ET 07-0018, Responses A24 - A30, A33 and A36 - A37 to Additional Information Needs Identified During Audit of NRC Request for Additional Information Related to License Renewal Application
From kanterella
(Redirected from ML071450173)
Jump to navigation
Jump to search
ML071450173 | |
Person / Time | |
---|---|
Site: | Wolf Creek |
Issue date: | 05/09/2007 |
From: | Garrett T Wolf Creek |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
ET 07-0018 | |
Download: ML071450173 (730) | |
Similar Documents at Wolf Creek | |
---|---|
Category:Environmental Impact Statement
MONTHYEARML0812606082008-05-31031 May 2008
[Table view]NUREG-1437, Supp No. 32, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Final Report ML0812807492008-05-0808 May 2008 Notice of Availability of the Final Plant-Specific Supplement 32 to the Generic Environmental Impact Statement for Licence Renewal of Nuclear Plants Regarding Wolf Creek Generating Station (TAC MD3182) - FRN ML0714501182007-05-0909 May 2007 Response 62, to Environmental Report - References of NRC Request for Additional Information Re License Renewal Application ML0714501152007-05-0909 May 2007 Response to Environmental Report - References of NRC Request for Additional Information Re License Renewal Application, Consisting of Draft Supplement to the Final Environmental Impact Statement for Reallocation of Water Supply Storage ET 07-0015, Response 62 Continue, to Environmental Report - References of NRC Request for Additional Information Re License Renewal Application2007-05-0909 May 2007 Response 62 Continue, to Environmental Report - References of NRC Request for Additional Information Re License Renewal Application ET 07-0018, Responses A24 - A30, A33 and A36 - A37 to Additional Information Needs Identified During Audit of NRC Request for Additional Information Related to License Renewal Application2007-05-0909 May 2007 Responses A24 - A30, A33 and A36 - A37 to Additional Information Needs Identified During Audit of NRC Request for Additional Information Related to License Renewal Application 2008-05-08 Category:Environmental Report MONTHYEARML13127A0842013-04-29029 April 2013
[Table view]2012 Annual Radioactive Effluent Release Report - Report 36 ML13142A3102013-04-24024 April 2013 Operating Corp. - Annual Radiological Environmental Operating Report ML11123A1932011-04-27027 April 2011 Submittal of 2010 Annual Radiological Environmental Operating Report ML11109A0662011-04-11011 April 2011 2010 Annual Environmental Operating Report ET 07-0017, Response 64, to Master List for Audit Needs of NRC Request for Additional Information Re License Renewal Application2007-05-0909 May 2007 Response 64, to Master List for Audit Needs of NRC Request for Additional Information Re License Renewal Application ET 07-0018, Responses A24 - A30, A33 and A36 - A37 to Additional Information Needs Identified During Audit of NRC Request for Additional Information Related to License Renewal Application2007-05-0909 May 2007 Responses A24 - A30, A33 and A36 - A37 to Additional Information Needs Identified During Audit of NRC Request for Additional Information Related to License Renewal Application ML0714303632007-05-0909 May 2007 Responses 2 - 10, to Master List for Audit Needs of NRC Request for Additional Information Re License Renewal Application ML0714303672007-05-0909 May 2007 Response 11, to Master List for Audit Needs of NRC Request for Additional Information Re License Renewal Application ML0714303722007-05-0909 May 2007 Responses 20 - 29, to Master List for Audit Needs of NRC Request for Additional Information Re License Renewal Application ML0714303822007-05-0909 May 2007 Responses 30 - 33, and 38, to Master List for Audit Needs of NRC Request for Additional Information Re License Renewal Application ML0714304972007-05-0909 May 2007 Responses 39, 41- 44, and 46 - 51, to Master List for Audit Needs of NRC Request for Additional Information Re License Renewal Application ML0714305402007-05-0909 May 2007 Responses 52 - 56, to Master List for Audit Needs of NRC Request for Additional Information Re License Renewal Application ML0714305882007-05-0909 May 2007 Responses 12 - 15, 17, and 19, to Master List for Audit Needs of NRC Request for Additional Information Re License Renewal Application ML0714403742007-05-0909 May 2007 Responses 1, 2, 3, 5, 8, 9 & 10 to Environmental Report - References of NRC Request for Additional Information Re License Renewal Application ML0714403772007-05-0909 May 2007 Response 12 to Environmental Report - References of NRC Request for Additional Information Re License Renewal Application ML0714501482007-05-0909 May 2007 Responses A1 - A10 to Additional Information Needs Identified During Audit of NRC Request for Additional Information Related to License Renewal Application ML0714501492007-05-0909 May 2007 Responses A11 - A19 and A23 to Additional Information Needs Identified During Audit of NRC Request for Additional Information Related to License Renewal Application ML0714501502007-05-0909 May 2007 Responses A39 - A45 and A48 - A50 to Additional Information Needs Identified During Audit of NRC Request for Additional Information Related to License Renewal Application ML0714305472007-05-0909 May 2007 Responses 58 - 62, 67, 69, and 70, to Master List for Audit Needs of NRC Request for Additional Information Re License Renewal Application ML0714501512007-05-0909 May 2007 Responses A51 - A54 and A61 - A66 to Additional Information Needs Identified During Audit of NRC Request for Additional Information Related to License Renewal Application ML0711501302007-04-19019 April 2007 2006 Annual Radiological Environmental Operating Report for the Period of January 1, 2006 Through December 31, 2006 ML0633803132006-11-30030 November 2006 Transmission Lines Figure 3-2 ML0627703052006-09-27027 September 2006 Applicants Environmental Report; Operating License Renewal Stage ML0612301102006-04-27027 April 2006 Annual Radiological Environmental Operating Report ML0511202022005-04-15015 April 2005 2004 Annual Radiological Environmental Operating Report ML0510404282005-04-0808 April 2005 2004 Annual Environmental Operating Report ML0512403392004-12-31031 December 2004 Annual Radioactive Effluent Release Report, Report 28, 01/01/2004 Through 12/31/2004 ML0512403482004-09-29029 September 2004 Attachment I, Wolf Creek Generating Station, Administrative Procedure AP 07B-003, Revision 5, Offsite Dose Calculation Manual ML0411200432004-04-15015 April 2004 Annual Radiological Environmental Operating Report ML0411200752004-04-14014 April 2004 Annual Environmental Operating Report ML0312605242003-04-29029 April 2003 Annual Environmental Operating Report RA-03-0059, Submittal of Wolf Creek Nuclear Operating Corporation Evaluation of Stress Corrosion Cracking for Component Cooling Water System Piping2003-04-18018 April 2003 Submittal of Wolf Creek Nuclear Operating Corporation Evaluation of Stress Corrosion Cracking for Component Cooling Water System Piping 2013-04-29 Category:Letter type:ET MONTHYEARET 23-0006, CFR 50.55a Request Number CI3R-01 for the Third Containment Inservice Inspection Program Interval for Proposed Alternative Frequency to Containment Unbonded Post-Tensioning System Components2023-05-17017 May 2023
[Table view]CFR 50.55a Request Number CI3R-01 for the Third Containment Inservice Inspection Program Interval for Proposed Alternative Frequency to Containment Unbonded Post-Tensioning System Components ET 23-0005, 10 CFR 50.55a Request Number I4R-08 for the Fourth Inservice Inspection Program Interval, Relief for Extension of Follow Up Examination Requirements for Reactor Pressure Vessel Head Penetration Nozzles with Mitigated Alloy 600/82/182 Peen2023-03-16016 March 2023 10 CFR 50.55a Request Number I4R-08 for the Fourth Inservice Inspection Program Interval, Relief for Extension of Follow Up Examination Requirements for Reactor Pressure Vessel Head Penetration Nozzles with Mitigated Alloy 600/82/182 Peened ET 23-0003, License Amendment Request (LAR) for Removal of the Power Range Neutron Flux Rate - High Negative Rate Trip Function from Technical Specifications2023-03-0101 March 2023 License Amendment Request (LAR) for Removal of the Power Range Neutron Flux Rate - High Negative Rate Trip Function from Technical Specifications ET 23-0002, Supplement to License Amendment Request to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections2023-02-0707 February 2023 Supplement to License Amendment Request to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ET 23-0004, Response to Requests for Additional Information (RAI) Regarding License Amendment Request (LAR) for Deviation from Fire Protection Program Requirements2023-01-26026 January 2023 Response to Requests for Additional Information (RAI) Regarding License Amendment Request (LAR) for Deviation from Fire Protection Program Requirements ET 22-0006, Operating Corp. - Application to Revise Technical Specifications to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections2022-12-0101 December 2022 Operating Corp. - Application to Revise Technical Specifications to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ET 22-0010, License Amendment Request (LAR) for Deviation from Fire Protection Program Requirements2022-08-0202 August 2022 License Amendment Request (LAR) for Deviation from Fire Protection Program Requirements ET 22-0012, Supplement to License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating2022-07-12012 July 2022 Supplement to License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating ET 22-0011, Withdrawal of 10 CFR 50.55a Request I4R-08, Relief for Extension of Follow-up Examination and Visual Examination Requirements for Reactor Pressure Vessel Head Penetration Nozzles with Mitigated Alloy 600/82/182 Peened Surface2022-05-31031 May 2022 Withdrawal of 10 CFR 50.55a Request I4R-08, Relief for Extension of Follow-up Examination and Visual Examination Requirements for Reactor Pressure Vessel Head Penetration Nozzles with Mitigated Alloy 600/82/182 Peened Surface ET 22-0005, Response to Request for Additional Information Regarding License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating2022-04-13013 April 2022 Response to Request for Additional Information Regarding License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating ET 22-0003, CFR 50.55a Request I4R-09 for the Fourth Inservice Inspection Program Interval, Relief from Examination of Reactor Vessel Flange Threads2022-04-0606 April 2022 CFR 50.55a Request I4R-09 for the Fourth Inservice Inspection Program Interval, Relief from Examination of Reactor Vessel Flange Threads ET 22-0002, Operating Corp 10 CFR 50.55a Request Number I4R-08 for the Fourth Inservice Inspection Program Interval, Relief for Extension of Follow Up Examination and Visual Examination Requirements for Reactor Pressure Vessel Head .2022-04-0404 April 2022 Operating Corp 10 CFR 50.55a Request Number I4R-08 for the Fourth Inservice Inspection Program Interval, Relief for Extension of Follow Up Examination and Visual Examination Requirements for Reactor Pressure Vessel Head . ET 22-0004, Operating Corp - Response to Request for Confirmation of Information (RCI) Regarding Steam Generator Tube Inspection Report2022-03-15015 March 2022 Operating Corp - Response to Request for Confirmation of Information (RCI) Regarding Steam Generator Tube Inspection Report ET 22-0001, Removal of the Table of Contents from the Technical Specifications2022-01-12012 January 2022 Removal of the Table of Contents from the Technical Specifications ET 21-0017, Response to Request for Additional Information Regarding License Amendment Request - Revision to Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation2021-12-22022 December 2021 Response to Request for Additional Information Regarding License Amendment Request - Revision to Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation ET 21-0009, Results of the Steam Generator Tube Inservice Inspection During the 24th Refueling Outage2021-11-0101 November 2021 Results of the Steam Generator Tube Inservice Inspection During the 24th Refueling Outage ET 21-0015, Withdrawal of License Amendment Request for a Risk-Informed Resolution to GSI-1912021-10-20020 October 2021 Withdrawal of License Amendment Request for a Risk-Informed Resolution to GSI-191 ET 21-0012, Supplement to License Amendment Request for a Risk-Informed Resolution to GSI-1912021-10-11011 October 2021 Supplement to License Amendment Request for a Risk-Informed Resolution to GSI-191 ET 21-0004, License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating2021-09-29029 September 2021 License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating ET 21-0010, License Amendment Request - Revision to Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation2021-09-29029 September 2021 License Amendment Request - Revision to Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation ET 21-0005, Operating Corp., License Amendment Request for a Risk-Informed Resolution to GSI-1912021-08-12012 August 2021 Operating Corp., License Amendment Request for a Risk-Informed Resolution to GSI-191 ET 20-0013, Response to Request for Additional Information Re Application for Technical Specification Change Re Risk-Informed Justification for Relocation of Specific Surveillance Frequency Requirements to Licensee Controlled Program (TSTF-415)2020-10-26026 October 2020 Response to Request for Additional Information Re Application for Technical Specification Change Re Risk-Informed Justification for Relocation of Specific Surveillance Frequency Requirements to Licensee Controlled Program (TSTF-415) ET 20-0011, Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2020-10-0101 October 2020 Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI ET 20-0007, License Amendment Request for Replacement of Engineered Safety Features Transformers with New Transformers That Have Active Automatic Load Tap Changers2020-06-0808 June 2020 License Amendment Request for Replacement of Engineered Safety Features Transformers with New Transformers That Have Active Automatic Load Tap Changers ET 20-0008, Operating Corporation Update for Full Implementation of Open Phase Detection System2020-05-20020 May 2020 Operating Corporation Update for Full Implementation of Open Phase Detection System ET 20-0004, Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (TSTF-425)2020-04-27027 April 2020 Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (TSTF-425) ET 20-0002, Response to Request for Additional Information Regarding Utilizing Code Case N-666-1, Weld Overlay of Class 1, 2, and 3 Socket Welded Connections, Section XI, Division 12020-01-29029 January 2020 Response to Request for Additional Information Regarding Utilizing Code Case N-666-1, Weld Overlay of Class 1, 2, and 3 Socket Welded Connections, Section XI, Division 1 ET 19-0021, Errata for Supplemental Response to Request for Additional Information Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation2019-12-0909 December 2019 Errata for Supplemental Response to Request for Additional Information Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation ET 19-0020, Supplemental Response to Request for Additional Information Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation2019-11-13013 November 2019 Supplemental Response to Request for Additional Information Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation ET 19-0019, Response to Request for Additional Information Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation2019-09-10010 September 2019 Response to Request for Additional Information Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation ET 19-0018, Supplement to License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation2019-08-22022 August 2019 Supplement to License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation ET 19-0014, Lnserv1ce Inspection (ISI) Program Relief Request Number 14R-07, to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, D1v1s1on 12019-08-15015 August 2019 Lnserv1ce Inspection (ISI) Program Relief Request Number 14R-07, to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, D1v1s1on 1 ET 19-0002, License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation2019-03-18018 March 2019 License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation ET 19-0008, Response to Request for Additional Information Related to Thermal Conductivity Degradation for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption2019-03-0505 March 2019 Response to Request for Additional Information Related to Thermal Conductivity Degradation for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption ET 19-0003, License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Remove Use of a Blind Flange2019-02-25025 February 2019 License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Remove Use of a Blind Flange ET 19-0001, Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 42019-01-23023 January 2019 Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4 ET 18-0032, Operating Corporation Change of Date for Full Implementation of Open Phase Detection System2018-12-0707 December 2018 Operating Corporation Change of Date for Full Implementation of Open Phase Detection System ET 18-0035, Operating Corp., Supplemental Response to RAI for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-12-0606 December 2018 Operating Corp., Supplemental Response to RAI for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term ET 18-0029, (WCGS) - Results of the Twenty First Steam Generator Tube Inservice Inspection2018-10-31031 October 2018 (WCGS) - Results of the Twenty First Steam Generator Tube Inservice Inspection ET 18-0018, Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-06-19019 June 2018 Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term ET 18-0014, Response to Request for Additional Information Regarding the License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System2018-05-29029 May 2018 Response to Request for Additional Information Regarding the License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System ET 18-0016, Response to Generic Letter 2016-01, Monitoring of Neutron Absorbing Materials in Spent Fuel Pools Request for Supplemental Information2018-05-29029 May 2018 Response to Generic Letter 2016-01, Monitoring of Neutron Absorbing Materials in Spent Fuel Pools Request for Supplemental Information ET 18-0013, Relief Request Number I4R-06, Request for Relief from ASME Code Case N-729-4 for Reactor Vessel Head Penetration Nozzle Weld2018-05-0202 May 2018 Relief Request Number I4R-06, Request for Relief from ASME Code Case N-729-4 for Reactor Vessel Head Penetration Nozzle Weld ET 18-0011, (WCGS) - Guarantee of Payment of Deferred Premiums2018-04-30030 April 2018 (WCGS) - Guarantee of Payment of Deferred Premiums ET 18-0012, Operating Corp., Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-04-19019 April 2018 Operating Corp., Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term ET 18-0010, Financial Protection Levels2018-03-29029 March 2018 Financial Protection Levels ET 18-0007, Supplement to License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System2018-02-15015 February 2018 Supplement to License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System ET 18-0005, Withdrawal of License Amendment Request for Revision to the Emergency Plan2018-02-0505 February 2018 Withdrawal of License Amendment Request for Revision to the Emergency Plan ET 18-0004, Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-01-29029 January 2018 Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term ET 17-0025, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analyses Including Adoption of Alternative Source Term2017-11-14014 November 2017 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analyses Including Adoption of Alternative Source Term 2023-05-17 |