ML070680318

From kanterella
Jump to navigation Jump to search
Notification to Conduct a Triennial Fire Protection Baseline Inspection While Transition to 10 CFR Par 50.58(c) Is in Progress Inspection Report 05000266-07-006 (Drs); 05000301-07-006 (DRS)
ML070680318
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 03/09/2007
From: Julio Lara
Engineering Branch 3
To: Koehl D
Nuclear Management Co
References
IR-07-006 IR-07-006
Download: ML070680318 (11)


See also: IR 05000266/2007006

Text

March 9, 2007

Mr. Dennis L. Koehl

Site Vice President

Point Beach Nuclear Plant

Nuclear Management Company, LLC

6590 Nuclear Road

Two Rivers, WI 54241-9516

SUBJECT:

POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - NOTIFICATION TO

CONDUCT A TRIENNIAL FIRE PROTECTION BASELINE INSPECTION

WHILE TRANSITION TO 10 CFR PART 50.48(c) IS IN PROGRESS

INSPECTION REPORT 05000266/2007006(DRS); 05000301/2007006(DRS)

Dear Mr. Koehl:

On June 25, 2007, the U.S. Nuclear Regulatory Commission (NRC) will begin a triennial fire

protection baseline inspection at the Point Beach Nuclear Plant, Units 1 and 2. The inspection

will be conducted in accordance with Inspection Procedure 71111.05TTP, the NRCs baseline

fire protection inspection procedure for plants in the process of implementing 10 CFR 50.48(c),

NFPA 805. The inspection guidance is different from the regular triennial inspections in that the

inspectors will concentrate on the fire protection program infrastructure and the adequacy of

compensatory measures implemented for identified departures from code requirements. The

inspectors will not routinely inspect for or evaluate circuit related issues.

The schedule for the inspection is as follows:

Information gathering visit - June 13 - 15, 2007

On-site inspection activity - June 25 - 29, 2007, and July 9 - 13, 2007

The purpose of the information gathering visit is to: (1) obtain information and documentation

needed to support the inspection; (2) become familiar with the Point Beach Nuclear Plants fire

protection program, fire protection features, post-fire safe shutdown capabilities and plant

layout; and (3) arrange administrative details such as office space, availability of knowledgeable

office personnel and to ensure unescorted site access privileges.

Experience has shown that the baseline fire protection inspections are extremely resource

intensive both for the NRC inspectors and the licensee staff. In order to minimize the

inspection impact on the site and to ensure a productive inspection for both organizations, we

have enclosed a request for documents needed for the inspection. These documents have

been divided into four groups. The first group lists information necessary to aid the inspection

team in choosing specific focus areas for the inspection. It is requested that this information be

provided to the lead inspector via mail or electronically no later than May 9, 2007. The second

D. Koehl

-2-

group lists information necessary to ensure that the inspection team is adequately prepared for

the inspection. This information should be available on-site no later than June 13, 2007. The

third group of requested documents are those items that the inspection team will review, or

need access to, during the inspection. Please have this information available by the first day of

the on-site portion of the inspection (June 25, 2007). The fourth group lists the information

necessary to aid the inspection team in tracking issues identified as a result of the inspection.

It is requested that this information be provided to the lead inspector as the information is

generated during the inspection. It is important that all of these documents are up to date and

complete in order to minimize the number of additional documents requested during the

preparation and/or the on-site portions of the inspection.

The lead inspector for this inspection is Mr. George M. Hausman. We understand that our

initial regulatory contact for this inspection is Ms. Fritzie Flentje of your organization. If there

are any questions about the inspection or the material requested, please contact the lead

inspector at (630) 829-9743 or via e-mail at gmh1@nrc.gov.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and

its enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRC's document system

(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html

(the Public Electronic Reading Room).

Sincerely,

/RA/

Julio F. Lara, Chief

Engineering Branch 3

Division of Reactor Safety

Docket Nos. 50-266; 50-301

License Nos. DPR-24; DPR-27

Enclosure:

Fire Protection Inspection Document Request

See Attached Distribution List

D. Koehl

-3-

cc w/encl:

F. Kuester, President and Chief

Executive Officer, We Generation

D. Cooper, Senior Vice President, Group Operations

J. McCarthy, Site Director of Operations

D. Weaver, Nuclear Asset Manager

Plant Manager

Regulatory Affairs Manager

Training Manager

Site Assessment Manager

Site Engineering Director

Emergency Planning Manager

J. Rogoff, Vice President, Counsel & Secretary

K. Duveneck, Town Chairman

Town of Two Creeks

Chairperson

Public Service Commission of Wisconsin

J. Kitsembel, Electric Division

Public Service Commission of Wisconsin

State Liaison Officer

D. Koehl

-2-

group lists information necessary to ensure that the inspection team is adequately prepared for

the inspection. This information should be available on-site no later than June 13, 2007. The

third group of requested documents are those items that the inspection team will review, or

need access to, during the inspection. Please have this information available by the first day of

the on-site portion of the inspection (June 25, 2007). The fourth group lists the information

necessary to aid the inspection team in tracking issues identified as a result of the inspection.

It is requested that this information be provided to the lead inspector as the information is

generated during the inspection. It is important that all of these documents are up to date and

complete in order to minimize the number of additional documents requested during the

preparation and/or the on-site portions of the inspection.

The lead inspector for this inspection is Mr. George M. Hausman. We understand that our

initial regulatory contact for this inspection is Ms. Fritzie Flentje of your organization. If there

are any questions about the inspection or the material requested, please contact the lead

inspector at (630) 829-9743 or via e-mail at gmh1@nrc.gov.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and

its enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRC's document system

(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html

(the Public Electronic Reading Room).

Sincerely,

/RA/

Julio F. Lara, Chief

Engineering Branch 3

Division of Reactor Safety

Docket Nos.:

50-266; 50-301

License Nos.:

DPR-24; DPR-27

Enclosure:

Fire Protection Inspection Document Request

See Attached Distribution List

DOCUMENT NAME: C:\\FileNet\\ML070680318.wpd

G Publicly Available

G Non-Publicly Available

G Sensitive

G Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE RIII

RIII

RIII

NAME

GHausman: ls

PLouden

JLara

DATE

03/09/07

03/09/07

03/09/07

OFFICIAL RECORD COPY

D. Koehl

-3-

cc w/encl:

F. Kuester, President and Chief

Executive Officer, We Generation

D. Cooper, Senior Vice President, Group Operations

J. McCarthy, Site Director of Operations

D. Weaver, Nuclear Asset Manager

Plant Manager

Regulatory Affairs Manager

Training Manager

Site Assessment Manager

Site Engineering Director

Emergency Planning Manager

J. Rogoff, Vice President, Counsel & Secretary

K. Duveneck, Town Chairman

Town of Two Creeks

Chairperson

Public Service Commission of Wisconsin

J. Kitsembel, Electric Division

Public Service Commission of Wisconsin

State Liaison Officer

DISTRIBUTION:

TEB

CFL

EMH1

LXR1

RidsNrrDirsIrib

GEG

GLS

KGO

CAA1

RGK

DRPIII

DRSIII

PLB1

TXN

ROPreports@nrc.gov

FIRE PROTECTION INSPECTION DOCUMENT REQUEST

INITIAL REQUEST

Enclosure

1

Inspection Report: 05000266/2007006(DRS); 05000301/2007006(DRS)

Inspection Dates:

June 13 - 15, 2007

(Information Gathering Visit)

June 25 - 29, 2007

(On-site Inspection Activity)

July 9 - 13, 2007

(On-site Inspection Activity)

Inspection Procedures:

IP 71111.05TTP, Fire Protection-NFPA Transition Period (Triennial)

IP71111.05AQ, Fire Protection (Annual/Quarterly)

IP 71152, "Identification and Resolution of Problems"

Inspectors:

Lead Inspector:

George M. Hausman, (630) 829-9743

Team Members:

Alan K. Dahbur, (630) 829-9810

Dariusz Szwarc, (630) 829-9803

I.

Information Requested Prior to the Information Gathering Visit

The following information is requested by May 9, 2007. If you have any questions regarding

this information, please call the lead inspector as soon as possible. Please ensure that the

information to be provided in lists contain enough information to be easily understood by

someone who has a knowledge of the technology. All information should be sent to

Mr. George M. Hausman (e-mail address gmh1@nrc.gov). Electronic media is preferred, if

readily available. The preferred file format is a searchable .pdf file on a CDROM. The

CDROM should be indexed and hyper-linked to facilitate ease of use, if possible. Please

provide 4 copies of each CDROM submitted (one for each inspector and for a senior reactor

analysis).

(1)

The reactor plant's Individual Plant Examination for External Events (IPEEE) for fire,

results of any post-IPEEE reviews for fire, and listings of actions taken and/or plant

modifications conducted in response to IPEEE information for fire. Alternatively,

probabilistic risk analyses for fire and associated information, if it exists and is more

recent than the IPEEE.

(2)

A list of fire areas requiring alternative shutdown capability, i.e., those areas for which

10 CFR Part 50, Appendix R, Section III.G requirements are satisfied under

Section III.G.3, or where both safe shutdown trains can be affected.

(3)

A copy of the current version of the Fire Protection Program (FPP), Fire Hazards

Analysis (FHA), Safe Shutdown Analysis (SSA), Updated Safety Analysis Report

(USAR), Technical Specifications and License.

(4)

A copy of the current fire protection system Health Report, if available.

FIRE PROTECTION INSPECTION DOCUMENT REQUEST

INITIAL REQUEST

Enclosure

2

(5)

A copy of the current plant drawings referred to as Horse Notes, if available.

(6)

Status of 10 CFR 50.48(c), NFPA 805 implementation.

II.

Information Requested During the Information Gathering Visit

(June 13 - 15, 2007)

The following information is requested to be provided to the inspection team during the on-site

information gathering visit as one set of hard-copy documents. In addition, the requested

information is to be provided as a file searchable compact disc (CD), if possible. If a CD(s) can

be provided, three sets (one for each inspector) are requested.

(1)

Licensing Information

(a)

The Facilitys license, including the fire protection license condition;

(b)

All Nuclear Regulatory Commission (NRC) Safety Evaluation Reports (SERs)

applicable to fire protection (specifically including those SERs referenced by the

plant fire protection license condition) and all other associated licensing

correspondence applicable to fire protection;

(c)

The FPP and applicable portions of the USAR, as referenced by the fire

protection license condition;

(d)

Exemptions from 10 CFR 50.48 and 10 CFR Part 50, Appendix R, and

associated licensing correspondence;

(e)

For pre-1979 plants (i.e., Appendix R plants), a listing of all 10 CFR Part 50,

Appendix R sections and paragraphs that are applicable to the plant under

10 CFR 50.48(b)(1);

(f)

For pre-1979 plants, all licensing correspondence associated with those sections

of 10 CFR Part 50, Appendix R, that are not applicable to the plant under

10 CFR 50.48(b)(1). Specifically, the licensing correspondence associated with

those fire protection features proposed or implemented by the licensee that have

been accepted by the NRC staff as satisfying the provisions of Appendix A to

Branch Technical Position (BTP) APCSB 9.5-1 reflected in the NRC fire

protection SERs issued before February 19, 1981 (10 CFR 50.48(b)(1)(i)); or

those fire protection features which were accepted by the NRC staff in

comprehensive fire protection SERs issued before Appendix A to BTP

APCSB 9.5-1 was published in August 1976 (10 CFR 50.48(b)(1)(ii));

FIRE PROTECTION INSPECTION DOCUMENT REQUEST

INITIAL REQUEST

Enclosure

3

(g)

For post-1979 plants, all licensing correspondence associated with the

comparison to Standard Review Plan (NUREG-0800), Section 9.5.1 or

equivalent for licensing purposes; and

(h)

For plants intending to transition to NFPA 805, provide: (1) all correspondence

to and responses from the NRC, (2) a list of all areas showing assessment

review status, (3) assessments for all areas that have been completed, (4) a list

of all identified non-conformances, and their respective compensatory

measure(s).

(2)

Fire Protection Program

(a)

If not already provided under request II.(1)(c) above, FPP documents including

FHA and post-fire SSA;

(b)

A listing of changes made to the FPP (including associated adverse to SSA);

(c)

For pre-1979 plants, a listing of the protection methodologies identified under

10 CFR Part 50, Appendix R, Section III.G used to achieve compliance for

selected fire zones/areas (to be determined during information gathering

visit). That is, please specify whether 3 hour3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> rated fire barriers;

(Section III.G.2.a), 20 foot separation along with detection and suppression;

(Section III.G.2.b), 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> rated fire barriers with detection and suppression;

(Section III.G.2.c), or alternative shutdown capability; (Section III.G.3) is used for

each selected fire zone/area;

(d)

A list of Generic Letter 86-10 evaluations (i.e., a list of adverse to safe shutdown

evaluations);

(e)

A list of applicable codes and standards related to the design of plant fire

protection features. The list should include National Fire Protection

Association (NFPA) code versions committed to (i.e., the NFPA codes of record);

(f)

A list of plant deviations from code commitments and associated evaluations;

(g)

Plant layout drawings which identify plant fire area delineation, areas protected

by automatic fire suppression and detection, and the locations of fire protection

equipment.

(3)

Facility Information

(a)

Piping and instrumentation (flow) diagrams showing the components used to

achieve and maintain hot standby and cold shutdown for fires outside the control

room and those components used for those areas requiring alternative shutdown

capability;

FIRE PROTECTION INSPECTION DOCUMENT REQUEST

INITIAL REQUEST

Enclosure

4

(b)

Plant layout and equipment drawings which identify the physical plant locations

of hot standby and cold shutdown equipment for selected fire zones/areas (to be

determined during information gathering visit);

(c)

Plant layout drawings which identify the general location of the post-fire

emergency lighting units;

(d)

One-line schematic drawings of the electrical distribution system for

4160 Volts alternating current (Vac) down to 480 Vac;

(e)

One-line schematic drawings of the electrical distribution system for

250 Volts direct current (Vdc) and 125 Vdc systems as applicable; and

(f)

Safe shutdown cable routing database (requested electronically such as on

compact disc, if available).

(4)

Operations Response for Fire Protection

(a)

Pre-fire plans for selected fire zones/areas (to be determined during

information gathering visit);and.

(b)

Plant operating procedures which would be used and describe shutdown for a

postulated fire in selected fire zones/areas (to be determined during

information gathering visit).

(5)

Corrective Actions

(a)

Listing of open and closed fire protection condition reports (i.e., problem

identification forms and their resolution reports) since the date of the last triennial

fire protection inspection; and

(b)

Listing of fire impairments since the date of the last triennial fire protection

inspection.

(6)

General Information

(a)

A listing of abbreviations and/or designators for plant systems;

(b)

Organization charts of site personnel down to the level of fire protection staff

personnel; and

(c)

A phone list for on-site licensee personnel.

FIRE PROTECTION INSPECTION DOCUMENT REQUEST

INITIAL REQUEST

Enclosure

5

(7)

On-Site Discussions

In addition, during the information gathering visit, it is requested that licensee staff be

available for the following:

(a)

Informal discussion on plant procedures operators would use in the event of fire

and under what conditions would the plant be shutdown using alternative

shutdown methodology;

(b)

Informal discussion on the plants safe shutdown cable routing database and the

plant-wide cable routing database, as applicable; and

(c)

A tour of alternative shutdown and risk significant fire areas.

III.

Information Requested to be Available on First Day of Inspection

(June 25, 2007)

(1)

Procedures

(a)

List of the FPP implementing procedures (e.g., administrative controls,

surveillance testing, fire brigade);

(b)

List of maintenance and surveillance testing procedures for alternative shutdown

capability and fire barriers, detectors, pumps, and suppression systems;

(c)

List of maintenance procedures which routinely verify fuse breaker coordination

in accordance with the post-fire safe shutdown coordination analysis;

(d)

List of procedures and/or instructions that control the configuration of the reactor

plant's FPP, features, and post-fire safe shutdown methodology and system

design; and

(e)

List of procedures and/or instructions that govern the implementation of plant

modifications, maintenance, and special operations, and their impact on fire

protection.

(2)

Design and Equipment Information

(a)

Coordination calculations and/or justifications that verify fuse/breaker

coordination for selected fire zones/areas (to be determined during

information gathering visit) that are fed off of the same electrical buses as

components in the protected safe shutdown train;

FIRE PROTECTION INSPECTION DOCUMENT REQUEST

INITIAL REQUEST

Enclosure

6

(b)

Copies of significant fire protection and post-fire safe shutdown related design

change package descriptions (including their associated 10 CFR Part 50.59

evaluations) and Generic Letter (GL) 86-10 (or adverse to safe shutdown)

evaluations;

(c)

Gaseous suppression system pre-operational testing, if applicable, for selected

fire zones/areas (to be determined during information gathering visit);

(d)

Hydraulic calculations and supporting test data which demonstrate operability for

water suppression systems, if applicable, for selected fire zones/areas (to be

determined during information gathering visit);

(e)

Alternating current (ac) coordination calculations for 4160 Vac down to 480 Vac

electrical systems;

(f)

Vendor manuals and information for fire protection equipment (such as

detection, suppression systems, fire pumps), applicable to selected fire

zones/areas (to be determined during information gathering visit); and

(g)

List of all fire protection or Appendix R calculations.

(3)

Assessment and Corrective Actions

(a)

The three most recent fire protection Quality Assurance (QA) audits and/or fire

protection self-assessments; and

(b)

Corrective action documents (e.g., condition reports, including status of

corrective actions) generated as a result of the three most recent fire protection

Quality Assurance (QA) audits and/or fire protection self-assessments.

IV.

Information Requested to Be Provided Throughout the Inspection

(1)

Copies of any corrective action documents generated as a result of the inspection

teams questions or queries during this inspection.

(2)

Copies of the list of questions submitted by the inspection team members and the

status/resolution of the information requested (provided daily during the inspection to

each inspection team member).