MONTHYEARML23342A1162024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 IR 05000219/20230022023-11-0909 November 2023 EA-23-076 Oyster Creek Nuclear Generating Station - Notice of Violation and Proposed Imposition of Civil Penalty - $43,750 - NRC Inspection Report No. 05000219/2023002 ML23286A1552023-10-13013 October 2023 Defueled Safety Analysis Report (DSAR) ML23249A1212023-09-0606 September 2023 NRC Inspection Report 05000219/2023002, Apparent Violation (EA-23-076) ML23242A1162023-08-30030 August 2023 Biennial 10 CFR 50.59 and 10 CFR 72.48 Change Summary Report January 1, 2021 Through December 31, 2022 ML23214A2472023-08-22022 August 2023 NRC Inspection Report 05000219/2023002 IR 05000219/20230012023-05-31031 May 2023 NRC Inspection Report No. 05000219/2023001 IR 07200015/20234012023-05-16016 May 2023 NRC Independent Spent Fuel Storage Installation Security Inspection Report 07200015/2023401 ML23114A0912023-04-24024 April 2023 Annual Radioactive Effluent Release Report for 2022 ML23114A0872023-04-24024 April 2023 Annual Radioactive Environmental Operating Report for 2022 L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000219/20220022023-02-0909 February 2023 NRC Inspection Report No. 05000219/2022002 ML23031A3012023-02-0808 February 2023 Discontinuation of Radiological Effluent Monitoring Location in the Sewerage System ML23033A5052023-02-0202 February 2023 First Use Notification of NRC Approved Cask RT-100 ML23025A0112023-01-24024 January 2023 LLRW Late Shipment Investigation Report Per 10 CFR 20, Appendix G ML22347A2732022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 ML22297A1432022-12-15015 December 2022 Part 20 App G Exemption Letter L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 IR 07200015/20224012022-12-0606 December 2022 NRC Independent Spent Fuel Storage Installation Security Inspection Report 07200015/2022401 (Letter & Enclosure 1) ML22280A0762022-11-0202 November 2022 Us NRC Analysis of Holtec Decommissioning Internationals Funding Status Report for Oyster Creek, Indian Point and Pilgrim Nuclear Power Station ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22286A1402022-10-13013 October 2022 NRC Confirmatory Order EA-21-041 IR 05000219/20220012022-08-11011 August 2022 NRC Inspection Report 05000219/2022001 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22214A1732022-08-0202 August 2022 Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E ML22207B8382022-07-26026 July 2022 NRC Confirmatory Order EA-21-041 ML22130A6882022-05-10010 May 2022 Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G L-22-026, Occupational Radiation Exposure Data Report - 20212022-04-29029 April 2022 Occupational Radiation Exposure Data Report - 2021 ML22118A6122022-04-28028 April 2022 Annual Radioactive Environmental Operating Report for 2021 ML22118A5822022-04-28028 April 2022 Annual Radioactive Effluent Release Report for 2021 ML22091A1062022-04-0101 April 2022 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) L-22-022, and Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations - Holtec.2022-03-25025 March 2022 and Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations - Holtec. ML22069A3762022-03-10010 March 2022 Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G ML22032A0582022-03-0808 March 2022 EA-21-139; EA-150: Oyster Creek Nuclear Generating Station - NRC Investigation Report Nos.. 1-2021-002 & 1-2021-014 ML22060A2202022-03-0202 March 2022 NRC Office of Investigations Case No. 1-2021-009 ML22049B2452022-02-19019 February 2022 Late Low Level Radwaste Shipment Report Pursuant to 10 CFR 20 Appendix G IR 05000219/20214022022-01-26026 January 2022 EA-21-041: Confirmatory Order Related to Oyster Greek Nuclear Generating Station - NRC Investigation Report I-2020-007; NRC Inspection Report Nos. 05000219/2021402 & 07200015/2021401 ML22025A3422022-01-25025 January 2022 and Big Rock Point - Changes to Site Organization ML22025A2182022-01-25025 January 2022 Late LLRW Shipments Investigation Report Pursuant to 10 CFR 20, Appendix G ML22021B5512022-01-21021 January 2022 Compensatory Measures Not Implemented Per Site'S Physical Security Plan Due to Multiplexer (Mux) Power Supply Failure L-21-134, and Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Independent Spent Fuel Storage Installations2021-12-17017 December 2021 and Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Independent Spent Fuel Storage Installations ML21349A5192021-12-15015 December 2021 Commitment Change Summary Report ML21285A1912021-11-30030 November 2021 Nrc'S Analysis of Holtec Decommissioning International'S Decommissioning Funding Status Report for Oyster Creek Nuclear Generating Station and Pilgrim Nuclear Power Station, Docket Nos 50-219 and 50-293 IR 05000219/20210032021-11-16016 November 2021 NRC Inspection Report No. 05000219/2021003 L-21-118, Changes to Signature Authority & Addressee for Holtec Decommissioning International, LLC Correspondence Re to Oyster Creek Nuclear Generating Station, Pilgrim Nuclear Power Station, Indian Point Nuclear Generating Units 1, 2, 3, & Palisades2021-11-0909 November 2021 Changes to Signature Authority & Addressee for Holtec Decommissioning International, LLC Correspondence Re to Oyster Creek Nuclear Generating Station, Pilgrim Nuclear Power Station, Indian Point Nuclear Generating Units 1, 2, 3, & Palisades IR 05000219/20214042021-08-26026 August 2021 NRC Independent Spent Fuel Storage Security Inspection Report No. 07200015/2021402 and Security Decommissioning Inspection Report 05000219/2021404 - (Public) 2024-01-09
[Table view] |
Text
r UNITED STATES 0 NUCLEAR REGULATORY COMMISSION CREGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA 19406-1415 AUG 2 0 2003 Mr. John Skolds RI-2003-A-0098 Chairman and CEO of AmerGen AmerGen Energy Company, LLC 4300 Winfield Road 5 th Floor Warrenville, IL 60555
Dear Mr. Skolds:
The U.S. Nuclear Regulatory Commission recently received information concerning activities at the Oyster Creek Nuclear Generating Station. The details of this concern are provided in the enclosure to this letter.
We request that you conduct inspections or investigations as necessary to reasonably prove or disprove these concerns and request that you inform NRC Region I, ATTN: Mr. David J. Vito, within 30 days of the date of this letter of the details of your resolution of this matter.
NRC review of your response will include whether: (a) the individual conducting the investigation was independent of the organization affected by the concern; (b) the evaluator was proficient in the specific functional area; (c) the evaluation was of sufficient depth and scope; (d) appropriate root causes and generic implications were considered if the concerns were substantiated; and (e) the corrective actions, if necessary, were sufficient.
We request that your response only be sent to Mr. Vito at the following address:
Mr. David Vito P. 0. Box 80377 Valley Forge, Pennsylvania 19484 No other copies should be sent to the NRC. Please do not submit your response to the Document Control Desk. We also request that your response contain no personal privacy, proprietary, or safeguards information. If personal privacy or proprietary information is necessary to provide an acceptable response, then please provide a bracketed copy of your response that identifies the information that should be protected and a redacted copy of your response that deletes such information. If you request withholding of such material, CERTIFIED MAIL RETURN RECEIPT REQUESTED
Mr. John Skolds 2 RI-2003-A-0098 you must specifically identify the portions of your response that you seek to have withheld and provide in detail the bases for your claim of withholding (e.g., explain why the disclosure of information will create an unwarranted invasion of personal privacy or provide the information required by 10 CFR 2.790(b) to support a request for withholding confidential commercial or financial information). If safeguards information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21.
This letter should be controlled and distribution limited to personnel with a "need to know."
The response requested by this letter and the accompanying enclosure are not subject to the clearance procedures of the Office of Management and Budget as required by the Paperwork Reduction Act of 1980, Pub. L.96-511.
If you have any questions concerning this request, please contact Mr. Vito at (610) 337-5222.
Your cooperation with us is appreciated. We will gladly discuss any questions you may have concerning this information.
Sincerely, A. Randolph B ough, Director Division of Reactor Projects
Enclosure:
As Stated
NOT FOR PUBLIC DISCLOSURE Concerns have been raised about the level of fatigue plant employees have experienced due to the large increase in work hours, the changes in the normal types and patterns of work they perform and the lack of time off while they covered for the bargaining unit employees that went on strike. While the strike ended on August 7, 2003, these personnel are not yet scheduled to return to a normal work schedule for several weeks. Specifically, based on external observations of site engineering/environmental personnel, the staff supporting plant operation during the strike appeared tired and fatigued.