Request for Additional Information for the Review of the Susquehanna Steam Electric Station, Units 1 and 2, License Renewal Application (RAI 2.5-1 to RAI 2.5-2)
ML071970114
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 07/30/2007
From: Gettys E
NRC/NRR/ADRO/DLR/RLRA
To: Mckinney B
Susquehanna
Gettys Evelyn, NRR/DLR/RLRA 415-4029
References
TAC MD3019, TAC MD3020
Download: ML071970114 (7)


Text

July 30, 2007 Mr. Britt T. McKinney Sr. Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION

Dear Mr. McKinney:

By letter dated September 13, 2006, PPL Susquehanna, LLC submitted an application pursuant to 10 CFR Part 54, to renew the operating licenses for Susquehanna Steam Electric Station, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.

The request for additional information were discussed with Duane Filchner, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me at 301-415-4029 or e-mail EHG@nrc.gov.

Sincerely,

/RA/

Evelyn Gettys, Project Manager License Renewal Branch A Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388

Enclosure:

Request for Additional Information cc w/encl: See next page

ML071970114 OFFICE LA:DLR PM:RLRA:DLR BC:RLRA:DLR NAME IKing EGettys LLund DATE 07/30/07 07/30/07 07/30/07

Letter to B. McKinney from E. Gettys Dated July 30, 2007

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC SSmith (srs3)

SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDci RidsNrrDra RidsNrrDe RidsNrrDeEemb RidsNrrDeEeeb RidsNrrDss RidsOgcMailCenter RidsNrrAdes YDiaz RGuzman BRogers EGettys

Susquehanna Steam Electric Station, Units 1 and 2 cc:

Robert A. Saccone Vice President - Nuclear Operations PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467 Terry L. Harpster General Manager - Plant Support PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467 Rocco R. Sgarro Manager - Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Walter E. Morrissey Supervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467 Michael H. Crowthers Supervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Steven M. Cook Manager - Quality Assurance PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467 Luis A. Ramos Community Relations Manager, Susquehanna PPL Susquehanna, LLC 634 Salem Blvd., SSO Berwick, PA 18603-0467 Bryan A. Snapp, Esq.

Associate General Counsel PPL Services Corporation Two North Ninth Street, GENTW3 Allentown, PA 18101-1179 Supervisor - Document Control Services PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Richard W. Osborne Allegheny Electric Cooperative, Inc.

212 Locust Street P.O. Box 1266 Harrisburg, PA 17108-1266 Director, Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 35, NUCSA4 Berwick, PA 18603-0035 Regional Administrator, Region 1 U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Board of Supervisors Salem Township P.O. Box 405 Berwick, PA 18603-0035

Susquehanna Steam Electric Station, Units 1 and 2 cc: Dr. Judith Johnsrud National Energy Committee Sierra Club 443 Orlando Avenue State College, PA 16803 Ms. Julie Keys Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708

Enclosure SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION REQUEST FOR ADDITIONAL INFORMATION (RAI)

RAI 2.5-1 The General Design Criterion 17 described in Title 10 Code of Federal Regulations Part 50 (10 CFR Part 50), Appendix A, requires that electric power from the transmission network to the onsite electric distribution system be supplied by two physically independent circuits to minimize the likelihood of their simultaneous failure. In addition, the guidance provided by letter dated April 1, 2002, Staff Guidance on Scoping of Equipment Relied on to Meet the Requirements of the Station Blackout Rule (10 CFR 50.63) for License Renewal (10 CFR 54.4(a)(3)), states:

For purposes of the license renewal rule, the staff has determined that the plant system portion of the offsite power system that is used to connect the plant to the offsite power source should be included within the scope of the rule. This path typically includes switchyard circuit breakers that connect to the offsite system power transformers (startup transformers), the transformers themselves, the intervening overhead or underground circuits between circuit breaker and transformer and transformer and onsite electrical system, and the associated control circuits and structures. Ensuring that the appropriate offsite power system long-lived passive structures and components that are part of this circuit path are subject to an aging management review will assure that the bases underlying the SBO requirements are maintained over the period of extended license.

According to the above, both paths, from the safety-related 4 kiloVolt (kV) buses to the first circuit breaker from the offsite line, used to control the offsite circuits to the plant should be age managed. The guidance does not specify that the switchyard is not part of the plant system nor that the switchyard does not need to be included in the scope of license renewal. According to Section 2.5 of the license renewal application, the high voltage switchyard circuit breakers that connect to the offsite sources, the circuits connecting the startup transformers to the switchyard and the associated components and structures are not presently included within the scope of license renewal. Justify why these components are not within the scope of license renewal. In addition, explain in detail which high voltage breakers and other components in the switchyard will be connected from the startup transformers T10 and T20 up to the offsite power system for the purpose of station blackout recovery.