Dominion Energy Kewaunee, Inc.
')000 Dominion Boulevard, Glen Allen, VA now March 24, 2008 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Serial No. 08-0114 L1C/MH/RO Docket No.:
50-305 License No.: DPR-43 DOMINION ENERGY KEWAUNEE, INC.
KEWAUNEE POWER STATION FOLLOW-UP COMMITMENTS RELATED TO NRC SUPPLEMENTAL INSPECTION PURSUANT TO INSPECTION PROCEDURE 95002 On December 19, 2007, the U.S. Nuclear Regulatory Commission (NRC) completed a supplemental inspection at the Kewaunee Power Station (KPS) pursuant to Inspection Procedure 95002, "Inspection for One Degraded Cornerstone or Any Three White Performance Inputs in a Strategic Performance Area."
The supplemental inspection was conducted to review the Dominion Energy Kewaunee (DEK) actions taken to address a Yellow finding and a White performance indicator.
The Yellow finding involved a failure to evaluate and repair a fuel oil leak on an emergency diesel generator. The White performance indicator was in the area of "Unplanned Scrams per 7000 Critical Hours."
On February 6, 2008, a meeting was held between DEK and I\\IRC Region III representatives relative to the KPS 95002 inspection results. During the meeting, DEK discussed measures that have been or would be taken to address the Yellow inspection finding and White performance indicator.
Several of these measures were highlighted during the discussion.
A listing of the highlighted corrective actions that were considered important in preventing similar problems at Kewaunee was developed as a follow-up to this meeting.
This list of actions and associated completion dates are provided as an attachment to this letter. DEK is formally committing to complete these actions by the dates indicated in the attachment.
If you have questions or require additional information, please feel fre13 to contact Mr.
Thomas L. Breene at 920-388-8599.
Very truly yours,
~.ea(~ ~
William R. Matthews Senior Vice-President Nuclear Operations
Serial No. 08-0114 Follow-up Commitments Related to NRC Supplemental Inspection Page 2 of 2
Attachment:
Follow-Up Commitments Related To NRC Supplemental Inspection Commitments made by this letter:
Completion of the KPS corrective actions as listed in Attachment 1 of this letter.
cc:
Regional Administrator, Region III U. S. Nuclear Regulatory Commission 2443 Warrenville Road Suite 210 Lisle, IL 60532-4352 Ms. M. H. Chernoff Senior Project Manager U.S. Nuclear Regulatory Commission Mail Stop 08-H4A Washington, DC 20555-0001 NRC Senior Resident Inspector Kewaunee Power Station
Serial No. 08-0114 ATTACHMENT FOLLOW-UP COMMITMENTS RELATED TO NRC SUPPLEMENTAL INSPECTION PURSUANT TO INSPECTION PROCEDURE 95002 KEWAUNEE POWER STATION DOMINION ENERGY KEWAUNEE, INC.
Serial No. 08-0114 Attachment Page 1 of 1 FOLLOW-UP COMMITMENTS RELATED TO NRC SUPPLEMENTAL INSPECTION i
Initiating Document Summary of Commitment Steps Completion I
Date Root Cause Evaluation 40:
ACTION 1: Implement specific and defined 06/30/2008 NRC Identified Crosscutting expectations designed to change management Issues Remain Open in the behaviors in the area of PI&R.
Area of Problem Identification and Resolution (PI&R)
Root Cause Evaluation 41:
ACTION 4: A program was developed to perform an Complete Common Root Cause annual multidiscipline (independent of the Work Order Evaluation Screen team) review of all open corrective and elective work orders to ensure the requests are appropriately prioritized based on risk significance.
ACTION 9: Perform independent program health 04/30/2008 reviews in accordance with the Recovery Project Guideline for program health.
ACTION 11: Develop a Critical Equipment List for Complete KPS.
ACTION 12: Develop a Master Equipment List for 03/31/2009 KPS.
ACTION 13: Develop a Single Point Vulnerability List 12/31/2008 for KPS. (This will be performed in a 2-phase project.)
i KPS-SA-07-61 :
ACTION 1: Develop, communicate and begin 03/31/2008 Safety Culture Self implementation of a corrective action recovery change Assessment management plan.
ACTION 4: Clearly define the terms accountability 06/30/2008 and ownership to the management team and communicate associated expectations to the station.
Design Change 3663:
ACTION: DEK completed a plant modification which Complete Spray Shields installed spray shields around train A and B service water piping in the switchgear area of safeguards alley I
and around train B service water piping in the train A I
emergency diesel generator room. The spray shields will contain and direct leaks of a maximum of 100 I
GPM away from safety related equipment. The spray I
I shields were installed as part of the KPS plant risk I
reduction efforts that have been previously discussed with the NRC staff. Removal of the shields for I
maintenance will not render any equipment inoperable l
and will be controlled in accordance with 10 CFR 50.65 (a)(4).