Commitments and Information Related to Steam Generator Degradation and Continued Plant Operation
ML071310446
Person / Time
Site: Arkansas Nuclear 
Issue date: 05/11/2007
From: Mallett B
Region 4 Administrator
To: Mitchell T
Entergy Operations
References
Download: ML071310446 (4)


Text

May 11, 2007 Timothy G. Mitchell Vice President Operations Arkansas Nuclear One Entergy Operations, Inc.

1448 S.R. 333 Russellville, AR 72802-0967

SUBJECT:

ARKANSAS NUCLEAR ONE, UNIT 1 - COMMITMENTS AND INFORMATION RELATED TO STEAM GENERATOR DEGRADATION AND CONTINUED PLANT OPERATION

Dear Mr. Mitchell:

This refers to your letter to the Nuclear Regulatory Commission (NRC) regarding actions to address and compensate for degraded steam generator components during operation of the Arkansas Nuclear One, Unit 1, nuclear plant this cycle. Your letter,1CAN050704, dated May 11, 2007, provides commitments that you and the NRC have deemed necessary in order to support continued operation. In particular, you have committed to additional compensatory measures and to participate in a meeting with NRC management by Fall of 2007 to discuss operational steam generator performance and followup inspection activities during the next refueling outage. Further, we understand that you will provide the NRC staff with the results of your cause analysis of once through steam generator degradation in a correspondence prior to the meeting to discuss the operational steam generator performance.

Based on our review of your commitments, we have no objections to your plans to continue to operate the Arkansas Nuclear One, Unit 1, nuclear plant under the conditions described in your letter. We will continue to evaluate your plans, along with any further information you provide at the aforementioned management meeting. If you have any questions regarding these matters, please contact William B. Jones of my staff at (817) 860-8185.

Entergy Operations, Inc. In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter, and any responses you provide will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Bruce S. Mallett Regional Administrator Docket: 50-313 License: DPR-51 cc:

Senior Vice President

& Chief Operating Officer Entergy Operations, Inc.

P.O. Box 31995 Jackson, MS 39286-1995 Vice President Operations Support Entergy Operations, Inc.

P.O. Box 31995 Jackson, MS 39286-1995 General Manager Plant Operations Entergy Operations, Inc.

Arkansas Nuclear One 1448 S. R. 333 Russellville, AR 72802 Director, Nuclear Safety Assurance Entergy Operations, Inc.

Arkansas Nuclear One 1448 S. R. 333 Russellville, AR 72802 Manager, Licensing Entergy Operations, Inc.

Arkansas Nuclear One 1448 S. R. 333 Russellville, AR 72802

Entergy Operations, Inc. Director, Nuclear Safety & Licensing Entergy Operations, Inc.

1340 Echelon Parkway Jackson, MS 39213-8298 Section Chief, Division of Health Radiation Control Section Arkansas Department of Health and Human Services 4815 West Markham Street, Slot 30 Little Rock, AR 72205-3867 Section Chief, Division of Health Emergency Management Section Arkansas Department of Health and Human Services 4815 West Markham Street, Slot 30 Little Rock, AR 72205-3867 Manager, Washington Nuclear Operations ABB Combustion Engineering Nuclear Power 12300 Twinbrook Parkway, Suite 330 Rockville, MD 20852 County Judge of Pope County Pope County Courthouse 100 West Main Street Russellville, AR 72801 James Mallay Director, Regulatory Affairs Framatome ANP 3815 Old Forest Road Lynchburg, VA 24501

Entergy Operations, Inc. Electronic distribution by RIV:

Regional Administrator (BSM1)

DRP Director (ATH)

DRS Director (DDC)

DRS Deputy Director (RJC1)

Senior Resident Inspector (RWD)

Branch Chief, DRP/E (JAC)

Senior Project Engineer, DRP/E (GDR)

Team Leader, DRP/TSS (FLB2)

RITS Coordinator (MSH3)

SUNSI Review Completed: __x___ ADAMS: #Yes G No Initials: _WBJ__

  1. Publicly Available G Non-Publicly Available G Sensitive
  1. Non-Sensitive C:\\FileNet\\ML071310446.wpd C:EB1 C:PBE D:DCI:NRR DRP/D DRS/D RA WBJ JClark MEvans ATHowell DDChamberlain BSMallet

/RA/

/RA/ JCK3 for

/RA/ T

/RA/

/RA/ RJC1 for

/RA/

5/11/07 5/ /07 5/ /07 5/ /07 05/ /07 05/ /07 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax