February 21, 2008 Mr. David A. Christian President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
SUBJECT:
MILLSTONE POWER STATION, UNIT NO. 2 LICENSE AMENDMENT REQUEST REGARDING CONTAINMENT SPRAY NOZZLE SURVEILLENCE FREQUENCY (TAC NO. MD4992)
Dear Mr. Christian:
By letter dated March 28, 2007 (Agencywide Documents Access and Management System Accession No. ML070880705), Dominion Nuclear Connecticut, Inc. (DNC) submitted a License Amendment Request (LAR) regarding containment spray nozzle surveillance frequency for Millstone Power Station, Unit No. 2. When applications for licensing actions are received, the Nuclear Regulatory Commission (NRC) staff schedules the review activity accordingly. Implicit in this scheduling is an expectation that adequate time will be available to allow the NRC staff to complete a thorough review of the application, including time to ask any additional questions the original application did not address, and time for DNC to respond to the request for additional information.
The NRC staff endeavors to complete routine licensing actions within 12 months of receipt of the application. The March 28, 2007, LAR requested approval of the proposed amendment by February 2008, providing only an 11-month review period. While the NRC staff has made every effort to complete this review within your requested time frame, we will not be able to disposition this request prior to March 2008.
Please contact Carleen Sanders at 301-415-1603 should you have any questions regarding this correspondence.
Sincerely
/ra/
John D. Hughey, Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-336 cc: See next page
February 21, 2008 Mr. David A. Christian President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
SUBJECT:
MILLSTONE POWER STATION, UNIT NO. 2 LICENSE AMENDMENT REQUEST REGARDING CONTAINMENT SPRAY NOZZLE SURVEILLENCE FREQUENCY (TAC NO. MD4992)
Dear Mr. Christian:
By letter dated March 28, 2007 (Agencywide Documents Access and Management System Accession No. ML070880705), Dominion Nuclear Connecticut, Inc. (DNC) submitted a License Amendment Request (LAR) regarding containment spray nozzle surveillance frequency for Millstone Power Station, Unit No. 2. When applications for licensing actions are received, the Nuclear Regulatory Commission (NRC) staff schedules the review activity accordingly. Implicit in this scheduling is an expectation that adequate time will be available to allow the NRC staff to complete a thorough review of the application, including time to ask any additional questions the original application did not address, and time for DNC to respond to the request for additional information.
The NRC staff endeavors to complete routine licensing actions within 12 months of receipt of the application. The March 28, 2007, LAR requested approval of the proposed amendment by February 2008, providing only an 11-month review period. While the NRC staff has made every effort to complete this review within your requested time frame, we will not be able to disposition this request prior to March 2008.
Please contact Carleen Sanders at 301-415-1603 should you have any questions regarding this correspondence.
Sincerely
/ra/
John D. Hughey, Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-336 cc: See next page DISTRIBUTION:
PUBLIC LPLI-2 R/F RidsNrrPMJHughey RidsNrrLAABaxter RidsRgn1MailCenter RidsNrrDorlLpl1-2 ADAMS Accession Number: ML080230562
- via email OFFICE LPL1-2/GE LPL1-2/PM LPL1-2/LA LPL1-2/BC NAME CSanders JHughey (REnnis for re telecom)
ABaxter HChernoff DATE 1/29/08 2/21/08 1/30/08 2/21/08 1/29/08 2/21/08
- 2/21/08 OFFICIAL RECORD COPY
Millstone Power Station, Unit No. 2 cc:
Lillian M. Cuoco, Esquire Senior Counsel Dominion Resources Services, Inc.
Building 475, 5th Floor Rope Ferry Road Waterford, CT 06385 Edward L. Wilds, Jr., Ph.D.
Director, Division of Radiation Department of Environmental Protection 79 Elm Street Hartford, CT 06106-5127 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 First Selectmen Town of Waterford 15 Rope Ferry Road Waterford, CT 06385 Charles Brinkman, Director Washington Operations Nuclear Services Westinghouse Electric Company 12300 Twinbrook Pkwy, Suite 330 Rockville, MD 20852 Senior Resident Inspector Millstone Power Station c/o U.S. Nuclear Regulatory Commission P.O. Box 513 Niantic, CT 06357 Mr. J. Alan Price Site Vice President Dominion Nuclear Connecticut, Inc.
Building 475, 5th Floor Rope Ferry Road Waterford, CT 06385 Mr. J. W. "Bill" Sheehan Co-Chair NEAC 19 Laurel Crest Drive Waterford, CT 06385 Mr. Evan W. Woollacott Co-Chair Nuclear Energy Advisory Council 128 Terry's Plain Road Simsbury, CT 06070 Ms. Nancy Burton 147 Cross Highway Redding Ridge, CT 00870 Mr. Chris L. Funderburk Director, Nuclear Licensing and Operations Support Dominion Resources Services, Inc.
Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. William D. Bartron Licensing Supervisor Dominion Nuclear Connecticut, Inc.
Building 475, 5th Floor Rope Ferry Road Waterford, CT 06385 Mr. Joseph Roy, Director of Operations Massachusetts Municipal Wholesale Electric Company Moody Street P.O. Box 426 Ludlow, MA 01056 Mr. David A. Sommers Dominion Resources Services, Inc.
5000 Dominion Boulevard Glen Allen, VA 23060-6711