 CFR 50.46 LOCA Annual Report L-PI-22-033, Response to Request for Additional Information Prairie Island Nuclear Generating Plant, Units 1 and 2, Amendment to Adopt 24-Month Operating Cycles2022-06-10010 June 2022 Response to Request for Additional Information Prairie Island Nuclear Generating Plant, Units 1 and 2, Amendment to Adopt 24-Month Operating Cycles L-PI-22-003, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2022-06-0707 June 2022 Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections L-PI-22-024, Supplement to Application for License Amendment to Implement 24-Month Operating Cycle2022-03-0707 March 2022 Supplement to Application for License Amendment to Implement 24-Month Operating Cycle L-PI-21-047, Response to Request for Additional Information 24-Month Cycle Amendment Prairie Island Nuclear Generating Plant, Units 1 and 22021-12-0707 December 2021 Response to Request for Additional Information 24-Month Cycle Amendment Prairie Island Nuclear Generating Plant, Units 1 and 2 L-PI-21-045, Response to Request for Additional Information Cooling Water System License Amendment Request2021-11-0404 November 2021 Response to Request for Additional Information Cooling Water System License Amendment Request L-PI-21-029, Exigent License Amendment Request to Revise Technical Specification 3.7.8 to Allow a One-Time Extension of the Completion Time of Required Action B.12021-10-0707 October 2021 Exigent License Amendment Request to Revise Technical Specification 3.7.8 to Allow a One-Time Extension of the Completion Time of Required Action B.1 L-PI-21-006, License Amendment Request to Revise Technical Specification 3.3.1, Reactor Trip System (RTS) Instrumentation, to Incorporate Installed Bypass Test Capability for the Power Range RTS Functions2021-10-0202 October 2021 License Amendment Request to Revise Technical Specification 3.3.1, Reactor Trip System (RTS) Instrumentation, to Incorporate Installed Bypass Test Capability for the Power Range RTS Functions L-PI-21-032, Response to Request for Additional Information Amendment Request to Adopt TSTF-471 and 571-T for Prairie Island2021-09-30030 September 2021 Response to Request for Additional Information Amendment Request to Adopt TSTF-471 and 571-T for Prairie Island L-PI-21-016, Application for License Amendment to Implement 24-Month Operating Cycle2021-08-0606 August 2021 Application for License Amendment to Implement 24-Month Operating Cycle L-PI-21-027, 2020 10 CFR 50.46 LOCA Annual Report2021-06-28028 June 2021 2020 10 CFR 50.46 LOCA Annual Report L-PI-21-023, Independent Spent Fuel Storage Installation - 2020 Annual Radiological Environmental Monitoring Program Report2021-05-14014 May 2021 Independent Spent Fuel Storage Installation - 2020 Annual Radiological Environmental Monitoring Program Report L-PI-21-007, Application to Revise Technical Specifications to Adopt TSTF-471, Eliminate Use of the Term Core Alterations in Actions and Notes2021-04-19019 April 2021 Application to Revise Technical Specifications to Adopt TSTF-471, Eliminate Use of the Term Core Alterations in Actions and Notes L-PI-20-050, Request for a One-Time Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Exercise Requirements, Due to COVID-19 Pandemic2020-10-0707 October 2020 Request for a One-Time Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Exercise Requirements, Due to COVID-19 Pandemic L-PI-20-051, Supplement to Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements2020-09-28028 September 2020 Supplement to Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements L-PI-20-026, Response to Request for Additional Information: License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiativ2020-09-0101 September 2020 Response to Request for Additional Information: License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 L-PI-20-028, 75 Day Letter2020-08-27027 August 2020 75 Day Letter L-PI-20-035, = Request for Revision to Reactor Vessel Material Surveillance Capsule Removal Schedule2020-07-28028 July 2020 = Request for Revision to Reactor Vessel Material Surveillance Capsule Removal Schedule L-PI-20-023, Independent Spent Fuel Storage Installation, Response to Request for Additional Information: License Amendment Request to Expand the Storage Capacity of the Independent Spent Fuel Storage Installation (ISFSI)2020-06-10010 June 2020 Independent Spent Fuel Storage Installation, Response to Request for Additional Information: License Amendment Request to Expand the Storage Capacity of the Independent Spent Fuel Storage Installation (ISFSI) L-PI-20-014, Supplement to License Amendment Request: Expand the Storage Capacity of the Independent Spent Fuel Storage Installation (ISFSI2020-04-29029 April 2020 Supplement to License Amendment Request: Expand the Storage Capacity of the Independent Spent Fuel Storage Installation (ISFSI L-PI-20-004, License Amendment Request to Revise Technical Specifications (TS) to Remove Note I from Limiting Condition for Operating (LCO) 3.4.12 and LCO 3.4.132020-03-30030 March 2020 License Amendment Request to Revise Technical Specifications (TS) to Remove Note I from Limiting Condition for Operating (LCO) 3.4.12 and LCO 3.4.13 L-PI-20-001, License Amendment Request to Address Issues Identified in Westinghouse Nuclear Safety Advisory Letter NSAL-09-5, Revision 1, and NSAL-15-12020-01-29029 January 2020 License Amendment Request to Address Issues Identified in Westinghouse Nuclear Safety Advisory Letter NSAL-09-5, Revision 1, and NSAL-15-1 L-PI-19-041, Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements2019-12-23023 December 2019 Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements L-PI-19-031, License Amendment Request: Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2019-12-16016 December 2019 License Amendment Request: Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b 2024-08-23
[Table view] Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50
MONTHYEARL-PI-24-044, Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-10-21021 October 2024 Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program L-PI-24-014, License Amendment Request to Revise the Technical Specification Definition of Reactor Trip System (RTS) Response Time and Apply Response Time Testing to RTS Trip Functions with Time Delay Assumption2024-06-0303 June 2024 License Amendment Request to Revise the Technical Specification Definition of Reactor Trip System (RTS) Response Time and Apply Response Time Testing to RTS Trip Functions with Time Delay Assumption ML24155A2222024-05-28028 May 2024 Methodology Evaluation Report for Elimination of Response Time Testing Prairie Island Reactor Trip System Rev. 1 ML23215A1672023-12-15015 December 2023 Acceptance of Requested Licensing Action Amendment Request to Revise Surveillance Requirement 3.8.1.2 Note 3 L-PI-23-025, License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 32023-09-28028 September 2023 License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 3 L-PI-23-006, License Amendment Request to Revise Technical Specification 3.7.8 Required Actions2023-06-22022 June 2023 License Amendment Request to Revise Technical Specification 3.7.8 Required Actions L-PI-23-007, Supplement to Application to Revise Technical Specification Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)2023-03-28028 March 2023 Supplement to Application to Revise Technical Specification Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) L-PI-22-040, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2022-10-0606 October 2022 Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections L-PI-22-003, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2022-06-0707 June 2022 Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections L-PI-22-024, Supplement to Application for License Amendment to Implement 24-Month Operating Cycle2022-03-0707 March 2022 Supplement to Application for License Amendment to Implement 24-Month Operating Cycle ML21320A2262021-11-15015 November 2021 License Amendment Request: Standard Emergency Plan and Consolidated Emergency Operations Facility for the Monticello Nuclear Generating Plant and the Prairie Island Nuclear Generating Plant L-PI-21-006, License Amendment Request to Revise Technical Specification 3.3.1, Reactor Trip System (RTS) Instrumentation, to Incorporate Installed Bypass Test Capability for the Power Range RTS Functions2021-10-0202 October 2021 License Amendment Request to Revise Technical Specification 3.3.1, Reactor Trip System (RTS) Instrumentation, to Incorporate Installed Bypass Test Capability for the Power Range RTS Functions L-PI-21-016, Application for License Amendment to Implement 24-Month Operating Cycle2021-08-0606 August 2021 Application for License Amendment to Implement 24-Month Operating Cycle L-PI-21-007, Application to Revise Technical Specifications to Adopt TSTF-471, Eliminate Use of the Term Core Alterations in Actions and Notes2021-04-19019 April 2021 Application to Revise Technical Specifications to Adopt TSTF-471, Eliminate Use of the Term Core Alterations in Actions and Notes L-PI-20-051, Supplement to Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements2020-09-28028 September 2020 Supplement to Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements L-PI-20-004, License Amendment Request to Revise Technical Specifications (TS) to Remove Note I from Limiting Condition for Operating (LCO) 3.4.12 and LCO 3.4.132020-03-30030 March 2020 License Amendment Request to Revise Technical Specifications (TS) to Remove Note I from Limiting Condition for Operating (LCO) 3.4.12 and LCO 3.4.13 ML20058F9432020-02-27027 February 2020 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - License Amendment Request: Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules Revision 4 L-PI-20-001, License Amendment Request to Address Issues Identified in Westinghouse Nuclear Safety Advisory Letter NSAL-09-5, Revision 1, and NSAL-15-12020-01-29029 January 2020 License Amendment Request to Address Issues Identified in Westinghouse Nuclear Safety Advisory Letter NSAL-09-5, Revision 1, and NSAL-15-1 L-PI-19-031, License Amendment Request: Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2019-12-16016 December 2019 License Amendment Request: Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b L-PI-19-040, License Amendment Request: Revise Technical Specification 5.5.14 to Permanently Extend Containment Leakage Rate Test Frequency2019-10-0707 October 2019 License Amendment Request: Revise Technical Specification 5.5.14 to Permanently Extend Containment Leakage Rate Test Frequency L-PI-19-006, Emergency License Amendment Request Regarding One-Time Extension for Technical Specification Completion Time Requirements2019-01-29029 January 2019 Emergency License Amendment Request Regarding One-Time Extension for Technical Specification Completion Time Requirements L-PI-18-064, License Amendment Request (LAR) to Revise Current Licensing Basis, Supplement 12018-12-0404 December 2018 License Amendment Request (LAR) to Revise Current Licensing Basis, Supplement 1 L-PI-18-014, License Amendment Request (LAR) to Revise Current Licensing Basis2018-10-0202 October 2018 License Amendment Request (LAR) to Revise Current Licensing Basis L-PI-18-031, License Amendment Request to Adopt TSTF-439, Revision 2, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an Lco.2018-06-26026 June 2018 License Amendment Request to Adopt TSTF-439, Revision 2, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an Lco. L-PI-18-005, License Amendment Request to Revise License Condition Associated with Implementation of NFPA 8052018-05-18018 May 2018 License Amendment Request to Revise License Condition Associated with Implementation of NFPA 805 ML17090A2012017-03-31031 March 2017 License Amendment Request to Revise Technical Specification for Plant/Unit Staff Qualifications Education and Experience Eligibility Requirements for Licensed Operators ML17094A5762017-03-29029 March 2017 License Amendment Request to Revise Emergency Action Level (EAL) Scheme ML17055C3592017-02-23023 February 2017 License Amendment Request: Revision to Emergency Plan Staff Augmentation Response Times L-PI-16-060, License Amendment Request to Revise Technical Specification 3.8.7 to Remove Non-Conservative Required Action2016-08-31031 August 2016 License Amendment Request to Revise Technical Specification 3.8.7 to Remove Non-Conservative Required Action L-PI-16-020, License Amendment Request Regarding One-Time Extension for Technical Specification Surveillance Requirement 3.8.4.3. DC Sources- Operating.2016-04-0707 April 2016 License Amendment Request Regarding One-Time Extension for Technical Specification Surveillance Requirement 3.8.4.3. DC Sources- Operating. L-PI-16-003, Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Revision 2, Using the Consolidated Line Item Improvement Process2016-01-25025 January 2016 Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Revision 2, Using the Consolidated Line Item Improvement Process ML15327A2282015-11-17017 November 2015 License Amendment Request for Spent Fuel Pool Criticality Technical Specification Changes L-PI-15-087, Enclosures 7 & 8: Modeling of Fuel Assemblies Containing Both Ifba and Gadolinia Absorber Rods with Westinghouse Core Design Code Systems and Affidavit2015-10-31031 October 2015 Enclosures 7 & 8: Modeling of Fuel Assemblies Containing Both Ifba and Gadolinia Absorber Rods with Westinghouse Core Design Code Systems and Affidavit L-PI-15-030, Application to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process2015-06-29029 June 2015 Application to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process L-PI-14-034, License Amendment Request (LAR) to Revise Technical Specification (TS) 3.3.3, Event Monitoring (EM) Instrumentation, and Additional Conditions Related to Alternative Source Term License Amendment Implementation2014-12-11011 December 2014 License Amendment Request (LAR) to Revise Technical Specification (TS) 3.3.3, Event Monitoring (EM) Instrumentation, and Additional Conditions Related to Alternative Source Term License Amendment Implementation L-PI-14-072, License Amendment Request (LAR) to Revise the Licensing Basis Analysis for a Waste Gas Decay Tank Rupture2014-08-21021 August 2014 License Amendment Request (LAR) to Revise the Licensing Basis Analysis for a Waste Gas Decay Tank Rupture L-PI-14-037, License Amendment Request (LAR) to Revise Technical Specification (TS) 3.8.1, AC Sources- Operating, Emergency Diesel Generator Voltage and Frequency Limits2014-06-0909 June 2014 License Amendment Request (LAR) to Revise Technical Specification (TS) 3.8.1, AC Sources- Operating, Emergency Diesel Generator Voltage and Frequency Limits ML14126A7272014-05-0505 May 2014 Supplement to License Amendment Request (LAR) for Cyber Security Plan Implementation Date Extension L-PI-13-102, License Amendment Request (LAR) to Revise Staff Augmentation Times in the Prairie Island Nuclear Generating Plant (PINGP) Emergency Plan2013-12-20020 December 2013 License Amendment Request (LAR) to Revise Staff Augmentation Times in the Prairie Island Nuclear Generating Plant (PINGP) Emergency Plan ML13333B6742013-11-27027 November 2013 License Amendment Request (LAR) for Northern States Power Company, Minnesota (NSPM) Cyber Security Plan Implementation Date Extension L-PI-13-076, Supplement to License Amendment Request for Exception to Technical Specification 5.5.14 Testing Requirements Associated with Steam Generator Replacement2013-07-25025 July 2013 Supplement to License Amendment Request for Exception to Technical Specification 5.5.14 Testing Requirements Associated with Steam Generator Replacement L-PI-13-071, Supplement to License Amendment Request (LAR) to Revise Emergency Plan (EP) Emergency Action Levels (Eals): RA 1.2 and Fuel Clad Barrier Loss Criteria2013-07-23023 July 2013 Supplement to License Amendment Request (LAR) to Revise Emergency Plan (EP) Emergency Action Levels (Eals): RA 1.2 and Fuel Clad Barrier Loss Criteria L-PI-13-030, License Amendment Request (LAR) to Add a Methodology to Technical Specification (TS) 5.6.5, Core Operating Limits Report (Colr).2013-05-23023 May 2013 License Amendment Request (LAR) to Add a Methodology to Technical Specification (TS) 5.6.5, Core Operating Limits Report (Colr). L-PI-13-017, License Amendment Request (LAR) to Revise Technical Specification (TS) 3.5.3, ECCS (Emergency Core Cooling System) - Shutdown2013-02-20020 February 2013 License Amendment Request (LAR) to Revise Technical Specification (TS) 3.5.3, ECCS (Emergency Core Cooling System) - Shutdown L-PI-12-110, License Amendment Request (LAR) to Revise Emergency Plan (EP) Emergency Action Levels (Eals): RA1.2 and Fuel Clad Barrier Loss Criteria2012-12-13013 December 2012 License Amendment Request (LAR) to Revise Emergency Plan (EP) Emergency Action Levels (Eals): RA1.2 and Fuel Clad Barrier Loss Criteria ML12278A4052012-09-28028 September 2012 Prairie Island, Units 1 and 2, License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactors L-PI-12-054, Application to Revise Technical Specifications Associated with Steam Generator Replacement and Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection2012-07-25025 July 2012 Application to Revise Technical Specifications Associated with Steam Generator Replacement and Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection L-PI-12-055, License Amendment Request for Exception to Technical Specification 5.5.14 Testing Requirements Associated with Steam Generator Replacement2012-07-25025 July 2012 License Amendment Request for Exception to Technical Specification 5.5.14 Testing Requirements Associated with Steam Generator Replacement L-PI-12-028, License Amendment Request (LAR) to Revise Technical Specification (TS) 3.8.1, AC Sources - Operating Emergency Diesel Generator Voltage Limits2012-05-15015 May 2012 License Amendment Request (LAR) to Revise Technical Specification (TS) 3.8.1, AC Sources - Operating Emergency Diesel Generator Voltage Limits L-PI-11-037, License Amendment Request to Add Diesel Fuel Oil License Bases and Revise Technical Specifications 3.7.8 Re Cooling Water System & 3.8.3 Re Diesel Fuel Oil2011-08-11011 August 2011 License Amendment Request to Add Diesel Fuel Oil License Bases and Revise Technical Specifications 3.7.8 Re Cooling Water System & 3.8.3 Re Diesel Fuel Oil 2024-06-03
[Table view] |
Text
NMC CommittedtoNuclearExcelle Prairie Island Nuclear Generating Plant Operated by Nuclear Management Company, LLC CL April 11,2008 L-PI-08-024 10 CFR Part 54 U S Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Prairie Island Nuclear Generating Plant Units 1 and 2 Dockets 50-282 and 50-306 License Nos. DPR-42 and DPR-60 Application for Renewed Operating Licenses Pursuant to U. S. Nuclear Regulatory Commission (NRC) regulations 10 CFR Parts 50, 51 and 54, the Nuclear Management Company, LLC (NMC) hereby applies for renewal of Facility Operating License Number DPR-42 for the Prairie Island Nuclear Generating Plant (PINGP) Unit 1, and Facility Operating License Number DPR-60 for PINGP Unit 2.
The current Facility Operating Licenses for PINGP Unit 1 and Unit 2 expire at midnight, August 9, 2013, and October 29, 2014, respectively. By this application, NMC requests that both PINGP Facility Operating Licenses be extended for 20 years beyond their current expiration dates to midnight, August 9, 2033 for Unit 1 and October 29, 2034 for Unit 2.
The enclosed Application for Renewed Operating Licenses is submitted in accordance with the applicable requirements of 10 CFR Part 54, Sections 54.17, 54.19, 54.21, 54.22 and 54.23. This application meets the timeliness requirements of 10 CFR 2.109(b) and 10 CFR 54.17(c) and provides the administrative, technical, and environmental information sufficient to support the NRC findings required by 10 CFR 54.29. In accordance with the requirements of 10 CFR 54.21, measures are described which provide assurance that the effects of aging will be adequately managed, consistent with the current licensing basis, for the requested period of extended operation. In some cases, new aging management programs or enhancements to existing programs are described.
Accompanying this application, in accordance with 10 CFR 54.23 and 10 CFR 51, is the Applicant's Environmental Report (ER). During the performance of the environmental review, no new and significant information was identified that would either invalidate NRC Category 1 findings in NUREG-1437 or identify any new issues requiring evaluation. A review of the applicable Category 2 issues determined that the impacts of PINGP license renewal will be small.
1717 Wakonade Drive East 9 Welch, Minnesota 55089-9642 Telephone: 651.388.1121 4133 MJ1e
Document Control Desk Page 2 Changes to the current licensing basis that are made subsequent to this application, and which have a material effect on the content of this application, will be identified in amendments to this document in accordance with 10 CFR 54.21(b). Such amendments will be submitted annually while the application is under NRC review, and at least three months prior to the scheduled completion of the NRC review.
By separate correspondence NMC plans to request NRC approval of the transfer of operating authority for the Prairie Island Units 1 and 2 from NMC to the owner of the plant, Northern States Power Company (NSP). If approved, that transfer of operating authority will not have any material effect on the attached License Renewal Application.
Because NSP is currently the owner-licensee, corporate information on NSP, including its directors and principal officers, is already included in Section 1 of the License Renewal Application. provides a Compact Disc (CD) containing the LRA and ER as Adobe PDF files, formatted in a manner that is consistent with "Guidance for Electronic Submissions to the Commission," Revision 3. This CD contains files suitable for entry into the NRC's record retrieval system, ADAMS. provides the list of preliminary regulatory commitments made in this application. As discussed in Enclosure 2, these commitments reflect the contents of the LRA as submitted, but are considered preliminary in that the specific wording of some commitments may change, and additional commitments may be added, during the NRC review. Any other actions discussed in the LRA should be considered intended or planned actions. These other actions are included for informational purposes but are not considered regulatory commitments.
If there are any questions or if additional information is needed, please contact Mr. Eugene Eckholt, License Renewal Project Manager, at 651-388-1121, extension 4137.
Summary of Commitments This letter includes 35 preliminary commitments. The final commitments, as confirmed by the NRC in the Safety Evaluation Report for the renewed operating licenses, will become effective upon NRC issuance of the renewed operating licenses.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on April 11, 2008.
Michael D. Wadley Site Vice President, Prairie Island Nuclear Generating Plant Units 1 and 2 Nuclear Management Company, LLC
Document Control Desk Page 3
Enclosures:
- 1. One (1) Compact Disc of the PINGP License Renewal Application, including the Environmental Report, containing the following files:
001 Prairie Island LRA.pdf (19,946,342 bytes, publicly available) 002 Prairie Island ER (TOC-2).pdf (34,205,057 bytes, publicly available) 003 Prairie Island ER (Chap 3-9).pdf (12,594,926. bytes, publicly available) 004 Prairie Island ER (Attach A-F).pdf (29,395,523 bytes, publicly available)
- 2. Preliminary License Renewal Commitments cc: Mayor, City of Red Wing President of the Prairie Island Indian Community Tribal Council Minnesota Department of Commerce Administrator, Region III, USNRC License Renewal Project Manager, Prairie Island, USNRC Operating Reactor Licensing Project Manager, Prairie Island, USNRC Resident Inspector, Prairie Island, USNRC
Document Control Desk L-PI-08-024 Enclosure 1 Prairie Island Nuclear Generating Plant License Renewal Application Compact Disk
Document Control Desk L-PI-08-024 Enclosure 2 Preliminary License Renewal Commitments The following table provides the list of preliminary commitments included in the Application for Renewed Operating Licenses (LRA) for Prairie Island Nuclear Generating Plant (PINGP) Units 1 and 2. These commitments reflect the contents of the LRA as submitted, but are considered preliminary in that the specific wording of some commitments may change, and additional commitments may be made, during the NRC review of the LRA.
The final commitments as submitted by NMC, and accepted by NRC, are expected to be confirmed in the NRC's Safety Evaluation Report (SER) for the renewed operating licenses. The final commitments, as confirmed in the SER, will become effective upon NRC issuance of the renewed operating licenses. In addition, as stated in the LRA, the final commitments will be incorporated into the Updated Safety Analysis Report (USAR).
Commitment Commitment Implementation Related LRA Number Schedule Section Number 1 Each year, following the submittal of the PINGP License 12 months after 1.4 Renewal Application and at least three months before the LRA submittal scheduled completion of the NRC review, NMC will submit date and at least amendments to the PINGP application pursuant to 10 CFR 3 months before 54.21(b). These revisions will identify any changes to the completion of Current Licensing Basis that materially affect the contents of the NRC review License Renewal Application, including the USAR supplements.
2 Following the issuance of the renewed operating license, the First USAR A1.0 summary descriptions of aging management programs and update in TLAAs provided in Appendix A, and the final list of License accordance with Renewal commitments, will be incorporated into the PINGP 10 CFR 50.71(e)
USAR as part of a periodic USAR update in accordance with 10 following CFR 50.71(e). Other changes to specific sections of the PINGP issuance of USAR necessary to reflect a renewed operating license will also renewed be addressed at that time. operating licenses 1 of 15
Document Control Desk L-PI-08-024 Enclosure 2 Preliminary License Renewal Commitments Commitment Commitment Implementation Related LRA Number Schedule Section Number 3 An Aboveground Steel Tanks Program will be implemented. U1 - 8/9/2013 B2.1.2 Program features will be as described in LRA Section B2.1.2. U2 - 10/29/2014 4 Procedures for the conduct of inspections in the External U1 - 8/9/2013 B2.1.6 Surfaces Monitoring Program, Structures Monitoring Program, U2 - 10/29/2014 Buried Piping and Tanks Inspection Program, and the RG 1.127 Inspection of Water-Control Structures Associated with Nuclear Power Plants Program will be enhanced to include guidance for visual inspections of installed bolting.
5 A Buried Piping and Tanks Inspection Program will be U1 - 8/9/2013 B2.1.8 implemented. Program features will be as described in LRA U2 - 10/29/2014 Section B2.1.8.
6 The Closed-Cycle Cooling Water System Program will be U1 - 8/9/2013 B2.1.9 enhanced to include an internal visual examination of U2 - 10/29/2014 accessible surfaces of components serviced by closed-cycle cooling water when the systems or components are opened during scheduled maintenance or surveillance activities.
7 The Compressed Air Monitoring Program will be enhanced to U1 - 8/9/2013 B2.1.10 require that Station and Instrument Air System air quality be U2 - 10/29/2014 monitored and maintained in accordance with the instrument air quality guidance provided in ISA S7.0.01-1996. Particulate testing will be revised to use a particle size methodology as specified in ISA S7.0.01.
2 of 15
Document Control Desk L-PI-08-024 Enclosure 2 Preliminary License Renewal Commitments Commitment Commitment Implementation Related LRA Number Schedule Section Number 8 An Electrical Cable Connections Not Subject to 10 CFR 50.49 Ul - 8/9/2013 B2.1.11 Environmental Qualification Requirements Program will be U2 - 10/29/2014 completed. Program features will be as described in LRA Section B2.1.11.
9 An Electrical Cables and Connections Not Subject to 10 CFR U1 - 8/9/2013 B2.1.12 50.49 Environmental Qualification Requirements Program will U2 - 10/29/2014 be implemented. Program features will be as described in LRA Section B2.1.12.
10 An Electrical Cables and Connections Not Subject to 10 CFR Ul - 8/9/2013 B2.1.13 50.49 Environmental Qualification Requirements Used in Instrumentation Circuits Program will be implemented. Program features will be as described in LRA Section B2.1.13.
11 The External Surfaces Monitoring Program will be enhanced as UI - 8/9/2013 B2.1.14 follows: U2 - 10/29/2014
- The scope of the program will be expanded as necessary to include all metallic and non-metallic components within the scope of license renewal that require aging management in accordance with this program.
" The program will ensure that surfaces that are inaccessible or not readily visible during plant operations will be inspected during refueling outages.
- The program will ensure that surfaces that are inaccessible or not readily visible during both plant operations and refueling outages will be inspected at 3 of 15
Document Control Desk L-PI-08-024 Enclosure 2 Preliminary License Renewal Commitments Commitment Commitment Implementation Related LRA Number Schedule Section Number intervals that provide reasonable assurance that aging effects are managed such that the applicable components will perform their intended function during the period of extended operation.
12 The Fire Protection Program will be enhanced as follows: U1 - 8/9/2013 B2.1.15
" The program will require functional testing of the halon U2 - 10/29/2014 system smoke detectors in the guardhouse every five years.
" The program will require periodic visual inspection of the fire barrier walls, ceilings, and floors to be performed during walkdowns at least once every refueling cycle.
13 The Fire Water System Program will be enhanced as follows: U1 - 8/9/2013 B2.1.16 U2 10/29/2014
" The program will be expanded to include eight additional -
yard fire hydrants in the scope of the annual visual inspection and flushing activities.
" The program will require that sprinkler heads that have been in place for 50 years will be replaced or a representative sample of sprinkler heads will be tested using the guidance of NFPA 25, "Inspection, Testing and Maintenance of Water-Based Fire Protection Systems" (2002 Edition, Section 5.3.1.1.1). Sample testing, if performed, will continue at a 10-year interval following the initial testing.
4 of 15
Document Control Desk L-PI-08-024 Enclosure 2 Preliminary License Renewal Commitments Commitment Commitment Implementation Related LRA Number Schedule Section Number 14 The Flux Thimble Tube Inspection Program will be enhanced as Ul - 8/9/2013 B2.1.18 follows: U2 - 10/29/2014
" The program will require that the interval between inspections be established such that no flux thimble tube is predicted to incur wear that exceeds the established acceptance criteria before the next inspection.
" The program will require that re-baselining of the examination frequency be justified using plant-specific wear rate data unless prior plant-specific NRC acceptance for the re-baselining was received. If design changes are made to use more wear-resistant thimble tube materials, sufficient inspections will be conducted at an adequate inspection frequency for the new materials.
- The program will require that flux thimble tubes that cannot be inspected must be removed from service.
15 The Fuel Oil Chemistry Program will be enhanced as follows: U1 - 8/9/2013 B2.1.19
" Particulate contamination testing of fuel oil in the eleven U2 - 10/29/2014 fuel oil storage tanks in scope of License Renewal will be performed, in accordance with ASTM D 6217, on an annual basis.
- One-time ultrasonic thickness measurements will be performed at selected tank bottom and piping locations prior to the period of extended operation.
5 of 15
Document Control Desk L-PI-08-024 Enclosure 2 Preliminary License Renewal Commitments Commitment Commitment Implementation Related LRA Number Schedule Section Number 16 A Fuse Holders Program will be implemented. Program features Ul - 8/9/2013 B2.1.20 will be as described in LRA Section B2.1.20. U2 - 10/29/2014 17 An Inaccessible Medium Voltage Cables Not Subject to 10 CFR Ul - 8/9/2013 B2.1.21 50.49 Environmental Qualification Requirements Program will U2 - 10/29/2014 be implemented. Program features will be as described in LRA Section B2.1.21 18 An Inspection of Internal Surfaces in Miscellaneous Piping and U1 - 8/9/2013 B2.1.22 Ducting Components Program will be implemented. Program U2 - 10/29/2014 features will be as described in LRA section B2.1.22.
19 The Inspection of Overhead Heavy Load and Light Load U1 - 8/9/2013 B2.1.23 (Related to Refueling) Handling Systems Program will be U2 - 10/29/2014 enhanced as follows:
- Program implementing procedures will be revised to ensure the components and structures subject to inspection are clearly identified.
- Program inspection procedures will be enhanced to include the parameters corrosion and wear where omitted.
20 A Metal-Enclosed Bus Program will be implemented. Program U1 - 8/9/2013 B2.1.26 features will be as described in LRA Section B2.1.26. U2 - 10/29/2014 21 For the Nickel-Alloy Nozzles and Penetrations Program, PINGP U1 - 8/9/2013 B2.1.27 commits to the following activities for managing the aging of 6 of 15
Document Control Desk L-PI-08-024 Enclosure 2 Preliminary License Renewal Commitments Commitment Commitment Implementation Related LRA Number Schedule Section Number nickel-alloy components susceptible to primary water stress U2 - 10/29/2014 corrosion cracking:
" Comply with applicable NRC orders, and
" Implement applicable NRC Bulletins, Generic Letters, and staff-accepted industry guidelines.
22 The Nickel-Alloy Penetration Nozzles Welded to the Upper Ul - 8/9/2013 B2.1.28 Reactor Vessel Closure Heads of Pressurized Water Reactors U2 - 10/29/2014 Program will be enhanced as follows:
- The program will require that any deviations from implementing the appropriate required inspectioh methods of the NRC First Revised Order EA-03-009, "Issue of Order Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors," dated February 20, 2004 (Order), as amended, will be submitted for NRC review and approval in accordance with the Order, as amended.
" The program will require that any deviations from implementing the required inspection frequencies mandated by the Order, as amended, will be submitted for NRC review and approval in accordance with the Order, as amended.
" The program will require that relevant flaw indications detected during the augmented inspections of the upper vessel head penetration nozzles will be evaluated in 7 of 15
Document Control Desk L-PI-08-024 Enclosure 2 Preliminary License Renewal Commitments Commitment Commitment Implementation Related LRA Number Schedule Section Number accordance with the criteria provided in the letter from Mr. Richard Barrett, NRC, Office of Nuclear Reactor Regulation (NRR), Division of Engineering to Alex Marion, Nuclear Energy Institute (NEI), dated April 11, 2003, or in accordance with NRC-approved Code Cases that incorporate the flaw evaluation procedures and criteria of the NRC's April 11, 2003, letter to NEI.
The program will require that, if leakage or evidence of cracking in the vessel head penetration nozzles (including associated J-groove welds) is detected while ranked in the "Low," "Moderate," or "Replaced" susceptibility category, the nozzles are to be immediately reclassified to the "High" susceptibility category and the required augmented inspections for the "High" susceptibility category are to be implemented during the same outage the leakage or cracking is detected.
23 A One-Time Inspection Program will be completed. Program U1 - 8/9/2013 B2.1.29 features will be as described in LRA Section B2.1.29. U2 - 10/29/2014 24 A One-Time Inspection of ASME Code Class 1 Small-Bore U1 - 8/9/2013 B2.1.30 Piping Program will be completed. Program features will be as U2 - 10/29/2014 described in LRA Section B2.1.30.
25 For the PWR Vessel Internals Program, PINGP commits to the U1 - 8/9/2011 B2.1.32 following activities for managing the aging of reactor vessel U2 - 10/29/2012 internals components:
8 of 15
Document Control Desk L-PI-08-024 Enclosure 2 Preliminary License Renewal Commitments Commitment Commitment Implementation Related LRA Number Schedule Section Number
- Participate in the industry programs for investigating and managing aging effects on reactor internals;
- Evaluate and implement the results of the industry programs as applicable to the reactor internals; and
- Upon completion of these programs, but not less than 24 months before entering the period of extended operation, submit an inspection plan for reactor internals to the NRC for review and approval.
26 The Reactor Head Closure Studs Program will be enhanced to U1 - 8/9/2013 B2.1.33 incorporate controls that ensure that any future procurement of U2 - 10/29/2014 reactor head closure studs will be in accordance with the material and inspection guidance provided in NRC Regulatory Guide 1.65.
9 of 15
Document Control Desk L-PI-08-024 Enclosure 2 Preliminary License Renewal Commitments Commitment Commitment Implementation Related LRA Number Schedule Section Number 27 The Reactor Vessel Surveillance Program will be enhanced as U1 - 8/9/2013 B2.1.34 follows: U2 - 10/29/2014
" A requirement will be added to ensure that all withdrawn and tested surveillance capsules, not discarded as of August 31, 2000, are placed in storage for possible future reconstitution and use.
" A requirement will be added to ensure that in the event spare capsules are withdrawn, the untested capsules are placed in storage and maintained for future insertion.
28 The RG 1.127, Inspection of Water-Control Structures U1 - 8/9/2013 B2.1.35 Associated with Nuclear Power Plants Program will be U2 - 10/29/2014 enhanced as follows:
" The program will include inspections of concrete and steel components that are below the water line at the Screenhouse and Intake Canal. The scope will also require inspections of the Approach Canal, Intake Canal, Emergency Cooling Water Intake, and Screenhouse immediately following extreme environmental conditions or natural phenomena including an earthquake, flood, tornado, severe thunderstorm, or high winds.
" The program parameters to be inspected will include an inspection of water-control concrete components that 10 of 15
Document Control Desk L-PI-08-024 Enclosure 2 Preliminary License Renewal Commitments Commitment Commitment Implementation Related LRA Number Schedule Section Number are below the water line for cavitation and erosion degradation.
The program will visually inspect for damage such as cracking, settlement, movement, broken bolted and welded connections, buckling, and other degraded conditions following extreme environmental conditions or natural phenomena.
29 A Selective Leaching of Materials Program will be completed. U1 - 8/9/2013 B2.1.36 Program features will be as described in LRA B2.1.36. U2 - 10/29/2014 30 The Structures Monitoring Program will be enhanced as U1 - 8/9/2013 B2.1.38 follows: U2 - 10/29/2014 The following structures, components, and component supports will be added to the scope of the inspections:
o Approach Canal o Fuel Oil Transfer House o Old Administration Building and Administration Building Addition o Component supports for cable tray, conduit, cable, tubing tray, tubing, non-ASME vessels, exchangers, pumps, valves, piping, mirror insulation, non-ASME valves, cabinets, panels, racks, equipment enclosures, junction boxes, bus ducts, breakers, transformers, instruments, diesel equipment, housings for HVAC fans, louvers, and 11 of 15
Document Control Desk L-PI-08-024 Enclosure 2 Preliminary License Renewal Commitments Commitment Commitment Implementation Related LRA Number Schedule Section Number dampers, HVAC ducts, vibration isolation elements for diesel equipment, and miscellaneous electrical and mechanical equipment items o Miscellaneous electrical equipment and instrumentation enclosures including cable tray, conduit, wireway, tube tray, cabinets, panels, racks, equipment enclosures, junction boxes, breaker housings, transformer housings, lighting fixtures, and metal bus enclosure assemblies o Miscellaneous mechanical equipment enclosures including housings for HVAC fans, louvers, and dampers o SBO Yard Structures and components including SBO cable vault and bus duct enclosures.
o Fire Protection System hydrant houses o Caulking, sealant and elastomer materials o Non-safety related masonry walls that support equipment relied upon to perform a function that demonstrates compliance with a regulated event(s).
" The program will be enhanced to include additional inspection parameters.
" The program will require an inspection frequency of once every five (5) years for structures and structural components within the scope of the program. The 12 of 15
Document Control Desk L-PI-08-024 Enclosure 2 Preliminary License Renewal Commitments Commitment Commitment Implementation Related LRA Number Schedule Section Number frequency of inspections can be adjusted, if necessary, to allow for early detection and timely correction of negative trends.
The program will require periodic sampling of groundwater and river water chemistries to ensure they remain non-aggressive.
31 A Thermal Aging Embrittlement of Cast Austenitic Stainless U1 - 8/9/2013 B2.1.39 Steel (CASS) Program will be implemented. Program features U2 - 10/29/2014 will be as described in LRA Section B2.1.39.
32 The Water Chemistry Program will be enhanced to require U1 - 8/9/2013 B2.1.40 increased sampling to be performed as needed to confirm the U2 - 10/29/2014 effectiveness of corrective actions taken to address an abnormal chemistry condition.
33 The Metal Fatigue of Reactor Coolant Pressure Boundary U1 - 8/9/2013 B3.2 Program will be enhanced as follows: U2 - 10/29/2014 The program will monitor the six component locations identified in NUREG/CR-6260 for older vintage Westinghouse plants, either by tracking the cumulative number of imposed stress cycles using cycle counting, or by tracking the cumulative fatigue usage, including the effects of coolant environment, using cycle-based or stress-based fatigue usage monitoring. The following locations will be monitored:
o Reactor Vessel Inlet and Outlet Nozzles (Cycle 13 of 15
Document Control Desk L-PI-08-024 Enclosure 2 Preliminary License Renewal Commitments Commitment Commitment Implementation Related LRA Number Schedule Section Number Counting) o Reactor Pressure Vessel Shell to Lower Head (Cycle Counting) o RCS Hot Leg Surge Line Nozzle (Stress-Based Fatigue Usage Monitoring) o RCS Cold Leg Charging Nozzle (Stress-Based Fatigue Usage Monitoring) o RCS Cold Leg Safety Injection Accumulator Nozzle (Cycle-Based Fatigue Usage Monitoring) o RHR-to-Accumulator Piping Tee (Cycle-Based Fatigue Usage Monitoring)
" The program will implement stress-based fatigue usage monitoring for selected locations subject to pressurizer insurge/outsurge transients. The following locations will be monitored:
o RCS Hot Leg Surge Line Nozzle (also a NUREG/CR-6260 Location) o Pressurizer Lower Head (Heater Penetrations) o Pressurizer Surge Nozzle o Pressurizer Surge Line Elbow
- Program acceptance criteria will be clarified to require corrective action to be taken before a cumulative fatigue usage factor exceeds 1.0 or a design basis transient cycle limit is exceeded.
14 of 15
Document Control Desk L-PI-08-024 Enclosure 2 Preliminary License Renewal Commitments Commitment Commitment Implementation Related LRA Number Schedule Section Number 34 Reactor internals baffle bolt fatigue transient limits of 1835 U1 - 8/9/2013 B3.2 cycles of plant loading at 5% per minute and 1835 cycles of U2 - 10/29/2014 plant unloading at 5% per minute will be incorporated into the Metal Fatigue of Reactor Coolant Pressure Boundary Program and USAR Table 4.1-8.
35 PINGP will perform a fatigue evaluation of pressurizer and U1 - 8/9/2013 4.3.1.3 surge line locations affected by insurge/outsurge transients. U2 - 10/29/2014 This evaluation will determine the cumulative fatigue usage from past operation, accounting for the periods of both "Water Solid" and "Standard Steam Bubble" operating strategies, and will project the cumulative fatigue usage of selected locations for 60 years. Analysis results will be incorporated, as applicable, into the Metal Fatigue of Reactor Coolant Pressure Boundary Program.
15 of 15