8/31/07 Byron - Mid-Cycle Performance Review and Inspection Plan for 09/01/2007 - 12/31/2008
ML072430548
Person / Time
Site: Byron  Constellation icon.png
Issue date: 08/31/2007
From: Pederson C
Division Reactor Projects III
To: Crane C
Exelon Generation Co, Exelon Nuclear
References
Download: ML072430548 (7)


Text

August 31, 2007 Mr. Christopher M. Crane President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

BYRON STATION

Dear Mr. Crane:

On August 14, 2007, the NRC staff completed its performance review of Byron Station for the first half of the calendar year (CY) 2007 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous 12 months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as Official Use Only - Security-Related Information will include the security cornerstone review and resultant inspection plan.

Plant performance for the most recent quarter at the Byron Station Unit 1 was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at Unit 1.

Plant performance for the most recent quarter on Unit 2 was within the Regulatory Response column of the NRCs Action Matrix. This conclusion is based on the fact that the first submittal of Mitigating Systems Performance Index (MSPI) results for the Auxiliary Feedwater System was White during the second quarter of CY 2006 and has remained White since that time. We conducted the supplemental inspection (95001) during the week of February 5, 2007. This inspection concluded that, in general, the root cause analysis and the planned corrective actions were appropriate to address the concerns associated with the auxiliary feedwater system.

The enclosed inspection plan details the inspections, less those related to security, scheduled through December 31, 2008. Significant inspections planned include a Triennial Fire Protection inspection in November 2007, an Evaluation of Changes, Tests, or Experiments and Permanent Plant Modifications inspection in January 2008, and a Component Design Bases inspection in July 2008. The inspection plan is provided to allow for the resolution of any scheduling conflicts

C. Crane and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

The NRC is currently evaluating the scope and frequency of all the baseline inspection procedures. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact Richard A. Skokowski at (630) 829-9620 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA by A. H. Hsia for/

Cynthia D. Pederson, Director Division of Reactor Projects Docket Nos. 50-454, 50-455 License Nos. NPF-37; NPF-66

Enclosure:

Byron Station Inspection/Activity Plan DISTRIBUTION:

See next page

C. Crane and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

The NRC is currently evaluating the scope and frequency of all the baseline inspection procedures. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact Richard A. Skokowski at (630) 829-9620 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA by A. H. Hsia for/

Cynthia D. Pederson, Director Division of Reactor Projects Docket Nos. 50-454, 50-455 License Nos. NPF-37; NPF-66

Enclosure:

Byron Station Inspection/Activity Plan DISTRIBUTION:

See next page DOCUMENT NAME:G:\Branch TSS\ALL MOC\midcycle 2006 to 2007\Byron\Byron MOC 2007 Letter.wpd G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive

  • See previous concurrence To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME RSkokowski*:dtp CPederson*AHH for DATE 08/29/07 08/30/07 OFFICIAL RECORD COPY

Letter to C. Crane from C. Pederson dated August 31, 2007

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

BYRON STATION cc w/encl: Site Vice President - Byron Station Plant Manager - Byron Station Regulatory Assurance Manager - Byron Station Chief Operating Officer Senior Vice President - Nuclear Services Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing Manager Licensing - Braidwood and Byron Senior Counsel, Nuclear Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency State Liaison Officer, State of Illinois State Liaison Officer, State of Wisconsin Chairman, Illinois Commerce Commission B. Quigley, Byron Station President, Village of Leaf River President, Village of Davis Junction President, Village of Stillman Valley Ogle County Board Chairman Ogle County Sheriff/EMA Coordinator EMA Coordinator, Winnebago County Winnebago County Board Chair Winnebago County Sheriff/ESDA Mayor of Oregon Mayor of Byron President, Village of Mt. Morris Mayor of Rochelle INPO

Letter to C. Crane from C. Pederson dated August 31, 2007

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

BYRON STATION DISTRIBUTION:

RAG1 TEB RFK RidsNrrDirslpab JLC1 MAS KGO JKH3 RML2 SAM9 SRI Byron DRPIII DRSIII PLB1 TXN

Byron Inspection / Activity Plan 09/01/2007 - 12/31/2008 No. of Staff Planned Dates Inspection Inspection Activity Title on Site Start End Type BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 09/05/2007 09/06/2007 Baseline Inspections IP 71151-BI01 Reactor Coolant System Activity 09/05/2007 09/06/2007 Baseline Inspections IP 71151-OR01 Occupational Exposure Control Effectiveness 09/05/2007 09/06/2007 Baseline Inspections IP 71151-PR01 RETS/ODCM Radiological Effluent 09/05/2007 09/06/2007 Baseline Inspections BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P 11/05/2007 11/09/2007 Baseline Inspections BI ENG - TRIENNIAL FIRE PROTECTION INSPECTION 3 IP 7111105T Fire Protection [Triennial] 11/12/2007 11/30/2007 Baseline Inspections BI ENG - ENGINEERING MODIFICATIONS / 50.59 INSP. 2 IP 7111102 Evaluation of Changes, Tests, or Experiments 01/14/2008 02/01/2008 Baseline Inspections IP 7111117B Permanent Plant Modifications 01/14/2008 02/01/2008 Baseline Inspections OL EXAM - BYRON INITIAL LIC ON-SITE VALIDATION 6 W90180 BYRON - INITIAL EXAM - APRIL/MAY 2008 04/28/2008 05/02/2008 Not Applicable BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 7112101 Access Control to Radiologically Significant Areas 03/24/2008 03/28/2008 Baseline Inspections IP 7112102 ALARA Planning and Controls 03/24/2008 03/28/2008 Baseline Inspections BI ENG - ENGINEERING INSERVICE INSPECTION 1 IP 7111108P Inservice Inspection Activities - PWR 03/17/2008 04/11/2008 Baseline Inspections BI EP - EP ROUTINE INSPECTION / PI VERIFICATION 1 IP 7111402 Alert and Notification System Testing 04/07/2008 04/11/2008 Baseline Inspections IP 7111403 Emergency Response Organization Augmentation Testing 04/07/2008 04/11/2008 Baseline Inspections IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 04/07/2008 04/11/2008 Baseline Inspections IP 71151-EP01 Drill/Exercise Performance 04/07/2008 04/11/2008 Baseline Inspections IP 71151-EP02 ERO Drill Participation 04/07/2008 04/11/2008 Baseline Inspections IP 71151-EP03 Alert & Notification System 04/07/2008 04/11/2008 Baseline Inspections OL EXAM - BYRON INITIAL LICENSE EXAM (05/19 - 30) 6 W90122 OL - INITIAL EXAM - BYRON - MAY/JUN 2006 05/19/2008 05/30/2008 Not Applicable ISFSI - ISFSI INSPECTION 1 IP 60856 Review of 10 CFR 72.212(b) Evaluations 07/01/2008 09/01/2008 Other Routine BI ENG - COMPONENT DESIGN BASES INSPECTION 5 IP 7111121 Component Design Bases Inspection 07/21/2008 08/22/2008 Baseline Inspections BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 08/11/2008 08/15/2008 Baseline Inspections IP 71151-BI01 Reactor Coolant System Activity 08/11/2008 08/15/2008 Baseline Inspections

Byron Inspection / Activity Plan 09/01/2007 - 12/31/2008 No. of Staff Planned Dates Inspection Inspection Activity Title on Site Start End Type BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 71151-OR01 Occupational Exposure Control Effectiveness 08/11/2008 08/15/2008 Baseline Inspections IP 71151-PR01 RETS/ODCM Radiological Effluent 08/11/2008 08/15/2008 Baseline Inspections BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 7112101 Access Control to Radiologically Significant Areas 10/06/2008 10/10/2008 Baseline Inspections IP 7112102 ALARA Planning and Controls 10/06/2008 10/10/2008 Baseline Inspections BI ENG - ENGINEERING INSERVICE INSPECTION 1 IP 7111108P Inservice Inspection Activities - PWR 10/06/2008 10/24/2008 Baseline Inspections BI OL - BIENNIAL REQUAL. PROGRAM INSPECTION 2 IP 7111111B Licensed Operator Requalification Program 11/03/2008 11/07/2008 Baseline Inspections BI ENG - BIENNIAL HEAT SINK INSPECTION 1 IP 7111107B Heat Sink Performance 12/01/2008 12/05/2008 Baseline Inspections