ML073240962

From kanterella
Jump to navigation Jump to search
Request for Information (Cdbi), Request for Information an NRC Biennial Baseline Component Design Basis Inspection (CDBI) 05000331-08-006
ML073240962
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 11/19/2007
From: Ann Marie Stone
NRC/RGN-III/DRS/EB2
To: Richard Anderson
Duane Arnold
References
IR-08-006
Download: ML073240962 (9)


See also: IR 05000331/2008006

Text

November 19, 2007

Mr. Richard L. Anderson

Vice-President

Duane Arnold Energy Center

3277 DAEC Road

Palo, IA 52324-9785

SUBJECT:

DUANE ARNOLD ENERGY CENTER

REQUEST FOR INFORMATION AN NRC BIENNIAL

BASELINE COMPONENT DESIGN BASES INSPECTION (CDBI)

05000331/2008006(DRS)

Dear Mr. Anderson:

On February 11, 2008, the NRC will begin a biennial baseline Component Design Bases

Inspection (CDBI) at the Duane Arnold Energy Center. A team of six inspectors will perform this

3-week inspection. This inspection will be performed in accordance with NRC Baseline Inspection

Procedure (IP) 71111.21.

The CDBI inspection focuses on components that have high risk and low design margins. The

components to be reviewed during this baseline inspection will be identified during an in-office

preparation week prior to the first week of the on-site inspection. In addition, a number of risk

significant operator actions and operating experience issues, associated with the component

samples, will also be selected for review.

The inspection will include three weeks on-site, including the information gathering during the first

on-site week. The inspection team will consist of six NRC inspectors, of which five will focus on

engineering and one on operations. The current inspection schedule is as follows:

On-site weeks: February 11, 2008, through February 15, 2008;

February 25, 2008, through February 29, 2008; and

March 10, 2008, through March 14, 2008.

The team will be preparing for the inspection, mainly during the week of February 4, 2008, as

discussed in the attached enclosure. A Region III Senior Reactor Analyst may accompany the

inspection team during the week of February 11, 2008, to review probabilistic risk assessment

data, and assist in identifying risk significant components, which will be reviewed during the

inspection.

Experience with previous baseline design inspections of similar depth and length has shown that

these type of inspections are extremely resource intensive, both for the NRC inspectors and the

licensee staff. In order to minimize the inspection impact on the site and to ensure a productive

inspection for both parties, we have enclosed a request for information needed for the inspection.

R. Anderson

-2-

It is important that all of these documents are up to date and complete in order to minimize the

number of additional documents requested during the preparation and/or the on-site portions of

the inspection. Insofar as possible, this information should be provided electronically to the lead

inspector. The information request has been divided into three groups:

The first group lists information necessary for our initial inspection scoping activities.

This information should be available to the lead inspector no later than January 10, 2008. By

January 23, 2008, the lead inspector will communicate the initial selected set of approximately

30 high risk components.

The second group of documents requested are those items needed to support our in-office

preparation activities. This set of documents, including the calculations associated with the

initial selected components, should be available at the Regional Office no later than

January 31, 2008. During the in-office preparation activities, the team may identify additional

information needed to support the inspection.

The last group includes the additional information above as well as plant specific reference

material. This information should be available to the team on February 11, 2008. It is also

requested that corrective action documents and/or questions developed during the inspection

be provided to the lead inspector as the documents are generated.

The lead inspector for this inspection is Mr. Andrew Dunlop. We understand that our licensing

contact for this inspection is Mr. Bob Murrell of your organization. If there are any questions about

the inspection or the material requested in the enclosure, please contact the lead inspector at

(630) 829-9726 or via e-mail at axd7@nrc.gov.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document Room

or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS),

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public

Electronic Reading Room).

Sincerely,

/RA by Andrew Dunlop Acting For/

Ann Marie Stone, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-331

License No. DPR-49

Enclosure:

Component Design Bases Inspection (CDBI) Document Request

DISTRIBUTION

See next page

R. Anderson

-2-

It is important that all of these documents are up to date and complete in order to minimize the number of

additional documents requested during the preparation and/or the on-site portions of the inspection. Insofar

as possible, this information should be provided electronically to the lead inspector. The information

request has been divided into three groups:

The first group lists information necessary for our initial inspection scoping activities. This information

should be available to the lead inspector no later than January 10, 2008. By January 23, 2008, the lead

inspector will communicate the initial selected set of approximately 30 high risk components.

The second group of documents requested are those items needed to support our in-office preparation

activities. This set of documents, including the calculations associated with the initial selected

components, should be available at the Regional Office no later than January 31, 2008. During the in-

office preparation activities, the team may identify additional information needed to support the

inspection.

The last group includes the additional information above as well as plant specific reference material.

This information should be available to the team on February 11, 2008. It is also requested that

corrective action documents and/or questions developed during the inspection be provided to the lead

inspector as the documents are generated.

The lead inspector for this inspection is Mr. Andrew Dunlop. We understand that our licensing contact for

this inspection is Mr. Bob Murrell of your organization. If there are any questions about the inspection or the

material requested in the enclosure, please contact the lead inspector at (630) 829-9726 or via e-mail at

axd7@nrc.gov.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure

will be available electronically for public inspection in the NRC Public Document Room or from the Publicly

Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC

Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA by Andrew Dunlop Acting For/

Ann Marie Stone, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-331

License No. DPR-49

Enclosure:

Component Design Bases Inspection (CDBI) Document Request

DISTRIBUTION

See next page

G:\\DRS\\Work in Progress\\Ltr 111907 Duane Arnold RFI SNS.doc

Publicly Available

Non-Publicly Available

Sensitive

Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE RIII

RIII

RIII

RIII

NAME

SSheldon for ADunlop: ls

SBurgess

AMStone

DATE

11/ /07

11/ /07

11/ /07

OFFICIAL RECORD COPY

Letter to Mr. Richard L. Anderson from Ms. A M. Stone dated November 19, 2007.

SUBJECT:

DUANE ARNOLD ENERGY CENTER

INFORMATION REQUEST FOR AN NRC BIENNIAL

BASELINE COMPONENT DESIGN BASES INSPECTION (CDBI)

05000331/2008006(DRS)

cc w/encl:

J. Stall, Senior Vice President, Nuclear and Chief

Nuclear Officer

R. Helfrich, Senior Attorney

M. Ross, Managing Attorney

W. Webster, Vice President, Nuclear Operations

M. Warner, Vice President, Nuclear Operations Support

R. Kundalkar, Vice President, Nuclear Engineering

J. Bjorseth, Site Director

D. Curtland, Plant Manager

S. Catron, Manager, Regulatory Affairs

Chief Radiological Emergency Preparedness Section,

Dept. Of Homeland Security

M. Rasmusson, State Liaison Officer

Letter to Mr. Richard L. Anderson from Ms. A. M Stone dated November 19, 2007.

SUBJECT:

DUANE ARNOLD ENERGY CENTER

INFORMATION REQUEST FOR AN NRC BIENNIAL

BASELINE COMPONENT DESIGN BASES INSPECTION (CDBI)

05000331/2008006(DRS)

cc w/encl:

J. Stall, Senior Vice President, Nuclear and Chief

Nuclear Officer

R. Helfrich, Senior Attorney

M. Ross, Managing Attorney

W. Webster, Vice President, Nuclear Operations

M. Warner, Vice President, Nuclear Operations Support

R. Kundalkar, Vice President, Nuclear Engineering

J. Bjorseth, Site Director

D. Curtland, Plant Manager

S. Catron, Manager, Regulatory Affairs

Chief Radiological Emergency Preparedness Section,

Dept. Of Homeland Security

M. Rasmusson, State Liaison Officer

DISTRIBUTION:

TEB

DWS

RidsNrrDirsIrib

MAS

KGO

JKH3

SRI Duane Arnold

CAA1

DRPIII

DRSIII

PLB1

TXN

ROPreports@nrc.gov

INFORMATION REQUEST FOR DUANE ARNOLD ENERGY CENTER

COMPONENT DESIGN BASES INSPECTION (CDBI)

1

ENCLOSURE

Inspection Report: 05000331/2008006(DRS)

Inspection Dates:

February 11, 2008, through February 15, 2008;

February 25, 2008, through February 29, 2008; and

March 10, 2008, through March 14, 2008.

Inspection Procedure:

IP 71111.21 Component Design Bases Inspection

Lead Inspector:

Andrew Dunlop, Lead Inspector

(630) 829-9726

Axd7@nrc.gov

I.

Information Requested Prior to the On-site Information Gathering/Inspection Week

The following information is requested by January 10, 2008, or sooner, to facilitate

inspection preparation. If you have any questions regarding this information, please call

the team leader as soon as possible. (Please provide the information electronically in

pdf files, Excel, or other searchable formats, preferably on CDROM. The CDROM

should contain descriptive names, and be indexed and hyperlinked to facilitate ease of

use. Information in lists should contain enough information to be easily understood by

someone who has knowledge of boiling water reactor technology).

1.

Risk ranking of top 150 components from your site specific probabilistic safety

analysis (PSA) sorted by Risk Achievement Worth (RAW). Include values for

Birnbaum Importance, Risk Reduction Worth (RRW), and Fussell-Veseley (FV)

(as applicable).

2.

Provide a list of the top 200 cut-sets from your PSA.

3.

Risk ranking of operator actions from your site specific PSA sorted by RAW.

Provide copies of your human reliability worksheets for these items.

4.

If you have an External Events or Fire PSA Model, provide the information

requested in Items 1 and 2 for external events and fire. Provide narrative

description of each coded event (including fire, flood zone description).

5.

Any pre-existing evaluation or list of components and associated calculations

with low design margins, (i.e., pumps closest to the design limit for flow or

pressure, diesel generator close to design required output, heat exchangers

close to rated design heat removal etc.).

INFORMATION REQUEST FOR DUANE ARNOLD ENERGY CENTER

COMPONENT DESIGN BASES INSPECTION (CDBI)

2

ENCLOSURE

6.

List of available design (setup) margins for valves in the motor-operated valve

(MOV) and air-operated valve (AOV) programs.

7.

List of high risk Maintenance Rule systems/components based on engineering or

expert panel judgment.

8.

Structures, systems, and components (SSCs) in the Maintenance Rule (a)(1)

category.

9.

Site top ten issues list (if applicable).

10.

System Health Reports, System Descriptions, and/or Design Basis Documents

that are associated with each of the selected components.

11.

A list of operating experience evaluations for the last 3 years.

12.

Information of any common cause failure of components experienced in the last

5 years at your facility.

13.

List of Root Cause Evaluations associated with component failures or design

issues initiated/completed in the last 5 years.

14.

Current management and engineering organizational chart.

15.

Electronic copies of Updated Final Safety Analysis Report, Technical

Specifications, Technical Specifications Bases, and Technical Requirements

Manual.

II.

Information Requested (for the approx. 30 selected components) to be Available

by January 31, 2008, (will be reviewed by the team in the Regional office during

the week of February 4, 2008). This information should be separated for each

selected component, especially if provided electronically (e.g., folder with

component name that includes calculations, condition reports, maintenance

history, etc).

1.

List of condition reports (corrective action documents) associated with each of

the selected components for the last 4 years.

2.

The corrective maintenance history associated with each of the selected

components for the last 4 years.

3.

Copies of calculations associated with each of the selected components

INFORMATION REQUEST FOR DUANE ARNOLD ENERGY CENTER

COMPONENT DESIGN BASES INSPECTION (CDBI)

3

ENCLOSURE

(if not previously provided), excluding data files. Please review the calculations

and also provide copies of referenced material (such as drawings, engineering

requests, vendor letters).

4.

A list of modifications associated with each of the selected components.

5.

Copies of operability evaluations associated with each of the selected

components and plans for restoring operability, if applicable.

6.

Copies of selected operator work-around evaluations associated with each of the

selected components and plans for resolution, if applicable.

7.

Copies of any open temporary modifications associated with each of the selected

components, if applicable.

8.

Trend data on the selected electrical/mechanical components performance for

last 3 years (For example, pumps performance including in-service testing, other

vibration monitoring, oil sample results, etc., as applicable).

9.

A copy of any internal/external self-assessments and associated corrective

action documents generated in preparation for the inspection.

10.

A copy of engineering/operations related audits completed in the last 2 years. 4

11.

Provide list of PRA assumptions regarding operator actions and the associated

procedures.

III.

Additional Information to be Provided on February 11, 2008 On-site (for final 15 -

20 selected components)

Request for the additional information needed will be provided during the week of

February 4, 2008. The lead inspector will provide a list of added information.

IV.

Information Requested to be provided throughout the inspection

1.

Copies of any corrective action documents generated as a result of the teams

questions or queries during this inspection;

2.

Copies of the list of questions submitted by the team members and the

status/resolution of the information requested (provide daily during the inspection

to each team member);

INFORMATION REQUEST FOR DUANE ARNOLD ENERGY CENTER

COMPONENT DESIGN BASES INSPECTION (CDBI)

4

ENCLOSURE

3.

One complete set of P&IDs and one line electrical drawings (paper copies); and

4.

Reference materials (make available if needed during all on-site weeks):

IPE/PRA report;

Procurement documents for components selected (verify retrievable);

Plant procedures (normal, abnormal, emergency, surveillance, etc.); and

Vendor manuals.

If you have questions regarding the information requested, please contact the lead inspector.