March 22, 2007 Carolina Power & Light Company ATTN: Mr. Robert Duncan Vice President - Harris Plant Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Code: Zone 1 New Hill, NC 27562-0165

SUBJECT:

REQUALIFICATION PROGRAM INSPECTION - SHEARON HARRIS NUCLEAR PLANT

Dear Mr. Duncan:

In a telephone conversation on March 21, 2007, Mr. Richard S. Baldwin, NRC Senior Operations Engineer, and Ken Bailey, Supervisor of Operator Continuing Training, made arrangements for the NRC to inspect the licensed operator requalification program at the Shearon Harris Nuclear Plant. The inspection is planned for the week of May 21, 2007, which coincides with your regularly scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program. It is our understanding that your simulator is committed to ANSI/ANS-3.5-1998, American National Standard for Nuclear Power Plant Simulators for use in Operator Training and Examination.

In accordance with 10 CFR 55.59(c), the NRC has requested that you submit (one week prior to the inspection/make ready upon arrival), the material as specified in the Enclosure, in order to support the NRC's inspection program needs. Mr. Bailey has been advised of this request and provided with the name and address of the NRC lead inspector assigned to this inspection.

This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number Part 55 (3150-0018), which expires on June 30, 2009.

The public reporting burden for this collection of information is estimated to average 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail at SLF@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0101), Office of Management and Budget, Washington, DC 20503.

The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB approval number.

CP&L 2

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Thank you for your cooperation in this matter. If you have any questions regarding this inspection, please contact Mr. Richard S. Baldwin at (404) 562-4642 or myself at (404) 562-4607.

Sincerely,

\\\\RA\\\\

Robert C. Haag, Chief Operations Branch Division of Reactor Safety Docket No. 50-400 License No. NPF-63

Enclosure:

Materials Request List cc w/encl:

Paul Fulford, Manager Performance Evaluation and Regulatory Affairs PEB 5 Carolina Power & Light Company Electronic Mail Distribution Chris L. Burton Director of Site Operations Carolina Power & Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution Eric McCartney Plant General Manager--Harris Plant Progress Energy Carolinas, Inc.

Shearon Harris Nuclear Power Plant Electronic Mail Distribution J. Wayne Gurganious Training Manager-Harris Plant Progress Energy Carolinas, Inc.

Harris Energy & Environmental Center Electronic Mail Distribution Thomas J. Natale, Manager Support Services Carolina Power & Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution David H. Corlett, Supervisor Licensing/Regulatory Programs Carolina Power & Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution David T. Conley Associate General Counsel - Legal Department Progress Energy Service Company, LLC Electronic Mail Distribution John H. O'Neill, Jr.

Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washington, DC 20037-1128 cc w/encl contd - See next page

CP&L 3

cc w/encl contd Beverly Hall, Chief, Radiation Protection Section N. C. Department of Environmental Commerce & Natural Resources Electronic Mail Distribution Public Service Commission State of South Carolina P. O. Box 11649 Columbia, SC 29211 Chairman of the North Carolina Utilities Commission c/o Sam Watson, Staff Attorney Electronic Mail Distribution Robert P. Gruber Executive Director Public Staff NCUC 4326 Mail Service Center Raleigh, NC 27699-4326 Herb Council, Chair Board of County Commissioners of Wake County P. O. Box 550 Raleigh, NC 27602 Tommy Emerson, Chair Board of County Commissioners of Chatham County Electronic Mail Distribution Mr. J. Wayne Gurganious Training Manager - Harris Plant Harris Energy & Environmental Center Progress Energy Carolinas, Inc.

P. O. Box 327, State Road 1127 New Hill, NC 27562-0165

___ML070820005______________________

OFFICE RII:DRS RII:DRS RII:DRP SIGNATURE RSB2 RCH RXM1 NAME RBaldwin BHaag RMusser DATE 3/22/2007 3/22/2007 3/22/2007 3/ /2007 3/ /2007 3/ /2007 3/ /2007 E-MAIL COPY?

YES NO YES NO YES NO YES NO YES NO YES NO YES NO

2 Materials Request List The items listed below are being requested per telephone conversation on March 21, 2007, to support the upcoming IP-71111.11 inspection in May 2007 at the Shearon Harris Nuclear Plant.

Items in paragraph "A" are to be sent prior to the inspection. They must be received in our office by May 7, 2007. Please have the items listed in paragraph "B" ready for our review upon arrival on May 21, 2007.

A.

In-office inspection material:

1.

Exam results since last requal inspection, copies of exam that had pass/failure rates significantly outside the average.

2.

A copy of the last biennial requal written examination (2RO/SRO exams) and all biennial re-takes.

3.

List of personnel scheduled for requal testing the week of 05/21/07.

4.

Copies of simulator scenarios for this exam (when available).

5.

Program evaluation for the previous 2 years training cycle.

6. A list of all personnel that reactivated their licenses since the last requal inspection.

7.

Simulator:

List of all open simulator discrepancies (SSRs).

Copy of the Simulator Management and Configuration Procedures.

List of all closed simulator SSRs for last 12 months.

List of Simulator Performance tests.

B.

On-site inspection material:

1.

Condition Reports and LERs resulting from human performance errors since the last requal inspection.

2.

All training feedback forms since the last requal inspection.

3.

All remedial training packages since the last requal inspection.

4.

Security badge and HP printouts for all (selected) personnel that reactivated their licenses since the last requal inspection.

Enclosure 5.

Copies of the reference list for all administrative procedures which direct the training process, including development of training and test materials, remedial training, modifications, plant and industry experience.

6.

Records for maintenance of active licenses - time on shift 56/60 hrs/qtr since the last requal inspection.

7.

All Medical Exam Records with a copy of the individuals licence attached.

8.

Simulator JPMs and in-plant JPMs that have been administered for this requal exam.

9.

Copy of an Organizational Chart for the training department including the simulator group.

10.

Complete list of all Licensed individuals complete with license restrictions.

11.

Security procedures for the simulator.

Enclosure

CP&L