MONTHYEARML24016A0052024-01-23023 January 2024 Summary of Meeting with Holtec Decommissioning International, LLC, Regarding Power Operations Technical Specifications ML23313A1592023-11-0909 November 2023 U.S. Nuclear Regulatory Commission Summary of the October 10, 2023, Public Meeting to Discuss Monticello'S Condensate Backwash Receiving Tank Fatigue Evaluation ML23303A2132023-11-0101 November 2023 Summary of Meeting with Holtec Decommissioning International, LLC Regarding Plan to Submit a License Transfer Request as Part of a Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant ML23275A0222023-10-0505 October 2023 Summary of September 21, 2023, Public Meeting with Northern States Power Company Regarding Proposed License Amendment Request to Revise the Pressure Temperature Limits Report ML23263A0012023-09-27027 September 2023 Summary of August 29, 2023, Meeting with Holtec Decommissioning International, LLC Regarding Plan to Submit an Exemption Request as Part of a Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclea ML23200A2602023-07-20020 July 2023 Summary of July 14, 2023, Public Meeting with Northern States Power Company Regarding Proposed Alternative to Defer Periodic Verification Testing of Reactor Water Clean-Up Inboard Isolation Valve ML23199A0262023-07-18018 July 2023 Summary of Public Outreach to Discuss the NRC 2022 End of Cycle Plant Performance Assessment of Point Beach Nuclear Plant, Units 1 and 2 ML23184A0862023-07-11011 July 2023 6/23/2023 Summary of Pre Application Public Meeting with Xcel Energy on Prairie Island ISFSI Amendment Application ML23179A2102023-06-28028 June 2023 Summary of June 5, 2023, Public Meeting with Northern States Power Company Regarding Neutron Fluence Values for Reactor Pressure Vessel Welds ML23171B1222023-06-22022 June 2023 Summary of Meeting with Holtec Decommissioning International, LLC Regarding Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant ML23157A0432023-06-0808 June 2023 Summary of Public Outreach to Discuss the NRC 2022 End-Of-Cycle Plant Performance Assessment of Monticello Nuclear Generating Plant ML23157A0232023-06-0606 June 2023 Summary of the May 24, 2023, Public Outreach to Discuss the NRC 2022 End-of-Cycle Plant Performance Assessment of Prairie Island Nuclear Generating Plant, Units 1 and 2 ML23123A3942023-05-15015 May 2023 Summary of Public Meeting with Northern States Power Company Regarding Planned License Amendment Request to Revise Technical Specification 3.7.8, Cooling Water System ML23118A1762023-05-0404 May 2023 Audit Summary for License Amendment Request Regarding Risk-Informed Approach for Closure of Generic Safety Issue 191 ML23110A0152023-05-0101 May 2023 Summary March 22, 2023, Monticello Units 1 Subsequent License Renewal Application Public Environmental Scoping Meeting ML23115A4642023-05-0101 May 2023 Summary, March 29, 2023, Monticello Units 1 Subsequent License Renewal Application Public Environmental Scoping Meeting ML23115A4382023-05-0101 May 2023 March 29, 2023, Meeting Summary for Environmental Review of Subsequent License Renewal Application for Monticello Nuclear Generating Plant, Unit 1 ML23110A0142023-05-0101 May 2023 Memo March 22, 2023, Monticello Unit 1, Subsequent License Renewal Application Public Environmental Scoping Meeting ML23107A1212023-04-20020 April 2023 Summary of Meeting with Holtec Decommissioning International, Llc Regarding Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant ML23074A1212023-04-0303 April 2023 March 8, 2023, Summary of Public Meeting with Northern States Power Company Regarding Monticello Nuclear Generating Plant Alternative Request PR-08 to Defer Quarterly Testing of Components of High Pressure Coolant Injection System ML22292A2612022-10-31031 October 2022 PSDAR Meeting Summary ML22292A0122022-10-24024 October 2022 Meeting Summary for Environmental Pre Submittal Meeting for Subsequent License Renewal Application, on September 13, 2022 ML22144A0022022-09-14014 September 2022 Summary of February 16, and May 18, 2022, Meetings with Nextera Energy/Florida Power & Light Company Regarding Planned Submittal of License Amendment Request for a Common Fleet Emergency Plan ML22208A2192022-08-0303 August 2022 Summary of July 25, 2022, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to the Amendment to Adopt Advanced Framatome Inc. Methodology for Determining Core Operating Limits for Monticello Plant ML22208A1952022-08-0303 August 2022 Summary of July 26, 2022, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to the Alternative Request for Excess Flow Check Valves at Monticello Nuclear Generating Plant ML22181B1182022-06-30030 June 2022 Summary of the June 23, 2022, Public Outreach to Discuss the NRC 2021 End-of-Cycle Plant Performance Assessment of Point Beach Nuclear Plant, Units 1 and 2 ML22132A0892022-05-12012 May 2022 Summary of the April 26, 2022, Public Outreach to Discuss the NRC 2021 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant ML22130A7172022-05-10010 May 2022 Summary of the May 3, 2022, Public Outreach to Discuss the NRC 2021 End-Of-Cycle Plant Performance Assessment of Monticello and Prairie Island Nuclear Generating Plant, Units 1 and 2 ML22084A3852022-03-31031 March 2022 Meeting Summary for Environmental Pre Submittal Meeting for Subsequent License Renewal Application on March 15, 2022 ML22032A0112022-02-0303 February 2022 Summary of January 27, 2022, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to a Planned Relief Request to Test Excess Flow Check Valve ML22019A2792022-01-20020 January 2022 Summary of Public Webinar with NextEra Energy Point Beach, LLC Regarding Future License Amendment and Exemption Request for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant ML22004A0772022-01-0606 January 2022 Summaries of December 8, 2021 Draft Supplemental Environmental Impact Statement for Subsequent License Renewal Application Public Meetings ML21294A0442021-11-0808 November 2021 Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to a License Amendment to Extended the Allowed Outage Time for the Vertical Motor Driven Cooling Water System Pump ML21295A2532021-10-26026 October 2021 Summary of Public Webinar with NextEra Energy Point Beach,Llc Regarding Proposed Future LAR to Adopt TSTF-505, Rev.2, Provide Risk Informed Extended Completion Times-RITSTF Initiative 4B, at Point Beach Plant, Units 1&2 (L-2021-LRM-0086) ML21288A1222021-10-20020 October 2021 SLRA Summary of August 5, 2021, Public Meeting on Proposed Aging Management Activities of Irradiated Concrete and Steel Reactor Vessel Supports ML21285A0312021-10-15015 October 2021 Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to Planned License Amendment to Extend Allowed Outage Time for Fuel Oil Storage Tank for Monticello Nuclear Plant ML21214A1652021-08-27027 August 2021 SLRA June 30, 2021, Public Meeting - Proposed Aging Management of Reactor Vessel Internals ML21214A1512021-08-27027 August 2021 SLRA June 3, 2021, Public Meeting - Proposed Aging Management Activities of Irradiated Concrete and Steel Reactor Vessel Supports ML21229A1692021-08-23023 August 2021 Summary of August 11, 2021, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to a Planned License Amendment Allow Bypass Testing of the Power Range Nuclear Instrumentation System Channels ML21200A2262021-07-19019 July 2021 Summary of the July 1, 2021, Public Outreach to Discuss the NRC 2020 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant ML21161A2992021-06-17017 June 2021 Summary of May 18, 2021 Public Webinar with Nextera Energy Point Beach, LLC Regarding Path Forward for Generic Letter 2004-02 Closure ML21167A1842021-06-16016 June 2021 Summary of the June 9, 2021, Public Outreach to Discuss the NRC 2020 End-Of-Cycle Plant Performance Assessment of Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant, Units 1 and 2 ML21166A2192021-06-15015 June 2021 Summary of June 10, 2021, Public Webinar to Discuss the NRC 2020 End-Of-Cycle Plant Performance Assessment of the Point Beach Nuclear Plant ML21145A0482021-06-0202 June 2021 Summary of May 12, 2021, Teleconference with Entergy Nuclear Operations, Inc. to Discuss Potential License Amendment Request Related to Permanently Defueled Technical Specifications for Palisades Nuclear Plant ML21148A1162021-06-0101 June 2021 SLRA Public Meeting Discussion Questions 6-3-21 ML21137A1042021-05-20020 May 2021 Summary of May 6, 2021, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to a Planned License Amendment to Transition to a 24 Month Operating Cycle ML21098A0742021-04-13013 April 2021 Summary of March 25, 2021, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to a Planned License Amendment to Adopt Advanced Framatome Methods ML21075A3422021-03-17017 March 2021 Meeting Summary: Public Scoping Meeting for the Environmental Review of the Subsequent License Renewal Application for Point Beach Nuclear Plant, Unit Nos. 1 and 2 (EPID No.: L-2020-SLE-0002) - Memo 2024-01-23
[Table view] |
Text
March 6, 2007 LICENSEE: Nuclear Management Company, LLC (NMC)
FACILITY: Point Beach Nuclear Plant Monticello Nuclear Plant Palisades Nuclear Plant Prairie Island Nuclear Plant
SUBJECT:
SUMMARY
OF THE FEBRUARY 21, 2007, PUBLIC MEETING TO DISCUSS THE NMC CONDUCT OF OPERATIONS ACTION PLAN On February 21, 2007, the Nuclear Regulatory Commission (NRC) held a public meeting at the Region III Office in Lisle, Illinois, with NMC representatives. The purpose of the meeting was to discuss the actions implemented by NMC Management to improve fleet conduct of operations for the Point Beach, Monticello, Palisades, and Prairie Island Nuclear Plants.
Mark Reddemann began the meeting with introductions of plant management. NMCs policy on Fleet Excellence was presented with the pillars of Organizational, Operational, Training, and Equipment Excellence. This was followed by a discussion of the Palisades Auxiliary Feedwater Pump event where the pumps were not in automatic operation.
Discussions continued with NMC leadership identifying a need for fleet-wide action which included:
- a. Reinforcing expectations with operators
- b. Benchmarking with a Fleet task force
- c. Changing Fleet Procedures
- d. Training
- e. Assessments
- f. Monitoring The meeting notice can be found in ADAMS at ML070380582 and the licensees presentation slides can be found in ADAMS at ML070510674. A list of NRC and licensee meeting participants can be found in the attached Enclosure.
Before adjourning the meeting, the NRC provided the opportunity for members of the audience to ask questions.
Nuclear Management Company, LLC In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this document will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
/RA/
Christine A. Lipa, Chief Branch 4 Division of Reactor Projects Docket Nos. 50-266; 50-301, 50-263 50-255, 50-282; 50-306 License Nos. DPR-24; DPR-27, DPR-20 DPR-22, DPR-42; DPR-60
Enclosure:
As Stated DISTRIBUTION:
See next page
Nuclear Management Company, LLC In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this document will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Christine A. Lipa, Chief Branch 4 Division of Reactor Projects Docket Nos. 50-266; 50-301, 50-263 50-255, 50-282; 50-306 License Nos. DPR-24; DPR-27, DPR-20 DPR-22, DPR-42; DPR-60
Enclosure:
As Stated DISTRIBUTION:
See next page DOCUMENT NAME: C:\FileNet\ML070710527.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII N RIII NAME GKolcum:dtp CLipa DATE 03/06/07 03/06/07 OFFICIAL RECORD COPY
Nuclear Management Company, LLC cc w/encl: Dennis L. Koehl, Site Vice President Paul A. Harden, Site Vice President J. Conway, Site Vice President T. Palmisano, Site Vice President F. Kuester, President and Chief Executive Officer, We Generation D. Cooper, Senior Vice President, Group Operations J. McCarthy, Site Director of Operations D. Weaver, Nuclear Asset Manager Plant Manager Regulatory Affairs Manager Training Manager Site Assessment Manager Site Engineering Director Emergency Planning Manager J. Rogoff, Vice President, Counsel & Secretary K. Duveneck, Town Chairman Town of Two Creeks Chairperson Public Service Commission of Wisconsin J. Kitsembel, Electric Division Public Service Commission of Wisconsin State Liaison Officer M. Sellman, President and Chief Executive Officer R. Fenech, Senior Vice President, Nuclear Fossil and Hydro Operations L. Lahti, Manager, Regulatory Affairs A. Udrys, Esquire, Consumers Energy Company S. Wawro, Director of Nuclear Assets, Consumers Energy Company Supervisor, Covert Township Office of the Governor State Liaison Office, State of Michigan L. Brandon, Michigan Department of Environmental Quality -
Waste and Hazardous Materials Division Manager, Nuclear Safety Assessment Nuclear Asset Manager, Xcel Energy, Inc.
R. Nelson, President Minnesota Environmental Control Citizens Association (MECCA)
Commissioner, Minnesota Pollution Control Agency D. Gruber, Auditor/Treasurer, Wright County Government Center Commissioner, Minnesota Department of Commerce Manager - Environmental Protection Division Minnesota Attorney Generals Office Regulatory Affairs Manager Nuclear Asset Manager
Nuclear Management Company, LLC State Liaison Officer, Minnesota Department of Health Tribal Council, Prairie Island Indian Community Administrator, Goodhue County Courthouse Commissioner, Minnesota Department of Commerce Manager, Environmental Protection Division Office of the Attorney General of Minnesota
Nuclear Management Company, LLC DISTRIBUTION:
TEB CFL EMH1 LXR1 RidsNrrDirsIrib GEG GLS KGO RGK DRPIII DRSIII PLB1 TXN MLC JBG JAE PST CST1 JTA
Enclosure PUBLIC MEETING PRINCIPAL ATTENDEES February 21, 2007 NRC J. Caldwell, Regional Administrator M. Satorius, Director, Division of Reactor Projects C. Pederson, Director, Division of Reactor Safety S. West, Deputy Director, Division of Reactor Projects A. Boland, Deputy Director, Division of Reactor Safety B. Burgess, Chief, Branch 2, Division of Reactor Projects R. Skokowski, Chief, Branch 3, Division of Reactor Projects C. Lipa, Chief, Branch 4, Division of Reactor Projects H. Peterson, Branch Chief, Division of Reactor Safety M. Kunowski, Project Engineer, Division of Reactor Projects Nuclear Management Company M. Reddemann, Vice President, Nuclear Operations Support J. McCarthy, Site Director of Operations, Point Beach Nuclear Plant B. MacKissock, Operations Manager, Monticello Nuclear Generating Plant L. Blocker, Operations Manager, Palisades Nuclear Plant R. Harrsch, Operations Manager, Point Beach Nuclear Plant F. Forrest, Operations Manager, Prairie Island Nuclear Generating Plant B. Beltz, Shift Manager, Point Beach Nuclear Plant J. Kindred, Shift Manager, Monticello Nuclear Generating Plant T. Mulford, Shift Manager, Palisades Nuclear Plant