Resolution Schedule for DPOs 2006-002 and 2006-003
ML071150219
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 12/18/2006
From:
NRC/OE
To:
References
DPO-2006-002, DPO-2006-003, FOIA/PA-2007-0162
Download: ML071150219 (1)


Text

RESOLUTION SCHEDULE FOR DPOs 2006-002 AND 2006-003 Below is listed the projected schedules for resolution of the two subject DPOs.

The delays have been related to several factors:

The initiation of Panel work and scheduling the first Panel meeting was delayed due to several other competing priorities and travel schedules of various Panel members (approximately one and one-half month delay).

The review was more complex than normal DPO Panel activities due to the assignment of two DPOs to one Panel. This assignment was appropriate due to the similarities between the DPOs, but increased the Panel workload handling the two issues simultaneously.

The issues involved in the DPOs had their root in actions taken by the NRC approximately 20 years ago with multiple revisions of GDC-4. Due to age of the background materials, reconstruction of the history was complicated and time consuming.

Because the matter involved in resolving the DPOs concerned an interpretation of the revisions to GDC-4, the Panel determined that it desired a review of its conclusions by the Office of General Counsel (approximately two week delay).

DPO Milestone DPO-2006-002 DPO-2006-003 Panel issues report 11/09/2006 10/26/2006 (complete)

OD/Submitter comments on 11/19/2006 11/06/2006 Panel Report (10 calendar days)

Panel evaluates comments 11/27/2006 11/13/2006 and issues final report (7 calendar days)

OD issues DPO decision 12/18/2006 N 12/04/2006 (21 calendar days)

Total 220 calendar days 206 calendar days (target 130-190 calendar days)