June 21, 2007 MEETING

SUMMARY

LICENSEE:

ENTERGY NUCLEAR OPERATIONS, INC.

FACILITY:

JAMES A. FITZPATRICK NUCLEAR POWER PLANT

SUBJECT:

SUMMARY

OF JUNE 5, 2007, ANNUAL ASSESSMENT MEETING WITH ENTERGY NUCLEAR NORTHEAST On June 5, 2007 at 12:30 p.m., an annual assessment meeting was conducted at the Joint News Center in Fulton, New York, between the Nuclear Regulatory Commission (NRC) and Entergy Nuclear Operations, Inc. (Entergy). The NRC requested the meeting with Entergy officials to discuss the NRCs assessment of the safety performance of the James A.

FitzPatrick Nuclear Power Plant for calendar year 2006. A list of meeting attendees is attached.

The NRC presented and discussed its assessment of the safety performance of the James A.

FitzPatrick Nuclear Power Plant for the period of January 1 through December 31, 2006. The NRC presentation included a discussion on the NRC, its strategic goals, the Reactor Oversight Process, and performance assessment results for calendar year 2006. As part of this regulatory performance meeting, Entergy acknowledged and agreed with NRC's assessment and presented its perspective on the stations performance.

The NRC and Entergy presentations were followed by a short question and answer period.

Feedback forms submitted by the public following the meeting will be evaluated. NRCs assessment letter can be found in ADAMS with an accession number of ML070610609. The annual assessment meeting notice with the attached meeting agenda, and the NRC and Entergy meeting slides can be located in ADAMS package ML070950570. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA by Blake D. Welling For/

Eugene W. Cobey, Chief Projects Branch 2 Division of Reactor Projects

Attachment:

Meeting Attendees

2 Meeting Attendees Name Bonnie Bostian Wayne Rheaume Jim Costedio Kay Daitcher Gene Dorman Kevin Mulligan Steve Bono Tim Page Tom Gurdziel Ed Stronski Pete Dietrich Organization (If Any)

Entergy Entergy Entergy GP Entergy Entergy Entergy Entergy local resident citizen Entergy

2 Meeting Attendees Name Bonnie Bostian Wayne Rheaume Jim Costedio Kay Daitcher Gene Dorman Kevin Mulligan Steve Bono Tim Page Tom Gurdziel Ed Stronski Pete Dietrich Organization (If Any)

Entergy Entergy Entergy GP Entergy Entergy Entergy Entergy local resident citizen Entergy Distribution:

E. Cobey, DRP B. Welling, DRP D. Orr, DRP G. Hunegs, DRP, SRI D. Dempsey, DRP, RI R. Martin, DRP, OA SUNSI Review Complete: BDW (Reviewers Initials)

DOCUMENT NAME: C:\\FileNet\\ML071720269.wpd After declaring this document An Official Agency Record it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP NAME BWelling ECobey/BDW FOR DATE 06/20/07 06/20/07 OFFICIAL RECORD COPY ML071720269