ML073240962
| ML073240962 | |
| Person / Time | |
|---|---|
| Site: | Duane Arnold |
| Issue date: | 11/19/2007 |
| From: | Ann Marie Stone NRC/RGN-III/DRS/EB2 |
| To: | Richard Anderson Duane Arnold |
| References | |
| IR-08-006 | |
| Download: ML073240962 (9) | |
See also: IR 05000331/2008006
Text
November 19, 2007
Mr. Richard L. Anderson
Vice-President
Duane Arnold Energy Center
3277 DAEC Road
Palo, IA 52324-9785
SUBJECT:
DUANE ARNOLD ENERGY CENTER
REQUEST FOR INFORMATION AN NRC BIENNIAL
BASELINE COMPONENT DESIGN BASES INSPECTION (CDBI)
Dear Mr. Anderson:
On February 11, 2008, the NRC will begin a biennial baseline Component Design Bases
Inspection (CDBI) at the Duane Arnold Energy Center. A team of six inspectors will perform this
3-week inspection. This inspection will be performed in accordance with NRC Baseline Inspection
Procedure (IP) 71111.21.
The CDBI inspection focuses on components that have high risk and low design margins. The
components to be reviewed during this baseline inspection will be identified during an in-office
preparation week prior to the first week of the on-site inspection. In addition, a number of risk
significant operator actions and operating experience issues, associated with the component
samples, will also be selected for review.
The inspection will include three weeks on-site, including the information gathering during the first
on-site week. The inspection team will consist of six NRC inspectors, of which five will focus on
engineering and one on operations. The current inspection schedule is as follows:
On-site weeks: February 11, 2008, through February 15, 2008;
February 25, 2008, through February 29, 2008; and
March 10, 2008, through March 14, 2008.
The team will be preparing for the inspection, mainly during the week of February 4, 2008, as
discussed in the attached enclosure. A Region III Senior Reactor Analyst may accompany the
inspection team during the week of February 11, 2008, to review probabilistic risk assessment
data, and assist in identifying risk significant components, which will be reviewed during the
inspection.
Experience with previous baseline design inspections of similar depth and length has shown that
these type of inspections are extremely resource intensive, both for the NRC inspectors and the
licensee staff. In order to minimize the inspection impact on the site and to ensure a productive
inspection for both parties, we have enclosed a request for information needed for the inspection.
R. Anderson
-2-
It is important that all of these documents are up to date and complete in order to minimize the
number of additional documents requested during the preparation and/or the on-site portions of
the inspection. Insofar as possible, this information should be provided electronically to the lead
inspector. The information request has been divided into three groups:
The first group lists information necessary for our initial inspection scoping activities.
This information should be available to the lead inspector no later than January 10, 2008. By
January 23, 2008, the lead inspector will communicate the initial selected set of approximately
30 high risk components.
The second group of documents requested are those items needed to support our in-office
preparation activities. This set of documents, including the calculations associated with the
initial selected components, should be available at the Regional Office no later than
January 31, 2008. During the in-office preparation activities, the team may identify additional
information needed to support the inspection.
The last group includes the additional information above as well as plant specific reference
material. This information should be available to the team on February 11, 2008. It is also
requested that corrective action documents and/or questions developed during the inspection
be provided to the lead inspector as the documents are generated.
The lead inspector for this inspection is Mr. Andrew Dunlop. We understand that our licensing
contact for this inspection is Mr. Bob Murrell of your organization. If there are any questions about
the inspection or the material requested in the enclosure, please contact the lead inspector at
(630) 829-9726 or via e-mail at axd7@nrc.gov.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document Room
or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS),
accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public
Electronic Reading Room).
Sincerely,
/RA by Andrew Dunlop Acting For/
Ann Marie Stone, Chief
Engineering Branch 2
Division of Reactor Safety
Docket No. 50-331
License No. DPR-49
Enclosure:
Component Design Bases Inspection (CDBI) Document Request
DISTRIBUTION
See next page
R. Anderson
-2-
It is important that all of these documents are up to date and complete in order to minimize the number of
additional documents requested during the preparation and/or the on-site portions of the inspection. Insofar
as possible, this information should be provided electronically to the lead inspector. The information
request has been divided into three groups:
The first group lists information necessary for our initial inspection scoping activities. This information
should be available to the lead inspector no later than January 10, 2008. By January 23, 2008, the lead
inspector will communicate the initial selected set of approximately 30 high risk components.
The second group of documents requested are those items needed to support our in-office preparation
activities. This set of documents, including the calculations associated with the initial selected
components, should be available at the Regional Office no later than January 31, 2008. During the in-
office preparation activities, the team may identify additional information needed to support the
inspection.
The last group includes the additional information above as well as plant specific reference material.
This information should be available to the team on February 11, 2008. It is also requested that
corrective action documents and/or questions developed during the inspection be provided to the lead
inspector as the documents are generated.
The lead inspector for this inspection is Mr. Andrew Dunlop. We understand that our licensing contact for
this inspection is Mr. Bob Murrell of your organization. If there are any questions about the inspection or the
material requested in the enclosure, please contact the lead inspector at (630) 829-9726 or via e-mail at
axd7@nrc.gov.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure
will be available electronically for public inspection in the NRC Public Document Room or from the Publicly
Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC
Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA by Andrew Dunlop Acting For/
Ann Marie Stone, Chief
Engineering Branch 2
Division of Reactor Safety
Docket No. 50-331
License No. DPR-49
Enclosure:
Component Design Bases Inspection (CDBI) Document Request
DISTRIBUTION
See next page
G:\\DRS\\Work in Progress\\Ltr 111907 Duane Arnold RFI SNS.doc
Publicly Available
Non-Publicly Available
Sensitive
Non-Sensitive
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
OFFICE RIII
RIII
RIII
RIII
NAME
SSheldon for ADunlop: ls
SBurgess
AMStone
DATE
11/ /07
11/ /07
11/ /07
OFFICIAL RECORD COPY
Letter to Mr. Richard L. Anderson from Ms. A M. Stone dated November 19, 2007.
SUBJECT:
DUANE ARNOLD ENERGY CENTER
INFORMATION REQUEST FOR AN NRC BIENNIAL
BASELINE COMPONENT DESIGN BASES INSPECTION (CDBI)
cc w/encl:
J. Stall, Senior Vice President, Nuclear and Chief
Nuclear Officer
R. Helfrich, Senior Attorney
M. Ross, Managing Attorney
W. Webster, Vice President, Nuclear Operations
M. Warner, Vice President, Nuclear Operations Support
R. Kundalkar, Vice President, Nuclear Engineering
J. Bjorseth, Site Director
D. Curtland, Plant Manager
S. Catron, Manager, Regulatory Affairs
Chief Radiological Emergency Preparedness Section,
Dept. Of Homeland Security
M. Rasmusson, State Liaison Officer
Letter to Mr. Richard L. Anderson from Ms. A. M Stone dated November 19, 2007.
SUBJECT:
DUANE ARNOLD ENERGY CENTER
INFORMATION REQUEST FOR AN NRC BIENNIAL
BASELINE COMPONENT DESIGN BASES INSPECTION (CDBI)
cc w/encl:
J. Stall, Senior Vice President, Nuclear and Chief
Nuclear Officer
R. Helfrich, Senior Attorney
M. Ross, Managing Attorney
W. Webster, Vice President, Nuclear Operations
M. Warner, Vice President, Nuclear Operations Support
R. Kundalkar, Vice President, Nuclear Engineering
J. Bjorseth, Site Director
D. Curtland, Plant Manager
S. Catron, Manager, Regulatory Affairs
Chief Radiological Emergency Preparedness Section,
Dept. Of Homeland Security
M. Rasmusson, State Liaison Officer
DISTRIBUTION:
TEB
DWS
RidsNrrDirsIrib
MAS
KGO
JKH3
SRI Duane Arnold
CAA1
DRPIII
DRSIII
PLB1
TXN
ROPreports@nrc.gov
INFORMATION REQUEST FOR DUANE ARNOLD ENERGY CENTER
COMPONENT DESIGN BASES INSPECTION (CDBI)
1
ENCLOSURE
Inspection Report: 05000331/2008006(DRS)
Inspection Dates:
February 11, 2008, through February 15, 2008;
February 25, 2008, through February 29, 2008; and
March 10, 2008, through March 14, 2008.
Inspection Procedure:
IP 71111.21 Component Design Bases Inspection
Lead Inspector:
Andrew Dunlop, Lead Inspector
(630) 829-9726
Axd7@nrc.gov
I.
Information Requested Prior to the On-site Information Gathering/Inspection Week
The following information is requested by January 10, 2008, or sooner, to facilitate
inspection preparation. If you have any questions regarding this information, please call
the team leader as soon as possible. (Please provide the information electronically in
pdf files, Excel, or other searchable formats, preferably on CDROM. The CDROM
should contain descriptive names, and be indexed and hyperlinked to facilitate ease of
use. Information in lists should contain enough information to be easily understood by
someone who has knowledge of boiling water reactor technology).
1.
Risk ranking of top 150 components from your site specific probabilistic safety
analysis (PSA) sorted by Risk Achievement Worth (RAW). Include values for
Birnbaum Importance, Risk Reduction Worth (RRW), and Fussell-Veseley (FV)
(as applicable).
2.
Provide a list of the top 200 cut-sets from your PSA.
3.
Risk ranking of operator actions from your site specific PSA sorted by RAW.
Provide copies of your human reliability worksheets for these items.
4.
If you have an External Events or Fire PSA Model, provide the information
requested in Items 1 and 2 for external events and fire. Provide narrative
description of each coded event (including fire, flood zone description).
5.
Any pre-existing evaluation or list of components and associated calculations
with low design margins, (i.e., pumps closest to the design limit for flow or
pressure, diesel generator close to design required output, heat exchangers
close to rated design heat removal etc.).
INFORMATION REQUEST FOR DUANE ARNOLD ENERGY CENTER
COMPONENT DESIGN BASES INSPECTION (CDBI)
2
ENCLOSURE
6.
List of available design (setup) margins for valves in the motor-operated valve
(MOV) and air-operated valve (AOV) programs.
7.
List of high risk Maintenance Rule systems/components based on engineering or
expert panel judgment.
8.
Structures, systems, and components (SSCs) in the Maintenance Rule (a)(1)
category.
9.
Site top ten issues list (if applicable).
10.
System Health Reports, System Descriptions, and/or Design Basis Documents
that are associated with each of the selected components.
11.
A list of operating experience evaluations for the last 3 years.
12.
Information of any common cause failure of components experienced in the last
5 years at your facility.
13.
List of Root Cause Evaluations associated with component failures or design
issues initiated/completed in the last 5 years.
14.
Current management and engineering organizational chart.
15.
Electronic copies of Updated Final Safety Analysis Report, Technical
Specifications, Technical Specifications Bases, and Technical Requirements
Manual.
II.
Information Requested (for the approx. 30 selected components) to be Available
by January 31, 2008, (will be reviewed by the team in the Regional office during
the week of February 4, 2008). This information should be separated for each
selected component, especially if provided electronically (e.g., folder with
component name that includes calculations, condition reports, maintenance
history, etc).
1.
List of condition reports (corrective action documents) associated with each of
the selected components for the last 4 years.
2.
The corrective maintenance history associated with each of the selected
components for the last 4 years.
3.
Copies of calculations associated with each of the selected components
INFORMATION REQUEST FOR DUANE ARNOLD ENERGY CENTER
COMPONENT DESIGN BASES INSPECTION (CDBI)
3
ENCLOSURE
(if not previously provided), excluding data files. Please review the calculations
and also provide copies of referenced material (such as drawings, engineering
requests, vendor letters).
4.
A list of modifications associated with each of the selected components.
5.
Copies of operability evaluations associated with each of the selected
components and plans for restoring operability, if applicable.
6.
Copies of selected operator work-around evaluations associated with each of the
selected components and plans for resolution, if applicable.
7.
Copies of any open temporary modifications associated with each of the selected
components, if applicable.
8.
Trend data on the selected electrical/mechanical components performance for
last 3 years (For example, pumps performance including in-service testing, other
vibration monitoring, oil sample results, etc., as applicable).
9.
A copy of any internal/external self-assessments and associated corrective
action documents generated in preparation for the inspection.
10.
A copy of engineering/operations related audits completed in the last 2 years. 4
11.
Provide list of PRA assumptions regarding operator actions and the associated
procedures.
III.
Additional Information to be Provided on February 11, 2008 On-site (for final 15 -
20 selected components)
Request for the additional information needed will be provided during the week of
February 4, 2008. The lead inspector will provide a list of added information.
IV.
Information Requested to be provided throughout the inspection
1.
Copies of any corrective action documents generated as a result of the teams
questions or queries during this inspection;
2.
Copies of the list of questions submitted by the team members and the
status/resolution of the information requested (provide daily during the inspection
to each team member);
INFORMATION REQUEST FOR DUANE ARNOLD ENERGY CENTER
COMPONENT DESIGN BASES INSPECTION (CDBI)
4
ENCLOSURE
3.
One complete set of P&IDs and one line electrical drawings (paper copies); and
4.
Reference materials (make available if needed during all on-site weeks):
IPE/PRA report;
Procurement documents for components selected (verify retrievable);
Plant procedures (normal, abnormal, emergency, surveillance, etc.); and
Vendor manuals.
If you have questions regarding the information requested, please contact the lead inspector.