January 30, 2008

Mr. Barry S. Allen

Site Vice President

FirstEnergy Nuclear Operating Company

Perry Nuclear Power Plant

P. O. Box 97, 10 Center Road, A-PY-290

Perry, OH 44081-0097

SUBJECT:

PERRY NUCLEAR POWER PLANT REQUEST FOR INFORMATION FOR AN

NRC TRIENNIAL BASELINE COMPONENT DESIGN BASES INSPECTION

(CDBI) 05000440/2008006(DRS)

Dear Mr. Allen:

On May 5, 2008, the NRC will begin a triennial baseline Component Design Bases Inspection

(CDBI) at the Perry Nuclear Power Plant. A team of six inspectors will perform this

3-week inspection. This inspection will be performed in accordance with NRC Baseline

Inspection Procedure (IP) 71111.21.

The CDBI inspection focuses on components that have high risk and low design margins. The

components to be reviewed during this baseline inspection will be identified during an in-office

preparation week prior to the first week of the on-site inspection. In addition, a number of risk

significant operator actions and operating experience issues, associated with the component

samples, will also be selected for review.

The inspection will include three weeks on-site, including the information gathering during the

first on-site week. The inspection team will consist of six NRC inspectors, of which five will

focus on engineering and one on operations. The current inspection schedule is as follows:

On-site weeks: May 5, 2008, through May 9, 2008;

May 19, 2008, through May 23, 2008; and

June 2, 2008, through June 6, 2008.

The team will be preparing for the inspection, mainly during the week of April 28, 2008, as

discussed in the attached enclosure. A Region III Senior Reactor Analyst may accompany the

inspection team during the week of May 5, 2008, to review probabilistic risk assessment data,

and assist in identifying risk significant components, which will be reviewed during the

inspection.

Experience with previous baseline design inspections of similar depth and length has shown

that these type of inspections are extremely resource intensive, both for the NRC inspectors and

the licensee staff. In order to minimize the inspection impact on the site and to ensure a

productive inspection for both parties, we have enclosed a request for information needed for

the inspection.

B. Allen

-2-

It is important that all of these documents are up to date and complete in order to minimize the

number of additional documents requested during the preparation and/or the on-site portions of

the inspection. Insofar as possible, this information should be provided electronically to the lead

inspector. The information request has been divided into three groups:

The first group lists information necessary for our initial inspection scoping activities.

This information should be provided to the lead inspector no later than March 24, 2008. By

April 11, 2008, the lead inspector will communicate the initial selected set of approximately

30 high risk components.

The second group of documents requested are those items needed to support our in-office

preparation activities. This set of documents, including the calculations associated with the

initial selected components, should be provided to the lead inspector at the Regional Office

no later than April 23, 2008. During the in-office preparation activities, the team may identify

additional information needed to support the inspection.

The last group includes the additional information above as well as plant specific reference

material. This information should be available to the team at Perry on May 5, 2008. It is

also requested that corrective action documents and/or questions developed during the

inspection be provided to the lead inspector as the documents are generated.

The lead inspector for this inspection is Dr. Stuart Sheldon. We understand that our licensing

contact for this inspection is Mr. Kenneth Russell of your organization. If there are any

questions about the inspection or the material requested in the enclosure, please contact the

lead inspector at (630) 829-9727 or via e-mail at sns2@nrc.gov.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRC's document system

(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the

Public Electronic Reading Room).

Sincerely,

/RA/

Ann Marie Stone, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-440

License No. NPF-58

Enclosure:

Component Design Bases Inspection (CDBI) Document Request

DISTRIBUTION

See next page

B. Allen

-2-

It is important that all of these documents are up to date and complete in order to minimize the number of

additional documents requested during the preparation and/or the on-site portions of the inspection.

Insofar as possible, this information should be provided electronically to the lead inspector. The

information request has been divided into three groups:

The first group lists information necessary for our initial inspection scoping activities. This information

should be provided to the lead inspector no later than March 24, 2008. By April 11, 2008, the lead

inspector will communicate the initial selected set of approximately 30 high risk components.

The second group of documents requested are those items needed to support our in-office

preparation activities. This set of documents, including the calculations associated with the initial

selected components, should be provided to the lead inspector at the Regional Office no later than

April 23, 2008. During the in-office preparation activities, the team may identify additional information

needed to support the inspection.

The last group includes the additional information above as well as plant specific reference material.

This information should be available to the team at Perry on May 5, 2008. It is also requested that

corrective action documents and/or questions developed during the inspection be provided to the lead

inspector as the documents are generated.

The lead inspector for this inspection is Dr. Stuart Sheldon. We understand that our licensing contact for

this inspection is Mr. Kenneth Russell of your organization. If there are any questions about the

inspection or the material requested in the enclosure, please contact the lead inspector at (630) 829-9727

or via e-mail at sns2@nrc.gov.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure

will be available electronically for public inspection in the NRC Public Document Room or from the

Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the

NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Ann Marie Stone, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-440

License No. NPF-58

Enclosure:

Component Design Bases Inspection (CDBI) Document Request

DISTRIBUTION

See next page

G:\\DRS\\Work in Progress\\Ltr 01 08 Perry Request for Information SNS.doc

Publicly Available

Non-Publicly Available

Sensitive

Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE: RIII

RIII

RIII

RIII

NAME:

SSheldon: ls

AMStone

DATE:

01/28/08

01/30/08

OFFICIAL RECORD COPY

Letter to Mr. Barry S. Allen from Ms. A M. Stone dated January , 2008.

SUBJECT:

PERRY NUCLEAR POWER PLANT REQUEST FOR INFORMATION FOR AN

NRC TRIENNIAL BASELINE COMPONENT DESIGN BASES INSPECTION

(CDBI) 05000440/2008006(DRS)

cc w/encl:

J. Hagan, President and Chief Nuclear Officer - FENOC

J. Lash, Senior Vice President of Operations and

Chief Operating Officer - FENOC

D. Pace, Senior Vice President, Fleet Engineering - FENOC

J. Rinckel, Vice President, Fleet Oversight - FENOC

Director, Fleet Regulatory Affairs - FENOC

Manager, Fleet Licensing - FENOC

Manager, Site Regulatory Compliance - FENOC

D. Jenkins, Attorney, FirstEnergy Corp.

Public Utilities Commission of Ohio

Ohio State Liaison Officer

R. Owen, Ohio Department of Health

Letter to Mr. Barry S. Allen from Ms. A M. Stone dated January , 2008.

SUBJECT:

PERRY NUCLEAR POWER PLANT REQUEST FOR INFORMATION FOR AN

NRC TRIENNIAL BASELINE COMPONENT DESIGN BASES INSPECTION

(CDBI) 05000440/2008006(DRS)

cc w/encl:

J. Hagan, President and Chief Nuclear Officer - FENOC

J. Lash, Senior Vice President of Operations and

Chief Operating Officer - FENOC

D. Pace, Senior Vice President, Fleet Engineering - FENOC

J. Rinckel, Vice President, Fleet Oversight - FENOC

Director, Fleet Regulatory Affairs - FENOC

Manager, Fleet Licensing - FENOC

Manager, Site Regulatory Compliance - FENOC

D. Jenkins, Attorney, FirstEnergy Corp.

Public Utilities Commission of Ohio

Ohio State Liaison Officer

R. Owen, Ohio Department of Health

DISTRIBUTION:

RAG1

TJW2

TEB

RidsNrrDirslpab

JLC1

GEG

KGO

RML2

SRI Perry

DRPIII

DRSIII

PLB1

TXN

ROPreports@nrc.gov

INFORMATION REQUEST FOR PERRY NUCLEAR POWER PLANT

COMPONENT DESING BASES INSPECTION (CDBI)

Enclosure

1

Inspection Report: 05000440/2008006(DRS)

Inspection Dates:

May 5, 2008, through May 9, 2008;

May 19, 2008, through May 23, 2008; and

June 2, 2008, through June 6, 2008.

Inspection Procedure:

IP 71111.21 Component Design Bases Inspection

Lead Inspector:

Stuart Sheldon, Lead Inspector

(630) 829-9727

sns2@nrc.gov

I.

Information Requested Prior to the On-site Information Gathering/Inspection Week

The following information is requested by March 24, 2008, or sooner, to facilitate

inspection preparation. If you have any questions regarding this information, please call

the team leader as soon as possible. (Please provide the information electronically in

pdf files, Excel, or other searchable formats, preferably on CDROM. The CDROM

should contain descriptive names, and be indexed and hyperlinked to facilitate ease of

use. Information in lists should contain enough information to be easily understood by

someone who has knowledge of boiling water reactor technology).

1.

Risk ranking of top 150 components from your site specific probabilistic safety

analysis (PSA) sorted by Risk Achievement Worth (RAW). Include values for

Birnbaum Importance, Risk Reduction Worth (RRW), and Fussell-Veseley (FV)

(as applicable).

2.

Provide a list of the top 200 cut-sets from your PSA.

3.

Risk ranking of operator actions from your site specific PSA sorted by RAW.

Provide copies of your human reliability worksheets for these items.

4.

If you have an External Events or Fire PSA Model, provide the information

requested in Items 1 and 2 for external events and fire. Provide narrative

description of each coded event (including fire, flood zone description).

5.

Any pre-existing evaluation or list of components and associated calculations

with low design margins, (i.e., pumps closest to the design limit for flow or

pressure, diesel generator close to design required output, heat exchangers

close to rated design heat removal etc.).

INFORMATION REQUEST FOR PERRY NUCLEAR POWER PLANT

COMPONENT DESING BASES INSPECTION (CDBI)

Enclosure

2

6.

List of available design (setup) margins for valves in the motor-operated valve

(MOV) and air-operated valve (AOV) programs.

7.

List of high risk Maintenance Rule systems/components based on engineering or

expert panel judgment.

8.

Structures, systems, and components (SSCs) in the Maintenance Rule (a)(1)

category.

9.

Site top ten issues list (if applicable).

10.

A list of operating experience evaluations for the last 3 years.

11.

Information of any common cause failure of components experienced in the last

5 years at your facility.

12.

List of Root Cause Evaluations associated with component failures or design

issues initiated/completed in the last 5 years.

13.

Current management and engineering organizational chart.

14.

Electronic copies of Updated Final Safety Analysis Report, Technical

Specifications, Technical Specifications Bases, and Technical Requirements

Manual.

II.

Information requested (for the approx. 30 selected components) to be available by

April 23, 2008, (will be reviewed by the team in the Regional office during the week

of April 28, 2008). This information should be separated for each selected

component, especially if provided electronically (e.g., folder with component

name that includes calculations, condition reports, maintenance history, etc).

1.

List of condition reports (corrective action documents) associated with each of

the selected components for the last 4 years.

2.

The corrective maintenance history associated with each of the selected

components for the last 4 years.

3.

Copies of calculations associated with each of the selected components (if not

previously provided), excluding data files. Please review the calculations and

also provide copies of referenced material (such as drawings, engineering

requests, and vendor letters).

4.

System Health Reports, System Descriptions, and/or Design Basis Documents

that are associated with each of the selected components.

INFORMATION REQUEST FOR PERRY NUCLEAR POWER PLANT

COMPONENT DESIGN BASES INSPECTION (CDBI)

Enclosure

3

5.

A list of modifications associated with each of the selected components.

6.

Copies of operability evaluations associated with each of the selected

components and plans for restoring operability, if applicable.

7.

Copies of selected operator work-around evaluations associated with each of the

selected components and plans for resolution, if applicable.

8.

Copies of any open temporary modifications associated with each of the selected

components, if applicable.

9.

Trend data on the selected electrical/mechanical components performance for

last 3 years (For example, pumps performance including in-service testing, other

vibration monitoring, oil sample results, etc., as applicable).

10.

A copy of any internal/external self-assessments and associated corrective

action documents generated in preparation for the inspection.

11.

A copy of engineering/operations related audits completed in the last 2 years.

12.

Provide list of PRA assumptions regarding operator actions and the associated

procedures.

III.

Additional Information to be provided on May 5, 2008 on-site (for final 15 - 20

selected components)

During the in-office preparation activities, the team will be making final selections and

may identify additional information needed to support the inspection. The lead inspector

will provide a list of the additional information needed during the week of April 28, 2008.

IV.

Information Requested to be provided throughout the inspection

1.

Copies of any corrective action documents generated as a result of the teams

questions or queries during this inspection.

2.

Copies of the list of questions submitted by the team members and the

status/resolution of the information requested (provide daily during the inspection

to each team member).

3.

One complete set of P&IDs and one line electrical drawings (paper copies).

4.

Reference materials. (make available if needed during all on-site weeks):

INFORMATION REQUEST FOR PERRY NUCLEAR POWER PLANT

COMPONENT DESIGN BASES INSPECTION (CDBI)

Enclosure

4

IPE/PRA report;

Procurement documents for components selected (verify retrievable);

Plant procedures (normal, abnormal, emergency, surveillance, etc.); and

Vendor manuals.

If you have questions regarding the information requested, please contact the lead inspector.