ML070930685

From kanterella
Jump to navigation Jump to search
Requests for Additional Information for the Review of the Wolf Creek Generating Station, Unit 1, License Renewal Application
ML070930685
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 04/10/2007
From: Veronica Rodriguez
NRC/NRR/ADRO/DLR/RLRB
To: Garrett T
Wolf Creek
rodriguez v m, ADRO/DLR/RLRB, 415-3703
References
Download: ML070930685 (7)


Text

April 10, 2007Mr. Terry J. GarrettVice President Engineering Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839

SUBJECT:

REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THEWOLF CREEK GENERATING STATION, UNIT 1, LICENSE RENEWAL APPLICATION

Dear Mr. Garrett:

By letter dated September 27, 2006, Wolf Creek Nuclear Operating Corporation submitted anapplication pursuant to 10 CFR Part 54, to renew the operating license for Wolf Creek Generating Station, Unit 1, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.These requests for additional information were discussed with Lorrie Bell, and a mutuallyagreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me at 301-415-3703 or e-mail VMR1@nrc.gov

.Sincerely,/RA/Verónica M. Rodríguez, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor RegulationDocket No. 50-482

Enclosure:

Requests for Additional Informationcc w/encl: See next page

ML070930685OFFICELA:DLRPM:RLRB:DLRBC:RLRB:DLRNAMESFigueroaVRodríguezRAuluck DATE04/05/07 04/09/07 04/10/07 EnclosureWOLF CREEK GENERATING STATION (WCGS), UNIT 1LICENSE RENEWAL APPLICATION (LRA)REQUEST FOR ADDITIONAL INFORMATION (RAI)SCOPING AND SCREENING RESULTS Scoping and Screening Results: Structures RAI 2.4-1LRA Section 2.4.9 states that structural features are provided to protect safety-relatedcomponents from flooding. The staff requests that the applicant identify these structural features, which are used to protect safety-related components from flooding, and discuss whether they should be within the scope of license renewal.RAI 2.4-2LRA Section 2.4.10 states that there is a wooden H-frame structure within each of the twotransmission power lines. However, LRA Table 2.4-10 does not list the wooden H-frame as a structure within the scope of license renewal. The staff requests that the applicant justify its exclusion from the scope of license renewal. RAI 2.4-3The staff requests that the applicant clarify if the component type structural steel described inLRA Table 2.4-13 include the trash rack and stop log slots, guideways for the traveling water screens, and walls. If not, the staff requests that the applicant explain and justify its response. AGING MANAGEMENT PROGRAMSConcrete Containment Tendon Prestress RAI B.3.3-1LRA Section B.3.3 states that procedures which list surveillance tendons will be extended toinclude random samples for the 40, 45, 50, and 55 year surveillances.

The staff requests thatthe applicant discuss the differences between these enhanced procedures and the current procedures. RAI B.3.3-2LRA Section B.3.3 states that "Procedures will be enhanced to explicitly require a regressionanalysis for each tendon group after every surveillance; and to invoke and describe regression analysis methods used to construct the lift-off trend lines, including the use of individual tendon data in accordance with Information Notice (IN) 99-10, "Degradation of Prestressing Tendon Systems in Prestressed Concrete Containments." The staff requests that the applicant address the following: (1)Describe the enhanced procedures and requirements of the regression analysis for eachtendon group after every surveillance(2)Discuss the difference between the current procedures and requirements and the enhancedprocedures and requirements to be used during the period of extended operation (3)Describe the analysis methods used to construct the lift-off trend lines, and the differencebetween the current methods and the enhanced onesTIME-LIMITED AGING ANALYSISConcrete Containment Tendon Prestress AnalysisRAI 4.5-1LRA Table 4.5-2 indicates that two tendon types, dome hoop and cylinder hoop, are combinedinto one horizontal hoop group. The total number of examined tendons for these two types was seven for the first, third, and fifth year surveillance, and three for the tenth, fifteenth, and twentieth year surveillance. Two dome hoop tendons were inspected at the first and third year surveillance; however, no dome hoop tendon was inspected after the third year surveillance.

ASME Code Section XI, Subsection IWL-2520, "Examination of Unbonded Post-Tensioning Systems", states that tendons on dome and cylinder shall be characterized into two different tendon types because of their geometry and position in the containment. In addition, Subsection IWL-2520 states that the minimum number of surveillance tendons is four for each type of tendons for the first, third, and fifth year surveillance, and three for the tenth, fifteenth, and twentieth year surveillance. The staff requests that the applicant justify this deviation from the ASME Code requirements.RAI 4.5-2LRA Table 3.5-2 states that the seven horizontal tendons forces at the first year surveillancewere 1358.0 kips, 1359.0 kips, 1381.0 kips, 1409.0 kips, 1348.0 kips, 1422.0 kips, and 1387.0 kips. The average value of these seven tendons force is 1380.6 kips, which is different from the value of 1416.0 kips shown on LRA Figure 4.5-1. The staff requests that the applicant explain this discrepancy.RAI 4.5-3LRA Figure 4.5-1, Note 4, states that "The surveillance program predicted force lines werecalculated per wire. The values plotted here assume 170 wires per tendon. Some tendons have fewer due to failure to meet acceptance criteria at installation, or due to removal for surveillance testing." If the numbers of wires in a tendon is less than 170 due to failure to meet acceptance criteria at installation, or due to removal for surveillance testing, the predicted magnitude of force of that tendon based on the assumption of 170 wires would be higher than itshould have been. Therefore, the staff requests that the applicant provide its basis for using the assumed 170 wires per tendon instead of using the actual numbers of wires per tendon to calculate the tendon force.RAI 4.5-4Based on the discussion of RAIs 4.5-2 and 4.5-3, the staff requests that the applicant establish a new trend line in LRA Figure 4.5-1 with actual prestressed tendon force. The trend line points should be calculated based on the actual number of wires multiplied by the lift-off-wire force.

Letter to T. Garrett, from V. Rodriguez, dated April 10, 2007DISTRIBUTION:

SUBJECT:

REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THEWOLF CREEK GENERATING STATION, UNIT 1, LICENSE RENEWAL APPLICATION HARD COPY DLR RF E-MAIL:PUBLICRWeisman GGalletti SSmith (srs3)

SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb

RidsNrrDci RidsNrrDra RidsNrrDe RidsNrrDeEemb RidsNrrDeEeeb RidsNrrDeEqvb

RidsNrrDss RidsOgcMailCenter RidsNrrAdes


VRodriguez

CJacobs JDonohew GPick, RIV SCochrum, RIV Wolf Creek Generating Station cc:Jay Silberg, Esq.Pillsbury Winthrop Shaw Pittman, LLP 2300 N Street, NW Washington, DC 20037Regional Administrator, Region IVU.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-7005Senior Resident InspectorU.S. Nuclear Regulatory Commission P.O. Box 311 Burlington, KS 66839Chief Engineer, Utilities DivisionKansas Corporation Commission 1500 SW Arrowhead Road Topeka, KS 66604-4027Office of the GovernorState of Kansas Topeka, KS 66612Attorney General120 S.W. 10 th Avenue, 2 nd FloorTopeka, KS 66612-1597County ClerkCoffey County Courthouse 110 South 6 th StreetBurlington, KS 66839Thomas A. Conley, Section ChiefRadiation and Asbestos Control Kansas Department of Health and Environment Bureau of Air and Radiation 1000 SW Jackson, Suite 310 Topeka, KS 66612-1366Vice President Operations/Plant ManagerWolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839Supervisor LicensingWolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839U.S. Nuclear Regulatory CommissionResident Inspectors Office/Callaway Plant

8201 NRC Road Steedman, MO 65077-1032Kevin J. Moles, ManagerRegulatory Affairs Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839Lorrie I. Bell, Project ManagerWolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839Mr. James RossNuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708