ML070870597

From kanterella
Jump to navigation Jump to search

License Amendment, Issuance of Amendments Nos 251 & 195 Regarding Technical Specification Task Force Change TSTF-484, Use of TS 3.10.1 for Scram Time Testing Activities
ML070870597
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 05/17/2007
From: Martin R
NRC/NRR/ADRO/DORL/LPLII-1
To: Madison D
Southern Nuclear Operating Co
Martin R, NRR/DORL, 415-1493
Shared Package
ML070870587 List:
References
TAC MD4225, TAC MD4226
Download: ML070870597 (26)


Text

May 17, 2007 Mr. Dennis R. Madison Vice President - Hatch Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513

SUBJECT:

EDWIN I. HATCH NUCLEAR PLANT, UNIT NOS. 1 AND 2, ISSUANCE OF AMENDMENTS REGARDING TECHNICAL SPECIFICATION TASK FORCE (TSTF) CHANGE TSTF-484, "USE OF TS 3.10.1 FOR SCRAM TIME TESTING ACTIVITIES" (TAC NOS. MD4225 and MD4226)

Dear Mr. Madison:

The Nuclear Regulatory Commission has issued the enclosed Amendment No. 251 to Renewed Facility Operating License DPR-57 and Amendment No. 195 to Renewed Facility Operating License NPF-5 for the Edwin I. Hatch Nuclear Plant, Units 1 and 2, respectively. The amendments consist of changes to the Technical Specifications (TSs) in response to your application dated February 2, 2007.

The amendments revise Limiting Condition for Operation (LCO) 3.10.1 to be consistent with TSTF-484, Revision 0, "Use of Technical Specification 3.10.1 for Scram Time Testing Activities."

A copy of the related Safety Evaluation is also enclosed. A Notice of Issuance will be included in the Commission's biweekly Federal Register notice.

Sincerely,

/RA/

Robert E. Martin, Sr. Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-321 and 50-366

Enclosures:

1. Amendment No. 251 to DPR-57
2. Amendment No. 195 to NPF-5
3. Safety Evaluation cc w/encls: See next page

May 17, 2007 Mr. Dennis R. Madison Vice President - Hatch Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513

SUBJECT:

EDWIN I. HATCH NUCLEAR PLANT, UNIT NOS. 1 AND 2, ISSUANCE OF AMENDMENTS REGARDING TECHNICAL SPECIFICATION TASK FORCE (TSTF) CHANGE TSTF-484, "USE OF TS 3.10.1 FOR SCRAM TIME TESTING ACTIVITIES" (TAC NOS. MD4225 and MD4226)

Dear Mr. Madison:

The Nuclear Regulatory Commission has issued the enclosed Amendment No. 251 to Renewed Facility Operating License DPR-57 and Amendment No. 195 to Renewed Facility Operating License NPF-5 for the Edwin I. Hatch Nuclear Plant, Unit Nos. 1 and 2, respectively. The amendments consist of changes to the Technical Specifications (TSs) in response to your application dated February 2, 2007.

The amendments revise Limiting Condition for Operation (LCO) 3.10.1 to be consistent with TSTF-484, Revision 0, "Use of Technical Specification 3.10.1 for Scram Time Testing Activities."

A copy of the related Safety Evaluation is also enclosed. A Notice of Issuance will be included in the Commission's biweekly Federal Register notice.

Sincerely,

/RA/

Robert E. Martin, Sr. Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-321 and 50-366

Enclosures:

1. Amendment No. 251 to DPR-57
2. Amendment No. 195 to NPF-5
3. Safety Evaluation cc w/encls: See next page DISTRIBUTION: Public RidsAcrsAcnwMailCenter LPL2-1 R/F GHill (4 hard copies)

RidsNrrDorlLpl2-1 (EMarinos) RidsNrrDirsItsb (TKobetz)

RidsNrrPMRMartin (hard copy) RidsRgn2Mail Center(SShaeffer)

RidsNrrLAMOBrien (hard copy) RidsNrrDorlDpr RidsNrrPMPBamford (hard copy) TWertz, NRR Package No. ML070870587 *Transmitted by SE dated Amendment No. ML070870597 Tech Spec No. ML071410099 OFFICE NRR/LPL2-1/PM NRR/LPL2-1/PM NRR/ITSB NRR/LPL2-1/LA NRR/LPL2-1/BC NAME RMartin:nc PBamford TKobetz MOBrien EMarinos DATE 5/7/07 03/26/07 3/14/07* 5/7/07 5/8/07 OFFICIAL RECORD COPY

SOUTHERN NUCLEAR OPERATING COMPANY, INC.

GEORGIA POWER COMPANY OGLETHORPE POWER CORPORATION MUNICIPAL ELECTRIC AUTHORITY OF GEORGIA CITY OF DALTON, GEORGIA DOCKET NO. 50-321 EDWIN I. HATCH NUCLEAR PLANT, UNIT NO.1 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 251 Renewed License No. DPR-57

1. The Nuclear Regulatory Commission (the Commission) has found that:

A. The application for amendment to the Edwin I. Hatch Nuclear Plant, Unit 1 (the facility) Renewed Facility Operating License No. DPR-57 filed by Southern Nuclear Operating Company, Inc. (the licensee), acting for itself, Georgia Power Company, Oglethorpe Power Corporation, Municipal Electric Authority of Georgia, and City of Dalton, Georgia (the owners), dated February 2, 2007, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations as set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations set forth in 10 CFR Chapter I; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

2. Accordingly, the license is hereby amended by page changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Renewed Facility Operating License No. DPR-57 is hereby amended to read as follows:

(2) Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 251, are hereby incorporated in the license. Southern Nuclear shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.

3. This license amendment is effective as of its date of issuance and shall be implemented within 30 days from the date of issuance.

FOR THE NUCLEAR REGULATORY COMMISSION

/RA/

Evangelos C. Marinos, Chief Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Attachment:

Changes to Renewed Facility Operating License No. DPR-57 and the Technical Specifications Date of Issuance: May 17, 2007

ATTACHMENT TO LICENSE AMENDMENT NO. 251 RENEWED FACILITY OPERATING LICENSE NO. DPR-57 DOCKET NO. 50-321 Replace the following pages of the License and the Appendix A Technical Specifications (TSs) with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.

Remove Pages Insert Pages License License Page 4 Page 4 TSs TSs 3.10-1 3.10-1 3.10-2 3.10-2 Bases Bases B 3.10-1 B 3.10-1 B 3.10-2 B 3.10-2 B 3.10-3 B 3.10-3 B 3.10-4 B 3.10-4 B 3.10-5 B 3.10-5

SOUTHERN NUCLEAR OPERATING COMPANY, INC.

GEORGIA POWER COMPANY OGLETHORPE POWER CORPORATION MUNICIPAL ELECTRIC AUTHORITY OF GEORGIA CITY OF DALTON, GEORGIA DOCKET NO. 50-366 EDWIN I. HATCH NUCLEAR PLANT, UNIT NO. 2 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 195 Renewed License No. NPF-5

1. The Nuclear Regulatory Commission (the Commission) has found that:

A. The application for amendment to the Edwin I. Hatch Nuclear Plant, Unit 2 (the facility) Renewed Facility Operating License No. NPF-5 filed by Southern Nuclear Operating Company, Inc. (the licensee), acting for itself, Georgia Power Company, Oglethorpe Power Corporation, Municipal Electric Authority of Georgia, and City of Dalton, Georgia (the owners), dated February 2, 2007, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations as set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations set forth in 10 CFR Chapter I; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

2. Accordingly, the license is hereby amended by page changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Renewed Facility Operating License No. NPF-5 is hereby amended to read as follows:

(2) Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 195 are hereby incorporated in the license.

Southern Nuclear shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.

3. This license amendment is effective as of its date of issuance and shall be implemented within 30 days from the date of issuance.

FOR THE NUCLEAR REGULATORY COMMISSION

/RA/

Evangelos C. Marinos, Chief Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Attachment:

Changes to Renewed Facililty Operating License No. NPF-5 and the Technical Specifications Date of Issuance: May 17, 2007

ATTACHMENT TO LICENSE AMENDMENT NO. 195 RENEWED FACILITY OPERATING LICENSE NO. NPF-5 DOCKET NO. 50-366 Replace the following pages of the License and the Appendix A Technical Specifications (TSs) with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.

Remove Pages Insert Pages License License Page 4 Page 4 TSs TSs 3.10-1 3.10-1 3.10-2 3.10-2 Bases Bases B 3.10-1 B 3.10-1 B 3.10-2 B 3.10-2 B 3.10-3 B 3.10-3 B 3.10-4 B 3.10-4 B 3.10-5 B 3.10-5

SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 251 TO RENEWED FACILITY OPERATING LICENSE NO. DPR-57 AND AMENDMENT NO. 195 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-5 SOUTHERN NUCLEAR OPERATING COMPANY, INC.

EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 DOCKET NOS. 50-321 AND 50-366

1.0 INTRODUCTION

By application dated February 2, 2007 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML070360149), Southern Nuclear Operating Company (SNC, the licensee) requested changes to the Technical Specifications (TS) for the Edwin I. Hatch Nuclear Plant, Units 1 and 2.

The proposed changes would revise Limiting Condition for Operation (LCO) 3.10.1, and the associated Bases, to expand its scope to include provisions for temperature excursions greater than 212 degrees Farenheit (oF) as a consequence of inservice leak and hydrostatic testing, and as a consequence of scram time testing initiated in conjunction with an inservice leak or hydrostatic test, while considering operational conditions to be in Mode 4.

These changes are based on TS Task Force (TSTF) change traveler TSTF-484, Revision 0, that has been approved generically for the boiling water reactor (BWR) Standard TS, NUREG-1433 (BWR/4) and NUREG-1434 (BWR/6) by revising LCO 3.10.1, and the associated Bases, to expand its scope to include provisions for temperature excursions greater than 212 oF as a consequence of inservice leak and hydrostatic testing, and as a consequence of scram time testing initiated in conjunction with an inservice leak or hydrostatic test, while considering operational conditions to be in Mode 4. A notice announcing the availability of this proposed TS change using the consolidated line item improvement process was published in the Federal Register on November 27, 2006 (71 FR 68642).

2.0 REGULATORY EVALUATION

2.1 Inservice Leak and Hydrostatic Testing The Reactor Coolant System (RCS) serves as a pressure boundary and also serves to provide a flow path for the circulation of coolant past the fuel. In order to maintain RCS integrity,Section XI of the American Society of Mechanical Engineers (ASME), Boiler and Pressure Vessel Code, (ASME Code) requires periodic hydrostatic and leakage testing. Hydrostatic tests are required to be performed once every 10 years and leakage tests are required to be performed each refueling outage. Appendix G to 10 CFR Part 50 states that pressure tests and leak tests of the reactor vessel that are required by Section XI of the ASME Code must be completed before the core is critical.

NUREG-1433, General Electric Plants, BWR/4, Revision 3, Standard Technical Specifications (STSs) and NUREG-1434, General Electric Plants, BWR/6, Revision 3, STSs, both currently contain LCO 3.10.1, Inservice Leak and Hydrostatic Testing Operation. LCO 3.10.1 was created to allow for hydrostatic and leakage testing to be conducted while in Mode 4 with average reactor coolant temperature greater than 212 oF provided certain secondary containment LCOs are met.

TSTF-484, Revision 0, Use of TS 3.10.1 for Scram Time Testing Activities, modifies LCO 3.10.1 to allow a licensee to implement LCO 3.10.1, while hydrostatic and leakage testing is being conducted, should average reactor coolant temperature exceed 212 oF during testing.

This modification does not alter current requirements for hydrostatic and leakage testing as required by Appendix G to 10 CFR Part 50.

2.2 Control Rod Scram Time Testing Control rods function to control reactor power level and to provide adequate excess negative reactivity to shut down the reactor from any normal operating or accident condition at any time during core life. The control rods are scrammed by using hydraulic pressure exerted by the control rod drive (CRD) system. Criterion 10 of Appendix A to 10 CFR Part 50 states that the reactor core and associated coolant, control, and protection systems shall be designed with appropriate margin to assure that specified acceptable fuel limits are not exceeded during any condition of normal operation, including the effects of anticipated operational occurrences. The scram reactivity used in design basis accidents (DBAs) and transient analyses is based on an assumed control rod scram time.

NUREG-1433, General Electric Plants, BWR/4, Revision 3, STSs and NUREG-1434, General Electric Plants, BWR/6, Revision 3, STS both currently contain surveillance requirements (SRs) to conduct scram time testing when certain conditions are met in order to ensure that Criterion 10 of Appendix A to 10 CFR Part 50 is satisfied. SR 3.1.4.1 requires scram time testing to be conducted following a shutdown greater than 120 days while SR 3.1.4.4 requires scram time testing to be conducted following work on the CRD system or following fuel movement within the affected core cell. Both SRs must be performed at reactor steam dome pressure greater than or equal to 800 psig and prior to exceeding 40 percent rated thermal power (RTP).

TSTF-484, Revision 0, Use of TS 3.10.1 for Scram Time Testing Activities, would modify LCO 3.10.1 to allow SR 3.1.4.1 and SR 3.1.4.4 to be conducted in Mode 4 with an average

reactor coolant temperature greater than 212 oF. Scram time testing would be performed in accordance with LCO 3.10.4, Single Control Rod Withdrawal - Cold Shutdown. This modification to LCO 3.10.1 does not alter the means of compliance with Criterion 10 of Appendix A to 10 CFR Part 50.

3.0 TECHNICAL EVALUATION

The existing provisions of LCO 3.10.1 allow for hydrostatic and leakage testing to be conducted while in Mode 4 with average reactor coolant temperature greater than 212 oF, while imposing Mode 3 secondary containment requirements. Under the existing provision, LCO 3.10.1 would have to be implemented prior to hydrostatic and leakage testing. As a result, if LCO 3.10.1 was not implemented prior to hydrostatic and leakage testing, hydrostatic and leakage testing would have to be terminated if average reactor coolant temperature exceeded 212 oF during the conduct of the hydrostatic and leakage test. TSTF-484, Revision 0, Use of TS 3.10.1 for Scram Time Testing Activities, modifies LCO 3.10.1 to allow a licensee to implement LCO 3.10.1, while hydrostatic and leakage testing is being conducted, should average reactor coolant temperature exceed 212 oF during testing. The modification will allow completion of testing without the potential for interrupting the test in order to reduce reactor vessel pressure, cool the RCS, and restart the test below 212 oF. Since the current LCO 3.10.1 allows testing to be conducted while in Mode 4 with average reactor coolant temperature greater than 212 oF, the proposed change does not introduce any new operational conditions beyond those currently allowed.

SR 3.1.4.1 and SR 3.1.4.4 require that control rod scram time be tested at reactor steam dome pressure greater than or equal to 800 psig and before exceeding 40-percent rated thermal power (RTP). Performance of control rod scram time testing is typically scheduled concurrent with inservice leak or hydrostatic testing while the RCS is pressurized. Because of the number of control rods that must be tested, it is possible for the inservice leak or hydrostatic test to be completed prior to completing the scram time test. Under existing provisions, if scram time testing can not be completed during the LCO 3.10.1 inservice leak or hydrostatic test, scram time testing must be suspended. Additionally, if LCO 3.10.1 is not implemented and average reactor coolant temperature exceeds 212 oF while performing the scram time test, scram time testing must also be suspended. In both situations, scram time testing is resumed during startup and is completed prior to exceeding 40-percent RTP. TSTF-484, Revision 0, Use of TS 3.10.1 for Scram Time Testing Activities, modifies LCO 3.10.1 to allow a licensee to complete scram time testing initiated during inservice leak or hydrostatic testing. As stated earlier, since the current LCO 3.10.1 allows testing to be conducted while in Mode 4 with average reactor coolant temperature greater than 212 oF, the proposed change does not introduce any new operational conditions beyond those currently allowed. Completion of scram time testing prior to reactor criticality and power operations results in a more conservative operating philosophy with attendant potential safety benefits.

It is acceptable to perform other testing concurrent with the inservice leak or hydrostatic test provided that this testing can be performed safely and does not interfere with the leak or hydrostatic test. However, it is not permissible to remain in TS 3.10.1 solely to complete such testing following the completion of inservice leak or hydrostatic testing and scram time testing.

Since the tests are performed with the reactor pressure vessel (RPV) nearly water solid, at low decay heat values, and near Mode 4 conditions, the stored energy in the reactor core will be

very low. Small leaks from the RCS would be detected by inspections before a significant loss of inventory occurred. In addition, two low-pressure emergency core cooling systems (ECCS) injection/spray subsystems are required to be operable in Mode 4 by TS 3.5.2, ECCS-Shutdown. In the event of a large RCS leak, the RPV would rapidly depressurize and allow operation of the low-pressure ECCS. The capability of the low-pressure ECCS would be adequate to maintain the fuel covered under the low decay heat conditions during these tests.

Also, LCO 3.10.1 requires that secondary containment and standby gas treatment system be operable and capable of handling any airborne radioactivity or steam leaks that may occur during performance of testing.

The protection provided by the normally required Mode 4 applicable LCOs, in addition to the secondary containment requirements required to be met by LCO 3.10.1, minimizes potential consequences in the event of any postulated abnormal event during testing. In addition, the requested modification to LCO 3.10.1 does not create any new modes of operation or operating conditions that are not currently allowed. Therefore, the staff finds the proposed change acceptable.

4.0 STATE CONSULTATION

In accordance with the Commissions regulations, the Georgia State official was notified of the proposed issuance of the amendment. The State official had no comments.

5.0 ENVIRONMENTAL CONSIDERATION

The amendment changes a requirement with respect to installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20. The NRC staff has determined that the amendment involves no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendment involves no significant hazards consideration, and there has been no public comment on such finding (72 FR 11395). Accordingly, the amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Pursuant to 10 CFR 51.22(b) no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendment.

6.0 CONCLUSION

The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commissions regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.

7.0 REFERENCES

1. NUREG-1433, General Electric Plants, BWR/4, Revision 3, Standard Technical

Specifications (STS), August 31, 2003

2. NUREG-1434, General Electric Plants, BWR/6, Revision 3, Standard Technical Specifications (STS), August 31, 2003
3. Request for Additional Information (RAI) Regarding TSTF-484, April, 7, 2006, ADAMS accession number ML060970568
4. Response to NRC RAIs Regarding TSTF-484, June 5, 2006, ADAMS accession number ML061560523
5. TSTF-484 Revision 0, Use of TS 3.10.1 for Scram Times Testing Activities, May 5, 2005, ADAMS accession number ML052930102
6. TSTF Response to NRC Notice for Comment, September 20, 2006, ADAMS accession number ML062650171 Principal Contributor: T. Wertz Date: May 17, 2007 Edwin I. Hatch Nuclear Plant, Units 1 & 2 cc:

Mr. Dennis R. Madison Mr. Jeffrey T. Gasser Vice President - Hatch Executive Vice President Edwin I. Hatch Nuclear Southern Nuclear Operating Company, Inc.

11028 Hatch Parkway North P.O. Box 1295 Baxley, GA 31513 Birmingham, AL 35201-1295 Laurence Bergen Mr. K. Rosanski Oglethorpe Power Corporation Resident Manager 2100 E. Exchange Place Oglethorpe Power Corporation P.O. Box 1349 Edwin I. Hatch Nuclear Plant Tucker, GA 30085-1349 P.O. Box 2010 Baxley, GA 31515 Mr. R. D. Baker Manager - Licensing Southern Nuclear Operating Company, Inc.

P.O. Box 1295 Birmingham, AL 35201-1295 Resident Inspector Plant Hatch 11030 Hatch Parkway N.

Baxley, GA 31531 Harold Reheis, Director Department of Natural Resources 205 Butler Street, SE., Suite 1252 Atlanta, GA 30334 Steven M. Jackson Senior Engineer - Power Supply Municipal Electric Authority of Georgia 1470 Riveredge Parkway, NW Atlanta, GA 30328-4684 Mr. Reece McAlister Executive Secretary Georgia Public Service Commission 244 Washington St., SW Atlanta, GA 30334 Arthur H. Domby, Esq.

Troutman Sanders Nations Bank Plaza 600 Peachtree St, NE, Suite 5200 Atlanta, GA 30308-2216 Chairman Appling County Commissioners County Courthouse Baxley, GA 31513