MONTHYEARIR 05000280/20240102024-10-0202 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000280/2024010 and 05000281/2024010 IR 05000280/20240052024-08-26026 August 2024 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2024005 and 05000281-2024005), Rev 1 IR 05000280/20240112024-08-13013 August 2024 Comprehensive Engineering Team Inspection Report 05000280/2024011 and 05000281/2024011 IR 05000280/20240022024-08-0101 August 2024 Integrated Inspection Report 05000280/2024002 and 05000281/2024002 IR 05000280/20244032024-05-22022 May 2024 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000280/2024403 and 05000281- 2024403 IR 05000280/20240012024-04-30030 April 2024 Integrated Inspection Report 05000280-2024001 and 05000281-2024001 IR 05000280/20244022024-04-29029 April 2024 Security Baseline Inspection Report 05000280/2024402 and 05000281/2024402 ML24095A2172024-04-12012 April 2024 – Review of the Spring 2023 Steam Generator Tube Inspection Report IR 05000280/20230062024-02-28028 February 2024 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Reports 05000280/2023006 and 05000281/2023006 IR 05000280/20230042024-02-0909 February 2024 Integrated Inspection Report 05000280/2023004 and 05000281/2023004 IR 05000280/20244012024-02-0606 February 2024 Security Baseline Inspection Report 05000280/2024401, 05000281/2024401 and 07200002/2024401 IR 05000280/20230102024-01-18018 January 2024 – Age Related Degradation Inspection Report 05000280-2023010 and 05000281-2023010 IR 05000280/20233012023-12-28028 December 2023 – NRC Operator License Examination Report 05000280/2023301 and 05000281/2023301 IR 05000280/20230032023-10-25025 October 2023 Integrated Inspection Report 05000280/2023003 and 05000281/2023003 ML23256A2672023-09-21021 September 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report IR 05000280/20220042023-09-0101 September 2023 Reissue - Surry Power Station - Integrated Inspection Report 05000280/2022004 and 05000281/2022004 IR 05000280/20230052023-08-23023 August 2023 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2023005 and 05000281/2023005) IR 05000280/20230022023-08-0404 August 2023 – Integrated Inspection Report 05000280/2023002 and 05000281/2023002 IR 05000280/20230012023-05-0505 May 2023 – Integrated Inspection Report 05000280/2023001 and 05000281/2023001 IR 05000280/20234012023-04-21021 April 2023 – Security Baseline Inspection Report 05000280 2023401 and 05000281 2023401 ML23086B9172023-03-24024 March 2023 Steam Generator Tube Inspection Report for the Fall 2022 Refueling Outage IR 05000280/20220062023-03-0101 March 2023 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Reports 05000280/2022006 and 05000281/2022006 ML23041A0232023-02-13013 February 2023 Integrated Inspection Report 05000280/2022004 and 05000281/2022004 IR 05000280/20220032022-11-0707 November 2022 Integrated Inspection Report 05000280/2022003 and 05000281/2022003, Operation of an Independent Spent Fuel Storage Installation Report 07200055/2022001, and Exercise of Enforcement Discretion IR 05000281/20224022022-10-21021 October 2022 Security Baseline Inspection Report 05000280/ 2022402 and 05000281/2022402 IR 05000280/20224042022-10-19019 October 2022 Security Baseline Inspection Report 05000280/2022404 and 05000281/2022404 IR 05000280/20224032022-09-0808 September 2022 Security Baseline Inspection Report 05000280/2022403 and 05000281/2022403 IR 05000280/20220052022-08-24024 August 2022 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Reports 05000280/2022005 and 05000281/2022005) IR 05000280/20220022022-08-0404 August 2022 Integrated Inspection Report 05000280/2022002 and 05000281/2022002 Final IR 05000280/20220112022-07-0606 July 2022 Biennial Problem Identification and Resolution Inspection Report 05000280/2022011 and 05000281/2022011 IR 05000280/20220012022-05-11011 May 2022 Integrated Inspection Report 05000280/2022001 and 05000281/2022001 IR 05000280/20224012022-03-29029 March 2022 Security Baseline Inspection Report 05000280/2022401 and 05000281/2022401 IR 05000280/20224052022-03-22022 March 2022 Material Control and Accounting Program Inspection Report 05000280/2022405 and 05000281/2022405 IR 05000280/20220102022-03-15015 March 2022 NRC Inspection Report 05000280/2022010 and 05000281/2022010 IR 05000280/20210062022-03-0202 March 2022 Annual Assessment Letter for Surry Power Station, Units 1 and 2 (Reports No. 05000280/2021006 and 05000281/2021006) IR 05000280/20210042022-02-11011 February 2022 Integrated Inspection Report 05000280/2021004 and 05000281/2021004 IR 05000280/20210032021-11-24024 November 2021 Integrated Inspection Report 05000280/2021003 and 05000281/2021003 IR 05000280/20213012021-11-10010 November 2021 NRC Operator License Examination Report 05000280/2021301 and 05000281/2021301 IR 05000280/20210112021-11-0101 November 2021 Triennial Fire Protection Team Inspection Report 05000280/2021011 and 05000281/2021011 ML21265A4532021-10-0505 October 2021 Inspection Report 2021 FOF (IP92707) IR 05000280/20210052021-08-31031 August 2021 Mid-Cycle Letter Revised Updated Inspection Plan for Surry Power Station, Units 1 and 2 (05000280/2021005 and 05000281/2021005) IR 05000280/20210012021-08-26026 August 2021 Updated Inspection Plan for Surry Power Station, Units 1 and 2 -(05000280/2021001 and 05000281/2021001) IR 05000280/20210102021-08-16016 August 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000280/2021010 and 05000281/2021010 IR 05000280/20210022021-08-12012 August 2021 Integrated Inspection Report 05000280/2021002 and 05000281/2021002 IR 05000280/20214022021-06-14014 June 2021 Security Baseline Inspection Report 05000280/2021402, 05000281/2021402 and 07200002/2021401 ML21120A1552021-04-30030 April 2021 Integrated Inspection Report 05000280/2021001 and 05000281/2021001 IR 05000280/20200062021-03-0303 March 2021 Annual Assessment Letter for Surry Power Station, Units 1 and 2 NRC Inspection Reports 05000280/2020006 and 05000281/2020006 IR 05000280/20214012021-02-0909 February 2021 Security Baseline Inspection Report 05000280/2021401 and 05000281/2021401 IR 05000280/20200042021-02-0202 February 2021 Integrated Inspection 05000280/2020004 and 05000281/2020004; and 07200055/2020003 IR 05000281/20200402020-12-30030 December 2020 95001 Supplemental Inspection Supplemental Report 05000281/2020040 2024-08-26
[Table view] Category:Letter
MONTHYEARML24302A1762024-10-22022 October 2024 Core Operating Limits Report Surry 2 Cycle 33 Pattern Hot Revision 0 ML24283A0702024-10-0707 October 2024 Annual Submittal of Technical Specifications Bases Changes Pursuant to Technical Specification 6.4.J IR 05000280/20240102024-10-0202 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000280/2024010 and 05000281/2024010 ML24270A0022024-09-25025 September 2024 Inservice Inspection Owners Activity Report (OAR) ML24248A1712024-09-0303 September 2024 Proposed License Amendment Request - Temporary Service Water Supply to the Component Cooling Heat Exchangers IR 05000280/20240052024-08-26026 August 2024 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2024005 and 05000281-2024005), Rev 1 ML24219A2372024-08-23023 August 2024 Issuance of Amendment Nos. 319 and 319, Adoption of TSTF-577, Rev. 1, Revised Frequencies for Steam Generator Tube Inspection, ML24207A0402024-08-21021 August 2024 Summary of July 17, 2024, Public Meeting - TS 3.7/3.14 AOT for SW Piping Maintenance IR 05000280/20240112024-08-13013 August 2024 Comprehensive Engineering Team Inspection Report 05000280/2024011 and 05000281/2024011 ML24164A0012024-08-12012 August 2024 Proposed Alternative Relief Request V-1 Inservice Testing of Pressure Isolation Valves (EPID l-2023-LLR-0060) IR 05000280/20240022024-08-0101 August 2024 Integrated Inspection Report 05000280/2024002 and 05000281/2024002 05000280/LER-2024-001, Troubleshooting Initiated Unknown Turbine Trip Feature in Control System2024-07-30030 July 2024 Troubleshooting Initiated Unknown Turbine Trip Feature in Control System ML24165A2782024-07-17017 July 2024 Issuance of Amendment Nos. 318 and 318, Reclassification of Regulatory Guide 1.97 Variable for Low Head Safety Injection ML24165A1232024-07-17017 July 2024 Proposed Alternative Relief Request P-1, P-2 Inservice Testing of Residual Heat and Containment Spray Pumps (EPID l-2023-LLR-0058) ML24190A4192024-07-0808 July 2024 Inservice Testing (IST) Program for Pumps and Valves Revised Sixth IST Interval Start Date and Updated Technical Specifications References for Alternative Request V-1 ML24179A2932024-07-0101 July 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24166A0622024-06-18018 June 2024 – Proposed Alternative Relief Request P-3, P-4 Inservice Testing of Boric Acid, Component Cooling Water Pumps ML24157A0542024-06-13013 June 2024 Audit Summary in Support of License Amendment Request for Proposed Reclassification of Low Head Safety Injection Flow Instrumentation Related to Regulatory Guide 1.97 ML24143A1622024-06-12012 June 2024 – Correction to Issuance of Amendment Nos. 297 and 280 and Surry Units 1 and 2, Correction to Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code ML24141A2862024-05-22022 May 2024 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000280/2024403 and 05000281- 2024403 IR 05000280/20244032024-05-22022 May 2024 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000280/2024403 and 05000281- 2024403 ML24141A2512024-05-20020 May 2024 Proposed License Amendment Request - Reclassification of Low Head Safety Injection Flow Indication Regulatory Guide 1.97 Variable - Supplemental Information ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24136A2302024-05-13013 May 2024 Core 1 Cycle 33 Pattern Mdr Revision 0 ML24130A2032024-05-0909 May 2024 Proposed License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections Supplemental Information ML24130A2492024-05-0909 May 2024 Submittal of Information in Support of Surry Power Station Unit 1 Thermal Shield Flexure Replacement Campaign ML24130A1192024-05-0707 May 2024 Inservice Test Program for Pumps and Valves Sixth Interval Update and Associated Relief and Alternative Requests - Response to Request for Additional Information Regarding Alternative Request V-1 ML24122C6522024-04-30030 April 2024 Annual Radiological Environmental Operating Report ML24142A3852024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report IR 05000280/20240012024-04-30030 April 2024 Integrated Inspection Report 05000280-2024001 and 05000281-2024001 ML24122B3032024-04-29029 April 2024 Associated Independent Spent Fuel Storage Installation, Revision to Emergency Plan Report of Change IR 05000280/20244022024-04-29029 April 2024 Security Baseline Inspection Report 05000280/2024402 and 05000281/2024402 ML24115A1952024-04-24024 April 2024 Notification of Surry Power Station Comprehensive Engineering Team Inspection - U.S. NRC Inspection Report 05000280/2024011 and 05000281/2024011 ML24054A0142024-04-22022 April 2024 Issuance of Amendment Nos. 297 and 280, and Surry Power Station Unit Nos. 1 and 2, Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24108A1812024-04-15015 April 2024 Proposed License Amendment Request - Reclassification of Low Head Safety Injection Flow Indication Regulatory Guide 1.97 Variable Supplemental Information ML24095A2172024-04-12012 April 2024 – Review of the Spring 2023 Steam Generator Tube Inspection Report ML24088A2482024-03-26026 March 2024 Inservice Testing Program for Pumps and Valves Sixth Interval Update and Associated Relief and Alternative Requests- Response to Request for Additional Information ML24087A2082024-03-22022 March 2024 Proposed License Amendment Request Addition of Containment Limiting Condition for Operation and Surveillance Requirements ML24078A2642024-03-21021 March 2024 – Regulatory Audit in Support of License Amendment Request to Proposed Reclassification of Regulatory Guide 1.97 Variable for Low Head Safety Injection Flow Instrumentation ML24087A1522024-03-18018 March 2024 Annual Changes, Tests, and Experiments Report Regulatory Commitment Evaluation Report ML24023A5762024-03-0808 March 2024 Correction to Issuance of Amendment Nos. 315 and 315, Regarding Revised Emergency Plan for Relocation of the Technical Support Center IR 05000280/20230062024-02-28028 February 2024 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Reports 05000280/2023006 and 05000281/2023006 ML24032A4712024-02-20020 February 2024 Exemption from Select Requirements of 10 CFR Part 73 - Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24057A0612024-02-19019 February 2024 And Virgil C. Summer Power Nuclear Stations - Nuclear Property Insurance Coverage ML24051A1782024-02-19019 February 2024 Proposed License Amendment Request - Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections IR 05000280/20230042024-02-0909 February 2024 Integrated Inspection Report 05000280/2023004 and 05000281/2023004 IR 05000280/20244012024-02-0606 February 2024 Security Baseline Inspection Report 05000280/2024401, 05000281/2024401 and 07200002/2024401 2024-09-03
[Table view] |
See also: IR 05000280/2008006
Text
October 19, 2007
Virginia Electric and Power Company
ATTN: Mr. David A. Christian
Sr. Vice President and
Chief Nuclear Officer
Innsbrook Technical Center - 2SW
5000 Dominion Boulevard
Glen Allen, VA 23060-6711
SUBJECT: NOTIFICATION OF SURRY POWER STATION - COMPONENT DESIGN
BASES INSPECTION NRC INSPECTION REPORT 05000280/2008006 AND
05000281/2008006
Dear Mr. Christian:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
Region II staff will conduct a component design bases inspection at your Surry Power Station
during the weeks of January 28-February 1, 2008, February 11-15, 2008, and February 25-29,
2008. The inspection team will be led by Mr. Robert Berryman, a Senior Reactor Inspector
from the NRC's Region II Office. This inspection will be conducted in accordance with the
baseline inspection procedure, Procedure 71111.21, Component Design Bases Inspection,
issued September 20, 2007.
The inspection will evaluate the capability of risk significant / low margin components to function
as designed and support proper system operation. The inspection will also include a review of
selected operator actions, operating experience, and modifications.
During a telephone conversation on October 15, 2007, Mr. Berryman confirmed with Mr. Paul
Kershner of your staff, arrangements for an information gathering site visit and the three-week
onsite inspection. The schedule is as follows:
- Information gathering visit: Week of January 14-18, 2008.
- Onsite weeks: January 28-February 1, 2008, February 11-15, 2008, and
February 25-29, 2008.
The purpose of the information gathering visit is to meet with members of your staff to identify
risk-significant components and operator actions. Information and documentation needed to
support the inspection will also be identified. Mr. Walt Rogers, a Region II Senior Reactor
Analyst, may accompany Mr. Berryman and the inspection team during the information
gathering visit to review probabilistic risk assessment data and identify risk significant
components which will be examined during the inspection.
VEPCO 2
The enclosure lists documents that will be needed prior to the information gathering visit.
Please contact Mr. Berryman prior to preparing copies of the materials listed in the enclosure.
The inspectors will try to minimize your administrative burden by specifically identifying only
those documents required for the inspection preparation.
During the information gathering visit, the team leader will also discuss the following inspection
support administrative details: office space, supplemental documents requested to be made
available to the team in the Region II office prior to the inspection preparation week of
January 21, 2008; arrangements for site access; and the availability of knowledgeable plant
engineering and licensing personnel to serve as points of contact during the inspection.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRC's document system
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Thank you for your cooperation in this matter. If you have any questions regarding the
information requested or the inspection, please contact Mr. Berryman at (404) 562-4817 or me
at (404) 562-4519.
Sincerely,
/RA/
Binoy B. Desai, Chief
Engineering Branch 1
Division of Reactor Safety
Docket Nos.: 50-280, 50-281
License Nos.: DPR-32, DPR-37
Enclosure: Information Request for Surry Power Station Component Design Bases Inspection
cc w/encl:
Chris L. Funderburk, Director
Nuclear Licensing and
Operations Support
Virginia Electric & Power Company
Electronic Mail Distribution
Donald E. Jernigan
Site Vice President
Surry Power Station
Virginia Electric & Power Company
Electronic Mail Distribution
(cc w/encl contd - See page 3)
VEPCO 3
(cc w/encl contd)
Virginia State Corporation Commission
Division of Energy Regulation
P. O. Box 1197
Richmond, VA 23209
Lillian M. Cuoco, Esq.
Senior Counsel
Dominion Resources Services, Inc.
Electronic Mail Distribution
Attorney General
Supreme Court Building
900 East Main Street
Richmond, VA 23219
Distribution w/encl:
S. P. Lingam, NRR
Richard Jervey, NRR
RIDSNRRDIRS
PUBLIC
_________________________
OFFICE RII:DRS
SIGNATURE RA
NAME RBERRYMAN
DATE 10/18/2007 10/ /2007 10/ /2007 10/ /2007 10/ /2007 10/ /2007 10/ /2007
E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO
COMPONENT DESIGN BASES INSPECTION
Please provide the information electronically in .pdf files, Excel, or other searchable format on
CDROM. The CDROM should be indexed and hyperlinked to facilitate ease of use. Lists
should contain enough information to be easily understood to someone who has a knowledge
of pressurized water reactor technology.
1. From your most-recent probabilistic safety analysis (PSA) excluding external events
and fires:
a. Two risk rankings of components from your site-specific probabilistic safety
analysis (PSA): one sorted by Risk Achievement Worth (RAW), and the other
sorted by Birnbaum Importance.
b. A list of the top 500 cutsets.
2. From your most-recent probabilistic safety analysis (PSA) including external events
and fires:
a. Two risk rankings of components from your site-specific probabilistic safety
analysis (PSA): one sorted by Risk Achievement Worth (RAW), and the other
sorted by Birnbaum Importance.
b. A list of the top 500 cutsets..
3. Risk ranking of operator actions from your site specific PSA sorted by RAW. Provide
copies of your human reliability worksheets for these items.
4. Any pre-existing evaluation or list of components and calculations with low design
margins (i.e., pumps closest to the design limit for flow or pressure, diesel generator
close to design required output, heat exchangers close to rated design heat removal,
MOV risk-margin rankings, etc.).
5. A list of station applicability evaluations/reviews performed and documented in the
station corrective action program in the past two years for industry events, critical
equipment failures, and safety related equipment vulnerabilities [as communicated by
NRC generic communications, industry communications, 10 CFR part 21 notifications,
etc.]
6. A list of safety related SSC design modifications implemented within the last two years,
sorted by affected system.
7. This item deleted. Corrective action lists will be requested after the component sample
is determined.
8. A list of common-cause failure of components that have occurred at Surry Power Station
and have been identified within the last five years.
Enclosure
2
9. A list of operability evaluations completed within the last two years, sorted by associated
component or system.
10. Contact information for a person to discuss PRA information prior to the information
gathering trip: name, title, phone number, and e-mail address.
11. List of equipment currently on the sites Station Equipment Reliability Issues List,
including a description of the reason(s) why each component is on that list and
summaries (if available) of your plans to address those reasons.
12. List of equipment currently in RIS 05-020 (formerly GL 91-18) status.
13. List of equipment currently in MR (a)(1) status.
Enclosure