July 5, 2007 Carolina Power and Light Company ATTN: Mr. Robert J. Duncan, II Vice President - Harris Plant Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Code: Zone 1 New Hill, North Carolina 27562-0165
SUBJECT:
MEETING ANNOUNCEMENT - PUBLIC MEETING SHEARON HARRIS NUCLEAR POWER PLANT DOCKET NO. 50 - 400
Dear Mr. Duncan:
This letter confirms the telephone conversation between Mr. Mike Heath of your staff and Mr. Caudle Julian of this office on July 2, 2007, concerning an inspection exit meeting (Category One public meeting) which has been scheduled for July 27, 2007, beginning at 9:00 a.m. (EDT). The meeting notice, which provides location and additional details, is enclosed. The purpose of the meeting is for the NRC to present the results of the NRCs inspection of the Harris Nuclear Power Plant license renewal program to be conducted July 9 - 27, 2007, at the Harris site.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/NRC/ADAMS/index.html (the Public Electronic Reading Room).
Should you have any questions concerning this meeting, please contact Caudle A. Julian at (404) 562-0545.
Sincerely,
/RA by Robert Carrion for/
George T Hopper, Chief Engineering Branch 3 Division of Reactor Safety Docket No.:
50-400 License No.:
Enclosure:
As stated
OFFICE RII:DRP RII:CIP SIGNATURE RAM RPC1 for NAME RMusser CJulian DATE 07/05 /2007 07/05/2007 7/ /2007 7/ /2007 7/ /2007 7/ /2007 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO YES NO
2 cc w/encl:
Paul Fulford, Manager Performance Evaluation and Regulatory Affairs PEB 5 Carolina Power & Light Company Electronic Mail Distribution Chris L. Burton Director of Site Operations Carolina Power & Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution Eric McCartney Plant General Manager--Harris Plant Progress Energy Carolinas, Inc.
Shearon Harris Nuclear Power Plant Electronic Mail Distribution J. Wayne Gurganious Training Manager-Harris Plant Progress Energy Carolinas, Inc.
Harris Energy & Environmental Center Electronic Mail Distribution Thomas J. Natale, Manager Support Services Carolina Power & Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution David H. Corlett, Supervisor Licensing/Regulatory Programs Carolina Power & Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution David T. Conley Associate General Counsel - Legal Department Progress Energy Service Company, LLC Electronic Mail Distribution John H. O'Neill, Jr.
Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washington, DC 20037-1128 Beverly Hall, Chief, Radiation Protection Section N. C. Department of Environmental Commerce & Natural Resources Electronic Mail Distribution Public Service Commission State of South Carolina P. O. Box 11649 Columbia, SC 29211 Chairman of the North Carolina Utilities Commission c/o Sam Watson, Staff Attorney Electronic Mail Distribution Robert P. Gruber Executive Director Public Staff NCUC 4326 Mail Service Center Raleigh, NC 27699-4326 Herb Council, Chair Board of County Commissioners of Wake County P. O. Box 550 Raleigh, NC 27602 Tommy Emerson, Chair Board of County Commissioners of Chatham County Electronic Mail Distribution Distribution (See page 3)
3 Meeting Notice to Robert J. Duncan, II from George T. Hopper dated July 5, 2007.
SUBJECT:
SHEARON HARRIS NUCLEAR POWER PLANT - NRC INSPECTION REPORT 05000400/2007007 Distribution w/encl:
Region II Administrators Secretary Region II DRP Division Secretary Region II Division Directors and Deputies Region II Counsel Region II State Liaison Officer Region II Public Affairs Officer Region II Resource Management Branch Region II Receptionist Region II Regional Coordinator OEDO Headquarters Operations Officer PMNS P. OBryan, DRP C. Julian, CIP M. Heath, NRR L. Regner, NRR T. Boyce, NRR C. Evans (Part 72 Only)
L. Slack, RII EICS RIDSNRRDIRS OE Mail (email address if applicable)
PUBLIC
SUBJECT:
PUBLIC MEETING WITH PROGRESS ENERGY FACILITY:
SHEARON HARRIS NUCLEAR PLANT DOCKET:
50 - 400 DATE & TIME:
Friday, July 27, 2007 9:00 a.m. (EDT)
LOCATION:
New Horizons Fellowship Annex 820 E. Williams St.
Apex, NC 27502 PURPOSE:
The NRCs Policy Statement Enhancing Public Participation in NRC meetings, effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC Web site, www.nrc.gov, and contains information regarding visitors and security.
CATEGORY:
This is a Category 1 meeting: The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.
NRC OFFICES PARTICIPATING:
Region II PARTICIPANTS:
NRC Caudle Julian Inspection Team Leader, DRS, RII Phil OBryan Senior Resident Inspector LICENSEE Mike Heath, Manager Harris License Renewal Project Other members of Harris staff MEETING CONTACT: Caudle Julian, NRC, RII, (404) 562-0545 caj@nrc.gov