ML070680259

From kanterella
Jump to navigation Jump to search
Report for IWE Inspections Performed for RF022, 05/15/2001
ML070680259
Person / Time
Site: Vermont Yankee Entergy icon.png
Issue date: 05/15/2001
From: Connell R
Vermont Yankee
To: Girroir D
- No Known Affiliation, Office of Nuclear Reactor Regulation
References
Download: ML070680259 (324)


Text

.

To: DennisGirroir 5/15/2001 From Ralph Connell Re: Report for TWE Inspections Performed for RF022 (Reference Report for IWE Inspections Performed for WOZl dated 12/02/1999)

XNTRODUCTIOIY:

The objective in the current period for this new IWE inspection program was to gather as much information as we could for W021 and RF022. During RF021 the goal was to perform as many inspections as possible within the acceptable window without causing any interference with other outage work activities. The remahder of the required first period examinations was performed either before or during RF022.

After the IWE examinations performed during RFO 21 the Program Procedure PP7024 was revised to incorporate lessons learned. Some revisions were made to the appendices regarding inspected components and inspection criteria. As a result some of the examinations originally listed for the 1 period were revised and are reflected in the completion schedule included in this report. All required VI-3 examinations were moved to the 3d period as required by the ASME Section XI[ Code 1992/92A.

DISCUSSION:

The ASME Section XI Subsection ][WE Code requires an examination of the coated surfaces in order to determine the condition of the substrate. This examination of coated surfaces is for evidence of flaking, blistering, peeling, discoloration and other signs of distress of the underlying metal. The IWE examinations performed for W021 found only two areas of coating with signs of distress affecting the substrate. Those two areas were located at the drywefl interior moisture barrier and the other was on the drywell surface at the X-5G penetration. Both of these were evaluated by Mechanical Design Engineering and dispositions provided via the IDR process. IWE examinations during W 0 2 2 identified two more areas. These were areas of pitting and corrosion in the vent header and corrosion in the interior of penetrations X-207A-H. Both of these were also evaluated by Mechanical Design Engineering and dispositions provided via the LDR process. At many areas of the containment there is peeling or discoloration. Both of these issues have been previously identified and accepted via the OP5250 inspections.

The Maintenance Department has been perfiiming containment inspections for several years via OP5250 to evaluate the condition of the coatings on containment surfaces.

These inspections have compiled an excellent source of data documenting the conditions of the coatings and how these coatings are maintaining over time. The information provided fkom these reports provides the basis for disposition of issues identified on the IWEreports such as coating peeling and blistering.

Several areas were identified as inaccessible during the RF021 and RF022 IWE examination process. Those inaccessible areas are generally defined in PP7024. More specific information is included with the data supplied in this report.

DETAILS:

TORUS SURFACE The d a c e ffom just below the catwalk on the exterior surface to the horizontal mid point of the toms was inspected prior to IZF022 The remaining torus penetrations were examined prior to W022 and during RF022.

Penetrations X-207A-H were identified as having corrosion exceeding the provided acceptance criteria. IDR 01-08 was written on this item. This was addressed by Design Engineering and a design wall thickness for these penetrations was provided. The X-207A-H penetrations are acceptable for continued use and the corrosion identified does not exceed the required design wall thickness.

Torus penetration (includes penetrations in the vent system) examinations were completed for the first period.

The interior surface of the vent header examination was completed during RF022. There were areas of pitting and corrosion identified in the vent header that exceeded the provided acceptance criteria. IDR 01-07 was written to address the areas of pitting and corrosion Design Engineering addressed this IDR and provided new acceptance criteria for the vent header corrosion identified. All areas a e within the required design wall thickness provided by the Design Engineering resolution and are acceptable for Continued operation.

After review of the data gathered during W021, a portion of the containment surface at the joint seal area was declared as augmented. This area was examined and documented during RF022. No change was identified in the as inspected condition between RF021 and RF022 in the augmented area.

Since the area of the augmented s d c e was being prepared for seal installation and painting the opportunity to exmine this region with white metal exposed and all corrosion removed presented itself The entire circumference in the moisture barrier area was examined and the areas of pitting and pit depths were identified. All pitting

identified by this examination were bounded by the 1999 evaluation, VYM 99/139, and are acceptable for continued operation of the drywell.

Forty-three (43) percent of the required first period drywell penetration examinations were completed during RF021 the remainder was examined either prior to or during RF022. Many of these penetrations depicted debris and peeling paint. The diddebris is not considered to be detrimental to the containment structure. All penetration cavities were dry with no visible indication of moisture. The peeling paint was similar to that identified in the maintenance reports and is not unumal for the age and environmental conditions experienced by the coating.

The dirt/debris identified in the drywell penetration cavities is a housekeeping issue only, not a containment integrity concern. All large debris located in the penetrations examined has been removed. The remaining debris consists ofthe accumulation of dirt, dust and paint chips over the Iife of the plant. The quantity of debris in the penetrations identified is not a containment integrity concern. Most dddebris was lying in the concrete sleeve and not in contact with the penetration. All penetrations examined (except for X-207A-H) were dry with no indication of water. The penetrations typically have a small access and pose difficulty cleaning. The dilemma fiom inside the drywell is the accessibility to the penetrations and the ALARA cqncerns.

The drywell moisture barrier at the concrete floor to steel interface on the 238 level was identified as failed during RF021 examination. During RFO 22 this seal was replaced.

To deal with the paint chipping and corrosion in the seal area and to accommodate the seal installation a six-inch wide band of paint was removed in the seal area for the 111 circumference of the drywell at the 238 level. The seal was reinstalled per minor mod

  1. 2000-010.The six-inch band was re-coated with non-qualified coating. The area ofthe seal and coating was examined after installation to document the as installed condition.

This seal acts as a gasket at the concrete to steel interface to prevent moisture from penetrating under the concrete and to prevent it fkom setting in the interface setting up localized corrosion. This area is an area that regularly gets flooded with water due to the activities that take place during outages in the dry well. This area also is an area that experiences wear and tear at a much higher rate than the rest of the containment due to its location. As a result of the location and outage activities this is an area that requires regular maintenance to keep the moisture barrier seal and the paint in the moisture barrier area intact and properly protecting the steel containment. The logistics of trying to place qualified coating at this location and then set up to regularly maintain it can be difficult as was seen during RF022 not to mention very costly. X recommend that this moisture barrier area and the six-inch band of paint be declared a high maintenance area and designed as an area where unqualified coatings are approved and utilized. This will make the routine maintenance of this area much easier to perform resulting in better

maintenance of this area in the fitlare. If this approach were approved, repahting with qualified coating would not be required only maintenance activity to maintain the integrity of the non-qualified paint and moisture barrier seal. This maintenance should become a routine PM.

PRESSURERETkMNG BOLllNG Bolting examinations for X-200A & B and V16-19-5G& H were completed during W022 in the removed condition. Bolting examinations for V16-19-SA-F was examined in place. This completes the required first period IWEbolting examinations.

An estimated 80% of IWE examinations are completed prior to or during RFO21. The remaining 20% were completed prior to or during RF022 to complete the first period examination requirements.

There were two new IDRs generated, per DP4027, or contahment issues during RF022. All of these issues were addressed by Mechanical Design Engineering prior to RF022 startup.

Please find attached to this report for reference the Summary of First Period IWE Examinations. This repod provides details for the first period examinations.

1/23/1999

SUMMARY

OF FIRST PERIOD WE XAMINATiONS CONTAmhE T SURFACES (TORUS BAYS) ASME SECTION XI EXAM. CATEGORY E-A I

ASME IS1 REMARKS SECTION XI UDENTIFICATION COMPLETE ITEM NO. NO./DESCRIPTION TO DATE I I Intmal surfam above wata line completed RFO 21 EL11 TORUS BAY 1 E x t m l s u r f a excqt

~ area &om catwalk down to belt h e completed Remaking area to be inspeded after S/U RFMl(complaed pre RFO 22)

Gv looV Note: VT-1 completedbelow water line RF020 IrttmnaI surface above water line completed RFO 21 E1.11 TORUS BAY 2 GV 100 % External surface except area from catwalk down to belt limecompleted.

Remainingarea to be inspected after S/U RFMl (completed pre RFO

22) Note: VT-1 completed below water ImeRF020 Internal SUI%= above watpr line completed RFO 21 TORUS BAY 3 GV 100 % Extanal surface except area &om catwalk down to belt line compl+xl R e m a i n i n g i a e a t o b e ~ e d a f t e h S / U ~ l .( c o.m p I ~ p r e R F O 2 2 )

NOQCVT~Icompleted below wata lins RFOZO Internal d a c e above water line completed RFO 21 El.11 TORUS BAY 4 GV 100 Yo E x t a a l surface except area liom &ak down to belt line oonpleted.

Remaking area to be inspected after S/U RFOZl(0ompleted pre RFO 22)

Nate: VT-1 completed below water h e RFOZO Memat surface above water line compl&ed RFO 21 EL11 TORUS BAY 5 GV 100 % External surface except area eom catwalk down to belt b e completed Remaining area to be inspected after s/LT RF02l(completedpie RFO 22)

N&-. VT-1 c o ~ l e t e d below pat= line RF020 h a n a l surface above water line completedRFO 21 TORUS BAY 6 GV 100 % External d a c e except area fiom catwalk down t o belt line completed El.11 Remaining area to be inspeded afla S/U RF<ytl(completed pre RFO 22)

Nde: VT-I wmplezedbelow water lie RFO20 Intimal surface above water line completed RFO 21 El.ll TORUS BAY 7 GV 100 Yo Extmal surface except area fiom catwalk down to belt line completed Remaining area to be inspected S/U RF02l(completedpre RFO 22)

Note:VT-1 complezcd below watcr line RF020 EL11 TORUSBAY8 1 GV 1 100%

haanal M a c e above water line oompl&edRFO 21 External d c e excqqt area fiom catwalk down to belt line complehd RemainingaeatobeinspaiedaftaSIURFO2f(compl&uipreRFO 22)

Note: VT-1 completed below water h e EO20 Intemal sllrface abovewatex line completed RFO 21 TORUS BAY 9 GV 1w Yo Extemal surface except area *om catwalk down to belt line completed EL11 Remaining area to be inspected &er S/U RFO[Zl(oomplBedpre RFO 22)

Note: VT-1 completed below water line FCFO!20 Intimal surface above water line completed RFO 21 TORUS BAY 10 GV 100% Extemal sorface except area &om calk down to belt line completed EL1 1 Reznaining area to be inspeczed ater SiU RFO2l~completedpre RFO 22)

VT-1 c o ~ l e t e dbelow water line RF020 fnternalsurface abovewater line completed RFO 27 TORUS BAY 11 GV 100 % &mal smfilce e x q t area from catwalk down to belt line completed EL11 Remaining areato be inspectedafter S/U RFO2l(oompletedpre WO 22)

Notc VT-I completedbelow water line RF020 Internal surfkce above water line complered RFO 21 TORUS BAY 12 GV 100 Yo Exkana1 &ace except area from catwalk down to belt line completed.

El.1 I Remaining area to be inspected after S/URF(nl(completed pre RFO 22)

EL11 TORUS BAY 13 I I GV 100%

Note: VT-1 completed below water line RF020 htand slafiice above water h e conrpletedRFO 21 External slnface e x q t area fiom catwalk downto belt fine completed Remaining area to be inspected after SIU RFOZl(c0mpleted pre RFO 22)

Not= VT-1 completed below water line RF020 h t d surface above water line completed RFo 21 E1.11 TORUS BAY 14 100 % External surface except area from catwalk down to beltline completed.

Remabiag area to be inspeded aeer S N RFO2l(compleLed pre RFO 2)

Note: VT-1 completedbelow water Ime RF020 Wernal surface above water line completedRFO 21 TORUS BAY 15 100 Yo External except area &om catwalk down to belt line completed EL11 Remaining arcs to be mspccted after S/U RF~l(c0mpletedpre RFO 22)

Note: VT-I compldedbelow water lme RF020

8 Internal surface above water line compld RFO 21 TORUS BAY 16 GV 100 % Memal surfitce except area &om catwalk down to belt line rompleted-Remaining area to be inspeded after SN RFOZl(compl&edpie RFO 22)

Note: VT-1 completedbelow water line RF020 ASME SECTION XI EXAM. CATECX I THE VENT LJNE WAS COMPLJXEDFROM THE INTERNAL El.11 VENT SYSTEM SURFACEFSOZl. TIIEVACUUhIBREAKERLXNESWERE BAY2 COMPLETEDFROMTHEEXTERNALSURFACETOTEfE m m PENETRATION203ELBOW THEN FROM THE WSIDE FROM THE ASSEMBLY, 203 PEhEFRA270N TO THE EJ2OW VERTICAL WELD. THE VACUUM EXTERNAL SURFACE OF THE VENT HEADER AND INTERNAL BREAKERIKNES, AM)EXTERNAL SURFACES OF THE DOWNCOMERS WHERE ANDVENT COMPUTED WOZO.

I-EADER IN BAY 2 THEVENTHEADERINTERIOR,VENTLDEEXi'ERIO%AND AND BAY 3) THE REMAINDER OF THE VACUUM LINE WlLL BE S O U L E D FOR RF022. (completed pre RFO 22)

E1.20 THE VENT LINE WAS COMPLETED FROM THE INTERNAL SURFACE RFOZI. THE VACUUM BREAKER LENES WERE COWLETEDFROMTHEEX'l?5FWALSURFACETOTHE PENETRATION 203 ELBOW THEN FROM THE INSDE FROM THE 203 PENETRATIONTO THE ELBOW VERTICAL WELD. THE EXTERNAL SURFACEOFTHEVENTHEADER ANDINTERNAL AND EXTERNAL DOWNCOMER SURFACES WHERE COMPLETED RFOZO.

THEVENTUNEWAScoMpLETEDJ?ROMTHEt~3ERNAL.

EL1 1 VENT SYSTEM SURFACE RFO21. THE VACUWMBRIEAICERLINESWERE BAY 4 COMPETED FROMTHE EXTERNAL SURFACE TO THE (VENTLINE PENETRATION203 ELBOW THEN FRUM THE INSIDE FROM TIE ASSEMBLY, 203 PEEIETRATlON TO THE ELBOW VERTICAL WELD. THE VACWM EXTERNAL SURFACE OFTIXE VENT HEADER AND IhTERNAL BREAKERLINES, AM, EXTERNAL SURFACES OF THE DOWNCOMERS"RERE ANDVENT COIHPLETEDRFO20.

HEADER INBAY 4 TWE VENT HEADER INTERIOR, VENT LINE EXIERIOR, AND AM)BAY 5 ) THE REEdAINDER OF THE VACUUM LINE WLUBE SCHEDULED FOR RF022.(completed pre RFO 22)

THEVENTLINEWASCOMpI-,ETEDFROMTHJiINTERNAL I 1 SURFACE RF021. THE VACUUMBREAKERLJNES WERE COMPLETEDFROM THE EXTERNAL. SURFACE TO THE PENJXFtATION203 ELBOW THEN =OM THE INSIDE FROM THE 203 PENETRAnoNTO THE ELBOW VERTICAL WELD. THE EXTERNALSURFACE OF THE VENT HEADER AM> INTE,RNAL AM)EXTERNAL SURFACES OF THE DOWNCOMERS WHERE EL11 VENT SYSTEM SURFACE RF02I. THE VACUUM BREAKER tINES WERE BAY 6 COMPLETEDFROMTHEEXTERNAZ,SURFACETOTHE CVENTLINfi PENETRAnoN 203 ELBOW THEN FROM THE INSIDE FROM THE ASSEMBLY, 203 PENETRATION TO THE ELBOW VERTICAL WELD. THE VACUUM EXTERNAL SURFACE OF THE VENTHEADER AND INlZRNAL BREAKER LINES, AND EX7ERNAL SURFACES OF THEDOWNCOMERS WHERE ANDVENT COMF'LETED RFW.

KEADER IN BAY 6 THJSVENT HEADER BTERIOR, VENT LINE EXERIOR, ANI)

AND BAY 7) THE REMAINDER OF THE VACUUMLINE WILL BE SCHEDULED L I FOR RFO22. (completed pre RFO 22)

THEvEESrLINE WASCOMPLETEDFROMTHENIERNAL VENT SYSTEM GV 100% SWACERFOZl. THE VACUU~JIBREAKERLINES WERE BAY 8 COMPLETEDFROMTHEEXTERNALSURFACETOTHE m- PENETRATION 203 ELBOW THEN FROM THEINSIDE FROM THE ASSEMBLY, 203 PENETRATION TO THE ELBOW VERTICAL WELD. THE VACUUM EXTERN'& SURFACE OF THE VENT HEADER AM) INTERNAL BREAKERLMES, ANDExTETwAI,SuRFAcEsOFTHEDoWNcoMERswHERE A M )

m COMPLETED RF020.

HEADER IN BAY 8 THE VENT HEADER INTERIOR,VENT LINE EXTERIOR, AND AM) BAY 9 ) THE REMGIMlER OF THE VACUUM LINE W a L BE SCREDULED FOR RF022.(compldpre WO 22)

THE VENT LINE WAS COMPLETED FROMTHE INIERNAL VENT SYSTEM GV 100% SURFACE RFOZI. THE VACUUM BREAKER LINBS WERE BAY 10 COWLETEDFROM THE EXI'ERNAL SURFACE TO THE (VENTLINE PENETRAnoN 203 ELBOW THEN FRUM TNE INSIDE FRUM THE ASSEMBLY, 203 PESETRATIONTOTHE ELBOW VERTICAL WEU). THE VACUUM EXTERNALSURFACE OF THE VENT HEADER AND INTERNAL BEAKERLDES, AND ExTERNAz,SURFACES OF THE DOWNCOMERS WRERE A M ) VENT coMPLE,mRF020.

HEADER IN BAY THE VENT H E A D E R ~ R I O RVENTLINE ExTFmoxt,AND 10AM)BAY 11) THE REMAfMlER OF THE VACUUM LINE WIU BE SCHEDULED FOR RF022.(copnpleted pre RFO 22)

TlEVENTLINEWASCOMP~TlEDFROMTHE~~~

EI.11 VENT SYSTEM GV 100% SUREACERFO21. THE VACWMBREAKERWNES WERE BAY 12 COMPLETEDFROMTHEEXTERNALSURFACETOTHE m=

ASSEMBLY, PENETRATION 203 ELBOW THEN FROM THE INSIDE FROM THE 203 PENETRATIONTO THEELBOW VERTICAL Wms. THE VACUUM EXl'ERN~SURFACEOFTFE'vENTIlEADERANDINTElwAL BREAKERMNES, ANDE~ALSuRFAcEsOFTHEDOWNcoMERSWHERE ANDVENT COMPLETED wmo.

HEADER IN BAY TEVENTHEADERlNTERIORVENT~EXTERIOR,AND 12AND BAY 13) THE FSMAIhDER OF THE VACUUN LINE WELL BE SCHEJXUD FOR RFOZZ (completedpre RFO 22)

THE VENT LINE WAS COMPLJXED FROM TfIE MTERNAL El.ll VENT SYSTEM GV 100% SURFACERFo21. TliE VACUUMBREAKERLINES WERE BAY 14 c0MPL;ETED FROM THE EXERNAL SURFACE TO TRE (VENT- PENETRATION 203 ELBOW THEN FROM THE INSIDE FROM THE ASSEMLY, 203 PENFzaAnoN TO THE ELBOW VERTICAL WELD. THE VACWM EXTERNAL SURFACE OF THE VENT HEADER ANI) INTERNAL BREAKER-, AND EXTERNAL SURFACES OF THE DOWNCOMERS WHERE ANDVENT COMPLETED RFOZO.

HEADER IN BAY THE VENT HEADER INTERIOR,VENT LINE EXTERIOR AM) 14 AND BAY 15) THE REMAINDER OF THE VACUUM LINE Wac BE SCHEDULED FOR RFO22(completed pre RFO 22)

THEVENTL.DE WASCOhPLETBDFR0EiATHE:INIWWfi E1.11 VENT SYSTEM GV 100% SURFACE RFO2l. THE VACUUMBREAKERLINESWERE BAY 16 COMPLETED FROM THE EXTERNAL SURFACE TO THE mm- PENETRATION 203 ELBOW TIEN FROM THE INSIDE FROM TIJE ASSEMBLY, 203 PENETRATION TO THE ELBOW VER'MCAL WLD. THE VACUUM EXTERNALSURFACE0FTfIEVENTHEADERAM)INTERNAL BREAKERLJNES, AND EXTERNAL. SURFACES OF "HE DOWNCOMERS WHERE ANDVENT COMFLEm T(F020.

HEADER IN BAY THE VENT HEADER INTEXUOR, VENT LINE EXTERIOR, ANI) 16 AND BAY 1) THE REMAINDER OF THE VACUUM LME WILL BE SCHEDULED FOR RFO22. (completed pre RFO 22) r SURFACES (TORUSPENETRATIONS) ASME SECTION XI EXAM CATEGORY: E-A I I TausPco&ation GV 100% COMPLETEINTERNALANDEXTERNAL X-2OOA & B -

VT-3 100% COMPLETE FROM EXI'EWAL RF021 To~usPmettzdi~n GV 100% COMPETE FROMINTERNALRF02I X-20lA THRU H ExTERNAtTO BE SCHEDULED BEFORE OR DURING RFOZZ(comple4edpre RFO 22)

E1.11 El.ll i

El.ll EL11 I--

EL11 EL11 El.ll El.ll x-212 1

kEL1 1 Torus Peneiration GV 100% COMPETE FROMEXTERNALRFOtl (UMIERWATER)

X-213A & B E1.12 VT-3 1000/0 COMPUTE FROM EXTERNAL FS021 (UNDER WATER)

El.ll Torus P e n d o n GV 1ooO/o COMPL.ETlZFROMINTERNALAM3EXTERNALRF021 X-214 El.ll TorusPenetration GV 100% COMPLETE FROM INTERNAL AND EXTERNALRF021 X-215 El.ll TorusPenetration GV 100% COMPLFXE FROMINTERNAL AND EXERNAT- W021 X-216 1 i Et.11 Torus Penetration GV 100% COMPLETE FROM INTERNAL AND EXTERNAL RFO21 X-217 '

TonrsPene4ration GV 100% COMP~TE FROMINTEFWAL AND EXl'ERNALRFO21 I X-218

Torus Penetrasion GV 100% COUPLETE FROM INTERNAL AND EXTERNAL RF021 X-219 El.11 TorusPenetation GV 100% COMPLETE FROM INTERNAL AND EXTERNAL RFO21 x-220 El.ll TONSPenetration GV 100?/0 COMPLETE FROMINTERNAL AND EXIEKNAL RF021 x-221 E1.II Torus Penetration GV 1W?? COMPUTE FROMINTERNU AND EXIERNALRFO21 X-222 El.ll Tom Penetration GV 100% COWLEXE FROM INTERNAL AM)EXIZKNAL RFO21

~ ~ ~

E1.11 Torus Pen&ation GV 100?/0 COMPLETE FROMEXTE,RNALRF021 X-224A & B II INSULATIONPREVENTING INSPECTION FROM E X ' J X ~ A L ,

INTERNALUNDER WATER. THIS WILL BE RESCHEDULED WHEN DIVERS ARE IN TORUS OR TORUS HAS BEEN DRluNED

' Azx>NG WITH TKEUNDERWATERWAER SURFACES.

El.ll TorusPmetration GV 100% COMPLETE FROMEX'lERNAL RFOZ1 (UNDER WATER)

X-225 EL12 VT-3 100% COMPLETE FROMEXTERNAL.RFO21 o E R WATER)

EL11 Tarus Penetration X-226A & B 100% 1 COMPLETE FROMEXTERNALRFOZl (UNDERWATER)

EL12 VT-3 100% COMPLETE FROMEXTERNALRFO21 (UNDER WATER)

EI.11 TansPendmtion GV 100% COMPLETE FROMEXERNALRF021 (UNDER WATER)

X-227 E1.12 VT-3 100% CQWLETEFROMEXTERNAL.WO2f (UNDER WATER)

E1.ll 100% COMPLETED FROM EXTERIOR RFOX (NOT ACCESSIBLE FROM

~~

INTERIOR)

E1.11 TorusPenarstion GV 1W! COMPUTED FROM EXTERIOR RFO22 (NOTACCESSIBLE FROM X-229 INTERIOR)

ELI1 TorusP~ndration 100VO COMPLETED FROMEXTERIORRFCnl EL11 Torus Pm&ation GV UNDER WATER FROM INTERNAL)

X-231 A-H B,D,F,G & H COMPLETEDFROM EXERNAL. RFOZl CONTAINME JS) ASME SECTION XI EXAh4. CATEGORY: E-A EL11 IOOYO CUMPLETEI)FROMINTERNALRF021 238 to elevath 251 EXTERNALINACCESSIBLEBY DESIGN quadraut 0 to 90 EL22 degrees 100% COMPLETED FROM INTERNALRFO21 EXTERNAL INACCESSIBLEBY DESIGN EL11 ~ryw-~e~evatian 100% COMPLETED FROM INTERN& RFO21 238 to eIevdan 251 EXTERNAL INACCESSIBLEBY DESIGN quadrant 90 to 180 E1.12 &pees 100% COMPLETEDFROMINTERNALRFO21 EXTERNALINACCESSIBLEBY DESIGN El.ll n y W d elwation low?? COMPLETED FROM INTERNAL RF021 238 to elevation251 EXTERNAL INACCESSIBLE BY DESIGN quadrant 180 to 270 degrees

El. 12 VT-3 100% COhdPLETEDFROMINTERNALRFOZl EXTERNAL INACCESSXBLEBY DESIGN El.ll Drywell elevation COMPLETEDFROM INTERNAL RFOZl 238 to elevation 251 EXTERNAL INACCESSIBLEBY DESIGN quadrant 270 to 360 E1.12 CQMPLETEDFROMIN"ERNALRF021 EXTERNALINACCESSIBLEBY DESIGN EI.11 COMPLETED FROMINTERNALRF021 EXTERNALINACCXSSIBLE BY DESIGN E1.12 COMPLETEDFROM INTERNAL WOZl EXTERNAL JNACCESSIBLE BY DESIGN EL11 COMPLETED FROM INTERNAL RF021 EXTERNALINACCESSIBLE BY DESIGN El.ll COMPLETED FROMINTERNALRFOZl EXTERNALINACCESSIBLEBY DESIGN EL11 COMPLETED FROMIN'IENALRFO21 EXTERNALINACCWIJ3L.E BY DESIGN EL11 COh4HZTED FiROMINTERNaRFOZl EXXERNAL. INACCESSIBLEBY DWIGN E1.11 COMPLETED FROMINTERNALRF021 EXTERN& INACCESSIBLEBY DESIGN El.11 COMPLETEDFROM INTERNALRFOZ1 EXTERNALINACCESSIBLEBY DESIGN qua&& 180to 270 EL11 COMPLETED FROM INTERNAL RFOZl EXTERNALINACCESSIBLE BY DESIGN El.11 COMPLETED RFO21 El.11 CONTAINNE! T SURFACES (DRYWELLPENETRATIONS)

El.ll DrywellPemtzitiion GV low? COMPLETED IN"ER5Jfi AND EXTERNAL RF021 x-1 PORTIONS OF THE EXIZRNAL =A ARE INACCESSIBLE FROM DIRECT VISUALEXAMINATIONBY DESIGN EL11 DrywellPenemion GV 100% COMPLETEDINTERNALANDEXTEIWAZ,RF~I x-2 PORTIQNS OF THJ3 EXTERNAL AREA ARE INACCESSIBLE FROM DIRECT VISUAL EXAMINATIONBY DESIGN

EL11 Drywell Penetdon X-4 GV 1 I

1 100% I I

I COMPLETED~RNfiANDEXTERNALRF021 I

I El.ll Drywell PeneIration GV 100% COMPLETEDTNTERNALRFO21 X-5A THRUX-5H EXJTRNAL TO BE COMPLETED BEFORE OR DURING WO22(colnple&ed pre RFO 22)

E1.12 VT-3 COMPLETED FXOMTHEINTEFWAL SURFACE W021 ELI1 GV low0 COMPLETED FROM INTERIOR RFO21 RESCHEDULE EXIERIOR BEFORE OR DURING RFO22(c0mpl&d pre RFO 22)

I I

I I I El.11 GV 100% COMPLETED FROM INTERNAL RF021 EXTERNAL TO BE SCHEDULED BEFORE OR DURING RFo22(coqleted RFO 22)

El.11 Drywedl Penetration GV 100% COMPLETED FROM INTERNALRF021 X-7B EXTERNAL TO BE SCHEDULED BEFORE OR DURING RFo22fcompleted RFO 22)

El.ll Drywell Pffletratm GV 100% COMPLETED FROMINTERNAL W 0 2 1 x-7c EXTERNAL TO BE SCHEX)ULED BEFORE OR DURING RFo22(completed RFO 22)

I El.ll Drywell Pendration GV 100% COMPLETED FROMINTERXAL RFO21 X-7D EXTERNAL. TO BE SCHEDULED BEFORE OR DURING RFO22(comp leted RFO 22)

I El.ll Drywell Pen&ation GV 100% COMPLETED FROMXNIERNALRF021 x-8 EXTJ5RNAL TO BE SCHEDUED BEFORE OR DURING RFo2xCompleted pre RFO 22)

E1.12 w-3 100% COMPIETEDFROM~NALRF021 EL11 Drywell Penetration GV 100% COMPLETEDFROM DJTElWAL RFO2l X-9A EL11 DryWeuPenetratim GV 100% COMPLETED FROMINTERNAC RFO2l X-9B EXEFWAL TO BE SCHEDULED BEFORE OR DURING RFo22(completed RFO 22)

El.11 Drywell Penetration GV 100% RESCHEDULE FOR W 0 2 2 (oompleted RFO 22) Extarnal surface x-TO insulated restrictingaaess for GV Exam. N d internal srnfacehas limitedviewfromBdstingvanta~poirrts El.11 Drywell Penetration GV 100% RESCHEDULE FOR RF022 (complaed RFO 22) External d a c e x-11 insulatedrestrictingacceff for GV Exam Normal internal d c e h m limited view fiom &g vantage points El.ll Drywen Penetration GV 100% COMPLETED FROM INTERNAL RF021 (TNACCESSIBBLE AREA x-12 IDENTIFIED)

EXTERNALTO BE SCHEDULED BEFORE OR DURING RFOZ2(completed pre RFO 22)

El.ll Drywell Penei~atioa GV COMPLETEDFROMINTERNALRF021 X-13A RNAt TO BE SCHEDULEDBEFORE OR DURING W 0 2 2 EL11 Drywell Pen&mlion GV COMPLETED FROM INTERNAL RF021 X-13B TOBE SCHEDULEDBEFORE OR DURING RFOZZ Ell1 Drywell Penetration GV x-14 El.ll Drywen ILeoetration GV X-15 EL11 hyweu Pezle.tration GV X-16A El.ll DiywellPenetration GV X-16B El.11 Dlywdl Penetration GV COMPLETED FROMINTEWALRFOZl X-17 RNAL TO BE SCHEDULEDBEFORE OR DURING RF02f E1.11 Drywcn Penetration GV COMPLETED mOM INTERNAL RF021 X-18 AL TO BE SCHEDULEDBEFORE OR DURING W022 El.11 GV 100% COMPLETED FROMlNTERNALRFOZl EXTERNAL TO BE SCHEDULED BEFORE OR DURING W022 (completed RFO 22)

EL11 Drywell Pen&ation GV 1WA COMPLETEDFROMINTERNAL RFo21 x-20 EXTERN& TO BE SCHEDUUD BEFORE OR DURING RFo22(completed pre RFO 22)

EI.ll DryweU Penehatim GV 100% COMPLETED FROM INTERNAL RFO21 x-21 JXTl3RNA.L TO BE SCHEDULEDBEFORE OR DURING RFmz(C0mplekd pre RM 22)

I El.ll Drywell Penetration GV 100% COMPLETED FROMNI'ERNALRRlFOZl x-22 EXTERNACT0 BE SCHEDULEDBEFORE OR DURING RFo22(oompleted pre RM 22)

El. 11 Drywell Pen&itim GV 100% INSULATION PREVENTS ACCESS FOR GVEXAM FROM X-23 lNTERNAL SURFACE.(complded RFO 22)

El.ll DryweU Penetration GV lOoO/o INSULATIONPREVENTS ACCESS FOR GV E X A M FROM X-24 INTERNAL, SURFACE(oompletd RFO 22)

I I

El.ll GV 100% COWLETZD FROM INTERNALRF02 1 EXTERNALTO BE SCHEDULED BEFORE OR DURING RFot2(completed pre RFO 22)

El.ll Drywell Penetration GV 100% COMPLETEDFROkfINTERNALRF021 X-26 EXTERNALTO BE SCIfEDZILEDBEFORE OR DURING RFO22 (complaedpreRFO22)

I E1.12 100% COMPWTED FROM INTERN4.L -021 EI.11 Drjwell Penetration 100% COMPLETED FROM INTERNALRFO21 X-27 EXTERNAL TO BE SCHEIlULeDBEFORE OR DURING RFO22 (cmplered RFO 22)

El.11 Drywell Paletration X-28 I Gv 100% COMPLETED FROM INTERNALRF021 EXTERNALTO BE SCHEDULED BEFORE ORDUIUNGW022 (compleled RFO 22)

E1.11 100% REScIEDULE FOR RFO22 INTERNAL SURFACENOT SAFELY ACCESSIBLX FOR GV EXAMINATTON (completed RFO 22)

El.ll 100% COMPLETED FROM INTERNALRFoILl EXTERNAL TO BE S C E D W D BEFORE OR DURMG R.FO22 pmplaed pre RFO 22)

E1.12 VT-3 100% COMPLETEDFROM MTERNAL RFO21 EL11 DryweUPenetration GV 100% COMPLETEDFROMTNTEPNALRFOZl X-3 1 EXTERNALTO BE SCHEDULEDBEFOF33 OR DURING W022

{cOmpl&ed pre RFO 22)

E1.12 VT-3 lOoO/o COMPLETED FROM INTERNAL RF021 I

E1.11 DrywellPenelratim GV 1000/0 COMPLETED FROM INTERNAL RF021 x-32 EXTERNAL TO BE SCmDULED BEFORE OR DURING RFO22 (compldpre RIO 22)

EL12 100% COMPUTZD FROM INTERNALRF021 El.ll 100% COMPLETED FROMINTERNfiRFO21 J3TERNA.LTO BE SCHEDULED BEFORE OR DURING RF022 (completedpre RFO 22)

I EL11 100% RESCHEDULE FOR RFOZZ (complet& pre RFO 22)

EL11 DryweIlPene(rati0n X-35A I GV 100% COMPLETEDFROMINTERNALANDEXTERNALRmtl THISPENETRATION IS PARTIALLY ACCESSIBLEFOR GV EXAM ELI2 100% COMPLETED FROM INTERNALRFOZI El.ll LLzq-?-

X-35B 100% COMPLETED F?AOMINTERNALAND EXTERNAL RF021 THIS PENETRATIONIS PARTIALLY ACCESSIBLE FOR GV EXAM EL12 100% COMPKEIZD FROM W W A L R F 0 2 1 EL11 100% COMPLETED FROM INTERNAL AND EXTERNAL It3021 x-35c THISPENETRATlON IS P A R ~ ACCESSlBLE ~ Y FOR GV EXAM EL12 I VT-3 100% COMPLETED FROM INTERNALRF021 I

El.11 DryweliPeuetration GV 100% COWU3TED FROM INTERNAL AND EXTERNAZ.W 0 2 1 X-35D THIS PENETRATION IS PARTIALLY ACCESSIBLEFOR GV EXAM I-----

E1.12 / VT-3 100% COMFLETEDFROM~~ALRJ?O21 El.ll 1000/0 COMPLETED FROM INTERNALAND ?LXTERNALRFO21 THIS PEMETRATIONIS PARTIALLY ACCESSIBLE FOR GV EXAM

E1.12 VT 100% COMPLZEDFROMINTERNALRF021 EL11 Drywen Penetratim GV 100% COMPLETED FROM INTERNAL RFOZ1 X-36 EXTERNALTO BE SCHEDULED BEFORE OR DURING RF022 (compIptedpreRFO22)THLS PEmTRATIONIS NOT SAF'ELY ACCESSDBUFOR GV EXAM.

El.ll Drywell Penebatim GV 100% COMI)LETEDFROMINTERNALRFO21 X37A -NAL TO BE SCHEDULED BEFORE OR DURING UO22 (completedpre RFO 22) THIS PENE'IXATIONIS NOT ACCESSIBLE FOR GV EXAM DUE TO PROXIMITY OF PIPESTO EACH OTHER AND THEMINIMAL CLEARANCES BETWEEN THECRD PIPING ANDTHEcowm~s~vEs.

ELI1 GV 100% COMPLETED FROMINTERNALRFOZI EXTERNALTO BE SCHEDULED BEFORE OR DURXNGRF022 (compldpre RFO 22) THIS PENETRATION IS NOT ACCESSIBLE FOR G V EXAM DUE TO PRO'XIMITYOF PIPES TO EACH OTHER AND THE MINIMAL CLEARANCES BETWEEN THE CRD PIPING AM3 THE CONCREIX SLEEVES.

EL11 DIywellPenehation GV 100% COMPLETEDFROM JNEFSAL RFW1 x-37c EXTERNALTO BE SCHEDULED BEFORE OR DURING -022 (complplaedpre RFO 22) THls PENETRATIONIS NOT ACCESSIBLE FOR GV EXAM DUE TO PROXIh4lTY OF PIPES TO EACH OTfIER AND THE MINIMAL CLEARANCES BETWEEN THE CRD PIPING AND THECONCRETE SLEEVES.

EL11 GV 100% COMPLETED FROMINTERNALRFo21 MTERNALTO BE S C m U L E D BEFORE OR DURING RFO22 (coqlBed pre RFO 22) THlS PENETRATION IS NOT ACCESSBIB FOR CrV EXAM DUE TO PROxIMIn OF PIPES TO EACH OTHER AM3 THE MINIMAL CLEARANCES BETWEEN THE CRD PIPING AND THE CONCRETE SLEEVES.

EL11 Drywell Pen&atim GV 100% COMfLETEDFROMINTJBNURF021 X-38A EXTERNAL TO BE SCHEDULED BEFORE OK DURING RF022 (oompl&ed pre RFO 22)THIS PENETRATIONIS NOT ACCESSIBLE FOR QV EXAM DUE TO PROXIMITY OF PIPES TO EACH OTHER AM3 THE MZNIMAL CLEARANCES BETWEEN THE CkUl PIPING ANDTHE CONCRETE SLEEVES.

El.11 Drywell Pelle&tim GV 100% COMF'LETED FROM INTERNAL RFO21 X-38B EXlBFtNAL To BE SCHEDULED BEFORE OR DURING RF022

  • (aornpleted pre RFO 22) THIS PENJXRATXON IS NOT ACWSIBLE FOR GVEXAM DUE TO PROXIMITYOF PIPES TO EACH OTHER AND THE MINIMAC CLEARANCESBETWEEN THE CRD PPlNC3 AND THE CONCRETE SLEEVES.

El.ll Drywell Pen&ation GV 100% COMPLETED FROM MTERNAL RF021 X-38C EXTERNAL TO BE SCHEDULED BEFORE OR DURJNQ W022 (completed pRFO 22) THIS PENETRA~ONIS NOT ACCESSIBLE FOR GV EXAM DUE TO PROXIMITY OF PIPES TO EACH OTHER ANDTHEMINIMALCLEARANCESBETWEENTHECRDPIPLNG AND THE CONCRETE SLEEVES E1.11 Dryweu Penetration GV 100% COMPLETED FROM INTERNAL RFO21 X38D EXTERNALTO BE SCHEDULEDBEFORE OKDURING RFOZ2 (completed pre RFO 22) TMS 'PENETRATIONIS NOT ACCESSIBLE FOR G V EXAM DUE TO PROXIMITY OF PIPES TO EACH OTHER AND THE MINlMAL CLEARANCESBETWEEN THE CRD PIPING AND THE CONCRETE SLEEVES.

El.ll GV 100% COMPLETEDFROM INTERNAL RFO21 EX'ERN,M, TO BE SCKEDUUD BEFORE OK DURING R.F-2 (completed pre RFO 22) THIS PENETRATION'ISINACCESSIBLE FOR GV EXAM OF EXTERNAL,S W A C E S DUE TO INSIXATION

1 1 b

EI .11 DrywellPenctraticn GV 100% COMPETED FROM INTERNALWO21 X-39B EXTERNAL TO BE SCHEDULED BEFORE OR DURING W 0 2 2 (oompletedpre RFO 22)

El.ll COh4PLE7ED FROM INTERN& RF021 EXTERNALTO BE SCHEDULEDBEFORE OR DURING S O 2 2 (completedpre RFO 22) THIS PENETRATIONIS NOT SAFELY ACCESSIBLEFOR GVEXAM OF EXYERNm SURFACE El.11 COMPLETED FROM INTERNAL RFOZI EXERNAL TO BE SCHEDULED BEFORE OR DURING -022 (completedpre RFO 22) THIS PENETRATIONIS NOT SAFELY ACCESSIBLE FOR GV EXAM OF EXEWAL SURFACE E1.11 COMPLETED FROMINTERNAL RFO21 EXTERNAL TO BE SCHEDULEDBEFORE OR DURING W022 (completed pre RFO 22)THIS PENETRATIONIS NOT SAFELY ACCESSIBLE FOR GV EXAM OF EXTE;RNAZ.SURFACE El.11 COMPLETED FROMINIXRNALRFOZl EXTERNALTO 3 E SCHEDULED BEFORE OR DURING RF-2 (coql&edpre RFO 22) T H I S PENETRATIONIS NOT SAFELY ACCESSIBLE FOR GV EXAM OF EXTERNAL SURFACE EL11 DrywellPeneCraticn x-41 1 GV I 100% RESCHEDULE FOR RFO22 (completed RFO 22) THE INTERNAL SURFACEOF T H I S PENETRATIONISNOT S A F n Y ACCESSIBLE FOR GV EXAM EL11 COMPLETED FROMWIERNALRF021 EXTERNAL TO BE SCHEDULED BEFORE OR DURXNG BO22 (completed pre RFO 22)

El.11 DryWelIPenelxation GV 100% COMPLETED FROMINTERNALW 0 2 I x43 EXTERNAL TO BE SCHEDULED BEFORE OR DKJRING RF022 (completed RFO 22) THE EXTERNAL SURFACE OF TAIS PENETRATION IS NOT SAFELY ACCESSIBLEFOR GV EXAM El.ll DrywellPmdration GV 100% COMPLETEDFROM INTERNAcRFO21 X-44 EXTERNAL TO BE SCHEDULED BEFORE OR DURING W O 2 2 (completedRFO 22) THE EX'ERNAL SURFACEOF THIS PENETRATIONIS NOT SAFELY ACCESSIBLEFOR G V EXAM El.ll COMPLETED FROM INTERNAL RFO21 EXTEFWAL. TO BE SCHEDULED BEFOm OR DURING RF022 (completedpreRFO22)

EL11 DrywdlPndraticn GV 1MY0 COmLETED FROMINTERNALRFOZl X-46 EXTERNAL.TO BE S C m U L E D BEFORE OR DURING S o 2 2 (complded RFO 22) THF,EXTERNAL SURFACE OF THIS PENETRATION IS NOT SAFELY ACCESSIBLE FOR GVEXAM EL11 RESCHEDULE FOR RFO2ltfcompkted RFO 22) TIE INTERNAL SURFACE OF THIS PENETRATION IS NOT SAFELY ACCESSIBLE FOR GV EXAM El.ll COMPLETEDFROMINTEFWALRFO21 EXTERNALTO BE SCHEDULED BEFORE OR DURING RF022 L

(completedpre RFO 22)

EL11 DrywellPendon GV 100% COMPLETEDFROMINTERNALRFO21 x-49 EXTERNAL TO BE SCHEDlJLFD BEFORE OR DURING -022 (completed pre RFO 22)

EL11 COMPLETED FROM mTTERNAL RFO2I EXTERNALTO BE SCHEDULED BEFORE OR DURING RF022 (Completedpre W O 22)

COMPLETEDFROMMTERNALRF021 EXTERNAL TO BE SCIEDLJLl3lBEFORE OR DURING W022 (completed pre RFO 22)

COMPLETED FROM MTERNALRF021 EXlERNAI., TO BE SCHEDULED BEFORE OR DURING RF022 (completedpre RFO 22)

El.ll DryweuPenetratica GV 1MY0 COMPLETED FROM INTERNAL RFO21 (INACCESSIBLE AREA X-100A IDENTIFED)

EXTERNAL TO BE SCHEDULED BEFORE OR D W G RF022 (completedpre RFO 22)

COMPLETED FROM INTERNAL WON (INACCESSIBLE AREA IDENTIFIED)

EXTERNAL TO BE SCHEDULED BEFORE OR DURlNG RFO22 (completedpreRFO 22)

COMPLEETEI, FROM INTERNALWOZ1 (INACCESSIBLE AREA IDENTIFIED)

EXTERNALTO BE SCHEDULED BEFORE OR D U G RFO22

[completed pre RFO 22)

EL11 DryweUPmetration GV 100% COMPLJ373D FROM INTERNAL RFO21 (INACCESSIBLEAREA X-100D D-D)

EXTERNALTO BE SCHEDULED BEFORE OR DURING -022 (oompleted pre RFO 22) -

El.ll DryvpeUPeaetmtion GV 100?? COMPETED FROMWTERNALRF021 (rNACCESSIBLE AREA X-lO1A IDENTIFIED)

EXTJ3RNAL TO 3E SCHEDULED BEFORE OR DURING RFO22 (completed pre RFO 22)

COMPLETEDFROMINTERNAtRF021 (INACCESSIBLEAREA IDENTIFIED)

EXTERNAL TO BE SCHEDULED BEFORE OR DURING -022 (complaed pie RFO 22)

COMPLETED FROMINTERNALRF021 (l.NACCESSIBLEAREA IDENTIFIED)

EXTERNAZ,TO BE SCHEDULED BEFORE OR DURING W022 (completed pre RFO 22)

COMPLETEDFROM INTERNAL WOZ1 (INACCESSIBLE AREA m-D) 1 I 1 EXTERNAL TO BE SCHEDULED BEFORE OR DURING RRXZ (COmpTetedpreRFO 22)

I I I El.ll DrywellPenetration GV 100% COMPLETEDFROM INTERNAL RFO21 (INACCESSIBLE AREA x-102 ID-D)

EXTERNAL TO BE SCHEDULED BEFORE OR DURING RFO22 (completedpre RFO 22)

CO?dPIE'ED FROM INTERNALRFO21 (INACCESSIBLE AREA IDENTIFIED)

EXI'ER.NAL TO BE SCHEDULED BEFORE OR DuRINci RF022 (completedpre RFO 22) EXTERNAL SURFACE OF TIflS PENETRATIONIS NOT ACCESSIBLE FOR EXAMINATIONDUE TO DESIGN COMPLETED FROM INTEKNAL RF021 (INACCESSIBLE AREA IDENTIFIED)

EXTERNALTO BE SCEDULED BEFORE OR DURING RFO22 0

~

El.11 DrywellPenetmiion GV 100% COMpLJ3TED FROM INTERNALRFO21 (INACCESSIBLE AREA X-104B IDENTIFED)

EXTERNALTOBE SCHEDULEDBEFOREORDURINGRFO22 (completed pre RFO 22)

ELI1 DtywellPenetrrdim GV 100% COMPETED FXOMINTEWAL RFO21 (ILNACCESSIBLEAREA X-104c IDrnrn)

EXTERNAL TO BE SCHEDULED BEFORE OR DURING RF022 (oampleted pre RFO 22)

EL11 DrywellPenetration GV 100% COMPLETED FR0MLN"ERNALRFO;ZI (INACCESSIBLE AREA X-1O5A IDENTIFIED)

EX"ERNAL TO BE SCHEDULED BEFORE OR DURING I(Fo22 (completedpre RFO 22)

El .I 1 Drywen Penataticn GV 1OOVO COMPUTED FROM INTERNAL RF021 (TNACCESSDBLEAREA X-1OSB IDENTIFIED)

FxfERNALTO BE SCHEDULED BEFORE OR DURING W022 (COmplBed prs RFO 22)

EL11 COMPLETED FROM INTERNGLRF021 (INACCESSJELJ?AREA EL11 COh4PETED FROM INTERNAL RFO21 (INACCESSIBLEAREA EL11 El.11 CONTAINMENT SEALS. GASKETS, AND MOISTURE BARRIERS ASME SECTION XI EXAM. CATEGORY: E D I I I E ~ a m Vo REMARKS mmLETE TO DATE DRY WELL I 1 IhSPECTIONCOMftETED RF021 MOIsruRE DISCREPANCIESWERE IDENTIFIED AND DISPOSITION FOR BARRlER THIS lTEM IS WlTH MECHANICALDESIGNENGMERlNG vT-3 loo%

CONTNMENT SURFACESREQUIRING AUGMENTED ASME CLASS MC ASME SECTION XI EXAM:

JXAMINATION CATEGORY- E-C ASME SECTIONXI IS1 Exam  % REMARKS ITEM IDENTIFICATION COMPLET NUMBER NO./DESCRIPTION E TO DATE Drywell I[nterior E4.11 Surfaceatthe VT-1 100% The area jdenrifiedfor augmented exam of the Drywell surface at the Moisture Barrier moishuebarrier interface shaLl be from ccmtainmat plate weldjomt Intdace leiofX-5B to the containmentplate weld joint right ofpenetrrrtionX-I 5E and *om the m a d e metal intRfHce up 1 foot. Complete RFO22

.. .. . . . - . ..._..... ..... . .. . . . .. ... .__ . .... ...... .... .... ..... -. ~.

E4.12 Drywell Interior Volumetric 100% ?heareaidentiiedforaugmented examoftheDrywellsurfaceattbe Su&ce at the moisturebarrier i n t d c e shall be from contp' t plate wdd joint MohBarrier left of X-5B tothe c m t a h e n t plate weldjoiot right ofpenatation X-Interface 5E and fromthe concrete metal interfaceup 1 foot. ConpleteE O2 2 I t I I ASME Is1 Exam  % REMARKS SECTION XI IDENTIFICATION COMPLETE ITEM NO. NO.IDESCRIPTI0N TO DATE 1 IRESCHEDULE FOR RF022 (completedRFO 22)

E8.10 TORUS MANWAY Vl-1 1W/o FLANGE BOLTING PENETRATION 200A - ~

E8.10 TQRUS MANWAY VT-I 100% RESCHEDULE FOR RF022 (complaed RFO 22)

FLANGE BOLTING PENETRATIQN 200B -

E8.10 V16-19-5A-F VT-1 100?/0 E8.10 VT-I 100?40

To: DennisGirroir 12/02/1999 From: Ralph Connell Re: Report for IWE Inspections Performed for W021 INTRODUCTION:

The objective in the current period for this new NVE inspection program was to gather as much information as we could for RF021 and RF022. During RF021 the goal was to perform as many inspections as possible within the acceptable window without causing any interference with other outage work activities. The remainder of the required first period examinations will be scheduled for RFO22. An estimated 80% of the required first period examinations have been completed at the cbmpletion of RF02 1.

DISCUSSION:

The ASlwE Section XI Subsection MTE Code requires an examination of the coated sUTfaCes in order to determine the condition of the substrate. This examination of coated surf'aces is for evidence of flaking, blistering, peeling, discoloration and other signs of distress. The TWE examinations performed for W021 found only two areas of coating with signs of distress affecting the substrate. Those two areas were located at the drywell interior moisture barrier and the other was on the drywell surface at the X-5G penetration. Both of these were evaluated by Mechanical Design Engineering and dispositions provided via the IDR process. At m y iireas of the drywell there is peeling or discoloration. Both of these issues have been previously identified and accepted via the OP5250 inspections.

The Maintenance Department has been peri?o&g containment inspections for several years via OF5250 to evaluate the condition of the coatings on containment surfaces.

These inspections have compiled an excellent source of data documenting the conditions of the coatings and how these coatings are maintaining over time. The information provided from these reports provides the basis for disposition of issues identified on the IWEreports such as coating peeling and blistering. In all cases, except for the two areas specifically identified at the joint seal and the SG-penetration area, the peeling and blistering coating is a condition that applies to the outer epoxy coating. The primer coat remains intact providing acceptable protection of the metal surfaces.

Several areas were identified as inaccessible during the RF021 IWE examhation process. These inspection reports shall be reviewed for detail and validity. After the review the program procedure wilI be revised to recognize the inaccessible areas in the program, PP7024.

There were fiReen examhation reports rejected due to housekeeping concern. One report was a VT-3 for X-206A external surface, eigh for X-207A through H internal

t surface, two for X-9A & B external surface, and four for X-7A through D external surface. All of these examinations shall be rescheduled for inspection before or during RF022 after cleaning. There are also housekeeping issues on a portion of the external torus surface below the catwalk, which also require cleaning and reinspection.

DETAXLS:

TORUS SURFACE The torus inspections covered approximately 94% of the accessible Surface for general visual examination. Underwater locations are considered inaccessible for general visual examination. The Surface %om just below the catwalk on the exterior surface to the horizontal mid point of the torus was not inspected. This surface requires cleaning before it can be properly examined. A work order request has been submitted to perform this cleaning. The remaining 6% of this Surface can be inspected with the plant on line and should be completed prior to W 0 2 2 if cleaning is performed.

The underwater surface areas were completed in RF020 using VT-1 criteria. These inspections were performed prior to the formal development of the IWE program. In order to be conservative, VT-1 examinations were specified in anticipation of this area being classified as Category E-C augmented examination. The review of the torus inspection data generated fiom 1998 revealed that during the twenty-five plus years of operation there were no significant areas of general corrosiodmetal loss identified.

Therefore it may be concluded that the interior surface of the torus is not subject to accelerated corrosion and no augmented examination are required at this time. The IWE program as written reflects this philosophy. This is not to say that the torus will never be classified as Category E-C, but that classification, if necessary, will be the result of finding areas that are subject to accelerated corrosion. The scheduled TWE examinations will provide regular examinations of the torus and that data will be evaluated for applicability to Category E-C. The result of performing VT-1 and UT examinations was that it provided excellent baseline data. The VT-1 examinations performed during RF020 exceed the required IWEVT-3 examinations of the applicable surfaces.

IDR 99-07 provides the disposition for an area on torus bay 4 where metal was removed.

This area on bay 4 appears to be &om original construction and does not violate the minimum required thickness in this area OT the code referenced 10%. This area is acceptable as is. Reference VYM 99/147 for the complete details of this evaluation.

The examinations required for the first period have completions of 80% for the general visual inspections and 100% for the scheduled VT-3 exams. The vent header external surface, downcorners internal and downcomers external surfaces were completed during RF020 inspections using VT-1 examinations. The vent lines were completed during RF021. The exterior of the vent lines outside the torus, the remainder of the vacuum breaker lines external surfaces and the vent header interior surface will be rescheduled for

general visual examination before or during RF022. Tbe remaining 20% of the required first period examinations will be rescheduled for RF022.

IDR 99-06 was generated against nine rejected examination reports for cracks in the attachment clip tack welds that holds the vacuum breaker line bellows cover in place. The cracked welds for the vacuum breaker expansion joint cover attachment clips appeared to be a configuration issue as the cause. Tbe short-term evaluation was basically use as is.

An ER was also written for the issues addressed here, ER 99-1321, and will address the long-term corrective actions for the items identified 'within IDR 99-06. VYM 991145 provides the details of this evaluation.

Torus penetration (includes penetrations in the vent system) examinations completed 90% of the requirements for the first period, The areas remaining 10% of the penetrations to be examined were in the area of the torus requiring cleaning. These penetrations will be cleaned along with the torus surface and inspections should be completed prior to RF022.

RFO21 examinations completed 100% of the accessible drywell surface. The outer surface of the drywell is inaccessible by design except for the drywe11 head, which is accessible from both sides. Except for paint issues which have been previously identified by OP5250 and found acceptable, the only other issues dealing with the containment surfkce is the corrosion identified on the containment surface at the 5G penetration and the corrosion of the containment surface in areas along the joint seal. The joint seal area corrosion is described in more detail under heading Containment Seals, Gaskets, and Moisture Barriers. Tn these two cases the paint was ciacked and peeled. Investigation of these areas identified the corrosion in these areas.

In general, the paint peeling and flaking are the results of loss of paint film adhesion of the outercoat to the primer coat. Typically the primer coating under this peeling and flaking paint is in good condition and is tightly adhered to the base metal. The discoloration are the result of leakage and work activities from past events and work activities except those noted on IDR's for m h e r engineering evaluations. The blistering identified in the coating is most likely the result of gases or liquids within or underneath the paint, which exert pressure greater than the adhesion or cohesion of the paint at the area under stress. If the rate of diffision of the solvent vapor through the paint film is slower than the rate of formation of the vapor, blistering will occur. This would have occurred during the drymg process shortly after the paint was originally applied. It is not unusual to find some ofthis type of condition in this paint system. This condition is a paint issue only and does not affect the base metal.

IDR 99-018 is for corrosion identified on the containment (drywell) surface in the area of the X-5Gpenetration. No signrfcant wall loss is identified for this area. And no further

action is required, Reference VYM 99/139 for the complete details of this evaluation.

This area shall be scheduled for cleanup and repainting during RF022.

DRYFU3.LP.ENTRAnONS Forty-three (43) percent of the required first period drywell penetration examinations were completed during RF021. Many of these penetrations depicted debris and peeling paint in the examination reports. Follow up examinations of these penetrations pefformed by the Project Engineer Responsible Engineer revealed that the debris remaining in the penetrations consisted of an accumulation of dirt and peeled paint fiom approximately twenty-six years of operation. This debris is not considered to be detrimental to the containment structure. All penetration cavities were dry with no visible indication of moisture. The peeling paint was similar to that identified in the maintenance reports and is not unusual for the age and environmental conditions experienced by the coating. The remaining 57% of these penetrations shall be inspected prior to or during RF022.

The debris identified in the drywell penetration cavities is a housekeeping issue only, not a containment integrity concern. Ali large debris located in the penetrations examined have been removed, The remaining debris consists of the accumulation of dirt, dust and paint chips over the life of the plant. The quantity of debris in the penetrations identified is not a containment integrity concern. All penetrations examined were dry with no indication of water. The penetrations typically have a small access and pose difficulty cleaning. The dilemma fiom inside the drywell is the accessibility to the penetrations and the ALARA concerns. A work order request has been originated to dean the external sleeves of the drywell penetrations. During this time we will attempt to develop an acceptable process to perform this task. If an acceptable process can be developed for the extern1 sleeves we will investigate the possibility of cleaning the drywell internal sleeves on a case by case basis.

COhTUiWENT SEALS, GASKETS, AND MOISTURE BARRlElzs The entire drywell interior moisture barrier was inspected to the VT-3 criteria. This examination revealed cracked and peeling paint with arms.of corrosion on the base metal in the seal area. The paint was cracked in the bottom of this area for 360 degrees. This area has an ER and IDR written against it.

There was one rejected report for the drywell interior moisture barrier. This report was the original VT-3 examination of this area. IDR 99-012 was generated against this report for the engineering evaluation. This IDR was evaluated by MechanicaI Design Engineering and found to be adequate as is for structurd concerns. Paint coating and seal repairs should be pedomed at the earliest opportunity. Event Report 99-1594 was Written against this area, The disposition of this ER shall provide the details required to implement the repair. VYM 99/139 provides the details of this evaluation. It is the opinion of this author that the necessary repairs for this area should take place: during

RF022. The responsible department should be identified as early as possible as well as providing the necessary scope of work. The Project Engineering Responsible Engineer shall monitor the progress of this issue and provide regular reports to the Project Engineering Program Supervisor. This area shall be. evaluated for the applicability of Category E-C augmented examination prior to the revision of procedure PP7024.

No bolting was inspected for lWE for RF021. All bolting originally scheduled for RF021 will be review for the possibility of rescheduling to RF022.

SUMMARY

Although we did not complete all IWE first period examinations during RFO21, we did meet our original objective. That objective was to gather information regarding primary containment issues relating to the IWE program and to complete as many examinations as possible without impacting other outage work activities. An estimated 80% of IWE examinations are completed for the first period. The remaining 20% shall be rescheduled for RF022 for examination or reexamination. Some of the areas to be examined will require additional coordination due to cleaning requirements or accessibility requirements to complete the examinations.

There were four new IDRs generated, per DP4027, for containment issues during RF021. All of these issues were addressed by Mechanical Design Engineering prior to RF021 startup.

Please find attached to this report for reference the Summary of First Period IWE Examinations for RF021 and the maintenance 1999 Drywell Inspection Record. These reports provide detail for examinations completed and those required to be rescheduled for RF022 and a summary of the OW250 coating examinations.

1/23/1999

SUMMARY

OF FIRST PERIOD IWI XAMlNATIONSFOR RFO21 BAYS) ASME SECTION XI EXAM.CATEGORY E-A ASME IS1 REMARKS SECTiONXI IDENTIFICATION ITEM NO. NOlDESCRIPTION TO DATE Irbenal d a c e above water line compleed RFO 21 El.11 TORUS BAY I 94 % External surface except area fIom catwalk down to be& line compIeted Remaining area to be deaned and inspected afia S/U RF021 Nose: VT-I. completed below w a t a line RFW Irbbemal surface above water line complded BFO 21 E1.11 TORUS BAY 2 GV 94 Yo Exieand surface except area from catwalk down to belt lie completed.

Remaining areato be d e a d and inspeded after SKI RFo21

~

NCQe:VT-1 completed M o w wata lme RF020 lntaoalsurface above water h e completed RFO 21 E1.11 TORUS BAY 3 GV 94 Yo External surface except area &om catwalk down to belt line compleled Remaining area to be cleaned and inspected after SlIJ IC021 Ncte: VT-1 completed below water line RFO20 Intimal surfice above water line completed RFO 21 EL11 TORUS BAY 4 GV 94 vo External sud5ce except area fiom catwalk down to belt line completed.

Ranaiaing areato be deanedandinspeded afterS/URFO21 Note: VT-1 completedbelow water line RF-0 1

Intanal d a c e above water line coroplded RFO 21 El.ll TORUS BAY 5 94 Yo Extwal &ace except a m Grom catwalk down to belt line complete&

Gv Remaihgareato bedeaned andinspededafbSltTRF021 Note: VT-1 completedbelow wata line RF020 hitanal surface above water h e compldedRFO 21 TORUS BAY 6 GV 194% External surface except area h m adwafkdownto belt line compkkd.

EL11 Remaining area to be cleaned and mspeftedaftex S/U RFOZl N W VT-1 completed below water h e WOZO Intanal surface above wata line completed RFO 21 EI.11 TORUS BAY 7 GV 94 % Extemd surfaaz except area from catwalk down to belt line completed.

Remainingareat0 be cleaned and inspectedaftar S/U RFO21

_ I Nate: VT-1 completed Mow water line RF020 IosanaIsurface above water line completed RFO 21.

TORUS BAY 8 GV 94 Oh ExtemaI surfsce except area &om catwalk downto belt line completed El.ll Remaining- to b e d d and inspected a f b S/U RF021 Note: VT-1 wmpleted below water lme -0 Inteanal surfaceabove water line completed RFO 21 TORUS BAY 9 GV 94 Yo m a l srnface ex+ area from catwalk down to belt line completed EL11 Remammg area to be deaned and inspected after S l U RF021 Note: VT-1 com&ted below water line RF020 Intanalsurface above water line complezedRPO 21 TORUS BAY 10 GV 94 Yo External surface except area &om catwalk downto belt line completed.

EL11 Remaining area to be cleaned and inspected after Snr RFO21 Note VT-1 completed below water line W 0 2 0 Memat smfsce above water line completed E O 21 TORUS BAY 11 GV 94 % External snrface except area from catwalk down to belt line compIeted ELI1 R h h g atea to be dmed and inspected &e S/U RFOZI Note. VT-1 completedbelow w a k line RF020 El.11 1 TORUS i A Y 12 GV 94 %

Mema1s u r k e abovewater line completed RFO 21 E a 6slafa~ except area from catwalk down to bek Line completed.

Remaiaing areato be cleaned and inspected after SAJ RM21 NcQe: VT-1 completed below wster lineRFO20 hternal surfirce above water h e complaed RFO 21 TORUS BAY 13 GV 94 % External surfkce except area &om catwalk down to beIt line wmpleted El.ll Remainiig arm to be cleaned and inspectedd e r S/U RFO21 Nota VT-1completed bdow water lime WOZO brtenal surface above water lme completed RFO 21 EL11 TORUS BAY 14 GV 94 v b ExtemaJ. srtrface except area fiom catwalk down to belt line compl&ed.

Remaining area to be deaned and inspected after SIU RFO2l Nde: VT-I completedbelow water line RF020 Intam1 surface abovewater line completed RFO 21 TORUS BAY 15 J2xtemal suri3ce exapt area from catwalk down to belt line completd El.ll Remaining area to be cleaned and inspected after S/U RF021 I Nute: m-1completed bdow wata line RFOZO

1 El.11 1 TORUSBAY 16 GV 94 %

btanald a c e above water line completed RFO 21 E x t d d a c e except area Eom catwalk down to belt b Remaining mea to be cleaned and i n m after S/W -021 Note: VT-1 completed below water line RF020 ie completed n

ASME SECTI J XI EXAM. CATEGC Y: E-A EL11 VENT SYSTEM CrV 75% SURFACERFMl. THEVACUUMBREAKERXANESWERE BAY 2 COMPLETED FROM THE EXTERNAL SURFACE TO THE (VENTLINE PENETRATION 203 ELBOW THEN FROM THE INSlDE FROM THE ASSEMBLY, 203 PFlyETRATION TO THEELBOW VERTICAL WELD. TEIE VACUUM EXTERNAL SURFACE OFT HE VENT HEADER AND^^

BEAKER L N S , AND EXTERNAL SURFACES OF THE DOWNCOMERS WHERE ANDVENT COMPLETED RFO20.

HEADER M BAY 2 THE VENT HEADER TNTEHOR, VENT LINE EXTERIOR, AND AM)BAY 3) THE REMAINDER OF THE VACUUM LINE WILL BE SCHEDULED FOR RFO22.

El .20 vT3 THE VENT LINE WAS COMPLETED FROM THE INl73WAL 100% SURFACE RF021. THE VACUUM BREAKER LINES !WERE COMPLETED FROM THE EXTERNAL SURFACE TO THE PEhElXATIONZO3 ELBOW THEN FROM THE INSIDEFROM THE 203 PENMTRATION TO THE ELBOW VERTICAL WELD. THE lExTERNAcSURFAcEOFTHEVENTHEAIlERANDINTERNAL AM)EXTEN& DOWN COMER SURFACES WHERE COMPLETEDRFCYZO.

THE VEMT LINE WAS C O M P L E FROMTRE ~ INlZRN&

ELI1 VENT SYSTEM GV 75% SURFACE -021. TRE VACUUM BEAKER LIN3 WERE BAY 4 COMPLETEDFROMTHEEXTERNAL SURFACETOTHE (VENT= PENETRATION 203 ELBOW THEN FROM THE INSIDE FROM THE ASSEMBLY, 203 PENETRATION TO THE ELBOW VERTICAL WELD. THE VACUUM EXTERNALSURFACEOFTHEVENTHEADERANDINTERNAL BREAKERLINES, AND EXTERNAL SURFACES OF THE DOWNCOIWRS WHERE ANDVENT corn- RFOZO.

HEADER INBAY 4 THE VENT HEADER INTERIOR,VENT LINE EXTERIOR, AND AND BAY 5 ) THEREMAII\IDEROFTHEVAC~LINEwILLBESCHEDULED FOR RFO22.

THEVENTLINEWASCOh4PLETEDFEOMTHEINTERNAL EL20 YT3 100% SURFACE RF021. THE VACUUM BREAKERLINESWERE COMPLETEDFROMTHE EXTERNAL SURFACE TOTHE PENETRATION203 ELBOW THEN FROM TIE INSIDE FROM THE 203 PENf5TRATIONTO THE ELBOW VERTICAL WELD. THE EXTERNAL. SURFACE OF THE VENT HEADER AND INTERNAt AND EX'ERNAL SURFACES OF THE DOWNCOMERS WHERE COMPLETED RFOU).

THEVENTLINEWASCOMPLETEDFROMTHEINTERNAL VENT SYSTEM GV 75% SURFACE RYO21. THE VACUUM BREAKER LINES WERE BAY 6 COMPLETED FROM THE EXTEFWAL SURFACE TO "HE CVENTLN RENETRAnoN203 ELBOW THEN FROM THE INSIDE FROM THE ASSEMBLY. 203 PENETRATIONTO THE ELBOW VERTICAL WELD. THE VACUUM EXTERNALSURFACEOFTHEVENTHEADERANDINTERNAL BREAKER LINES, AND EXTERNAL SURFACES OF THE DOWNCOMERS WHERE AM, VENT corn- RF020.

HEADER IN BAY 6 THE VENT HEADER INJXRIOR, VENT LXNE EXTERKOR, AND AND BAY 7) THEREMAIMlElz OF THE VACUUM LINE WILL BE SCREDULED FOR RFO22.

THE VENT LINE WAS COMPUTED FROMTHE ETERNAL El.11 VENT SYSTEM GV 75% SURFACERFO21. THEVACUUMBREAKERLINES W E E BAY 8 COMPUTEDFROM THE EXTERNAL SURFACE TO THE (VENTLINE PENETRATION 203 ELBOW THEN FROM THE INSIDE FROM THE ASSEMBLY, 203 PENETRATIONTO THE ELBOW VERTICAL WELD. TRE VACUUM EXTERNAL.SURFACE OF THE VENT HEADER AM) INTERNAL BREAKERLINES, AND ExTEIENAI,SURFACES OF THE DOWNCOMERS WHERE.

ANDVENT COMPLETED RIFOZO.

HEADER INBAY 8 THE VENT HEADER INTEIUOR, VENT LINE EXTERIOR, AM3 AND BAY 9) THE REMAINDEROF THE VACWM LINE WIUBE SCHEDULED FOR RF022.

THEVENTLXNEWASCOMPLETEDFROMTHEINTERNAL El.ll VENT SYSTEM GV 75% SURFACE R302I. THE VACUUM BREAKER LZNES WERE BAY 10 COMPUTEDFROM THE EXTERNAL SURFACE TO THE CVENTLN PENETRATION 203 ELBOW THEN FROM THE INSIDE FROM THE ASSEMBLY, 203 PENETRATION TO THE ELBOW VERTICAL WELD. THE VACUUM EXTERNALSURFACE OF THE VENT HEADER AND INTERNAL BREAKERLINES, ANDEXTERNAL SURFACES OFTHEDOwNcoMmcS WHERE ANDVENT COMPLETED RFu20.

HEADER IN BAY THEVENT HEADER INTERIOR,VENT WNE EXTERIOR, AND 10 ANDBAY 11) THE REMAlNDER OF THE VACUUM LINE WILL BE SCHEDULED FOR RFO22.

THE VENT LINE WAS COMPLETED FROM THE INTERNAL El.11 VENT SYS'IEM GV 75% SURFACE RFO21. THE;VACUUM BREAKER LINES MRE BAY 12 COMPLETED FROM THE EXIEIUVAL SURFACE TO THE (VENTLINE PENETRATION203 ELBOW THEN FROM THE INSIDEFROM THE ASSEMBLY, 203 PENETRAnONTO THE ELBOW VERTICAL WELD. THE VACUUM EXTERNAL, SURFACE OFTHE VENT HEADER AND INTERNAL BREAKERLINES7 AND EXTERNAL SURFACES OF THE DOWNCOMERS WRERE ANDVENT COMPLETED RFOZO.

HEADER X N BAY THE VENT HEADER INTEFUOR, VENT LINE EXTERIOR.AND 12 AND BAY 13) THE RE-= OF THE VACWM LINE WILL BE SCHEDULED

~

FOR RF022.

THEVENTLINEWASCOMPLETEDFROMTHEINTERNAL EI.11 VENT SYSTEM GV SURFACE RFo21. TEE VACUUM BREAKER LMES WERE BAY 14 C0MPL.ETEDFROMTHEEXTERNALSURFACETOTHE m L m PEMETRATION203 ELBOW THEN FROM THE INSIDE FROM THE ASSEMBLY, 203 PENETR4TIONTO THE ELBOW VERTICAL WELD. THE VACWM ExTERNAtSURFACEOFTHEVENTHE;ADERANDINTERNAI, BREAKERLINES, AND JXEWAL.SURFACES OF THE D O W N ~ ~ W R ES R E ANDVENT COMPLETED RFOZO.

HEADER INBAY THE VENT HEADER INTERIOR,VENT LINE EX'ERlOR, AND 14 AM)BAY 15) THEREMAIMlER OF THE VACUUM LINE WILL BE SCHEDULED FOR RF022.

THEVENTLINEWASCOMPLETEDFROMTIAEINTERNAL El.11 VENT SYSTEM GV SURFACE FSO2l. TE VACWMBREAKERLINES WERE BAY 16 COh4PLETJW FROMTHE EXTERNAL SURFACE TO THE CiENTm PENETRATION 203 ELBOW THEN FROM THEINSIDE FROM THE ASSEMBLY, 203 PENETRATiON TO THE ELBOW VERTICAL. WELD. TRE VACUUM EXTERNALSURFACE OF THE VENT HEADER AND IN"ERNAL BREAKERLINES, AND EXTERNAL SURFACES OF THE DOWNCOMERS WHERE AND VENT COMPLETEDRF020.

KEADER IN BAY THEVJ%NTHEADERINTERIOR,VENTL.INEEXIERIO~AND 16ANDBAY 1) THERE~EROFTNEVACUUNIL~WILLBESCHEDULED FOR W022.

CONTAINME )NS) ASME SECTIONXI E X A U CATEGORY: E A EL11 Toms Pendration GV 100% COMPLETElNTERNALANDEXTERNAL X-200A & B El. 12 VT-3 100% COMPLETEFROM EXTERNALRF021 EL11 TorusPenetratiOn GV 50% COMPLETl?,FROMLNTERNALRIO21 X-201ATHRU H EXTERNAL. TO BE SCHEDULEDBEFORE OR DURING RFO22 El.11 To~usPpnehation GV 100% COMPLETE FROMINTERNU AND EXTERNAL RFO21 X-202ATHRU F

EL11 Torus Ppletration GV 100% COMPLETE FROM INTERNAL AM)EXTERNAL RFOZl X-202G THRU K f El.11 T o w Pendration GV 50% COMPLETE FROM INTERNALRFozl X-203A TIlRU F EXTERNALTO BE SCHEDULED BEFORE OR DURING RFO22 EL11 TorusPenerration GV 50% COMPLEI'E FROM INTERNALRFO21 X-203G THRU H FX'ERNAL TO BE SCHEDULED BEFORE OR DURING RF022 B1.11 TorusPeaetratim GV 100% COMPLE"EFROMlNTERNALANDEXTERNALRF021 X-205 A & D COMPLETED FROM lNW%!i?AL RFMI (s&C ARE BELOW EL11 TorusPeneet;ldion GV 75% WATER LINE FOR IN"ERN.4.L)

X-206A THRU D 3 & C COMPLETED FROM EXTERNAL RFO21 A & D EXTERNAL RESCHlEDuLE FOR RFOZ2 B & C COMPLETED FROM EXTERNAL RFO21 EL12 VT-3 50% A & D RESCHEDULE FOR W 0 2 2 EL11 Torus Penetration GV 100% OOMPLETE FROMEXTERNALRF02l (UNDERWATER)

X-206ETHRU F 1 E1.12 VT-3 100% COMPLETE FROMEXTERNALRF021 ELI1 TarusPene&atim GV 50% COMPLETEFROMEXTERNALRFOZX X-207A THRU H INERNAL TO BE RESCHEDuL;EI) FOR RFO22 EL11 Torus Paetrrdioa GV 100% COMPUTEFROMINTERN4.LANDEXTERNALRFO21 X-208A THRU D A&DCOMPLETEDFROMATERNALRF021(ggtcAREBELoW El.ll TorusPenetration GV 75% WATERLINEFORINTERNAL)

X-209A THRU D B & C COMPLE"E,D FROM EXTERNAL.W021 A&D RESCHEDULE FORRFO22 El.ll Toms P e n d m GV 100?40 COMPLETE FROM INTERNAL AND EXTERNALRFO21 X-21OA& B EI.11 Torus Penetrrdion GV 100% COMPLETEFROMMTERNALANDExTERNAtRFO21 X-211A & I3 El.ll Torus Penetration GV 100% COMPLETE FROMlNTERNAL ANDExTERNAt RFo21 x-212 El.ll TausPen&at.ion GV 100% COMPLETE FROMEXERNALRFO21 (UNDER WATER)

X-213A& B E1.12 VT-3 1o w 0 COMPLEIE FROMEXTERNALRFO21(UNDER WATER)

E1.11 Tarus Penetration GV 100% COMPLETE FROM R4IZRNAL AND EXTEXNALRFO21 X-214 El.ll TwusPendm GV 100% COMPLETE FROM INTl3RNAL AND EXTERNAL RF0221 X-215 El.ll TorusPenetration GV 100% COMPLETE FROM INTERNAL ANI)EXTERNAL RlW2l X-216 El.ll TorusPenetratiOn GV 100% COMPLETEFROMINTERNALANDEXTE~ALRFo21 X-2 17 EL11 TorusPenebatim GV 100% COMPI.ETEFROMINTERNALANDEXTERNALRFOZ1 X-218 EL11 Torus Pendratim GV 1ooY0 COMPlEF!ZFROMINTERNALANDEXTERNALRF021 X-219 E1.ll Twus Penetraiion GV 100% COMPLETE FROM INTERNAL A M )EXTERNAC RFO21 x-220

El.ll Torus PenetratiOn GV 1Wh COMPLETEFROM INTERNAL AND Ernma RFOzl x-221 El.ll Torus Penemtion GV 100% COMPLETEFROMrNTERNALANDEXTERNALRF021 x-222 El.ll Tarus Penetration GV 100% COMPETE FROMINTERNAL AND EXTERNAL S O 2 1 X-223 El. 11 TorusPenWon GV 100% COMPLETE FROMEXTERNGtRFO21 X-224A & B INSULAATIONPREVEWTIIW INSPECTION FROM EXTEIuIJAt, E1.12 VT-3 0% INTERNALUNDER WATER. NOT COMPLETE AT THIS TIME.

TOBERESCHEDULED. THIS WIUBERESCHEDULEDWHEN DlvERS ARE IN TORUS ALONG WITH THEUNDERWATER SURFACES. RESCHEDULET H I S ACTIVITY.

I El.11 TorusPenetrsrtion GV ' 1000? COMPLETE FROMEX"ERNAJ-.RFOZl(UNDER WATER)

X-225 E1.12 VT-3 100% COMPLJTTE FROMEXTERNaRFO21 (UNDERWATER)

El.ll , TorusPen&ration GV 100% COMPLETE FROMEXTERNALRF021(UNDERWATER)

X-226A & B EL12 VT-3 100% COMPLETEFROMEXTERNAI.WO21(UNDER WATER)

EL1 1 Tons Pen&ation GV 1Oooh COMPLETEFROMEXTERNALRFO21 (UNDER WATER)

X-227 EL12 VT-3 100% COMPLE'E FROMEXl73RNAL~OZI(UNDER WATER)

EL11 Torus Pen&atiw GV 100% COMPLETED FROMEXERIOR RFO21 (NOT ACCESSIBLE FROM X-228 INTIERXOR)

El.ll Torus Penetratioa OV 100% COMPLETED FROMEXTERIORRFOZl(NOT ACCESSIBLE FROM x-229 INTERIOR)

EL11 Torus Penetration GV 100% COMPLETED FROMEXTERIORRF021 x-230 A,C,E, &G COMPLETED FROM INTERIOR -1 (B,D,F &H ARE EL11 T o w Pen&&ion QV 80% UNDER WATERFROMIIWEIWAL)

X-231 A-H B,D,F,G & H COMPLETED FROMEXlEF?NALRFO21 RESCHESDULE A,C, 8t E FOR RF022 I

d SURFACES) ASME SECTION XI EXAM. CATEGORY: E-A El.11 Drywdlevatiw GV 100% CO-D FROMlNIERNALRFOZl 238to e l d o n 251 EXTERNAL INACCESSIBLEBY DESIGN quadrant 0 to 90 EL12 VT-3 100% COMP~DFROMlNTERNALRFO21 E;(cTERNAL INACCESSIBLEBY DESIGN Drywell elevation GV 100% COMPLETED FROM INTE,RNALlZFOZl 238 to e l d m 251 EXTERNALINACCFSSIBLE BY DESIGN quadrant90to 180 EL12 VT-3 1W/o COMPWTED FROMINTEFWAL RF021 I EXTERNALINACCESSIBLE BY DESIGN El.ll DryweU devation GV lW? COh4PL.ETED FROM INTERNAL RF02 1 238to elevation251 EXTERNAI,INACCESSIBLE BY DESIGN B1.12 EL11 180to 270 Drywen elevation 238toelevation251 quadrant 270 to 360 VT-3 GV 1QO%

100%

COMPLEXED FROMIN'ERNNALRFOZl EXERNAL INACCESSIBLEBY DESIGN COMPLETED FROMINTERNALRFOZ1 EXTERNALINACCESSIBLEBY DESIGN dw-I I

EL12 El.11 El.12


t--

~ryweue~evation 251 to elevation 269 quadrant 0to 90 degrees 1 1ooo/a 100%

lW?

COh4PLETED FROM INTERNALRFO2l EXTERNAL INACCESSIBLEBY DESIGN COMPWED FROM INTERNAL-021 EXTEKNALINACCESSIBLEBY DESIGN COMPLETED FROM INTERNAL RF021 EXTERNfi INACCESSIBLEBY DESIGN El.11 1

25 1 to elevation 269 EL11 1M)% COMPLElEDFROMINTERNALRFO21 EXTERNALINACCESSIBLE BY DESIGN E1.11 loOO? COMPLETEL) FROM INTERNALRFO2l EXlXRNAL. INACCESSIBLEBY DESIGN El.ll COMPLETED FROM INTERNALRFO21 JXIERNAT., INACCESSIBLEBY DESIGN I

EL11 COMPLETED PROMINTERNALW02L EXIXRNAL INACCESSIBLEBY DESIGN EL11 COMPLETED FROMINTERNAL RF021 EXTERNAL INACCESSIBE BY DESIGN El.ll lao% COMPLETEDFROMINTERNALRFo2i m R N A L DIACCESSIBLIEBY DESIGN El.ll COMPLETED WOZl El.ll COh4PLEIED NO21 I

CONTAINMENTSURFACES (DRYWELL PENETRAnrONS) I I 1 I 1ooOh COMPLETED@TERNALANDEXTERNALRIF021 x-i PORTIONS OF THEEXTERNAL AREA ARE INACCESSIBLE FROM DIRECT VISUALEXAMINATION BY DESIGN E1.11 DrywellPenetraticm GV 100% COMPLETED INTERNAL AND EXlWX4.L RF021 x-2 PORTIONS OF THE EXTERNAL AREA ARE INACCESS-FROM DIRECT VISUALEXAMMATION BY DESIGN EI.11 DrywellPenetratim GV 100% COMPLGTED INTERNAL AND EXTERNAL RF021 I x-4 I I EL11 I Drywenpenetration X-SATHRU X-5H I GV I500/0 I WMPL&'IEDINTERNAL RF021 EXTERNAL TO BE COMPLETED BEFORE OR DURING PO22

I E1.12 VT-3 COh4PIETEDFROM THE JNERNAL. SURFACE RFO21 E1.11 DrywellPenetration GV 50% COMPUTED FROMINTERIOR RFO21 Xd RESCHEDULEEXTERiOR BEFORE OR DURING RF022 EL12 VT-3 0% RESCHEDULE BEFORE OR DURING RFO22 El.11 DrywellPenetrrdion GV 50% COMP~TEDFROMINTERNALRF021 X-7A EXTERNAL TO BE SCHEDULED BEFORE OR DURING RF022 RESCHEDULEFORSO22 50% COMPtETED FROM INTERNALRFO21 EXTERNAL TO BE SCWEDULEDBEFORE OR DURING RF022 ELI2 RESCHEDLkE FOR RF022 EL11 x-7c El.11 DrywellPcnetratioO GV 50% COMPLa?TEDFROM INTERNAL RFOZl x-m EXTERNAC TO BE SCHEDULEDBEFOIU?OR DUIUNG RFo22 E1.12 VT-3 0% RESCHEDULE FOR RF022 EL11 DxywellPenehation GV SO% COMPLETEDFROMINERNALRF021 X-8 E1.12 VT-3 100% COMPLETED FROM INTERNAL RFO2l EL11 DrywellPeoetration GV 50% COMPLETED FROM INTERNALRF021 X-9A EXTJ5RNALTO BE SCHEDULED BEFORE OR DG - RF022 E1.12 VT-3 0% RESCHEDULE FOR RFO22 El.11 DryweItPenetrzticm GV 500/0 COMPETED FROM INTERNAL.RFMl X-9B EXTERNALTO BE SCFEDULED BEFORE OR DURING R.FOZ2 E1.12 VT-3 0% RESCHEDULE FOR RF022 El.ll DryweUPene&ation GV 0% RESCHEDULE FOR RFO22 x-10 El.ll DrywdlP+x~dion GV x-11 I El.ll DrywellPenetnrtion GV 50% COMPWIZD FROMINTERNALRF021 (INACCESSIBLE AREA x-12 mw1FIED)

EXTERNAL TO BE SCHEDULED BEFORE OR DURING RFO22 E1.ll 50% COMPLETED FROM INTERNAL RFOZl X-13A EXTERNALTO BE SCHEDULEDBEFORE OR DURING RFO22 EL11 50% COMPLETED FROMINTERNALRF021 X-13B ElLTERNAtToBE SCHEDULED BEFORE OR DURING RF022 EL11 DqwellPdon GV 0% THISPENETRATION IS NOT ACCESSIBLE WITHOUT X-14 SIGNEXCANT EFFORT TO ACCESS. STAGING WOULD HAVE TO BE BUILT. I AM LOOKING AT CLASSIFYING TlIS AS INACCESSIBLE FROM INSIDE. THE EXTERIOR INSPECTION WILL DETERMIBE HOW WE HAVE; TO DEAL WITH THIS PEN.

REVIEW FORRFOZ2 EL11 DrywellPen&ation GV 0% RESCHEDULE FOR RF022 X-15

I El.ll Drywell Pmetratiw GV 0% THIS PENETRATXONISNOT ACCESSIBLE WITHOUT X-16A SIGNIFICANTEFFORT TO ACCESS. STAGING WOULD HAVE TO BE BUILT. THE PEN ALSO HAS INSULATION CONFIGURATION RESTRlCTIONS AND DESIGN RESTRICTIONS. I AM LOOKING AT CLASSIFYING THIS AS WACCESSIBLE FROM INSIDE. TEE EXEMOR INSPECTION WILL DETE- HOW WE HAVE TO DEAL WITH THIS PEN.

REVIEW FOR RF022 El.11 Drywell Penetration GV 0% THIS PENETRATION IS NOT ACCESSIBLE WITHOUT X-16B SIGMFICANTEFFORT TO ACCESS. STAGING WOULD HAVE TO BE BUILT. THlS PEN ALSO HAS INSULATIONCONFIGURATION RESTRICTIONS AND DESIGN RESTRICTIONS. I AM LOOKING AT CLASSIFYINGTHIS AS INACCESSIBLE FROM INSIDE.THE EXTERIOR INSPECTION WIW, DETERMINE HOW WE HAVE TO DEAL WlTH THIS PEN.

REVEWFORRFO22 El.ll GV 50°% COMPLETEDFROM INTERNAL RF021 EXTERNAL TO BE SCHEDULEDBEFORE OR DURING RF022 E1.11 GV 50% COMPLETED FROMXNTERNALRFCnl EXTERNAL TO BE SCHEDULED BEFORE OR DURING RF022 EL12 VT-3 0% RESCHEDULE FOR RFO22 EL11 Dryweu Pcnetretion GV 50% COh4PLETEDFROM~ALRFO21 x-19 EXTERNAL TO BE SCHEDULED BEFORE OR DURING RFO22 EL12 VT-3 REscHlEDuLEFORM022 EL11 Drywell Penetration GV 50% COMPLETED FROM WTIERNAz.RFOZI x-20 EXTERNAL TO BE SCHEDULED BEFORE OR DURING RF022 ELI2 VT-3 EL11 Drywell PmiratiOn GV 50% COWLETED FROMINTERNALRFOZI x-2 1 EXTERNALTO BE SCHEDULEDBEFORE OR DURING RFO22 E1.12 VT-3 o?? RESCHEDULE FORRFO22 El.11 Drywell Penekatim GV 50% COMPLETED FROM DJTJ5RNA.L RFml x-22 EXIERNAL TO BE SCHJ3DULED BEFORE OR DURING RFW E1.12 VT-3 0% RESC-W FOR RF022 El.ll Drywell Peniratim GV OYO REscfxEDuLE FOR RF022 X-23 E1.12 VT-3 0% RESCHEDm FOR a 0 2 2 EL11 DrywelIPeaetration GV Do? RESCHEDULE FOR RF022 X-24 ELI2 VT-3 0% RESCHEDULE FOR W022 EL11 Pmetrsdigl GV 5076 COMPLETED FROMINTERNAL RFOZl X-25 EXTERNAL TO BE SCHEDULEDBEFOE OR DURING RFO22 El.ll Drywell Penetration GV 50% COMPLETED FROM INTERNAL RFOZl X-26 E M - . TO BE SCHEDULEDBEFORE OR DURING RF022 El.12 VT-3 1oOoh COMPI.liXED FROMINTERNALRF021 EL11 DlyWellPeaehation GV 50?? COh4PLETEDFROMINTERNALRFOZl X-27 EXTERNAL TO BE SCHEDULED BEFORE OR DURING RFm2 E1.12 VT-3 0% RESCHEDULE FOR W 0 2 2

I 1 I I EL11 ByweUPen&rat.im GV 50% COMPLETED FROMINTERNALRF021 X-28 EXTERNALTO BE SCHEDULED BEFORE OR DURING RFO22 El.11 DrywellPenetmtion GV 0% liEsCHEDuLE FORRFOZ!

x-29 El.ll DrywellPenetration GV SOYO COMPLETED F'ROMINTERNALRFOZl X-30 EXTERNAL To BE SCmDULED BEFORE OR DURING RFO22 E1.12 VT-3 100% COMPLETEDFROMINTERNAIRFO21 El.ll 1 ~ e . l l P e n e t d o n GV 50% COMPLETED FROMINTERNAtRFOZl EXTERNAL'IQ BE SCHEDULEDBEFORE OR DURING RF022 EL12 VT-3 100% COMPLETED FROM INTERNAL RFO2l EL11 DrywellPeatkation GV 50% COMPLETED FROMXNTEXNaRF021 X-32 EXTERNALTOBE SCNEDuI;EI> BEFORE OR DURING RMn2 EL12 VT-3 100% COMP@TED FROMINTERh'ALRF021 EL11 DrywellPenettatiOn GV 50% C O M P m D FROMXhTERNALRFO!Zl x-33 ~ A L BEFORE OR DURING E 0 2 2

~ TO BE SCHEDULED El.ll D~~~ollPenetraaioa G V ovo RESCFIEDULEFOR RFO22 x-34 EL12 VT-3 Ooh RESCHEDULEFOR RFOZZ El.ll hywdPeaetratiar GV 50% COMPLETED FROM INTERNALRF021 X-35A EXTERNAL TO BE SCHEDULED BEFORE OR DURMO R R X Z E1.12 VT-3 100% COMPL;ETEDFROMINTEWALRFOZl EL11 DrywdPenetratioo GV 50% COMF'LETED FROMINTERNALRFOZl X-35B EXTERNALTO BE SCHEDULEI) BEFORE OR DURING WO22 E1.12 VT-3 1OO?! COMPLEED FROM INTERNAL RFO21 ELI1 DryweuPaetmtion GV 5Ooh COM?L.!ZTEDFROMINTERNALRFO!Zl x-35c EXTERNALTOBE SCHEDULEDBEFORE OR DURING RFO22 E1.12 VT-3 100% COMPLETED FROM INTERNALRF021 El.ll DryWellPenetrati~n GV 500A COMPUETED FROM INTERNALRFO21 X-35D EXTERNAL TO BE SCHEDULEDBEFOF33 OR DURING RFOZP 1

E1.12 VT-3 100% COMPLETEDFROM TNTERNALRFMl El.11 DryweItPenWon GV 50?h COMP~FROM~RNALRF021 X-3 5E EXTERNALTO BE SCHEDULED BEFORE ORDURINGRFO22 E1.12 VT-3 100% COMF'LE~DFROMINTERNALWO21 EL11 DrywellPeaetration GV ' 50% MIMPEEDFROMINTERNAtRM3al X-36 EXTERNALTO BE SCHEDULED BEFORE OR DURING E 0 2 2 El.11 DrywellPenetration GV 50% COMPLETEDFROM lNTERNALRFO21 X-37A EXTERNAL TO BE SCHEDULED BEFORE OR DURING RFO22 EL11 IhyweUPenetratiOn GV 50% CQMPGTED FROMPJTERNALRF021 x-3% EXTERNALTO BE SCHEDULED BEFORE OR DURING RF022 El.ll IxywdPm&ation GV 50% coMpLEl33D FFtOMrmTERNALRFo21 x-37c EXTERNAL. TO BE SCHEDULEI)BEPORE OR DURING RFOZ2 El.11 DrywellPenetmtion GV 50% W M P W FROM INTERNAL RFO21 x-37D EXERNAL TO BE SCHEDUWED BEFORE OR DURING RFO22

DrywellPealetration GV 50% coMpLElEDFROMINTE~ALRFOZ1 X-38A EXTERNAL TO BE SCHEDULED BEFORE OR DURING W022 Drywell P ~ e t r a t i ~ m GV 50% COMPLETED F R O M I m E R N ~ R F 0 2 1 X-38B EXI'ERNAL TO BE SCHEDULED BEFORE OR D m RF022 El.11 Drywell P e n d m GV 50% COMPLETED FROM INTERNALRFozl X-38C EXTERNAL TO BE SCHEDULEDBEFORE OR DURING RED22 EL11 Drywell PeaQration GV 50% COMPLETED FROM TNTERNAL W 0 2 1 X-38D EXERNAL TO BE SCHEDULED BEFORE OR IlURINGRF022 E1.11 Drywell Penetratian GV 50% C O M p um FROM INTERNALRFOn X-39A EXTERNAL TO BE SCHEDULED BEFORE OR DURING E 0 2 2 EL11 Drywell Penaetration GV 50% COMPLETED FROMINTERNALRF021 x-39B FXERNAL TO BE SCHEDULED BEFOE OR DURING RFO22 ELI1 DIyWdl Penetratioo GV 50% COMPLJXEDFROMEVERNAL E O 2 1 X-40A EXTERNALTO BE SCHliDULED BEFOW OR DURING RF022 El.11 Drywell Pepetrrdion GV 50% COMPLETED FROM INTERNAL RF021 X-4OB EXTERNALTO BE SCHEDULED BEFORE OR DURING WO22 El.ll Drywell Penetratioa GV 50% COMPLETED FROMTNTERNALRFotl x4c EXTERNAL TO BE SCHEDULEDBEFORE OR DURING -2 El.11 Drywell Penemtion GV 50% COMPLETED FROMINTERNALRF021 X4D EXTERNAL TO BE S C H E D W BEFORE OR DURIh'G RFO2Z EL11 DrvFpell Pulc3mtim GV 0% RESCHEDULE FOR -022 X-41 El.ll Drywell Penehtioa GV 50% COA4PLETED FROMIh'TERNALRFOZl X42 33XIERNAL TO BE SCHEDUIXD BEFORE OR DURING RFo22 EL11 Drywell Penetration GV 50% COMPLETEDFROMW~ALRF021 x-43 EXTERNAL TO BE S C - W BEFORE OR DuIuNGRF022 El.11 DrywellPenetratiOo GV 50% COMPETED FROM INTBRNALRF021 X-44 EXTERNAL TO BE SCHEDULED BEFORE OR DURING RFOZZ ELI1 Dqweu Peoerratian GV 50% COMPLETEDFROM~AJ..RFOZ1 x45 EXl'EFWAL TO BE SCHEDULED BEFORe OR DURING WOZ2 El.11 GV 500h COMPLETED FROMINTERNAL. RFo21 E)tTERNALTO BE SCHEDULED BEFORE OR DURING RF022 ELI1 Drywen Penettasion GV 0% RESCHEDULEFOR RF022 x47 El.ll Drywell P a l w o n GV 50% COMPLETEDFROMKNTERNALRFo21 X48 FXTERNALTO BE SCHEDULED BEFORE OR DURING RFo22 E1.12 VT-3 0% RESCHEDULE FOR RF022 El.11 Drywell Penetdcn GV 50% COMPLETEDFROM INTERNAL. W021 x49 EXTERNAL TO BE SCHEDUIXD BEFOREOR DURING RF-2 EL11 Drywell Penetratim CrV 50% COMPLETEDFROM~RNALRF02I X-50 EXTERNAL TO BE SCHEDULED BEFOIZE OR DURING WO22 EL11 DryWellPenetration GV 50% COMP~TED FROMINTERNALRF021 X-51 EXTERNAL TO BE SCHEDULEDBEFORE OR DURING RFOZ2 El.ll Drywell Pmetrrdirm GV 50% COMPLETED FROM INTERNAtRFm1 X-52 EXTERNAL TO BE SCHEDULED =FORE OR DURJNG RF022

9 El.11 DrywelI Panetration GV 50% COMPLETED FROMINTERNALRFO21 (INACCESSIBLE AREA X-1 DOA IDENTIFED)

EXERNAL TO BE SCHEDUL;ED BEFORE OR DURING RF022 El.11 Drywelt Penetration GV 50% COMPLETED FROM INTERNAL RF021 (INACCESSIBLE AREA X-1 DOB IDENTIFID')

EXTERNALi.0 BE SCHEDULED BEFOREOR DURING R F ~ Z EL11 iorywell Penetratioa GV 50% COMPLETED FROMINTERNALRFo21 (INACCEWLBI3 AREA X-ZOOC IDENTIFIED)

EXTERNAL TO BE SCHEDULGD BEFORE OR DURING S O 2 2 El.ll GV 50% COMPLETED FR0MINTERhM.L RF02X (INACCESSIBLEAREA IDEN'IIFIED)

~

EXTERNALTO BE SCHEDULED BEFORE OR DURlNG RFO22 El.ll Drywell Penetration GV 50% COMPLETED FROM INTJZNa RFOZl WACCESSIBLE AREA X-101A IDENTIFIED)

EXTERNAL To BE SCHEDULED BEFORE OR DURMG RFO22 EL11 DIywell PenetdGn GV 50% COMPIEIED FlROMINTERNALRF021 (INACCESSIBLEAREA X-lO1B IDENTIFIED)

EX'IERNm TO BE SCHEDULED BEFORE OR DURING RFO22 EL11 Drywell Pgleaatim GV 50% COMPLETED F!LOM INTERNALRF022 (lNACCESSIBLE AREA x-101c m1-EXTERNALTO BE SCHEDULED BEFORE OR DURING RFO22 El.ll GV 5OQh COMPLETED FROM INTERNAL.RFO21 (INACCESSIBLE AREA IDENTIFIED)

EXTERNALTO BE SCIEDUJ3D BEFORE OR DURING S a 2 EL11 Dryweu Pmdration GV 50% COMPLETED FROMINTERNALRF021 (INACCESSII3LEAREA x-102 1D-D)

F,XTERNAL, TO BE SCHEDULED BEFORE OR DURING RFo22 El.ll Drywen Pmehtiul GV 50% COMPLETED FROMINTERNALW021 (DIACCCESSIBLE AREA X-103 IDENTXFED)

EXTERNALTOBESCHEDUKED BEFORE ORDURINGRFOZ2 EL11 DrywellPenetratian GV 500h COMPLETED FROM ENTERNAL.RFOZl (INACCESSIBLEAREA X-104A D 1 EXTERNALTO BE SCHEDULED BEFORE OR D W G RFOZ2 El.ll Drywell Penetratim GV 90% CONlpLETED FROM INTERNAL RXO21 (INACCESSIBLE AREA X-1 W B I D r n D )

EXTERNAJ.,TOBE SCHEDUJXDBEFORE OR DURINGWOZZ El.ll GV 50% COMPUTED FROM W R N A L RFozl (XNACCESmW AREA IDENTIFIED)

EXTERNAL TO BE SCHEDULED BEFORE OR DURJNG W 0 2 2 EL11 Drywell Penetration GV COMPUXED FROMm'"ERNALRFO21 (INACCESSIBLEAREA X-105A IDENTIFED)

EXTERNALTO BE SCHEDULED BEFORE ORDURING RFO22 EL11 m a ll Pm&Lation GV COMPLETED FROM INTERNAL RF(n1 (INACCESSBLE AREA X-105B m1-EXTERNAL TO BE SCHEDULED BEFORE OR DUEUNG W022 EL11 Drywen Penetration GV COMPLETED FROM INTERNAL WO21 (INACCESSIBLEAREA X-10.5'2 IDENTIFED)

EXTERNALTOBESCHEDULEDBEFOREORDURINGGRFo22 El.ll Drywell P a r e a n GV COMPLETED FROMTNTERNAt RFO21 (INACCESSlBLE AREA X-105D DDENTIFIED)

EXTERNALTO BE SCHEDULED BEFORE OR DURING RF022

El.11 DrywelIPenetrrdjoo GV 50% COh@mFRoMmRNAL,RFo21 X-106 EXTERNALTO 3E SCHEDULED BEFORE OR DURING RFM2 EL11 DrywellPenetmtion GV 504? COMPLETED FROM INTERNALRFOZI X-107 EX'ERNG I DBE SCHEDULEDBEFORE OR DURING RFO22 ASME ISI Exam % REMARKS SECTIONXI IDENTIFICATION m MP LBTE lTEM NO. NOJDESCRKPTKON TO DATE DRY WELL E530 INTERIOR VT-3 1OOoh INSPECTION COMPLETED RFOZ1 MOISTURE DISCREPANCIES WERE IDENTIFIED AND DISPOSITION FOR BARRIER THIS ITEM IS WlTH MECHANICAL DESIGN E N G m R I N G CONTAINMEWTPRESSURE RETAINING BOLTING ASME SECTIONXI EXAM. CATEGORY E-G

~

ASME Is1 SECTION XI IDENTIFICATION I E M NO. NOJDES~ON E8.10 TORUS W A Y o??

FLANGfi BOLTING PENETRATION 200A E8.10 TORUS MAMVAY o?? RESCHEDULE FOR RFO22 FLm~BOLTMo PENETRATION 200B E8.10 NEUTRON RESCHEDULJ3FORWO22 MO~ORING SYSTEM PEMETRAnoN 35A E8.10 NEUTRON 0%

MONITORKNG SYSTEM PENETRATION 35B E8.10 NEUTRON 0% lU3SCREDUL.EFOR RFO22 MONITORING SYSIXM PENETRATION 35c B.10 NEUTRON 0% RESCHEDULE FOR RFo22 MONITORING SYSTEM PENETRATION (SPARE) 35D E8.10 NEUTRON RESCI-EDULEFOR RF022 MONITORING SYSTEM PENETRATION 35E

Vermont Yankee Visual Examination Report Form Work Order No.: on -5037 VT-1, Containment Surfaces (m)

Page. / of Date: e5-/-CJ/

Component Method Photo Sketch Intermediate &/#

/ .---

&/A IDirect None None Intermediate e# .,

u/A EvaIuation Required?

~ ~ f i oe s VYNEP 8045.02 NE 8045 Rev. 1 Page 1 of 1

Instrument Instrument Make: ?G fi7n ~mr?+r.iL5 Instrument Model: 26 DL Ph3 Instrument SIN: .9,3 293a7 Instrument Dfsplay: CRT ( ) Digital (d Horitonta! Linearity Performed?: Yes ( ) No (/

Calibration Block Serial Number: >/c / - f . -2 Callbration Block Materiak c/c Product Form: Wrn ,,,$+

Block Temperature: 73- OF Thicknesses: -

,360 5.001 ,

M&TE Used?: Yes ( } No (4 M&TE Description [SIN: h!/h Calibration Times Initial Calibration: O%UO Check: 13 OQ Check <@

I Check: N//# Check: /?h Final: 16 3O Sketch and Examination Results:

Data Sheet No.: $US3 -0/-06$/

Procedure No/Rev. N E ~ 0 5 . 3REV +PC *A Page I of .A o a t e :

  • 5 @ 1 Workorder Number. ~-0654,?7-000 Thickness Calibration Data Sheet Drawing NumberlRev.: 6 2 02-2 EEv 0 Plant Location: DfZY UELL 2 3 2 ' e l . d Material: 6ON S T E E L Product Form: trl E O U6 F( 7 Nominal Thickness: 1.O " # 2 , s "

~~

Instrument Instrument Make: PANA M R1<1L's Instrument Model: 2 6 0 L P L 5 Instrument S/N: 9 3 1 2 9387 Instrument Display: CRT ( ) Digitat (4 Horizontal Linearity Performed?: Yes ( } No (v E/C i - F Calibration Block Serial Number: E/C 1-2 Calibration Blodc Material: CAR 8pA S?EC I Product Form: W U 6ti7 Block Temperature: 75 OF mim~sss: o ~ u d 'oI099",

, ima, z.oool~,z s a z ' n , 3,601 M & E Used?: Yes ( ) No (4 M&TEDescription /S/N:

Calibration Times Initial Calibration: 0000 Check: d/A Check: NIA Check: Check: Final: 1OS4 Sketch and Examination Results: E A E  ;

Evaluation Required:

Examiner.. Y MdfK E h?dLJA Level: Date: S- 9-01 t Level: EL Date:$/!/U/ Yes (4 No { )

Reviewer: Date: s'.i~* 0I t Form Number:

I Page t of 1 ANII: . Date: K-fY-! NE 8053 Original LPC#I -

Experience Hours Credit:

c 3

Visual Examination Report Form Work Order No.: 00 .e 37 VT-1, Containment Surfaces @WE)

Procedure No/Rev.: /vE 80 y 5 ,&Ev-1

. Page / of 6 Date: 5 0 /

Cornnonent

racks/L,inears

'hysical Damage

orrosion irosion 3ouges Near Evaluation Required?

VYNEF 8045.02 NE 8045 Rev. I c Page 1 of 1

Vermont Yankee VYNEF. 8045.04 NE 8045 Original Page 1 of 1 LPC # I

Vermont Yankee uaminer: Level: ~4 Date: 4

viewer: Date:

Y

viewer: Nh Date: dh NII: A # Date: e-//-@/

VYNEF 8045.04 NE 8045 Original Page 'I of 1 LPC #I

clu

.d

9 EVALUA?3ON 0.F DATA PROWED BY VT-1, CONTATNMENT SURFACES (rwE)

DATA SHEET No: 804541-019 During RFO 21 TWE examitTatioflsit was discovered that the Joint SeaI at the concrete to steel interfice on the 238 level ofthe containment had failed and there was evidence of corrosion in areas of the seal. As a resalt a portion of the circnmferenceof the seal interface area was declared as augmented. ?he joht seal itself was also scheduled for replacement duringRFO-22.

At the start ofW0-22 the examinersperformed;he reqniredVT-1 examinations of the augmented area at thejoint Seat to detemine ifany changes bad o c c u ~ r e dduring the last operating cycle. The results afthat examinationreveal no changes identifiedin the augmented a n a After the VT-1 examinatomwere cornprete the ptocess began for the joint seal replacement. A band of paint was removed h m the concrete floor up the steel contabment approximately6 wide for the full circumference. The recessed area for the joint seaI was aIs0 cleanedin preparation for the new seal installation. At this point a VT-3 examinationswas performed which identifieda band of pitting that covered much ofthe 3600-Begree circumference. A more detailed VT-1 was ordered by the Responsiie Engineer to detail this area prior to pamt/seaI instdlation.

Thisjoint seal area was identSed as an issue inthe early 1990s. (ER-99-1594deals with the issues from the 1990s resolution). In 1993 the joint seal area was cleaned and painted so as to form a paint joint seal at the mncfete to seal interface. The 2t~easidentifiedduring the RFO-21 examinations were areas that were experiencing evidence of corrosion and paint loss in this pdinteajointarea Some of the paint was still intad and providing adequate protection for the steel it was covering.

The new areas of pitting in the area of the joint seal are as a result of the coating removal to white metal in this area. This atea was not previously identified during RFU-21 because it was an old area of pitting that hadbeencoveredbythe1993 ~ g a n d h a d n o t e ~ ~ c e d a n y ~ e r d Asaresultofthe e~tim coatings being completely removed h m thisjoint area, this VT-1 examination was able to map this region without the impedance of any obmructioa The areas of pitting are isolated to the general area of the joint seal &&ace between the concrete and the steel. The pitting subsides as it move up or down out of thejointseal area. This was evident when a portion ofthe steel smfitce was exposed as a result of the removal of a concrete chip. The under slnface area exposed was approximately 9 wide and 3 deep in a crescent shape. The worst case pitting is isolated to a band in the joint seal areafromapproximately % wick to approximately 1 wide and is clescrii in the report as areas with general wastage and connected pitting All corrosion identifiedwithin this report is bounded by evaluation VYM 99/139.Based on this evaluation all aeas are well within the requmd design base metal t h i c a e s aed are acceptable for continued operation as is.

e phcmell Rewmiblle Engineer May 11,2001

Work Order NO.:^ 00.5037-004 w

Vermont Yankee IPC Procedure NolRev.:&'FS??P7 4b. R Visual Examination Report Form for VT-3 Moisture Barriers, Gaskets and Seals (!WE) Page 1 of 1 Date: ~ - l ~ -

1

~~

Vituat Aids Illumination Level Check Photo/Sketch Other (Describe]:

Evaluation Required?

Yes I No W N E F 8047.08 NE 8047 Original Page 1 of 1

Data Sheet No: 2?H Work Order No.: 60 -0Os037-Vermont Yankee Visual Examination Report Form for VT-3 Procedure NolRev.: AEpdy7&. 0 Other (Describe):

.&*5-%0/

Evaluation Level Date -.fey-#/ Required?

ayes Level rJh Date

@NO Date 3yt4b/ SLC Reviewer: Nh Date 4~

Date

-&:S W N E F 8047.07 NE 8047 Original Page 1 of 'I

Visual Examination Report Form for General Visual (IWE) page / of 1 Date: /?//6./00 Component Y

Examiner: Level Date VYNEF 8047.06 N E 8047 Original Page 1 of 1

VYNEF 8047.06 NE 8047 Original Page 1 of 1

I Work Order No.: 00 0 50 35 Vermont Yankee Procedure NolRev.: d E 90 7/0&:9+&..

Visual Examination Report Form for General Visual (IWE) Page I cf Date: / S / / l ; . / O Q 9 t Component Visual Aids Photo Sketch Method 0 Binoculars "bne IZHJone 6 e c t Q Mirror

-0 Attached 10 Attached 1 u Remote

&ght Source Examination location 0escriptj.on~Remarks Remote Examination ConditionslEquipment Remarks 0 6" Scale &&id&d IS f i Gitaj~Ik

~

f ..

I Examiner:

Reviewer:

Level Date Date Reviewer:

- Date /uh?/ZL ANII: Date to-t?d i

VYNEF 8047.b6 NE 8047 Originat Page 1 of 7

t Data Sheet No: m6-Vermont Yankee Work Order No.: . 00 - 0 SO 35 Procedure NoiRev.: go 7/on;9..'pc Visual Examination Report Form for General Visual (IWE) Page / of 1 Date: /#//6/00 -1 Component 3rawing NolRev.: a&4z

  • 473 Location:

Visuat Aids 1 Photo I Sketch I Method 3 Binoculars @%one mane d e c t 3 Mirror D Attached 0 Attached Remote k g h t Source Examination Location OescriptionlRemarks Remote Examination Conditions/Equipmcnt Remarks 0 6" Scale k%W;dqS;d is E&MClfr3~lk do& f~ lsCt+X;d,~04 &/A Examiner: Level Date Reviewe r : .Date VYNEF 8047.06 NE 8047 Original Page 1 of 1

r Data Sheet No: T d 6 - & - 3 <7 Vermont Yankee Visual Examination Report Form for Genera! Visual (IWE) v Visual Aids Photo Skerch Method 3 Binoculars d & I * &ne Bz6jrect tl Mirror d g h t Source Examination Location Description/Remarks Remote Exbmination ConditionslEquipment Remarks 0 6" Scale &jr+ut+w -% Z4L 0 c N/ A Examination Results, Details and Comments:

Examiner: Level Date Reviewer: Date Date $/?&

/

Date i 0 -pd I

VYNEF 8047.06 NE 8047 Oilginat Page 1 of 7

Vermont Yankee Procedure NolRev.: 8b f7/6&i~kd Visual Examination Report Form for General Visual {!WE) Page f of / Date: /O/J&/dO .I U

Visual Aids Photo Sketch Method El Binoculars UiTone GYIGne d r e c t 0 Mirror 0 Attached 0 Attached 0 Remote d g h t Source Examination Location DescriptionlRemarks Remote Exemination ConditionslEquiprnenr Remarks 4

Ci 6" Scale 0 Other .

&#%L,\LIT P LA C k 6&

dun?%

J x 8

231 A&, +E j vi, Examiner: Level Date Reviewer: Date Date /i&/a Date /D-("?d V

M N E F 8047 .Q 6 NE 8047 Original Page 1 of 1

t Data Sheet No: sdc- 35?

Work Order No.: 00 0 SObS Vermont Yankee Procedure NolRev.: -l Visual Examination Report Form for General Visual (IWE) Page I of f Date: /O//G/BQ ./

-~ -~ - v Visual Aids 1 Photo I Sketch I Method D Mirror a Attached 10 Attached D Remote d g h t Source Examination Location DescriptionlRemarks Remote Examination CanditionslEquiprnent Remarks 0 6" Scale SjhdL, '%Zl;*c, 8 4 mJ.4 Examiner: Level Date VYNEF 8047.06 NE 8047 Original Page 1 of 1

Visual Examination Report Form Work Order No.: 00 - 005 b 35%0 ProcedureNoRev.: NE @ q 5 VT-1, Bolting (IWE) Page I of 1 Date: q./?*oI Examiner: - Level:= Date: 1 0 Yes Examiner: Level: +Date: rJ I&

Reviewer: Date: 4/(h/

Reviewer:

VYNEF 8045.03 NE 8045 Original Page 1 of 1

-- 0. 1 I

d Vermont Yankee I DataSheetNo:

Work Order No.:

Bj693 Ob - 0056 35-00 e

oz.

Visual Examination Report Form ProcedureNoRev.: NE wc 1 5 VT-1, Bolting o[wlE)

Page 1 of f Date: r/*/9*0t 11 Component I

/DrawingNoRev.: 4 -19 If7 5

[ I

.t

--pDp.

g163 t

BoltingLength: H/A II

" Bolting Diameter: EJ/A "

~ PhotolSketch Method Examination f Bolting Components Examined Illumination Level Check d o n e 4 direct 6 Place 1 dolting 0 Washers Date 0 Attached 1 0 Remote 1 0 Removed Bushings 0 Flange Surface Initial 12:to 44cia Visual Aids Intermediate d/A ~~ IJ/p CI Magnifying Glass d u n i n a t i o n c a r ~ o . :J q -5 Intermediate &/A NA n*ICilrror Final r3:45 344-or LightmeterS/N: ~ 5 % SO^

Cracks/Linears Corrosion Erosion

\

Evidence of Leakage Other(Exdain) 13/A @/A 4 #

Examiner: Level:= Date: q*19 0(

0 Yes Examiner: Level: r-Jh nata.

Reviewer: Date: #/&A/

VYNEF 8045.03 NE 8045 Original Page 1 of 1

Vermont Yankee Data Sheet No: (-' J 16- I 4- 5 r,) @%r-o/-a3 Visual Examination Report Form Work Order No.: Ob - 00 56 35-00 ProcedureNoflRev.: AJ& mu5 VT-1, Bolting (rwE)

Page f of I Date: 4 19 *dI Visual Aids Magnifying Glass Mumination carmo.: J +5 d r o r l d i g h t Source (Describe): P E U m 0&I-n- CondiGonsLimihtions:

I RemarkslObservations LoosefMissing 4 &/A Thread Engagement /

Thread Damage J \

Galling J \

Coating Degradation r/ I I

Benflwisted J t I I Physicai Damage r/ I I I Fractured Parts / I J I

'Gouges J Cracksninean J I /

I Corrosion / 1 t 1 Erosion / I lwear < \ n IEvidence of Leakage 4 4 4

Examiner: Level: E Date: 'f r q ' 0\

0 Yes Examiner: Level!&

' Date: JfA Reviewer: &

/& & Date: +h$h/

Reviewer: Date:

Date: /*v4/

VYNEF 8045.03 NE 8045 Original Page 1 of 1

1 Vermont Yankee I Data Sheet No: &qaP-@l

- aJ I I Work Order No.: 00 00 56 35-00 Visual Examination Report Form ProcedureNoRev.: NE 80q5 VT-1, Bolting @WE)

Page i of I Date: L/./?*di -

Component

, I Corrosion 4 f I I 1 Erosion / I L

W&X d \

Evidence of Leakaee Other (Explain) @/A /- I Y Examiner: Level: *Date: 3

  • 14 0t Examiner: Level: + Date: SI*

a Yes Reviewer. Date: 'Il/t~[d~

I[ Reviewer: Date:

VYNEF 8045.03 NE 8045 Original Page 1 of 7

r, Vermont Yankee Data Sheet No: 8@r/*/L 01- QLT Visual Examination Report Form Work Order No.: 00 - 00 5035-00 ProcedureNoRev.: 8645 VT-1, Bolting @WE) Page of f Date: +/%O I Cornpon ent Component m: J Ib c SE System: PCAC It PhotolSketch I Method I Examination I BoIting CornDonenis Examined 1 Illumination Level Check 1)tJ Attached 0 Remote 0 Removed Bushings Flange Surface Visual Aids 'Intermediate d/A d/A 0 Magnifying Glass d u n i n a t i o n card/~o.: J-S Intermediate d/! d b 6 m 0 r d i g h t Source (Describe}: P E u w u 6# Final 13:6 a*CCt*O(

Remote Examination ConditlonCimitations:

LightmeterSM A 5 9 3 SOJ CaLDueDate: 4.f3 Coating Degradation I Corrosion I Erosion *f I Wear J: \ \

Evidence of Leakage e

a Yes WNEF 8045.03 NE 8045 Original Page 1 of 1

Vermont Yankee Data SheetNo: -5 -W- Ob Drawing No/Rev.: 4 -19 It?< a. I e163 BoltingLength H/fi Bolting Diameter: I PhotolSketch Method Examination BoIting Components Examined I. .-Illumination rp*

&&*-*;?*3;9r-B. n Level Check -c d o n e drect dplace dolting CI Washers $$$@&&E&: Time Date 0 Attached Q Remote Removed Bushings 0 Flange Surface Initial Visual Aids 0 Magnifying Glass mumination carno.: \IJ-5 Intermediate I NA I

&m*r d i g h t Source (Describe): P c u w u &T -. ~.

Final Remote Examhation Conditiodimitations:

Lightmeterm: ~ 5 9 a3 ~ q RemarkslObservations LooseiMissing rl @/A d A Thread Engagement /

Thread Damage J Galling J \

Coatipg Degradation r, I BentKwisted J I I Physical Damage c, I I 1 Fractured Parts / I / 1 Gouges .J Cmkfiinears J Corrosion / I I f Erosion I/ I I J \

+

Wear n I Evidence of Leakage Yes VYNEF 8045.03 NE 8045 Original Page 1 of 1

I Vermont Yankee Data Sheet No:

I Work Order No.: 40 uu +.,/or-00 u Visual Examination Report Form Procedure No/Rev.: A/& '?5 /

VT-1, Bolting (IWE)

Page / of / Date: 5-7-c3/

1 Drawing NoRev.:

PhotoolSketch

%d20A I

Method I

Examination I

B g g & ? ? e ;

Bolting ComponentsExamined U

I

" Bolting Diameter:

Illumination Level Check None E Direct II In PIace Rl Bolting 17 Washers Date I I I

[ydiat~~~t~~~,

Attached Remote 1 1Removed 1 0 Bushings Visual Aids Intermediate x -

0 Magnifying Glass Illumination CardNo..

$I Mirror L .

E Light Source (Describe): F39s&/9&f Final&g7 Remote Examination Conditionfimitations: t Lightmeter SFN: ~/2/53 Cal. Due Date: &#/y4d OYes PNo VYNEF 8045.03 NE 8045 Original Page 1 of 1

Vermont Yankee Work Order No.: B O - 0 0 y/@?-o0 0 Visual Examination Report Form VT-1, Bolting OWE)

Procedm NoRev.: ?5 &. /

Page / of / Date: ,$-q-o/

_c Component Component ID:,&lie vz -/P - 54 System:s ; pa *s IReviewer:

Reviewer: 4 Date:

ANII: w p 2 f & g & d Date: &-J-- e !

WNEF 8045.03 NE 8045 Original Page 1 of 1

I Data Sheet No: 6J - 390 Work Order No.: 0 0 - 00 5 6 35 Vermont ~ i n k e e Procedure No1Rev.Z PP 7bs .//c> .

Visual Examination R e ~ o r tForm for General Visual-(IWE) Page I of Date: '//L/aI /

Component Zomponent ID:- System: T o n u c, Irawing No/Rev.: & L. 0 Location:_Fule c :ur Sur.Cpee,<

Visual Aids Photo Sketch 1 Method p Binoculars B None lj3 None &) Direct &&a+&

7 Mirror 0 Attached 0 Attached a Remote El Light Source Examination Location Description/Remarks Remote Examination ConditionslEquipment Remarks 3 6" Scale ixamination Results, Details and Comments:

VYNEF 8047.06 NE 8047 Original Page '1 of 1 i

i Data Sheet NO: 4?-ar - 031 Work Order No.: 00 - 3'7 Vermont Yankee Procedure NolRev,: bOJ7 40 .

Visual Examination Report Form for General Visual (!WE) Page of 9 Date: <Ifb / I Visual Aids Photo I Sketch

@ Direct Method

&&4 0 Binoculars None None 8pcrg.s 3 Mirror 0 Attached fl Attached 0 Remote

$ light Source Examination Location Descriptionmemarks Remote Examjnation ConditianslEguipment Remarks 6" Scale z*+rPlOr bJp Ffie cc c, 4 Other V&* CCladler EJ/p Reviewer: - /vfl Date VYNEF 8047.06 NE 8047 OAginal Page 1 of 1 i

rs

INSERVICE DISCREPANCY REPORT (IDR)

IDR #: Jm Date: 5/2/ZOOl, Component:.-Y Location: D w e l l Performed By: Date :

Disposition/Repair:

ISI Program Coordinator: Date:

Repair Ef f o r t ;

Reference Document:

Repair Completion Date:

Service Induced: YES - NO BY: Date: ~-

Sample Pxpansion Required: YES -. NO BY: - Date: ,-

Sample Expansion:

IS1 Program Coordinator: Date :

Reinspection Required: YES NO -BY :

Subsequent Inspection Required: YES - NO -BY :

IS1 Supervisor Notified:

IS1 Program Coordinator: Date:

. Reinspection Completed Satisfactorily:

IS1 Supervisor : Date:

IDR Closed:

I S 1 Program Coordinator: Date :

VYAPF 4027.01 AP 4027 Rev. 4

  • Page 1 of 1

I Datasheet No: -6v- 360 Work Order No.: 0 0 - 00 56 5s ~~

Vermont Yankee Procedure NolRav.: @ 7024 /O Visual Examination Report Form for General Visual {IWE) Page i of / Date: !/l&,/O) t 3 Mirror 0 Attached 0 Attached 0 Remote C tight Swrce Examhation Location Desm*ption/Remarks Remote Examination ConditianslEquipment Remarks D 6* Scale Reuiewer:. , Date #/A WNEF 8047.06 NE 8047 Originat Page 1 of 1  :

Vermont Yankee Procedure NolRev.: 0 I

Visual Examination General Visual (IWE)Form for Report Page / of Date: f/3o/i /

Component Component ID: -X- 7 4 +eL, 1 / e75 systm: Q wd Drawing NotRev.: 3 9 t b - v/ iocation:, &+y 7Q%w 1 photo Sketch Method Visual Aids p None $!p None f!!f Direct 6 4 4 a Binoculars U Mirror 0 Attached 0 Attached U Remote tight Source &amination LWatian Description/Rema&s Remote Examination CooditionslEquipment Remarks 0 6" Scale &+t,-,(k~IIda~ gKkrwYI 4 4 Examiner: Level Examiner: Level Reviewer: Date Y 4.h Reviewer: Date VYNEF 8047.06 NE 8047 Original Page 1 of 1

Vermont Yankee Procedure NolRev.: PP 7QJ-9/0 .

Visual Examination Report Form for General Visual (IWE) Page / of Date: f / J C /df I Component Component ID: x- 8 System: bhv cM Visual Aids Phbto Sketch Method El Binoculars @ None B None @ Direct &rJ +a+&

0 Mirror 0 Attached 0 Attached U Remote

/2U Light Source Examination Location DescriptionlRemarks Remote Examination ConditionslEquipment Remarks L7 6 Scale aaad, U. U t a - NtR 0 Other

~- ~-

x - f3 ~

Examination Results, Details and Comments:

Examiner: &/A Level .I/A Date d.4 Reviewer: d3/A Date d/A Reviewer: #!A Date A)/A VYNEF 8097.06 NE 8047 Original Page 1 of 1

Data Sheet No: -

%0q7 - o( 043 Wark Order No.: 00 - 5 0 3&

Vermont Yankee Procedure NolRev.: 86 d7 40 Visual Examination Report Form for General Visual (IWE) Page I of. 1 Date: "/3&/OI Examiner: dl4 Level >I! Date Al/P.

Reviewer: Date Y

Reviewer: /v/A Date N/A W N E F 8047.46 NE 8047 Original Page 1 of 1

Vermont Yankee Procedure Nomev.: bo f? RO Visual Examination Report Form for General Visual (IWE) Page / of 1 Date: &&/

-~

Component Component ID: x- lo System: 3 ~c3r 4 L4 Drawing NolRev.: s i30 ci// Location: A~J 4&/ L Visual Aids Photo Sketch Method 0 Binoculars None Bp None # Direct &d 0 Mirror Q Attached 0 Attached 13 Remote Examiner:

Examiner:

Level Level a*4 Date Date V~&I

.r/A .

Reviewer:4 Y

D D a t e fioA/

Reviewer: MfA Date v2 VYNEF 8047.06 NE 8047 Original Page 1 of 1

Work Order No.:- QO 503b Vermont Yankee Procedure NolRev.: go47 R 0 Visual Examination Report Form for General Visual (IWE) Page / of 1 Date: %?k?/C3[

Component x- I (

I Component ID: System:-

I Light Source W N S 8047.0.6 NE 8047 Original Page 1 of 1

I Vermont Yankee Work Order No.: Q O - @ 50 3's Procedure NolRev.: PP 7 6 24 g/D Visual Examination Report Form for General Visual (IWE) Page of 1 Date: !h~ci/4j Component Visual Aids Photo Sketch Method Cl BinocuIars 9 None $9 None @ Direct 0~~~ Q.

0 Mirror Light Source Examination Location Description/Remarks Remote' Examination ConditionslEquipment Remarks I

I 0 6' Scale aI.4

' 0 Other 1 x- l')c I 1 Examination Results, Details and Comments:

Examiner: d/la Reviewer: r//A Date 41 Reviewer: - 44 Date Nh ANI!: Date //?!*(

1' VYNEF 8047.06 NE 8047 On'giflal Page 1 of 1 \

Data Sheet No: 6- GU- f g t Vermont Yankee Procedure NolRev.: f?y76 2 y / o Visual xamination Report Form for 8 General Visual (IWE) Page of / Date:  :/l-c/ot J Component Component ID: -

X 13 A 4-13 System: bA A d *rJC Xe&4,i>

&L-L 0 Mirror VYNEF 8067.06 NE 8047 Original Page 1 of 1

e Data Sheet No: go L/7 - 0 I -Dfco Work Order No.: 00 50 37 Vermont Yankee Procedure Nomev.: 047 R o Visual Examination Report Form for General Visual (IWE) Page i of ( Date: j///d/

Component

omponent ID: -x* / 4 System:

3rawing NolRev.:

Photo Sketch Method 7 Binoculars W None None p00irect &&-&

3 Mirror f 3 Attached 0 Attached f3 Remote p Light Source Examination Locetion Description/Remarks 1 Remote Examination ConditiondEquipment Remarks 7 6" Scale I] Other 0

Saminer: Level Dats M N E F 8047.Q6 NE 8047 Originat Page 1 of 1

Vermont Yankee Procedure NolRev.: gOV7 k o Visual Examination Report Form for General Visual (IWE) Page of I Date: ~/</oJ I Component

omponent 10: -x- /5 System: 3rc4 d c t x Irawing NolRev.: P 4/ Location:

I U Visual Aids Photo Sketch Method 3 Binoculars None None Direct 6 - 4 3 Mirror U Attached I3 Attached Cl Remote 81 Light Source Examination Location DescriptionlRemarks Remote Examination ConditionslEquipment Remarks J 6" Scale ak~~6"QCM 3 Other btqwclL YhJe Examiner: Level 9.'

J%

Date d7l.t Examiner: Level r//A Date uh-Reviewer:

U Date Qfb, Reviewer: Date #b ANII: Date s-@/

VYNEF 8047.06 NE 8047 Originaf Page 1 of 1 1

I

  • Data Sheet No: m e - 6J- 38 f I Vermont Yankee Work Order No.: 00- 04 50 3s Visual Examination Report Form for Procedure NolRev.: Pp 7&3-c(/c,'

General Visual (IWE) Page f of Date: ! / / 6 , / 6 j t Component Component ID: X 1b A System:

k Drawing NolRev,: -

.<?h, q/ Location: ~sL.A! s ~ A ts4-U Visual Aids Photo Sketch Method 5 Binoculars @ None C@ None Direct 6 6~ 4 *C 0 Mirror 0 Attached El Attached D Remote I$ Light Source Examination Location DescriptionlRemarks Remote Examination ConditionslEquipment Remarks U 6" Scale BFpuY & J & & I h q4 D Other x -/&A t

5p*&tq Examiner: LE U Level Rate !/lb /Q /

Examiner: MA Level e/! Date $/A Reviewer: &/A Date 41~

Reviewer: - d/A Date d A VY NEF 8047 .U6 NE 8047 Original Page 1 of 1 i

Vermont Yankee Procedure NolRev.: 930 L/7 RO Visual Examination Report Form for General Visual (IWE) Page 1 of Date: 5///0/

Component VYNEF 8047.06 NE 8047 Original Page 1 of 1

Work Order No.:

Vermont Yankee Procedure NolRev.: /?p70 ; t V 10.

Visual Examination Report Form for General Visual (IWE) Page / of I Date: 1/16 / o /

Component Visual Aids Phbto Sketch Method 0 Binoculars I$, None Nons 4~ Direct t r 4 ~ * ~ o . ~

0 Mirror 0 Attached 0 Attached D Remota

$ Light Source ExaminationLocation Oescription/Remarks Remota' Examination ConditionsiEquipment Remarks 0 6" Scale &&Mi d Ad "/A

[3 Other t x-r7 Examiner: d//3 Levet Date d/A Reviewer: Hh Date E.1/A Date .z/A Date /-3P/

VYNEF 8047.06 NE 8047 Originaf Page 1 of 1

6- 6 V - 377 I 8 Data Sheet N c x 3 - 2 )

Work Order No.: Don 0 0 50'35 Visual Aids Photo Sketch Method 0 Binoculars @None . IjZ None Direct &ea a r o-L 0 Mirror D Attached 13 Attached 0 Remote Light Source Examination Location Description/Remarks Remote' Examination ConditionslEquipment Remarks D 6" Scale fhyrrcb AI@.6 8

Examiner: LeveI&T.rJu*L Date 1/l&./O 1 Examiner: Ah% Level A# Date IJ/A Reviewer: &A Date &/A Reviewer: Date dh VYNEF 8047.06 NE 8047 Original Page 1 of 1 I

I Data Sheet NO: ZW- b d - 378 Vermont Yankee Work Order No.: 00 90 5 0 fs Procedure NolRev.:, P?p7 02(//0 ,

Visual Examination Report Form for General Visual (IWE) Page - I of -, I Date: !/'/b/~/ t Component Visual Aids Photo Sketch I Method Binoculars LX? None 03 None I Direct 6*3& r*L 0 Mirror 0 Attached 0 Attached I3 Remote Light Source Examination Location Description/Rernarks Remote Examination CanditionslEquiprnentRemarks 0 6" Scale bq Jrt( P*dcMr*  %

0 Other k- 19 Examiner: dh Level ~2 Date NA Reviewer: Date A/A Reviewer: - Date ANII: Date /43/4/

I' VYNEF 8047.05 NE 8047 Original Page 1 of 1 i

Vermont Yankee Procedure NolRev.:_dO $7 Ro Visual Examination Report Form for General Visual (IWE) ?age / oi i Date:qA,/o/

I Component ID: x- r9 Component system: 3& k )\c/cI Drawing No/Rev.: 5 2 0 - //

I

~~

Visual Aids Photo Sketch Method c1 Binoculars ga None pb: None FDirect 6*4LIc.vQ 0 Mirror C3 Attached Cl Attached 0 Remote Light Source Examination Location DescriptionlRemarks Remote Examination ConditionslEquipment Remarks 0 6' Scate si+JzR&d 5tllLcp- n//p 0 Other 7 %I*)LN I 4W&

Examination ~ e s u l t s ,Details andcomments:

&*/f-s #f k s ci;Ad/r& nyu 3444&4r, U b.* be co+cp;ficd.

b 5 f haminer: L e v a l e Date chh 1 Examiner: Level &/A Date &h Reviewer:%.e a

  • t Reviewer: Date W N E F 8047.M NE 8047 Original Page 1 of 1

Vermont Yankee Procedure NofAev.: pp 7oA4 /o Visual Examination Report Form for General Visual {IWEI page f of / Date: !//~/uI I Component Component ID: x System:

Visual Aids I Photo Sketch Method 0 Binocutars FjtNone @ None PDirect 6

  • c ~
  • p b ~

0 Mirror f&fLight Source Examhation Location Descriptim/Remarks Remote-Examination ConditionsEquipment Remarks 0 6 Scafe bq 4 PcAcht*+. aL\ q4 0 Other IXJZO I Examination Results, Details and Comments:

Examiner: ~h Level &/A Date Ab!h l Reviewer: /J/A Datenl/A.,

VYNEF 8097.06 NE 8047 Original Page 1 of 1 i

I Data Sheet No: E M 6 - gdm3 7 b Work Order No.: BO- 00 S O 4s Vermont Yankee Procedure No/Rev.: *#?P7o*f/u Visual Examination Report Form for General Visual (IWE) Page 1 _of 1 Date: //I610 / t Visual Aids Photo Sketch Method

@Binoculars *None Q None p) Direct &A c( L 0 Mirror D Attached 0 Attached I 0 Remote

~.

I ExaminationLocation DescriDtionlRernarks 1 kernote. Examination ConditionslEquipment Remarks

~ ~~

%Light Source 0 6" Scale 0 Other 1 X- I

~. - __

Examination Results, Details and Comments:

Reviewer: ~ I A Date e/#

VYNEF 80.47.06 NE 8047 Original Page 1 of 1

Data Sheet NO: 2 -6 37Y Work Order NO.: oo*oo 5 0 33 Vermont ~itnicee Procedure N o I R e v . : y p 7d 2 f/b Visual Examination Report Form for General Visual (IWE) Page / of Date:  !//6hL r Component Component ID: X -# LL, System: Bfi? d 4 Visual Aids Photo Sketch Method sf3inocutar.s None poria Direct 64+4*L El Mirror 0 Attached fl Attached Examiner: d/A Level dh Date ry/A Reviewer: &/A Date A//A Reviewer:- $/A Date ni/A VYNEF 8047.06 NE 8047 Original Page 1 of 1 t

C Data Sheet NO: SOy7- O / 037 1 Work Order No.: Po - 5 0 3 7 Vermont Yankee ROCedW8 NoiRev.: g047 L o Visual Examination Report Form for General Visual (IWE) Page / of / Date: 5//0/

Component Component ID: x* A 3 system: -&.I d c &i Drawing NolRev.:

Visual Aids s!!&w@ d/ Photo Location:

Sketch 3/z..d t 4 Method c1 Binoculars @ None None Direct br,~u*rzc(l 0 Mirror 0 Attached 0 Attached El Remote Examination Location Description/&marks Remote Examination ConditionsEquipment Remarks Other -

f Reviewer: Date ANII: Date & o /

WNEF 8047.06 NE 8047 Original Page 1 of 1

Vermont Yankee Visual Examination Report Form for General Visual (IWE)

Component Procedure NdHev.:

Pa98 Of 1 PP 7 0 2 ' f / 0 Date: ?//&Id t

I Component ID: x-A3 System: ~ H L3W e a Visual Aids mota Sketch Method p Binocu!ars b None $B None E, I Direct &a&* cQIC.

0 Mirror CJ Attached 0 Attached 10 Remote pS Liiltt Source Examination Location DescriptionlRemarks 1 Remote ExaminationCanditionslEquipment Remarks 0 6" Scale 3ftSLJ-a a.J*u;Or\

Reviewer: - '14 Date @/u

/

I/

bate I 4

VYNEF 8047.06 NE 8047 original Page 1 of 1 i.

C Data Sheet No: 8047 @D/-O3 b Work Order No.: 00 3'7 Vermont Yankee Procedure NoJRev.: yo $7 L o Visual Examination Report Form for General Visual (IWE) Page / of Date:<A/o I Component Component 10: K-29 system: 3 4 L3C.u Drawing NolRev.: 5- $41 Location: -44 I pluu Visual Aids Photo Sketch Method I3 Binoculars p None Pp None @ Direct 61~.++4~4 0 Mirror 0 Attached D Attached 0 Remote 9fUght Source Examination Location DesctiptionlRernarks Remote Examination ConditionsEquipment Remarks 0 6" Scale 2=*.3.(Fd 0 Other Ab,

&IL*&

4c. bL ye@&'

N/A.

Examination Results, Details and Comments:

H' Examiner:

Y Level 9 s Date s"/,,h /

IIReviewer:

Reviewer: - .'/A Date Date f///. f VYNEF 8047.06 NE 8047 Original Page 1 of 1

fi r

Data sheet No: 6Jn 37%

Work Order No.: 00-00 SO35 Vermont Y b k e e Proceciwe N~IEW.:, PP 7 b A c j / D '

Visual Examination Report Form for General Visual (IWE) Page - 1 of -I Date: !//C/O I Component Component IO: X%+ System: /t~)cs 4 5 9 a-0 - Yf E~-L,,A Drawing NoMev.: tacatim:

Visual Aids Photo Sketch Method ino oculars W None @ None PDitect LS&d**L t

CI Mirrar 0 Attached 0 Attached a Remote Light Source Examination Lacation DescriptionlRemarks Remote Examination ConditionsEquiprnent Remarks I3 6* Scale D q w 4 PLW4-n 1

H W N & 00d7.06 NE 8047 Original Page 1 of t I

VYN$8047.06 NE 8047 Original Page 1 of 1 i

c I

~ a t meet a NO: Zwe -t ~ 37/

1 work order NO.: 00 - 00 SO35 Vermont Yankee prOCeChU8 NOmeV.: /? 7d d. / O .

Visual Examination Report Form for General Visual (IWE) Page / of 1 Date: ! / J L A t Component Component tD: X - Ab System: .3 t ~ rA 6 4 Visual Aids Photo Sketch Method 0 Binoculars mNme SNanr, ~ aDirect

, 6

  • r- , ~L-Mirror 0 Attached D Attached 0 Remote p Light source Examination Location DescriptiodRemarks Remote Examination CanditionslEqrripmentRemarks U 6" Scale ' B f i p d P~c&#& VA 0 Other 1.

Examination Results, Oeta3s and Comments:

WNEF 804'7.06 NE 8047 Original Page 1 of 1 i

Vermont Yankee Procedure NdRev.: 8d d7 k!O .

Visual Examination Report Form for General Visual (IWE) Page / of I Date: $ff& t t Component 1 Component ID: System: h- L3 *4 Visual Aids Photo Sketch Method @

c1 Binoculars $ None @! None /Z Direct L a d 0 Mirror 0 Attached 0 Attached 0 Remote

@ Light Source Examination Location DescriptionlRematks Remote' Examination ConditionslEquipment Remarks 0 6- Scale # w d 4Y&.CA&k.

0 Utherphq d 4 &&e.

1 Reviewer: 44 Date 5%

VYNEF 8047.06 NE 8047 Original Page 1 of 'I i

Data %et No: 6 bf* evv 1 work Order NO.: 0 0 .. 4 0 5 0 35 Vermont Yankee Procedure NolRev.: pp 761!//0.

Visual Examination Report Form for General Visual (IWE) page I of / Date: ! / 1 6 / a L I D Mirror c1 Attached Attached

$I Light Source Examination Location DescriptionlRemarks Remote Examination CondifionsEquipmentRemarks I7 6" Scale El Other I x-LS I Examination Results, Details and Comments:

Examiner: rJ/n Level Ah Dale 'h Reviewer:- ' h Date 44 ate J!!

ANII: Date P I Y

VYNG 8047.06 NE 8047 Original Page 1 of 1 t

Vermont Yankee PfoC8dUr0 NO/RW.: /f Visual Examination Report Form for General Visual (IWE) Page of i Date: !//b,Ld 1 Commnent 1 Component ID:

II Visual Aids Sketch Method U Binoculars $ti None None c7 Mirror Light Source Cl 6" Scaie 0 Other I Examination Results, Details and Comments:

WNEF 8047.06 NE 8047 Original Page I of 1 1

Work Order No.: 6 0 -00 $035 Vermont Yankee Procedure Nomev.: Pfl 702 l//o.

Visual Examination Report Form for General Visual (IWE) Page I of 1 Date: '//&/b[ I Component il Component ID: X - 3~ System: 'Dm L3 4 I

Drawing NoiRev.: ,<?to + qf . Location: GK -.5Y/t&Gc Visual Aids Photo Sketch Method 0 Binoculars $4None ,j5t None )%#Direct 6 r ~ ~ p - L El Mirror 0 Attached 0 Attached I D Remote Light Source Examination Location DescrbtionlRernarks I Remote' Examination ConditionsiEquiprnentRemarks 0 6" Scale Examiner: d A Level d / ~ Date htlA Reviewer: d A D a t e . L ~

Reviewer:' rflA o a t e . L ,

ANII: Date i. 3r-0(

1 A VYNEF 8047.06 NE 8047 Original Page 1 of 1

I Data Sheet No: Z a E - 3rfs I Work Ordsr No.: 00 - 03 503s" I

Vermont Yankee procedure Nmev.:. PP 7 6 .t/o ~

Visual Examination Report Form for General Visual (IW) Page ,-Lof I - , Date: $/b/d r Component Component ID: c system: 3rz.r CJCY Drawing Nomev.: - '59'z tc( Location:. -ju&i 4 Visual Aids U Binoculars crp None Photo If None Sketch II@Direct 6 Method d

a Mirror D Attached 1 5 Attached 1 IO Remote

@ Light Source Examination Location DescriptionJRernarks Remote' Examination ConditionslEquuipment Remarks 0 6" Scale b y p d P&A&b,4,.h WN& 6047.06 NE 8047 Orighd Page 1 of 1

\

Vermont Yankee Visual Examination Report form for procedure Nomev.: pfl76  ?-. (//o. I General Visual (IWE) page 1 of I Date:

Component 0 Mirror 0 Attached 0 Attached U Remote I$ Light Source Examination Location DescriptionlRemarks Remote' Examination ConditianslEquipment Remarks 0 6" Scale t

0 Other I I

V Y N E 8047.06 NE 8047 Original Page 1 of 1 i

Vermont Yankee Procedure Na/Rev,: pp 7 0 4

  • Visual Examination Report Form for General Visual {IWE) Page / of 1 Date: !//fh/ I Visual Aids Photo Sketch Method 0 Binoculars pB None /I$None ?Direct w d 0 Mirror U Attached Attached I Remote p Light Source Examination Location DescriptionlRernarks 1 Remote Examination ConditionslEquiprnent Remarks D 6" Scale 0 Other I x- 3 3 I
  • \

Examination Results, Details and Comments:

?sArvlJn/A4 t9-U 45 VYNEF 8047.06 NE 8047 Original Page 1 of t i

Visual Aids Photo Sketch Method 3 Bioocu!ars None p31 None PDirect &

  • A d 3 Mirror tl Attached 13 Attached 1 D Remote Light Source Examination Location DescrjptionlRemarks Remote Examination ConditionslEquipment Remarks 3 6 Scale an-)C J 4 Pdd4 sh, Y4

&*Sa 3 Other

~

k - 3 v j-

- ~~- -- ~-

kamination Results, Details and Comments:

  1. I/

4+sf2lms.b4 Examiner: R4 to L &LJ u ? ~ Level & r c r i 4 u ~ Date

-4W.QJ-Examiner: uI/R Level & Date ?A seviewer: N/R Date  ?$

3eviewer: - Date Nh VYNEF 8047.06 NE 8047 Original Page 1 of 1 i

work Order NO.: 40 5 6 33 Vermont Yankee Visual Examination General Visual (IWE)Form for Report Page of Procedure NolRev.: 80q7 40 Date: T f i / O /

Component VYNEF 8047.06 NE 8047 Original Page 1 of 1

Data Sheet N o : X& E - 3C3 Work Order No.: 0 0 0 00 50 $5 Vermont Yankee Procedure NolRev.: f p 7b & / D .

Visual Examination Report Form for 0 General Visual (IWE) Page of Date: !//6/0/ t Component Visual Aids Photo Sketch Method J Binoculars Q None b None /%Direct kC,&

3 Mirror 0 Attached 0 Attached 0 Remote PLight Source Examination Location Description/Remarks Remote' Examination ConditionslEquipment Remarks 7 6" Scale b A l L s e M &!&du-&-,d' 6 O b 5 N/4 3 Other x- 3 7 j 4 e j Examiner: #/A -~evel rJk Date &/A Reviewer: U/h Date Iv/A VYNEF 8047.06 NE 8647 Original Page 1 of 1 i

C Data Sheet No: 8w3 -o/ # - 3 Vermont Yankee Visual Examination Report Form for General Visual (IWE)

Drawing Nomev.:

I I Location:

I R!S&L & -Id,*d uI Visual Aids I Piioto t Sketch I Method 0 Binoculars 0 Minor 0 Attached a Attached 1o Remote

@ Light Source Examination Location Description/Remarks ' Remote barnination ConditionslEqtlipmentRemarks 6' Scale &&+4f#& 3dlLCAC.c Examiner: MA Date #/A WNEF 8047.06 NE 8047 Original Page 1 of 1

Visual Examination Report Form for General Visual (IWE) Page -. 1 of -1 Date: !//-

c Component I

Level &/& Daet-.

Examiner: 'h Reviewer: #I% Date &h, WNEF 8047.06 NE 8047 Original Page 1 of 1 i

I Vermont Yankee Work Order No.:

Procedure NolRev.:

00 - 93b 8097 A3 .

VYNEF 8047.06 N E 8047 qriginal Page 1 of 1 1

Data Sheet No: - 6 v - 361 Work Order No.: 6 6 - Do $0 5r Vermont Yankee Procedure Nomev.: pp 70L ' f ( / D Visual Examination Report Form for Visual Aids Photo Sketch Method 0 Binoculars $F None $None $[ Direct 6ae~lrlr~L 0 Mirror D Attached 10 Attached 1 o Remote Light Source I Examination Location DescfiDtionlRematks Remote Exemination CanditionslEquiprnent Remarks 0 6" Scale Examination Results, Detans and Comments:

VYNEF 8047.06 NE 8647 Original Page 1 of 1 f

Vermont Yankee Procedure NolRev.: 26 #7 R U Visual Examination Report Form for General Visual (IWE) Page !of i Date: <I<h 1 Component Component ID: x47 .: System: >rz$ ulca Drawing NoiRev.: X?h #( Location:

d Visual Aids Photo Sketch Method 5 Binoculars $ None $Zl None 9 Direct &A&

Q Mirror 0 Attached n Attached 0 Remote I$ Light Source Examination Location DescriptionlRemarks Remote Examination ConditianslEquipment Remark:

0 6 Scale G+4PAJ44 SdrL-crPrcrr */A VYNEF 8047.06 NE 8047 Original Page 1 of 1

Work Order No.: Do - 00 $0 35 Vermont Yankee Procedure NofRev.: pp 76&</h.

Visual Examination Report Form for General Visual (IWE) Page c  !

_ of 1 Date: !/fG/o I I Component hmponent ID: x- 4 8 System: & k, &(A Visual Aids Photo Sketch Method 3 Binoculars None None Direct 4f aL 3 Mirror Attached D Attached 0 Remote Light Source Examination Location Description/Remarks Remote Examination ConditionslEquipmentRemarks 3 6"Scale b yd d kL-,k.oz);JL\ BauQtZu &

I3 Other -L g- LJ$ v:c34 4- mcu3 Examiner: f!/R Level Date 4 Reviewer: ph Date ~h Reviewer: - dh Date 4 Date /-3/& /

V VYNEF 8047.06 NE 8047 Original Page 1 of 1 I

t Data Sheet No: ZQe- v- 38 7 Work Order No.: 0 0 - on s a 35 Vermont Yankee Procedure NofRev.:, &? 7a 2.4 / O Visual xarnination Report Form for General Visual (iWE) Page / of i Date: !/l</f.l!

t Component I Component ID: c System:

3~7 LI i

Visual Aids Photo Sketch Method t! Binoculars $b None /Z! None Direct 6m ~ t a ~

El Mirror 0 Attached 0 Attached D Remote Light Source Examination Location OascFiption[Remarks Remota' Examination ConditionslEquipment Remarks Q 6" Scale 'bQc3uUP.WA)bd.m A'f4 0 Other x- L(4 1 Reviewer: - A 4 Date.&-

W N E F 8047.06 NE 8047 Original Page 1 of 1 t

Visual Examination Report Form for I!

Visual Examination Report General Visual Form for

{IWE) Page - of / Date: !//$h Component I

. Examiner: 15(/A V Level did Date Revi ANlI:

i I

W N E F 8047.06 NE 8047 Original Page 1 of 1 i

....-.-. . . ~.

Work Order No.: g0- O b 543s Vermont Yankee p p 7 0 2f / D .

Procedure NofRev.:

Visual Examination Report Form for General Visual (IWE) Page I of I Date:  ?/ir/ol z Component

omponent ID: x-SL  : System: art9 d 4 -

Visual Aids Photo Sketch Method J Binoculars IJ None eQ None jZ Direct L a 4 4r d-3 Mirror 0 Attached 0 Attached D Remote

$ Light Source Examination Location DescriptionlRernarks Remote Examination CooditionslEquipment Remarks J 6" Scale -p4 &&+A 6 ctd 3 Other i x- 5 %

Examiner: Level rulR Date $/A Reviewer: & Date J/A Reviewer: Date IJh Date l-S{+f Y

VYNEF 8047.06 NE 8047 Original Page 1 of 1 1

8 Data Sheet No: z d t&

Work Order No.: 00 - 0 0 s o 3 5 Vermont Yankee Procedure NdRev.: //70;~1//6 .

Visuat Examination Report Form for General Visual ([WE) Page / of / Date: ebyA 1 1 Component ZompDnent ID: x404 A,&,

r .

.k,v

.) b System: ' b a y ~ 3 6 ~

Drawing Nomev.: 5 5 s- Vt Location: ~~~L Visual Aids Photo Sketch t Method c3 Binoculars 1 @ None pb None Direct 64l~*1.&L Ip Mirror 0 Attached 0 Attached El Remote

!I Light Source Examination Location Description/Rernark Remote'Examination ConditionsEquipment Remarks 0 6" Scale Examindon Results, Details and Comments:

haminer: dI.4 Level J!A Date+.

Reviewer: JfA Date $!A Reviewer:, r/(A Date (/A VYNV 8047.06 NE 8047 brTginal Page 1 of 1 t

I Work Order No.:, 0 0 - 60503 5 Vermont Yankee Procedure NO~RW.: PP 7b P f / O Visual Examination Report Form for General Visual (IWE) Page / of ~ater_r/r(/o/ I I Component t Visuaf Aids photo I Sketch I Method

@ Mirror 10 Attached

~

1 CI Attached I cl Remote tight Source Examination Location DescriptionlRsmarks Remote-Examination ConditicnslEquipment Remarks 0 6 SCd8 hrty&Y fidC4?&W5 WNEF 8047.06 NE 8047 original Page 1 of 1 t

Vermont Yankee Visual Examination Report Form for General Visual {IWE)

Component

ompooent ID: -

X /a% System: bn+ k ~ c ~

Visual Aids Photo Sketch Method 3 Binoculars pl None $4 None p Direct G*rr,r~Qe~

1 Mirror kl Light Source Examination Location Descr$tion/Remarks Remote Examination ConditionslEquipment Remarks 3 6" Scale h q d 4 4-c L&*4*.& rJ/A.

3 Other 1 X-l13% I Examination Results, Details and Comments:

Examiner: #/A Level IJ/R Date '"/A Reviewer: &/A Date N/A Reviewer:

  • Date Nh VYNEF 8047.06 NE 8047 Origina!

Page 1 of 1 i

i Work Order No.: 00-00 5035 Vermont Yankee Procedure NolRev.: 8 p 70 %$

Visual Examination Report Form for Visual Aids Photo Sketch Method 3 Binoculars C% None 0 None 0 Direct N u t p*6G-d?,

3 Mirror 0 Attached !JAttached 0 Remote % A C t L G - d 5 b g! Light Source Examination location DescriptionjRemarks Remote' Examination ConditionslEquipment Remarks 0 6" Scale 'I>r y rJcLI pl&C.Cru=JiOrr,

&r'A 0 Other x- lo3 VYNEF 6047.06 NE 3047 Original Page 1 of 1 L

I e Data Sheet No: [-

Work Order No.:.. 190-OD $0 3c Vermont Yankee Praedure Nomev.: /p 70A Visual Examination Report Form for General Visual (!WE) Page of 4 Date: @d,/h/ t c -

Component I

Minor 0 Attached 0 Attached 0 Remote

~ g h Source t Examination Location Desuiptionmernarb Remote Examination ConditionsfEquipment Remarks D 6' Scale Examination Results, Details and Comments: I!

W N E F 8047.06 NE 8047 briginal Page 1 af t i

Vermont Yankee Visual Examination Report Form for General Visual (IWE) Page 1 of I Date: :hx/b/ t Component 0 Other I Fvnmination Re&, Details and Comments:

W N E F 8047.06 NE 8047 Original Page 1 of 1

1 Data Sheet N o : - z a c - -

btf 387 .

I Work Order No.: 00 00 503 5 verrnbnt Yankee Procedure NolRev.: #p 70 As/ / o Visual Examination Report Form for General Visual flWE)

Visua[ Aids Photo Sketch Method 3 Binoculars None )B None FDirect 6.1~~)a P*L

%Mirror 0 Attached 0 Attached a Remote I ExaminationLocation Descriotionlffemarks1 Remote Examination ConditionsIEquipment Remarks

~ ~

3 tight Source Examiner: Level lu/A Date Reviewer: N/A Date Nh Reviewer: EJh Date A/A ANII: I f Qate Id?/*f f

VYNEF 8047.06 NE 8047 Origina!

Page 1 of 1  !

C Data Sheet NO: Z w 6-G J - 38 8 Work Order NO.: 00-00 S O is Vermont Yankee Procedure Nomev.: @P 7 b LI/ /a Visual Examination Report Form for General Visual (JWE) Page 1 of Date: t . l a i Component component ID:

Drawing NolRev.:

Visual Aids y-107 s??-d - s//

Photo 1

System:

Location:

Sketch b . 9 ~ - L u -

gx.cc,,4 S Q ~ &

Method 0 Binoculars None None E

, l Direct 60,*

f$L Mirror U Attached 0 Attached CI Remote

$&Light Source Examination Location OescriptionlRemarks Remote Examination ConditionslEquipment Remarks 0 6 Scale aqb3A.q P u , k d ; o &) 4 4 D Other A- 107 Examination Results, Details and Comments:

RI -LJ- d2 AbLlG  % b

  • L 4 Cr+-ccA c**A ,A.-

L

&f?un e&*d*b D C di\ p-LA3 I, PLSUikS r n l AI&

, L s u k * .*.c4sfLc VYNEF 8047.06 NE 8047 Original Page 1 of 1

Vermont Yankee Visual Examination Report Form Work Order No.: t?d* 80ild/ 7 dbd VT-1, Containment Surfaces (IWE)

ProcedureNoRev.: &b fb / 1 Drawing Nomev.: 4-/9 /I67 !a.0 Other (Explain) 1 Examiner: Level: 4 Date: , ,

Evaluation Required?

Examiner: Level: &/A Date:

Reviewer: Date: </<kt yes d o VYNEF 8045.02 NE 8045 Rev. 1 Page 1 of 1

Vermont Yankee BorCs-a/ -s//

Reference Data Sheet No:

Visual Examination Page 2 of Date: s/I-//o /

Supplemental Report Form Component

omponent ID: )-ZOO4 System: %LV3 Raminer Level:, ..fA Date: 4 Zeviewer: Date: sydk/

ieviewer: 4 4 Date: 4 M I  :.&w Date: S- %/

VYNEE 8045.04 NE 8045 Original Page 1 of 1 t f c #I

Vermont Yankee I Work Order No.: 00 -0046)7~,060 Visual Examination Report Form VT-1, Bolting @WE)

Procedure NoRev.: h!k"goi/-T / RmG /

page I of / Date: 5-3-o/

~

II Comuonent Drawing NoRev.: L - ~ W We/v:

~ a Bolting Length: Y ;/8 'I' Bolting Diameter:

0 Magnifying Glass umination carmo.: y Yg

'Examiner: Level: &-Date: 4+

Reviewer:

ANII: #F& Date: 9-O /

W N E F 8045.03 NE 8045 Original Page 1 of 1

WorkOrderNo.: 00 - 00 94 / f . - C ' d 0 Visual Examination Report Form Procedure No/Rev.: /YE 86 95 Me*.. 0 VT-1, Bolting (IWE)

Page / of / Date: s - = s - ~ /

Evaluation Required?

Leve1:xDate: fi g0@

UYes VNo Examiner: Level: &Date:

Reviewer: Date: 1 I

Reviewer: h'h Date: IJ/A Date: 6-s-o!

VYNEF 8045.03 NE 8045 Original Page 1 of 1

Vermont Yankee Visual Examination Report Form VT-1, Bolting (IWE)

CA/3S86d //'

Drawing Nomev.: 7- 6 2 O ; L 4euoo

  • Bolting Length: ya" 'I Bolting Diameter:

II 0 Magnifying Glass OYes MNo VYNEF 8045.03 NE 8045 Original Page 7 of 1

Visual Examination Report Form for General Visual (IWE) page I of 1 Date: !//G/oI t Component WNEF 8047.06 NE 8047 Original Page 1 of 1 i

t Data Sheet No: Z h J 6- 6Q-396 Vermont Yankee Work Order No.: DO- 90

  • 5 Procedure NolRev.: pp 70 aq/b .

Visual Examination Report Form for General Visual (IWE) Page 1 of I Date: j l ~ ~ l o ti Component Zomponent ID: X - AQ 3 A +im Ir System: 7-04 u.<

hawing NoRev.: 6% 6 dc Visual Aids Photo Sketch Method 3 Binoculars IEl None @ I None Direct 6edr~oc 3 Mirror D Attached 0 Attached 0 Remote

~. ~

8 Light Source Examination Location DescriptionlRemarks Remote Examination ConditionslEquipment Remarks 7 6" Scale TSR.*S PeucccC~:gcu~ -14 Examination Results, Details and Comments:

c VYNEF 8047.06 NE 8047 Original Page 1 of 1

r 8

Data Sheet NO: 6Jw 39s Work Order No.: 9 0

  • 00 5 0 35 VYNEF 8047.06 NE 8047 Original Page 1 of 1

Vermont ~ i n k e e WNEF 8047.06 NE8047 Original Page 1 of 1

INSERVICE DISCREPANCY REPORT ( I D R )

IDR #: lL!dL&

Date : 5 /2/2001

  • Component: X-207A -. H Location: Drvweld, Mechanical D e s i g n Engineering Evaluation:

Performed By: Date :

Disposition/Repair:

~~ ~

ISI Program Coordinator: Date :

Repair Effort:

Reference Document:

Repair Completion Date:

Service Induced: =s - NO BY : Date :

7 Sample Expansion Required: NO -BY: Date: -.

Sample Expansion:

IS1 Program Coordinator: Date :

Reinspection Required: YES NO -BY:

Subsequent Inspection Required: YES - -BY :

IS1 Supervisor Notified:

IS1 Program Coordinator: Date :

Reinspection Completed Satisfactorily:

IS1 Supervisor: Date :

IDR Closed:

IS1 Program Coordinator: Date :

WAPF 4027.01 AP 4027 R e v . 4

  • Page 1 of 1

INSERVICE DISCREPANCY REPORT ( I D R )

IDR # : 01-07 Date: 5/2/2001 ,

Component: Vent He- r Location: Drvwell, Mechanical Design Engineering Evaluation:

  • % de -/ewe9 + cd-+ &$

Disposition/Regair:

IS1 Program Coordinator: +&e&?& Date: ?f+@

Repair Effort:

Reference Document: PA Repair Completion Date: Nd Service Induced : YES &- NO -BY: Date: ~ & i [

Sample Expansion Required: YES - NO )G BY: ate:

Sample Expansion:

Reinspection Required: YES - NO L BY: @

Subsequent Inspection Required: Yes - NO &BY:

  • IS1 Supervisor Notified:

I S 1 Program Coordinator: & D a t e : 5-/7/./

Reinspection Completed Satisfactorily:

IS1 Supervisor: &A Date: /4 5 5 - 1 IDR Closed:

IS1 Program Coordinator: i?i&%rw2 Date:

VYAPF 4027.01 AP 4027 Rev. 4 Page 1 of 1

r Data Sheet No: 80 Y 7 " 03 Work Order No.: 00' 5037 Vermont Yankee Procedure NolRev.: Rdq? 40 .

Visual Examination Report Form for General Visual (IWE) Page I of 9 Date: < / l / b /

Reviewer: - /v/3 Date /i4 VYNEF 8047.06 NE $047 Original Page t of 1 i

x b

Vermont Yankee Visual Examination Report Form for General Visual {IWE) 7 Component Visual Aids Photo Sketch Method 3 Binoculars qYNone @ None @ Direct &&&

3 Mirror 0 Attached r) Attached 0 Remote

!6 Light Source I Examination Location Description/Remarks Remote Examination CondifionslEquipment Remarks 3 6' Scale 7 Other

~

3xamination Results, Details and Comments:

Date 4Nk 0 ate VYNEF 8047,06 NE 8047 Original Page I of 1

VERMONT YANKEE TECHNICAL EVALUATION DOCUMEWATLON Technical Evaluation No. 20016 2 5 Tile: EVALUATION OF ASME SECTION XI - IWE FINDINGS FOR IDR 01-07 & IDR 0198 El QA (SafetyCIass, OQA. or Vital Fire) 0 Non QA (Non-Safety) (Check One}

Backsround This T.E. evaluates findinas from the IWE inspections of the vent header and vent Pipe bowls in the VY primaw containment. Specificalivaddressed are Inservice Discrepancv R ~ D o ft~ DRl ~s Nos. 01-07 and 01-08, design inputs (D1)I& 2.

Visual Inspections are performed on the VY primary containment in accordance with the American Society of Mechanical Engineers (ASME) Code Section Xi,Subsection IWE. The purpose of the inspections is to identify degradation of coatings and metal waJl loss to insure the continued structural integrity of the primary containment. The inspectors use a pre-evaluated acceptance criteria, 01 (31,to screen inspection results. The pre-evaluated criteria is based on VY calculation VYC-1032, Rev.1, DI (4), it serves as a threshold for further evaluation of the results by Design Engineering.

IDR 01-07 identifiesareas of general pitting and general corrosion in the vent header and the vent pipe bowls. DI (3) requires any indications adjacent to the vent header mitre joints, downcomer intersections, and vent pipe/header intersections be forwarded to Design Engineering for evaluation.

IDR 01-08 identifies corrosion on the internal surfaces of all (8) ofthe X-207 penetrations.

These penetrations were the !ow point drain in the bottom of each vent pipe bowl. Dl's (3)& (4) do not specifically address corrosion in the X-207 penetrations. The findings were forwarded to Design Engineering for evaluation.

Discussion I DR 01-07 1DR 01-07 identifies areas of general pitting and general corrosion in the vent header and the vent pipe bowls. A summary of the findings from IDR 01-07 is attached to this TE as Table 1 I As indicated on page 1 of 9 of Data Sheet No. 8047-01-031, the pitting areas identified have a minimum separation of (3) pit diameters. Areas identified with local pitting in the vent pipe bowls and in the vent header within 4 inches of the vent pipeheader intersections require an evaluation by Design Engineering. This TE will evaluate the findings shown in Table 1 against the acceptance criteria contained in DI(4).

As shown in Table 1, localized pitting was found in the lower portions of all (8)vent pipe bowis.

The areas of pitting correspond to zones 1 and 3 as shown in Figure 27 in Attachment A of VYC-1032,Rev. 1, Di (4). Permissible size indications for these zones are given in Figures 28 and 30 from D1(4>for zones 1 and 3 respectively. The limiting zone is zone 1. All pitting in the vent pipe bowls will be evahted using an enveloping comparison for zone I.From DI (3), a pit is

, WAPF 6045.02 Ap604S.02 Qriginal Page 1 of 6

W Technical evaluation No. TE 2001-0025 defined as a small area of surface corrosion less than 0.5 inch in diameter.

To envelop pitting found in the vent pipe bowls, the allowable depth of a 1 inch diameter surface indication wiil be compared against the largest measured pit depth from Table 1, Note that the areas of localized pitting shown in Table 1 only define the areas of pitting, not a zone of wall loss. From Figure 28, for a 1 inch diameter indication an allowable depth is greater than 0.10 inch. From Table 1 the maximum pit depth for the vent pipe bowls is 0.042 inches in X-5F.

Therefore all observed pitting in the vent pipe bowls is acceptable.

To envelop pitting found in the vent header, the same approach as for the vent pipe bowls will be used. Since the pitting is adjacent to the vent pipe intersection, Figure 30 for zone 3 will be used, From Figure 30; for a 1 inch diameter indication, an allowable depth is greater than 0.12 inch. From Table 1 the maximum pit depth for the vent header is 0.042 inches adjacent to X-5F.

Therefore all observed pitting in the vent header is acceptable.

The standing water found in the in the bottom of the bowl at X-5Halong with any other standing water accumulated in the other bowls during this refueling outage will be removed prior to drywell closeout per 5/4/01 telecon with B.Tietze, VY Facilities Supervisor.

1DR 01-08 IDR 01-08 identifies corrosion on the internal surfaces of all (8) of the X-207 penetrations, X-207 A to X-207H. Dl's (3) & (4) do not specifically address corrosion in the X-207 penetrations. The results were fowarded to Design Engineering for evaluation.

Each of these penetrations was the low point drain in the bottom of each vent pipe bowl. The original design of the X-207 penetration was a 1 inch nominal pipe which extended from the bottom ofthe vent pipe bowl down to an elevation below the Torus water level. These lines were removed and the pipe stubs were capped during the Torus Mark I Program Modifications under EDCR 80-11, Details a r e shown on VY drawings No. 6202-213 and 5920-9152,Dl's (6) &

(7).

Specific calculations for required wall thickness for the X-207 penetration are not contained in the original design analysis report, Dt (5). Due to the small size of the penetration (less than 2 inch nominal) no additional reinforcement was required by the ASME Code. Drawing No. 6202-213 shows the construction details for the penetration. The penetration is a 1 inch diameter schedule 80 pipe attached to the vent pipe head using a full penetration weld and a reinforcing fillet weld. The thinnest section is the wail of the 1 inch diameter pipe stub. Using the sizing requirements from the original design code, the required thickness for pressure and applied loads wiII be determined. This will be compared against the piping wall thickness with the estimated waIl loss from IDR 01-08 as shown on Data Sheet No. 8047-01-32.

From Dl (6),the pipe is 7 inch Sch. 80 seamless pipe A333 Gr.1, with a n outside diameter of 1.315inches, and a nominal thickness of 0.179 inch. The material ultimate strength is 55 KSi.

and the code allowable stress is 13.7Ksi. The minimum installed thickness of the pipe including the +/- 12.5%manufacturing tolerance is 0.157 inch. The effective throat of the 3/16fillet weld on the cap is .707{3/16) = 0.133 inch.

WAPF 6045.02-Ap6045.02 original Page 2 of 6

VY Technical evafmtiun No. TE 2001-0025 From ASME 111 & Vllt, DI (8),the required thickness for the 56 Psi design pressure (conservative considering this is an internal component) is taken from UG-27 of ASME VJII.

With P=56. Psi., R= 1.315/2= .658inch, & SE 43,700.Psi.:

PR , 't = 56'(0*658) = 0.0027 inch.

Circumferential Stress: t=

SE- 0.6P 13700.-0.6(56)

Longitudinal Stress: t= PR , t= 56'(0'658) =Z 0.001 3 inch.

2SE -F 0.4P 2(13700.)f 0.4(56)

Given the cantilever configuration and the small size of the stub, there are minimal loads on the stub, Using a 1.0% increase to account for rnisc. loads etc., the required wall thickness for the pipe will be taken as 0.003inch.

The minimum wall thickness including the 0.025 inch estimated wall ioss from Data Sheet No.

8047-01-32, is (0.157-.025)= 0.132 inch. This is significantly greater than the 0.003 inch required wall thickness.

AssurnDtionsfOpen items NONE Material Reauirementsflrnptementation Instructions NONE Conclusions 1DR 01-07:

The localized shallow pitting found in the bottom interior surfaces of the vent header and vent pipe bowls has been evaluated against the D1 (4) acceptance criteria and found acceptable.

The preparer of this T.E.accompanied the !WE examiners on this inspection. The interior condition of the vent header appears essentially the same as observed on a pre-IW E walkdown performed on 9/23/93. During the 1993 refueling outage the vent header was cleaned and a protective coating was applied to the bottom of each bowl and at stiffener plate locations at the downcomers. These coatings are still intact. The extent of light surface corrosion and local pitting appears about the same as was observed in 1993. This indicates that most of the pitting occurred prior to 1993, and that the mechanism is not currently aggressive. Based on this, no augmented inspections would be recommended.

IDR 01-08 The estimated wall joss in each of the X-207 penetrations has been conservatbely evaluated WAPF 6045XQ *

~ ~ 6 0 4 5 . 0Original 2

Page 3 of 6

W Technical evaluation No. TE 2001-0025 against code requirements and the reamining wall is significantly greater than the code required wall thickness.

The significant margin to code minimum wall thickness and the low expected rate of gakanic corrosion in the inerted containment during operation,would support that no augmented inspections would be recommended at this time.

Recommendations

1. The ZOO1 refueling outage Data Sheet 8047-01-031should be used as a baseline for the next scheduled !WE inspection of the vent header interior.
2. The next scheduled IWE visual inspection of the exterior of the vent pipe should include a specific note to check the exterior condition of the X-207 stubs.

Approvals/Ciosea ut e and provide signature/date.,l CE Independent Reviewer Department Manager Closeout (AN actions that were recommended by the TE and accepted by management have been initiated and any identified open ifems have been dispositioned.)

/ CE (signature) {date)

Aftachments A. Table I: Summary of Vent Header IWE Findings (1 Page}

6. VY Insetvice Discrepancy Report (IDR) No. 01-07 for Vent Header, dated 5/2/01. -1WE Data Sheet No. 8047-01-031. ( 10 Pages }

C. VY Inservice Discrepancy Report (IDR) No, 01-08 for X 207 A-H , dated 5/2/01. - IWE Data Sheet No. 8047-01-032.( 2 Pages)

WAPF 6045.02 Ap6045.02 Original Page 4 of 6

TECHNICAL EVALUATION DATABASE lNPUT TE 2001-025 Page 5 of 6 TE NO. 2001-025 TE

Title:

EVALUATION OF ASME SECTION XI - IW E FINDINGS FOR IDR 01-07& IDR 01-08 Keywords: Torus, ASME Section XI, IWE, Vent Pipe. Vent Header 1

  1. I DocumentTitle (including Rev. No. and Date, if appkable) 1 W Inservice Discrepancy Report (IOR) No. 01-07 for Vent Header, dated 32/01. (!WE Data Sheet No.

8047-01-031) 2 W Inservice Discrepancy Report (IDR) No.01-08for X 207 A-H ,dated 5/2/01. (IW E Data Sheet No.

8047-01-032) 3 W Design Engineering Memo: J.C.Fitzpatrick to J.H.Callaghan, subject: Pre-EvaluatedAcceptance Criteria for Primary ContainmentASME XI IWE Inspections, VYM 99/112, dated December 7,1999.

4 VY Calculation No. WG-1032, Rev.l Torus Shell & Vent System Thickness Requirements.

5 Certified Stress Report, ,Vernon - II, Vermont Yankee Project Containment Vessel, No. 9-6202-11, October 29,7968,by Chicago 8ridge & Iron- Oak Brook Engineering.

6 -

VY Drawing No. 6202-213, Rev 0.C8&I Drawing for Vent tine Header Intersection.

7 VY Drawing No. 5920-9152, Rev. 0,CB&! drawing for Modifications to Vent Header Drain Line 8 ASME Section 111 Nuclear Vessels, ?965 (with Winter 1965 Addenda) and ASME Section Vlll Unfired Pressure Vessefs ,1965.

I NONE 1

r # Reference Title (including Rev. No. and Date, if applicable}

9 ANSI 836.10-1979 Welded and Seamless Wrought Steel Pipe.

Data Entered inlo Database 1 Entry Verified I Signature Date Signature Date VYAPF 6045.03 .

AP 6045 origw Page 1of 1

-- 1--- -

TECHNlCAL EVALUATION REVIEW TE NO. 2001-025Pg 6 Of 6 TE#: 7001-025 Required Date: Y / Reviewer Assigned: h/-

Titte: EVALUATION OF ASME SEC'IWN XI - !WEFINDINGS FOR 1DR 01-07& IDR 01-08 Cornments: Resolution:

n/ahlE

  • I

/Oat$

to your area of expertise.

2, Verify Depattment Procedures, Program Inpuk. and output documents are appropriately addressed,

3. Meetings of discussions lo resolve questions and mmmenls are encouraged.
4. Resolution by telecon is acceptable and should be noted as such.
5. Make comments spaclllc, and avoid generalizations and queslions.
6. Lf no comments indicalo 'None"
7. Request Management asslstance if resolution can not be achieved.
8. Roturn all comments to Ihe CE by raquired date or request an edenslon.

VYAPF 6045.04 AP 6045 Orighal Page 1 of 1

TABLE 1 Summary of Vent Header IWE Findings Vent Pipe Findings D.I. (4) Vent Header Findings Bowl 63 Figure 27 between Zone{s)

X-5A Light scattered pitting at bottom of interior I& 3 X-5A ti X-55 Scattered pitting bottom interior surface adjacent to X-5A vent pipe surface adjacent to vent header A-6 intersection, depfh 0.015 intersection, ma. depth 0.035 X-56 General surface corrosion, no significant 3 X-56 & X-5C General surface corrosion, no significant metal loss. Scattered metal loss. pitting bottom interior surface adjacent to X-5B vent pipe intersection, depth 0.026 x-5c General surface corrosion, no significant 3 X-5C & X-5D General surface corrosion 1x1bottom interior surface, no significant metal loss with light scattered pitting at metal loss. Scattered pitting bottom interior surface adjacent to X-botlom of interior surface adjacent to vent header B-C intersectlon, depth 0.016.

5D vent pipe intersection,max. depth 0.025 X-5D General surface corrosion, no significant 1 X-5D & X-5E light general surface corrosion, no significant metal loss. Light metal loss with light scattered pitting at pitting bottom interior surface adjacent to vent pipe intersections.At bottom of interior surface adjacent to vent header C-D intersection, depth - 0.009 X-5D max. depth 0.009,at X-5E ma.depth 0.010. -

X-5E Light general surface corrosion, no significant 3 X-5E & X-5F General surface corrosion, no significant metal loss. Scattered metal loss. -

pittjng at X-5E vent pipe intersection, m a . depth 0.031over area size 2 by 3. Scattered pitting bottom interior surface adjacent to vent pipe X-5F, depth 0.042.

X-5F Scattered pitting at bottom of interior surface 3 X-5F & X-5G General surface corrosion. no significant metal loss. Scattered adjacent to vent header intersections:E-F, pitting at X-5G vent pipe intersection, Max. depth 0.025.

X-5G depth 0.042, and at F-G, depth 0.025, General corrosion and scattered pitting at 1,3 X-5G & X-5H General surface corrosion, no significant metal loss. Scattered bottom of interior surface adjacent to vent pitting at X-5G vent pips intersection, m a . depth 0.010*. Scattered pitting at X-5H vent pipe intersection,m a . depth 0.035*

approximate area 9bv 9.

0.010 X-5H Scattered pitting at bottom of interior surface 3 XSM & X-5A General surface corrosion on bottom interior surface, no significant adjacent to G-H vent header Intersection, metat loss.

m a depth - 0.025 area size 9x 14.

significantamount of water in bottom of bowl.

ATACHMENT A to T.E. NO. 2001-025 Page 1 of 1

Performed By: Date:

Disposition/Repair:

IS1 Program Coordinator: Date:.

Repair Effort:

Reference Document:

Repair Completion D a t e :

Service Induced: YES - NO - BY: ___ Date:.

sample Expansion Required: YES _u NO - BY: Date: .-

sample Expansion :

,-__ ~~- ~ ~~

IS1 Program Coordinator: Date :

Reinspection Required: YES NO 7 BY :

Subsequent Inspection Required: YES NO _c BY:.

rsI: Supervisor Notified:

I S 1 Program Coordinator: D a t e:

Reinspection Completed Satisfactorily:

IS1 Supervisor: Date:

IDR Closed:

Is1 Program Coordinator: Date:

VYAPF 4027.01 AP 4027 Rev. 4-Page 1 of 1

I- #

Data Sheet No: BO J? I - 0 3f Work Order NO.: 00 - 50 3 7 b Vermont Yankee Procedure NolRev.:. 8OJ7 40 .

Visual Examination General Visual Report (IWE) Form for Page 1 of 9 -Date:  ?/?/dl I f < Component CQmponent 10: f ~ *H+~ Q ~ A > System: -br+ 4 Drawing NolRev.: 62-02. 2-06 Location: tQtv ~3 c U Visual Aids Photo Sketch Method 0 Binoculars None a None IZf Direct ( 5

  • r r J 4 13 Attached 8 p35

@ Attached 0 Remote 0 Mirror Light Source Examinatian Location Oescription/Remarks Rem& Examination ConditionslEqulpmeot Remark 0 6 Scale $+irp.ior S,IP f6e aF 0 Other V.Acct # d a r rJh ination Results, Details and Comments:

t

\

x

.- XNSERVICE DISCREPANCY REPORT (IDR)

IDR #: QT-OS.

Date: 5La/20Q1 Component : X-207A - y Location: D m I D-4 XSI Supervisor: Date:

System Operability Affected: YES NO BY: BN Date:

Shift Supervisor Notified: YES NO L B Y :Date: d4/

Event Report Initiated: YES - NO L B Y : . H Date: flab/

Mechanical Design Engineering Evah.IatiOn:,

c Performed By:

. Date:

Disposition/Repair:,

IS1 Program Coordinator:, Date :

Repair E f f o r t :

Reference Document:

Repair Completion D a t e : .

Semice Induced: YES __ NO 7 BY: Date: .-

Sample Expansion Required: YES __. NO -BY: Date:,

Sample Expansion:

IS1 Program Coordinator: Date:

Reinspection Required: YES - NO -BY:

SubsecpenL Inspection Required: YES - NO -BY:

XSI Supervisor Notified:

I S 1 Program Coordinator: Date:

Reinspection Completed Satisfactorily:

ISI S u p e m i s a x : Date:

IDR Closed:

Date:

VYAFF 4 0 2 7 . 0 1 AP 4027 Rev. 4 .

Page 3. of 1

37 Vermont Yankee Work Order No.:

Procedure NolRev.:

00

  • 5 0

%f'? 4 0 Visual Examination Report Form for General

-~

Visual (fWE) Page I of / Date: 51/&

Cornaonent Drawing Nomev.: 5920- 4 ~ '

Visual Aids 0 Binocdars yffone Photo I &NoneSketch Direct +&d Method 0 Mirror I3 Attached 0 Attached D Remote Light Source barnination Location Descciptian/Rernarks Remote Examination ConditionslEquipment Remarks I3 6' Scale 2...t.rw&4-&w 6s-I Examination Results, Details and Comments:

Pcs Examiner: L e v e l 4 4 Dale f l l / d I Examiner: Lev el A?!&, Date Reviewer: *A Date Lf/./o/

Reviewer: pH Date @

AMI: Date

IJSERVICE DISCREPAXCY =PORT (IDR)

IDR #:  !&dB Date: 5/2/2001 I Component: - d Location: DrYwell L

IS1 Supervisor: D*d Date :

System Operability Affected: YES - NO j c B Y : BOcyD a t e : dh Shift Supervisor Notified: YES - NO -BY: )C LMZ D a t e : dJ-Event Report Initiated: YES - NO A B Y : Date: Q++&

Mechanical Design Engineering Evaluation:

Performed By:

Disposition/Repair:

IS1 Program Coordinator: Date: <I5/&

Repair Effort:

Reference Document: MFJ Repair Completion Date: A/!!

Service Induced: YES -E..,. NO BY: w Date: d &

Sample Expansion Required: YES - -

NO )r BY: e D a t e :

Sample Expansion:

, e w 2Iw.d d+fz+-L . &e H h2 - d

/.mz J&Z# .a&?b r n -/%72& #

1 IS1 Program Coordinator:

&&a&A Date: </d/

Reinspection Required: YES - NO &BY:

Subsequent Inspection Required: YES - NO L B Y : m IS1 Supervisor Notified:

IS1 Program Coordinator: *& Date: r?%k Reinspection Completed Satisfactorily:

IsI Supervisor: BW - w Date: s'/s/l/

IDR Closed:

I S 1 Program Coordinator: mu& Date:

VYAPF 4027.01 AP 4027 R e v . 4 -

Page 1 of 1

I Data Sheet No: 47-01 3%- -

Work Order No.: 00

  • 5037 Vermont Yankee ProcduraNomev.: 8bf7 40 Visual Examination Report Form for General Visual (IWEI Page / of 1 Date: 5/it/u Component Compooent 10: X-AQ? A , 4. C ,
  • h . G
  • f i6 , L L L d Visual Aids photo Sketch I Method 0 Binoculars Vffone None IIDirect o mimar I Remote

)!f Light Source Examination Location Description/Remarks M o t e Examination CanditionsEquiprnent Remarks 0 6 Scale >?&PA& kkhm f i d m i f.

Date @

M N E F 8047.06 NE 8047 Original Page 1 of 1

VERMONT YANKEE TECHNICAL EVALUATLON DOCUMENTATION Technical Evaluation No. 2001-025 I

Title:

EVALUATION OF ASME SECTION XI - IWE FlNDfNGSFOR IDR 01-07 & IDR 01-08 El QA (Safety Class, M I A , or Vital Fire) El Non QA (Non-Safety} (Check One)

Backaround This T.E. evaluates findinas from the IWEjnspections of the vent header and vent pipe bowls in the VY priman/ containment. Specifically addressed are Inservice Discrepancv Reoorts (IDR)

Nos. 01-07 and 01-08, desiqn inouts (Dl) I& 2.

Visual Inspections are performed on the VY primary containment in accordance with the American Society of Mechanical Engineers (ASME) Code Section XI, Subsection IWE. The purpose of the inspections is to identify degradation of coatings and metal wall loss to- insure fhe continued structural integrity of the primary containment. The inspectors use a pre-evaluated acceptance criteria, D1 (3)to screen inspection results. The pre-evaluatedcriteria is based on VY calculation VYC-1032,Rev.1 , Df (4) it serves as a threshold for further evaluation of the results by Design Engineering.

IDR 01-07 identifies areas of general pitting and general corrosion in the vent header and the vent pipe bowls. Dt (3) requires any indications adjacent to the vent header mitre joints, downcomer intersections, and vent pipdheader intersections be forwarded to Design Engineering for evaluation.

IDR 01-08 identjfies corrosion on the internal surfaces of all (8) of the X-207 penetrations.

These penetrations were the low point drain in the bottom of each vent pipe bowl. Dls (3)& (4) do not specifically address corrosion in the X-207 penetrations. The findings were forwarded to Design Engineeringfor evaluation.

Discussion IDR 01-07 IDR 01-07 identifies areas of general pitting and general corrosion in the vent header and the vent pipe bowls. A summary of the findings from IDR 01-07 is attached to this TE as Table 1.

As indicated on page 1 of 9 of Data Sheet No. 8047-01-031, the pitting areas identified have a minimum separation of 13) pit diameters. Areas identified with local pitting in the vent pipe bowls and in the vent header within 4 inches of the vent pipdheader intersections require an evaluation by Design Engineering. This TE will evaluate the findings shown in Table 1 against the acceptance criteria contained in DI (4).

As shown in Table I , localized pitting was found in the lower portions of all (8) vent pipe bowls.

The areas of pitting correspond to zmes 1 and 3 as shown in Figure 27 in Attachment A of Vyc-1032, Rev. 1, DI (4). Permissible size indications for these zones are given in Figures 28 and 30 from DI (4) for zones 1 and 3 respectively. The limiting zone is zone I. AI[ pitting in the vent pipe bowls will be evahated using an enveloping comparison for zone I.From DI (31,a pit is VYAPF 6045.02 Ap6045.02 Original-Page I o f 6

VY Technical evaluation No. TE 2001-0025 defined as a small area of surface corrosion less than 0.5 inch in diameter.

To envelop pitting found in the vent pipe bowls, the allowable depth of a I inch diameter surface indication will be compared against the largest measured pit depth from Table 1. Note that the areas of localized pitting shown in Table 1 only define the areas of pitting, not a zone of wall loss. From Figure 28,for a 1 inch diameter indication an allowable depth is greater than 0.10 inch. From Table 1 the maximum pit depth for the vent pipe bowls is 0.042 inches in X-5F.

Therefore all observed pitting in the vent pipe bowls is acceptabte.

To envelop pitting found in the vent header, the same approach as forthe vent pipe bowls will be used. Since the pitting is adjacent to the ventpipe intersection, Figure 30 for zone 3 will b e used. From Figure 30; for a 1 inch diameter indication, an allowable depth is greater than 0.12 inch. From Table 1 the maximum pit depth for the vent header is 0.042 inches adjacent to X-5F.

Therefore all observed pitting in the vent header Is acceptable.

The standing water found in the in the bottom of the bowl at X-5H dong with any other standing water accumulated in the other bowls during this refueling outage will be removed prior to drywell closeout per 5/4/01 telecon with 8.Tietze, VY Facilities Supervisor.

IDR 01-08 IDR 01-08identifies corrosion on the internal surfaces of all (8) of the X-207 penetrations, X-207 A to X-207H. Dl's (3) & (4) do not specifically address corrosion in the X-207 penetrations. The results were forwarded to Design Engineering for evaluation.

Each of these penetrations was the low point drain in the bottom of each vent pipe bowl. The original design of the X-207penetration was a Iinch nominal pipe which extended from the bottom of the vent pipe bowl down to an elevation below the Torus water level. These lines were removed and the pipe stubs were capped during the Torus Mark I Program Modifications under EDCR 80-1I . Details are shown on VY drawings No. 6202-213 and 5920-9152, Dl's (6)&

(7)*

Specific calculationsfor required wall thickness for the X-207 penetration are not contained in the original design analysis report, D1 (5).Due to the small size of the penetration (less than 2 inch nominal) no additional reinforcement was required by the ASME Code. Drawing No. 6202-213 shows the construction details for the penetration. The penetration is a 1 inch diameter schedule 80 pipe attached to the vent pipe head using a full penetration weld and a reinforcing fillet weld. The thhinnesf section is .the wall of the 1 inch diameter pipe stub. Using the sizing requirements from the original design code, the required thickness for pressure and applied loads will be determined. This will be compared against the piping wall thickness with the estimated wall loss from IDR 01-08 as shown on Data Sheet No. 8047-01-32.

From DI (6),the pipe is 1 inch Sch. 80 seamless pipe A333 Gr. I, with an outside diameter of I .315inches, and a nominal thickness of 0.1 79 inch. The material ultimate strength is 55 Ksi.

and the code allowable stress is 13.7 Ksi. The minimum installed thickness of the pipe including the 4- 12.5% manufacturingtolerance is 0.157 inch. The effective throat of the 3/16 fillet weld on the cap is .707(3/16)= 0.133inch.

VYAPF 6045.02

  • Ap6045.02 Origlnaf Page 2 of 6

W Technical evaluation No. TE 2001-0025 From ASME 111 & Vill, Dl (31,the required thickness forthe 56 Psi design pressure {consewative considering this is an internal component) is taken from UG-27 of ASM Vlll.

With P=56. Psi., R= 1.315 / 2 = ,658 inch, & SE =13,700.Psi.:

PR , t= 56'(0'658) = 0.0027 inch.

Circumferential Stress: t=

SE - 0.6P 13700.- 0.6(56)

PR 56.(0.658)

Longitudinal Stress: t= , t= = 0.001 3 inch.

2SE + 0.4P 2(137OO.)f 0.4(56)

Given the cantilever configuration and the small size of the stub, there are minimal loads on the stub. Using a 10%increase to account for misc. Ioads etc., the required wall thickness for the pipe will be taken as 0.003 inch.

The minimum wall thickness including the 0.025 inch estimated wall loss from Data Sheet No.

8047-01-32, is (0.157-.025) = 0.132 inch. This is significantly greater than the 0.003 inch required wall thickness, AssumDtionslODen Items NONE Materia! ReauirernentsflmPlementationInstructions NONE Conclusions IDR 01-07:

The localized shallow pitting found in the bottom interior surfaces of the vent header and vent pipe bowls has been evaluated against the D1 (4) acceptance criteria and found acceptable.

The preparer of this T.E. accompanied the IWE examiners on this inspection. The interior condition of the vent header appears essentially the same as observed on a pre-IWE walkdown performed on 9/23/93. During the 1993 refueling outage the vent header was cleaned and a protective coating was applied to the bottom of each bowl and at stiffener plate locations at the downcomers. These coatings are still intact. The extent of light surface corrosion a n d local pitting appears about the same as was observed in 1993. This indicates that most of the pitling occurred prior to 1993, and that the mechanism is not currently aggressive. Based on this, no augmented inspections would be recommended.

IDR 01-08 The estimated wall toss in each of the X-207 penetrations has been conservatively evaluated WAPF 6045.02

  • Ap6045.02 Original Page 3 of 6

VY Technical evaluation No. TE 2001-0025 against code requirements and the reamining wall is significantly greater than the code required wall thickness.

The slgnificant margin to code minimum wall thickness and the low expected rate of galvanic corrosion in the inerted containment during operation,'would support that no augmented inspections would be recommended at this time.

recommendations 1, The 2001 refueling outage Data Sheet 8047-01-031 should be used as a baseline forthe next scheduled fWE inspection of the vent header interior.

2. The next scheduled IWE visual inspection of the exterior of ihe vent pipe should include a specific note to check the exterior condition of the X-207 stubs.

Ap provaldCloseout arne and provide signaturddafe.)

CE Independent Reviewer Department Manager .

Closeout (All actions that were recommended by the TE and accepted by management have been initiated and any identified open iferns have been disposifioned.)

I CE (signature) (date)

Attachments A. Table 1: Summary of Vent Header IWE Findings (1 Page)

B. VY Inservice Discrepancy Report (IDR) No. 01-07for Vent Header, dated 5/2/01. -IWE Data Sheet No.8047-01-031.( 10 Pages }

C. VY Inservice Discrepancy Report (IDR) No. 01-08for X 207 A-H , dated 5/2/01. - IWE Data Sheet No. 8047-01-032.( 2 Pages}

VYAPF66045.02 .

~p6045.02original Page 4 of 6

TECHNICAL EVALUATION DATABASE lNPUT TE 2001-025 Page 5 of 6 TE NO. 2001-025 TE

Title:

EVALUATION OF ASME SECTION XI - IWE FiNDlNGS FOR iDR 01-07& IDR 01-08 Keywords: Torus, ASME Section Xi. IWE, Vent Pioe. Vent Header

  1. Document Title (including Rev. No. and Date, if applicable) 1 W Inservice Discrepancy Report (!OR)No.01-07for Vent Header, dated 5/2/07. ([WEData Sheet No.

1 8047-01-031) 2 I W Inservice Discrepancy Report (IDR) No. 01-08for X 207 A-H ,dated 5/2/01. (!WE Data Sheet No.

8047-01-032) 3 W Design Engineering Memo:J.C.F&patrick to J.H.Callaghan,subject: Pre-Evaluated Acceptance Criteria for Primary Containment ASME XI IWE Inspections, VYM 99/112, dated December 7,1999.

4 W Calculation No. WC-I 032,Rev.1 I' Torus SheH & Vent System Thickness Requirements.

5 -

Certified Stress Report, ,Vernon It, Vermont Yankee Project Containment Vessel, No. 9-6202-11, October 29,1968, by Chicago Bridge & Iron Oak Brook Engineering.

6 -

W Drawing No. 6202-213,Rev 0. CB&! Drawing for Vent Line Header Intersection.

7 VY Drawing No. 5920-9152,Rev. 0, CB&l drawing for Modifications to Vent Header Drain Line 8 ASME Section Ill Nuclear Vessels, 1965 (with Winter 1965 Addenda) and ASME Section VHI Unfired Pressure Vessels ,1965.

I- I I Desiqn Output Documents -ThefolIowing documents are impacted by this TE.

I # ] Document Title 1 1

General References I

Data Entered into Database t Entry Verified I Signature Date Signature Date WAPF 6045.Q3 AP 6045 Original Page 1 of 1

TECHNICAL EVALUATION REVIEW TE NO. 2001-025 Pg 6 of 6

-025 Required Date: M d 'J5. { Reviewer Assigned: hf-J, DdFFY TE#: 2 0 0 1

Title:

VALUPTI0N OF ASM E SECTION XI - IWE FINDINGS FOR IDR 07-07 h IDR 01-08 Resolutlon:

Comments:

dohlE

6. Ifno comments Indicate "None"
7. Request Management assistance if resolutlon can not be achieved.
8. Return all comments to heCE by requlred date or request an eaenslon.

VYAPF 6045.04 AP 6045 Original Page 1 of 1

TABLE 1 Summary of Vent Header IWE Findings Vent Pipe Findings D.I. (4) Vent Keader Findings Bowl 0 Figure 27 between Zona(s) I X-584 Light scattered pitting at bottom of interior I& 3 X-5A & X-56 Scattered pitting bottom interior surface adjacent to X-5A vent pipe surface adjacent to vent header A-6 -

intersection, max. depth 0.035" intersection, depth 0.015" -X-58 ti X - S General surface corrosion, no Significant metal loss. Scattered X-50 General surface corrosion, no significant 3 metal loss. pitting bottom interior surface adjacent to X-58 vent pipe intersection, depth 0.026" x-5c General surface corrosion, no significant 3 X-5C & X-5D General surface corrosion on bottom interior surface, no significant melal loss with light scattered pitting at metal loss. Scattered pitting bottom interior surface adjacent to X-bottom of interior surface adjacent to vent header 8-C intersection, depth 0.056".

50 vent pipe intersection, m a . depth 0.025" x-50 General surlace corrosion, no significant 1 X-5D & X-5E Light general surfacecorrosion, no significant metal loss. Light metai loss wrth light scattered pitting at pitting bottom interior surface adjacent to vent pipe Intersections.At bottom of interior surface adjacent to vent I header C-Dintersection. depth - 0.009" X-50 max. depth 0.009",at X-5E rnax:depth - 0.010".

1 Light general surface corrosion, no significant X-5E & X-5F General surface corrosion, no significant metal loss. Scattered X-5E 3 X-5F I metal loss.

Scattered pitting at bottom of interior surface 3 X-5F 8 X-5G pitting at X-5E vent pipe Intersection, max. depth 0.031"over area size 2" by 3'. Scattered pittingbottom interior surface adlacent to vent pipe X-5F, depfh 0.042" .

General surfacecorrosion, no significant metal loss. Scattered adjacent to vent header intersections: E-F, pitting at X-5G vent pipe intersection, m a . depth 0.025".

depth 0.042",and at F-GI depth 0.025 X-5G General corrosion and scattered pitting at 1,3 XSG & X-5M General surface corrosion, no significant metal loss. Scattered bottom of interior surface adjacent to vent pitting at X-5G vent pipe intersection, max. depth 0.010". Scattered ,

header intersections: F-G, rnax depth - pitting at X-5H vent pipe intersection, max. depth 0.035" 0.025" area size 9" x 1B I and at G-ti, depth - approximate area 9" by 9".

0.010" X-5H Scattered pitting at bottom of interior surface 3 X-5H & X-5A General surface corrosion on bottom interior surface, no significant adjacent to G-M vent header intersection, metal loss.

max depth 0.025"area size 9"x 14";

Significant amount of water in bottom of bowl.

ATACHMENT A to T.E. No. 2001-025 Page 1 of1

Dispositian/Repair:

IS1 Program Coordinator: Date : c _

Repair Effort:

Reference Document:

Repair Completion DYES Service Induced: ate: NO ___ BY: _e Date :

Sample Expansion Required: YES .___ NO ,- BY : Date:

Sample Expansion:

IS1 Program Coordinator: Date :

Reinspection Required:

Subsequent Inspection Required:

YES YES

- NO - , BY:

NO -. BY :

IS1 Supervisor Notified:

I S 1 Program Coordinator: Date:

Reinspection Completed Satisfactorily:

IS1 Supervisor: Date:

IDR Closed:

I S 1 Program Coordinator: D a t e :___L1 VYAPF 4027.01 AP 4027 Rev. 4 -

Page 1 of 1

Photo Sketch Method Visual Aids 3 Binoculars @ None CY None g pA9 ,= 0 Direct D Remote

& , 4 4 Reviewer: .w@ Date A  :

ANN: Date AUACHMENT

'3 a

0 og

\

x

.- INSERVICE DISCmPANCY REPORT (IDR)

IDR #: 01-08 Component: )I-207A -a Date:

Location: 3/2/2001 BYKAJ Mechanical Design Engineering Evaluation: *.

Performed

-, By: Date:

Disposition/Repair:

IS1 Program Coordinator: Date :

Repair Effort:

Reference Document:

Repair Completion Date:

Service Induced: YES - - NO BY : D a t e : ,-,

Sample Expansion Required: YES -NO -BY  : Date: -,

Sample Expansion:

ISI Program Coordinator: Date:

Reinspection Required: YES NO -BY  :

Subsequent Inspection Required: YES - -BY NO z IS1 Supervisor Notified:

fSI Program Coordinator: Date:

Reinspection Completed Satisfactorily:

IS1 Supervisor: Date :

I D R Closed:

Date:

VYAPF 4027.01 AP 4027 Rev. 4 .

Page I of 1

5037 Vermont Yankee Work Order No+ 00 Procedure Nomev.: %t/7 & 0 Visual Exam!nation Report Form for General Visual (IWE) Page I of / ate: s/i,/$

Component Reviewer: - /yp Qate 0 ANk Date VYNEF 8047.06 NE8047 Originaf Page 1 of 1

INSERVICE DISCREPANCY REPORT ( I D R )

IDR # : 01-09 Date: 05/07/01 I Component : P-18-lA R e c i r c . pump Location : Drvwell. 238 boltins. (OIA-N/W-lGA-m Discrepancy: Durincs VT-I. examination the followins was found: 1. The chrome rdate on the threads indicated on D w s . VYEM 5920-738 & 739 R / 1 amears to be,missfncr due to corrosion.

2. Evidence of leakase is indeterminate due to water l v i n s on t IS1 Supervisor: Date: -.-/.l/o/

System Operability Affected: Y E S - NO x- BY: Date: <h?

Shift Supervisor Notified: Y E S - NO BY: W Date: 5h!(

Event Report I n i t i a t e d : YES - NO -

x BY: -Date: </&

Mechanical Design Engineering Evaluation:--[ -t%&

Performed By:

Disposition/Repair:

I S 1 Program C o o r d i n a t o r : Bm?cd Date: 47573/

Repair E f f o r t :

Reference Document: /A Repair Completion Date: d/A n  ;

r ,r W (

Service Induced: YES NO BY: Date: gba-Oi Sample Expansion Required: YES - NO BY: e Date: - ~ W ~ l Sample Expansion:  % T E 2001- 633 [ R m e > m IS1 Program Coordinator: *dd Date: ,d/ ../J Reinspection Required: YES - NO J BY:(=$@

Subsequent Inspection Required: YES - NO f BY:*

IS1 Supervisor Notified:

IS1 Program Coordinator: Date: -.r./.7?/

Reinspection Completed Satisfactorily:

Is1 Supervisor: I.i/A Date:

IDR Closed:

IS1 Program Coordinator: Date: s//7k/

VYAPF 4027.01 .

AP 4027 Rev. 4 Page 1 of 1

Vermont Yankee Work Order No.: O/--/997-O 00 Visual Examination Report Form Procedure NdRev.: &&-BO 9.5 ,4?&9a /

VT-1, Bolting (Non-!WE)

Date 5-/ 7 - 0 / I I Experience Hours Credit:

VYNEF 8645.01 NE 8045 Rev. 1 Page 1 of 1

VERMONT YANKEE TECHNICAL EVALUATION DOCUMENTATION Technical Evaluation No. 2001434

Title:

EVALUATIONOF IS1 PROGRAM IDR NO. 01-09, P-18-1A REACTOR REClRC PUMP BOLTING El QA (Safety Class, OQA, or VW Fire) Non QA (Non-Safety) (Check One)

Backaround This T.E. evaluates findings from the ASME Section XI inspection of the Reactor Recirculation Pump,P-18-1A, cover to case cap screws as documented on Inservice Discrepancy Report. (IDR) No. 01-09 (Attachment A). The cap screws are 2-1/2 diameter 16" long, (Part No. 2-6) with washers (Part No. 2-5 )

as shown on W drawings 5920-738 & 5920-739, design inputs (D!) Nos. 2 & 3.

The 1st visual inspection of the pump cover to case bolting is documented on Data Sheet No. 804501-016, dated 5/5/01which is attached to the IDR. Recodable findings noted on the Data Sheet are:

1. Coating is missing.
2. Corrosion exists on portion of threads where they screw into the pump casing.
3. Water standing in scattered areas on top of casing. {could be from small bore piping above).

To assess the degree of corrosion at the bolt locations a walkdown of the bolts on both pumps was performedby Design EngineeringMIS (J.FitzpaWck & KBeardsley) on 5/9/01. Access to both pumps was facilitated by scaffolding erected for modifications to the attached RBCCW cooling lines.

The areas surrounding the bolt heads and washers on both pumps exhibit 8 light surface corrosion. The insulation on ihe attached RBCCW cooling lines was removedfor the piping modification, this permitted easy access to the cap screw heads and the surrounding areas. See the photos in attachment 6.The general surface corrosion may be the result of condensation from the exterior of the R3CCW tines or from water draining into this area during past replacementsof the pump seals. As shown in the photos in , corrosion by-products were observed on painted surfaces above the location of the cap screw heads. Other than the general surface corrosion there is no significant amount of additional corrosion evident at the cap screw head and washer interface.

The exposed threads on the cap screw at the pump casing coverbody interface are identified as having the chrome plating degraded and as exhibitingsome surface corrosion on the e w s e d threads. There appears to be minimal metal loss on the exposed threads. From DI 4, the ASME stress report forthe pumps, there is margin in the supplied bolt area over the required bolt area. This supplied margin ensures that the cap screws will perfom their design function and still meet ASME code requirementsfor allowable stress. The following quantifies this margin.

2-1/2" diameter cap screws , A193 Gr.67 2-1/2"-8N-2A, (DI 4)

From Table 8.2.10 in Marks Handbook (reference 5). Minor diameter = 2.343 inch From page 7 of the design stress report for the pump (DI 4), the totai bolt area required, Am,= 62.31 inches2 WAPF6045.02 Ap6045.02 Original Page 1 of 4

W Technical evaluation No. TE 2001-0034 The bok root diameter required to supply the total bolt area required, considering all bolts degraded is:

MinDiameter = J4xAreq =J4x62*31 = 2.27inch.

nl Gbolts nl Gbolts The allowable corroded thickness (lost metal) on each bolt is M( 2.343-2.27) = 0.0365, (approx 1/32).

Given that no significant metal loss was noted on the threads and the inert atmosphere in the containment during operation, corrosion is not expected to occur at a significant rate during future operation.

AssumDtionsJOoen Item2 NONE

~ le entationt structions NONE Conclusions The pumps casing cover/body bolting will perform its design function with the as-noted surface conditions.

Margin exists in the 2/12 diameter cap screws for future corrosion. No additional and/or augmented inspections other than planned IS1 are required.

Recommendations NONE ApprovalS(Close0ut(qrint nfind provide slgnature/date.)

Independent Reviewer Department Manager (signature) (date}

were recommended by the TE and accepted by rnaMgemen! have been initiated and any Mentified open items NONE REQUIRED

/ qdh!(tiate)

CE Attacbments A. IDR No. 01-09, for P-18-1A, Recirc. Pump Bolting. (01A-NNV-I 6 A - W ) , dated 5/7/01 (2 pages total)

8. Photographs of Recirc. Pump Casing Cover/Body Cap Screws (2 pages total)

VYAPF 6045.02 Ap6045.02 Original Page 2 of 4

TECHNICAL EVALUATION DATABASE INPUT TE 2003;034 Page 3 of4 TE No. 2001-034 TE Titfe: Evaluation of IS1 Proaram IDR No. 01-09,P-18-fA Reactor Recirc. PumD Boitinq Keywords: Purn~.Sottina. ASME Section XI, In-senrice I n s r n k n , P-18-1A

[ # I Design Output Doeuments The following documents are impacted by this TE.

Document Tile 1

-. NONE

    1. Reference T i e (including Rev. No.and Date, if applicable) 5 Marks Standard Handbook for Mechanlcal Engineers Ninth Edition, Q 1978, McGraw-Hill lnc.

Data Entered into Database / Enfry Verified /

Signature Date SQnature Date WAPF 6045.m AP 6045 W@nd Page I of 1

I TECHNICAL EVALUATION REVIEW TE NO. 2001-034 Pg 4 Of 4 TE #: .ZOO14 3 4 Required Date: Reviewer Assigned:

Comments: Resolution:

I s/%,

Date Notes and Requirements: DGE Signature &at6 '

1. Validate design Input appropriateness relative to your area of expertise.
2. Verify Department Procedures, Program inputs, and output documents are

. appropriately addressed.

3. Meetings or discussions to resolve questions and comments are encouraged.
4. 'Resolution by telecon Is acceptable and should be noted as such.

5, Make comments specific,and avoid gbneralizations and questlans.

6. If no comments indicate "None"
7. Request Management assistance if resolution can not be achieved.
8. . Return all comments to the CE by requlred date or request an extenston.

VYAPF 8045.04 AP 6045 Original Page 1 of 1

Data Sheet No: zde'-6r/-35?

Work Order No.: DO - 0 SQ3s Vermont Yankee Procedure NolRev.: 46 $0 1/7/M<'c~d Visual Examination Report Form for General Visual (IWE) Page I of / Date: h//&/bO' ./

7- Component U

Visual Aids Photo Sketch Method 0 Binoculars d o n e &ne E6rect 0 Mirror 0 Attached U Attached 0 Remote 04lght Source Examination Location DescriptianlRemarks Remote Examination ConditionslEquipmentRemarks 0 6" Scale &flu:& duaCAcI, e .I:

%+

0 Other Pl*.k&J:&Jx > O b A 3.b Level Date VYNEF 8047.06 NE 8047 Original Page 1 of 1

Vermont Yankee Procedure Nomev.: pp 70A \r/o .

Visual Examination Report Form for General Visual (1WE) Page I of I ~ate:I//L/cll t Visual Aids Photo Sketch Methad 0 Binocufars 1@ None 8 None @Direct bed&

13 Mirror 1CI Attached ~~ ~

10 Attached 10 Remote Light Source Examination Location DesctiptionlRemarks Remote Examination ConditionslEquipmentRemarks 0 6Scale 3 q J d Pw*(r&;-  !!/A 0 Other 4Y-3j 1 Examination Results, Details and Comments:

Examiner: p/A -~evel rc/A Date

,Reviewer: dh Date %

WNEF 8047.06 NE 8047 Original Page 1 of I

8 Data Sheet No: rdd - 6 v- 36 0 f Work Order No.: 0 0 - 0 0 5 0 35 Vermont Yankee Procedure NolRev.: @p702(t / O Visual Examination Report Form for General Visual (IWE) Page 1 of / Date: i//b,/o) I Component Component ID: X - S A 721r u &H System: 3- dcl/i Drawing NoFiev.: <?m- 4/ Location: c-2h&lj,& -Sd&.4caa/

I I Visual Aids Photo Sketch Method

@ Binoculars eP None None p Direct 6&4 (3 Mirror 0 Attached 0 Attached 10 Remote Light Source Examhation h a t i o n Description/Remarks Remote' Examination ConditionslEquipment Remarks 0 6" Scale 3 q - M Pede trcA1-tJks 1 &/+A 0 Other 1 Examination Results, Details and Comments:

WNEF 8047.06 NE8047 Original Page 1 of 1

Vermont Yankee Procedure Nomev.:  !?fly Q 2, f./O, Visual Examination Report Form for General Visual (IWE) Page 1 of 1 Date: l / f b ./Q, I r--

~

Component Component ID: x - 3 2, System: bfi, 4 Drawing No/Rev.: 5?Lo - q/ Location: 3,- 4q .

Visual Aids 0 Binocutars Qbhsone Photo 1 Sketch

()B None Method 9 Direct 644-t 0 Mirror 0 Attached 0 Attached U Remote I$ Light Source Examination Location DescriptionlRemarks Remote ExaminationCanditionslEquiprnent Remarks 113 6 Scale maminer: Level nc/R Date */R Reviewer: /fl Date h Reviewer:- Nh Date .J/A VYNEF 8047.06 .

NE 8047 Original Page 1 of 1 i

e Data Sheet No: z w d ..&v' 37/

Wofk Older No.: 00 4 00 50 35 Vermont Yankee Procedure Noiflev.: #?/ 7 d t? .

Visual Examination Report Form for General Visual (!WE) Page / of i Date:& 1 Component Component ID: x - Ab System: L c j d Drawing NolRev.: S92-d Location: ~ ~ f ~ ~ &A- ~ u4 c. v u C

-~ ~. __

I

~~

1

~

Visual Aids Photo Sketch Method 0 Binoculars WNone qP None ij3 Direct F* L-0 Mirror 0 Attached U Attached 0 Remote

~-

I)d tight Source Examination Location OescriptionlRemarks Remote Examination ConditionsfEquipment Remarks 0 6" Scale

&yocs. 44 Level .&$*'U&i Date f/l L,/dL Examiner: '14 Level d/A Date IJ/A Reviewer: 'h .Date '!

Reviewer: _#/!A

. Date .'lp VYNff 8047.06 NE 8047 Original Page 1 of 1 i

Vermont Yankee Procedure NolRev.: Pfl 70 29 10 .

Visual Examination Report Form for General Visual (!WE) Page 1 of I Date: !/[S/ol t Component Reviewer: 44 Reviewer: - #I4 Date ANII: D a t e s -

i v

VYNEF 8047.06 NE 8047 Original i Page 1 of 1

El.11 Drywell Paletration GV 1000/0 COMPLETED FROM INTERNAL RFO21 x-51 EX'FERNAL TO BE SCHEDULET, BEFORE OR DURING RMn2 (completed pre RFO 22)

E1.11 Drywen Penetration COMPLETED FROM NIXRNALRF021 x-52 EXTJ33AL. TO BE SCHEDULED BEFORE OR DURING RF022 (complded pre RFO 22)

EL11 Drywell Peamaticil COMPLETED FROM XNTERNAL RFO2 1 (INACCESSIBLE AREA X-lOOA m1-EXTERNAL TO BE SCHEDULED BEFORE OR DURING RFO22 (completed pre RFO 22)

El.ll Drywell Penetration COMPLETED FROMINTERNAL RF02X (JNACCESSJBLEAREA X-100B IDENTIFIED)

EXTERNAL TO BE SCHEDULED BEFORE OR DURING R F O n

@mpl"d pre RFO 22)

EL11 Drywell faretmtiar COMPLETED FROM INTERNALRFO21 (INACCESSIBLE AREA x-10oc IDENTIFIED)

EXTERNALTO BE SCHEDULEDBEFORE OR DURING RFOU (ccmpletedpre RFO 22)

E1.11 DryweU Padration COMPLETED FROM INTERN& RFO21 (INACCESSIBLE AREA X-100D IDENTIFED)

EXTERNAZ,TO BE SCHEDDULEDBEFORE OR DURING W022

@mpletCd pre RFO 22)

EL11 DIywellP&m COMPLETED FROMINERNAL RFO2I (INACCESSIBLE AREA X-lO1A IDENTIFIED)

EXTERNALTO BE SCHEDULED BEFORE OR DURING RFO22

@ompl&edpre RFO 22)

El.11 Drywell Penetration COMPLETED FROM INTERNAL RF021 (INACCESSIBLEAREA X-1O1B DENlTED)

EXTERNAL TO BE SCHEDULED BEFORE OR DURING -022 foompletedpre RFO 22)

EL11 Drywell Pmetratiaa x-IOIC Gv I 1my0 C O W S l Z D FROM INTERNALRFO21 (INACCESSIBLEAREA

-Dl EXTERNAL TO BE SCHEDULED BEFORE OR DURING RF022 fcompletedpre RFO 22)

EL1I Drywell Penshation COMPLETED FROM INTERNALRFO21 (INACCESSIBLE AREA X-IOID lDENlIFED)

EXTERNAL TO BE SCHEDULED BEFORE OR DURING R F m

~oompleted pre RFO 22)

El.ll Drywen Penetration COMPLETED FROM INTERNALRF021 (INACCESSIBLE AREA x-102 IDENTIFIED)

EXTERNALTO BE SCHEDULED BEFORE OR DURING -022 (compl~~eci pre RFO 22)

El.11 DryweU Penetration COMPLETED FROMINTERNAL RF021 QNACCESSIBLE AREA X-I03 WENTIFED)

EXlXRNAL. TO BE SCHEDULED BEFORE OR DURINO RFO22 (completed pre RFO 22) EXTERNAL SURFACE OF TIiIS PENETRATION IS NOT ACCESSIBLE FOR EXAMINATION DUE TO DESIGN EL11 Drywell Penebatim X-104A 1 1OOYO COMPLETED FROMINTEIWAL RF021 (INACCESSIBLEAREA IDENTIFIED)

EXTERNAL TO BE SCHEDULED BEFORE OR DURING RFO22

&ompleted pre RFO 22)

To: DennisGirroir 5/1Y200 1 From: Ralph Connell Re: Report for TWE Inspections Performed for RF022 (Reference Xeport for IWE Inspections Performed for RF021 dated 12/02/1999)

INTRODUCTION:

The objective in the current period for this new ][WE inspection program was to gather as much information as we could for RF021 and RF022. During RF021 the goal was to perform as many inspections as possible within the acceptable window without causing any interference with other outage work activities. The remainder of the required first period examinations was performed either before or during RFOZZ.

After the ZWE examinations performed during RFO 21 the Program Procedure PP7024 was revised to incorporate lessons learned. Some revisions were made to the appendices regarding inspected components and inspection criteria. As a result some of the examinations originally listed for the 1 period were revised and are reflected in the completion schedule included in this report. All required VT-3 examinations were moved to the 3d period as required by the ASME Section M Code 1992/92A.

DISCUSSION:

The ASME Section XI Subsection IWE Code requires an examination of tbe coated Surfaces in order to determine the condition of the substrate. This examination of coated surfaces is for evidence of flaking, blistering, peeling, discoloration and other signs of distress of the underlying metal. The IWE examinations performed for RFO21 found only two areas of coating with signs of distress affecting the substrate. Those two areas were located at the drywell interior moisture barrier and the other was on the drywell surface at the X-5Gpenetration. Both of these were evaluated by Mechanical Design Engineering and dispositions provided via the IDR process. IWE examinations during RF022 identified two more areas. These were areas of pitting and corrosion in the vent header and corrosion in the interior of penetrations X-207A-H. Both of these were also evaluated by Mechanical Design Engineering and dispositions provided via the IDR process. At many areas of the containment there is peeling or discoloration. Both of these issues have been previously identified and accepted via the OP5250 inspections.

The Maintenance Department has been performing containment inspections for several years via OP5250 to evaluate the condition of the coatings on containment surfaces.

These inspections have compiled an excellent source of data documenting the conditions of the coatings and how these coatings are maintaining over time. The information provided &om these reports provides the basis for disposition of issues identified on the IWE reports such as coating peeling and blistering.

9 Several areas were identified as inaccessible during the RF021 and W022 IWE examination process. Those inaccessible areas are generally defined in PW024. More specific information is included with the data supplied in this report.

DETAILS:

TORUSSURFACE The surface fkom just below the catwalk on the exterior surface to the horizontal mid point of the torus was inspected prior to W 0 2 2 The remaining torus penetrations were examined prior to RF022 and during RF022.

Penetrations X-207A-H were identified as having corrosion exceeding the provided acceptance criteria. IDR 01-08 was written on this item. This was addressed by Design Engineering and a design wall thickness for these penetrations was provided. The X-207A-H penetrations are acceptable for continued use and the corrosion identified does not exceed the required design wall thickness.

Torus penetration (includes penetrations in the vent system) examinations were completed for the first period.

The interior surface of the vent header examination was completed during RlF022. There were areas of pitting and corrosion identified in the vent header that exceeded the provided acceptance criteria. IDR 01-07 was written to address the areas of pitting and corrosion. Design Engineering addressed this IDR and provided new acceptance criteria for the vent header corrosion identified. All areas are within the required design wall thickness provided by the Design Engineering resolution and are acceptable fur continued operation.

A U G m N m D m L SURFACES After review of the data gathered during RF021, a portion of the containment surface at the joint seal area was declared as augmented. This area was examined and documented during RFO22. No change was identified in the as inspected condition between RFO21 and RF022 in the augmented area.

Since the area of the augmented s d a c e was being prepared for seal installation and painting the opportunity to examine this region with white metal exposed and all corrosion removed presented itself The entire circumference in the moisture barrier area was examined and the areas of pitting and pit depths were identified. All pitting

identified by this examination were bounded by the 1999 evaluation, VYM 99/139, and are acceptable for continued operation of the drywell.

Forty-three (43) percent of the required first period drywell penetration examinations were completed during NO21 the remainder was examined either prior to or during RF022. Many of these penetrations depicted debris and peeling paint. The dddebris is not considered to be detrimental to the containment structure. All penetration cavities were dry with no visible indication of moisture. The peeling paint was similar to that identified in the maintenance reports and is not unusual for the age and environmental conditions experienced by the coating.

The diddebris identified in the drywell penetration cavities is a housekeeping issue only, not a containment integrity concern. All large debris located in the penetrations examined has been removed. The remaining debris consists of the accumulation of dirt, dust and paint chips over the life of the plant. The quantity of debris in the penetrations identified is not a containment integrity concern. Most diddebris was lying in the concrete sleeve and not in contact with the penetration. All penetrations examined (except for X-207A-H) were dry with no indication of water. The penetrations typically have a small access and pose difficulty cleaning. The dilemma from inside the drywell is the accessibility to the penetrations and the ALATU concerns.

The drywell moisture barrier at the concrete floor to steel interface on the 238 level was identified as failed during RF021 examination. During RFO 22 this seal was replaced.

To deal With the paint chipping and corrosion in the seal area and to accommodate the seal installation a six-inch wide band of paint was removed in the seal area for the full circumference of the drywell at the 238 level. The seal was reinstalled per minor mod

  1. 2000-010.The six-inch band was re-coated with non-qualified coating. The area of the seal and coating was examined after installation to document the as installed condition.

This seal acts as a gasket at the concrete to steel interface to prevent moisture from penetrating under the concrete and to prevent it fiom setting in the interface setting up localized corrosion. This area is an area that regularly gets flooded with water due to the activities that take place during outages in the dry well. This area also is an area that experiences wear and tear at a much higher rate than the rest of the containment due to its location. As a result of the location and outage activities this is an area that requires regular maintenance to keep the moisture barrier seal and the paint in the moisture barrier area intact and properly protecting the steel containment. The logistics of trying to place qualified coating at this location and then set up to regularly maintain it can be difficult as was seen during RFO22 not to mention very costly. I recommend that this moisture barrier area and the six-inch band of paint be declared a high maintenance area and designed as an area where unqualified coatings are approved and utilized. This will make the routine maintenance of this area much easier to perform resulting in better

maintenance of this area in the fbture. If this approach were approved, repainting with qualified coating would not be required only maintenance activity to maintain the integrity of the nonqualified paint and moisture barrier seal. This maintenance should become a routine PM.

PRESSURERETAlN1.G BOLllNG Bolting examinations for X-200A & B and V16-19-5G& H were completed during RF022 in the removed condition. Bolting examinations or Vl6-19-5A-F was examined in place. This completes the required first period IWE bolting examinations.

SUMMARY

An estimated 80% of MrE examinations are completed prior to or during RFO21. The remaining 20% were completed prior to or during RF022 to complete the first period examination requirements.

There were two new IDRs generated, per DP4027, for containment issues G n g W022. All of these issues were addressed by Mechanical Design Engineering prior to RF022 startup.

Please find attached to this report for reference the Summary of First Period TWE Examinations. This repod provides details for the fir&period examinations.

1/23/1999

SUMMARY

OF FIRST PERIOD Twl XAMINATIONS CONTAINME

  • SURFACES (TORU! BAYS) ASME SECTION XI EXAhL CATEGORY. E-A ASME IS1 EXAM % REMARKS SECTlON X I IDENTIFICATION COMPLETE ITEM NO. NO.IDESCRIPTION TO DATE h e m a l surface above water line completedRFO 21 El.ll TORUS BAY 1 GV 100 yo Exi.emal surface except area ffm catwalk down to belt Line completed.

Remaining m to be mspeded after S/URFO2l(oompl&edpre RFO 22)

Nate: VT-1 completed below water line RFCUO m a l surface above water line completedRFO 21 EI.11 TORUS BAY 2 GV IW % Eldeanel surface except area 5om catwalk down to belt line completed.

Remaiming area to be inspected after SN RMnl (complaedpre RFO

~~ ~ ~

22) Note: VT-1 completed below water line RF020 Internal &ce above water line completed RFO 21 ELI1 TORUS BAY 3 GV 100 Yo Elagnal surface except area &omcatwalk down to beIt line complefed Rmnaiairig arca to be inspected a f t s S N RF(nl(c0mpletedp RFO 22)

$late: VT-I ~0mleted below water line RF020 banal d a c e above wata line completedRFO 21 El.ll TORUS BAY 4 GV 100 Yo Extemal surface except area fiom catwalk down to belt line compfeted Remaining area to be inspected after SKJ RF02l(completed pre RFO 22)

Ncte: VT-1 completed below water line RF-0 Internal surface above water line compIeted RFO 21 ELI1 TORUS BAY 5 GV F&temalsurfaw ex- area from catwak downto belt line completed Remainingarea to be inspected after S/WRF02l(completed pre RM)22)

Note: VT-1 ~ m p k k below d .water IhK RF020 Internal d a c e above water line complded RFO 21 TORUS BAY 6 GV I00 Yo E x t a d d a c e except area fiom catwalk downto belt line compIeted.

El.ll Remaining area to be inspecid a%er SN RF02l(compleLed pre RFO 22)

Nate: VT-1 completed below water line RF020 Mmalsurface abovewater line complded FSO 21 El.ll TORUS BAY 7 GV 100 % m a l d c e except area ikom catwalk dawn to belt line completed.

Remainingarea to be mspeded d e r S N RFO2l(compllBed pre RFO 22)

Nde: VT-1 complUed bdow water line RFOZO baemal d a c e above water Line completed RFO 21 TORUS BAY 8 GV 100 Yo Edema1 slpface except area fiom catwalk down to belt line completed-EL11 m i n i n g area to be inspected after SN WO22(compldedpre RFO 22)

Note: VT-1 completed below water line RFOZO krtanal sllrface above water line mnpleted RFO 21 TORUS BAY 9 GV 100 Oh Extemd d a w except area from catwalk down to bdt line completed.

El.ll Remaining area to be inspe&ed aAa S N RF02l(complaed pre RFO 22)

~~

Note: VT-1 completes below water line RF020 Internal d a c e above water rine completedRFO 21 TORUS BAY 10 GV 100 Yo Extanal sorface except area eom catwalk downto belt line oomplaed ELI1 Remaining area to be inspected aftex S/U RF02l(completedpre RFO 22)

Note: VT-1 completed below water line W020 fntemalsurfaoe above water Line canplaedRFO 21 TORUS BAY 11 GV loo % External surface excqt area fiom catwalk downto belt line mmplered EL11 Remaming area to be inspectedafter S N ~ l ( 0 o m p l e t e pre d RFO 22)

Note: VT-I completed below water line RF020 Intanald a c e above water line complded RFO 21 TORUS BAY 12 GV 100 Yo External surface except area 6.omcatwalk down to belt line completed E1.11 Remaining afes to be inspected a h SllJ RFoZl(c0mpleted pre RFO 22)

Note: VT-1 completed below water line RF020 bitema1 s u r f h abovewater line compleced RFO 21 TORUS BAY 13 GV 100 % External surf$= except area fiom catwalk down to be& h e completed EL11 Remaining area to be inspected a%= S N RFOZl(comp1eted pre RFO 22)

Note: VT-1 coqkted below water line RF020 Intemal surfaceabove water lime completed RFO 21 El.ll TORUS BAY 14 OV 100 % External SllrfaQ except area fiom catwalk &wm to belt line completed Remabing area to be inspected a&er S N RFO2l(complBed pre RM, 22)

~~

Note VT-1 completed below water line W 0 2 0 haernal surface above water tine complaedRFO 21 TORUS BAY 15 GV 100 % External SUrfaQ e x q t a r e *om catwalk down to belt line completed EL11 Izcmainingarea to be inspected after S / u RFCnl(c0mpleted pre rZF0 22)

Note: V7'-I completed below water line RF020

a Intend surface above water line coloplaed RFO 21 TORUS BAY 16 GV 100 % Exkznal sllrliice e x q t area h m catwalk downto belt Iinc completed El.11 Remakingareato bemspeded~erS/URF(nl(aomplBedpre~O22)

Nde: VT-I c~mpletedbelow water line RF020 ASME SECTIt J XI EXAM. CATEOC THE VENT LINE WAS COMPLETEa FROM THE TNTERNAt VENT SYSTEM SURFACE FS021. THE VACUUM BREAKER LXNES WERE BAY 2 COMPLETEDFROMTHEEXTERNALSURFACETOfltfE mum PENZTRATLON203 ELBOW THEN FROM THE INSIDE FROM THE ASSEMBLY, 203 Pl%ETlL4nON TO THE ELBOW VERTICAL WELD. THE VACUUM FXEWAL. SURFACE OF THE VENT HEADER AND INTERNAL BREAKER JXNES, A M )EXTERNAL SURFACES OF THE DOWNCOMERS A N D m COMPLETED RFWO.

HEAVJB IN BAY 2 THE VENT HEADER INTERIOR,VENT LINE -OR, AND AND BAY 3) THE REMAINDER OF THE VACUUM LINE WIU BE SCHEDULED FOR RFO22. (completed pre RFO 22)

TIiE VENT LINE WAS COMPLETED FROM THE INTERNAL SURFACE RF021. THE VACUUMBREAKER LINES WERE CONIPLETEDFROMTHEEmWALSURFACETOTHE PENETRATION 203 ELBOW THEN FROM THE INSIDE FROM THE 203 PENETRATONTO THE ELBOW VERTICAL WELD. THE EXTERNAL SURFACE OF THE VENT HEADER AND INTERNAL AM)EXTERNALDOWN COMER SURFACES WHERE COMPLETEDRF020.

THEVENTLINE WASCOMPLETEDFROMTHEINT'ERNAL.

VENT SYSTEM SURFACE W0.21.THE VACUUM BRWU<ER LINES BAY 4 COMl'LETJ3,DFROMTHEEXTERh'ALSuRFAcE TOTHE (VENTLINE PENETRATION 203 ELBOW THEN FROM THE INSIDE FROM TF5 ASSEMBLY, 203 PENETRATIONTO THE ELBOW VERTICAL WJZD. THE VACUUM EXTERNALSURFACE OF THE VENT HEADER AND INTERNAL.

BREAJERLDJES, AND EXTERNAL SURFACES OF THE DOWNCOMERS %'ERE AND VENT COhApLETED RFW.

HEADER M BAY 4 THE VENTHEADER JNTERIoR, VENT LINE m N O R , AND AM) BAY 5) THERJ3MNDEBOFTHEVACWUMLINEWIUBESCHEDULED FOR RFO22.(compl&edpre RFO 22)

THEVENTLINEWASCOh4PLETEDFROMTIIEINTERNAL SURFACE RF021. THE VACUUMBREAKERLINESWERE cOMpIE% FROM THE EXTERNAL SURFACE TO THE PENETRATION 203 ELBOW THEN FROM THE INSIDE FROM THE 203 PENETRATIONTO THE ELBOW VERTICAL WELD. THE ExIlERNAtSURFACE OF TNE HEADER AND INTE'FWAL AND EXTERNAL SURFACES OF THE DowNcOMERs WMERE COMPLETED RFo20.

THE V E h T LIME WAS OOMPLETEX) FROM THE INTERNAL VENT SYSTEM SURFACE RFO21. THE VACuuhiI BREAKER LINES BAY 6 COIvlPL.E~FROMTHEEXTERNALSURFACETOTHE (VENTLINE PENETRATION203 ELBOW THEN FROM THE INSIDE FROM THE ASSEMBLY, 203 PENETRATION TO THE ELBOW VERTICAL WELD. THE VACUUM EXTERNAL SURFACE OF THE VENT HEADER AND INTERNAL BREAKERLINES, AND EXTERNAL SURFACES OF THEDOWNCOMERS ANDVENT G o M P r n D RFmo.

HEADER IN BAY 6 THE VENT HEADER INTERIOR, VENT LINE EXTERIOR, AND AND BAY 7) TIE REMAINDER OF THE VACUUM LINE WILL BE SCHEDULED FOR RF022.(completed pre RFO 22)

VENT SYSTEM GV 100%

BAY 8 CV EN Tm ASSEMBLY, VACUUM BREAKER LINES, AND VENT LEADER IN BAY 8 AND BAY 9)

VENT SYSTEM GV 100% SURFACE -1. THE VACUUM BREASRLINES WERE BAY 10 COMPLETEDFROMTHEEXTERNALSURFACETOTHE

{VENTLME PENETRAnoN 203 ELBOW THEN FROM THE INSIDE FROM THE ASSEMBLY, 203 PENETRATION TO THE ELBOW VERTICAL W.THE VACUUM EXlXRNAL SURFACE OFTHE VENT HEADER AM) INTERNAL BREAKERLINES, AND EXTERNAL SURFACES OF THE DOWNCOMERS WAERE ANDVENT COMPLETED RFmo.

HEADER IN BAY THE VENT HEADER INTERIOR, VENT LXNE EXTERIOR,AND 10ANDBAY 11) THEREMAINIlEROFTHE VACWMLINEWIUBESCHEDUm I TfIEVENTLLNEWASC0MPLE"EDFROMTHEINXERNAL El.ll VENT SYSTEM GV 100% SURFACE RF021. THE VACUUM BREAKER LINES WERE BAY 12 COMPld3TEDFROMTHEEXTERNALSURE.'ACETOTRE (VENTLN PENETRATION203 ELBOW THEN FROM THE INSIDE FROM THE ASSEMBLY, 203 fENETRATIQNTO THE ELBOW VERTICAL WELD. THE VACUUM EXTERNAL SURFACE OFTHE VENTHEADERAND INTERNAL BREAELERLINES, ANDEXTERNAtSURFACESOFTHEWWNCOMERs WHERE AND VENT COMPLETED RF020.

HEADER IN BAY THE~HEAJlER~O~~Y3NEEXTERIOR,AND 12 AND BAY 13) THE REMAINDER OF THE VACUUM LINE WILL BE SCXEDUUD FOR RFO22 (completedpre RFO 22)

THEVENTLINEWASCOMPLETEDFROMTHEINTERNAL EL11 VENT SYSTEM GV 100% S G A C E W&1. THE VACUUMBREAKER LINES WERE BAY 14 COMPLJ3ZD FROM THE EXTERNa SURFACE TO THE (VENTLINE PENETRATION 203 ELBOW ITEN FROM THE INSIDE FROM THE ASSEMBLY, 203 PENXRATIONTO THE ELBOW VERTICAL WELD. THE VACUUM EXTERNAL SURFACE OF THE VENT HEADER AM)INTERNAL BREAKERLINES, ANDEXERNAL SURFACES OF THE DOWNCOMERS m RE ANDVENT COmLETEDRFmo.

HEADER IN BAY THE VENT HEADER INFERIOR, VENT LINEEXTERIOR, AND 14 AND BAY 15)

E1.11 VENT SYSTEM GV 100% SURFACE RFO21. THE VACUUM BEAKER LMES WERE BAY 16 C0MPETF.D FROM THE EXl33FWAL SURFACE ToTHE (VENTLINE PENETRATION 203 ELBOW THEN FROM THE INSIDE FROM THE ASsErnLY, 203 PENETRATION TO THE ELBOW VERTICAL WELD. THE VACUUM EXTERNAL SURFACE OF THE VENT HEADER AND INTERNAL BREAKERLINES, AND EXIZRNAL SURFACES OF THE DOWNCOMERS ANDVENT COMPLETEDwmo.

HEADER IN BAY THE VENTHEADER INTERIOR,VENT LINJ?EXTERIOR, ANI) 16 AND BAY 1) THE REMAINDER OF THE VACUUM LINE WILL BE SCHEDULED FOR xFO22. (completedpre RFO 22)

ASME SECTION XI EXAM. CATEGORY E-A EL11 TorusPgletratiOn GV 100% COMPLEmINTERNALANDEXTERNAL X-2OOA & B -~

E1.12 VT-3 100% COMPLETE FROM EXTERNAL -021 EL11 Torus Penetration GV 100% COMPLETE FROM INTERNALRFO21 X-201A THRU A EX"ZRNAL TO BE SCHEDULED BEFORE OR DURING RFOZXcompleted pre RFO 22)

El.11 TarusPendration X-202A THRU F GV 100% I COMPUTE FROM INTERNALAND EXI'ERNAL WO21 EL11 Torus Penekation X-202G THRU K GV 100% 1 COMPLETE FROMINTERNAL ANL) EXTERNAL E 3 0 2 1 EL11 Torus Penetration GV X-203A THRU F D BEFORE ORDWRING I

El.11 To~usPen&itioa GV COMPLETE FROM INTERNAL W021 X-203G THRU H RNAL TO BE SCHEDULED BEFORE OR DURING W 0 2 2 I

Torus Pmetnrtion GV COMPLETE FROM xNTEIu\JAL AND EXTERNAL W02I El.ll Tarus Pgletration GV X-206A THRU D I

El.12 VT-3 Toms Penplr;aion GV X-206E THRU F EL12 VT-3 El.ll T m P e n ~ m GV X-207A THRU H E D FOR RF02z(completed RFO 22 EL11 Torus Penetration GV COMPLETEFROMINT'ERNALANDEXTERNALRF021 X-208ATHRU D El.ll Taus Penetration GV X-209A THRU D I

El.ll TonrsPenetmtion GV X-2 1OA & EL EL11 Toms Penetration GV ioo% COMPLXTEFROM INTERNAL AND EXTERNAL S O 2 1 X-ZlIA&B EL11 Taus Pen&itim GV 100% COMPLETEFROMINTEKNALANDEXTERNALW021 x-212 EL11 Torus Penetration GV 100% COMPLEE FROMEXTERNAL RFCnl (UNDERWATER)

X-213A &. B EL12 I VT-3 100% COMPLETE FROME;rlTERNALRFO21W E R WATER)

El.ll Torus Penetration GV 100% COMPLETEFROMINTERN&AlWEXTERNAtRF021 X-2 I4 EL11 TorusPenWw GV 100% COMPLETE FROMKNTERNAL AND EXTERNAL RF021 X-21 5 EL11 Torus Pen&at.ion GV 100% COMPLETE FROMWRNAL AND EXTERNAL RFO21 X-216 EL11 Toms Pondration GV 100% COMPLETE FROM lNl'ERN& A M )EXEIRNAL RFOZ1 X-217 '

EL11 Taus Penetration GV 100% COMPLETE FROM INTERNALAND EXTERNAL RFO21 X-2 18

El.ll Torus Peaetnnion GV 100% COMPLETE FROM m A L AND EXTERN& RFO21 X-219 EL11 Torus Penetration GV 100% COMPLETE FROM INTERNAL AND EXTERNAL RFO21 EI.11 x-221 El.ll TorusPenetration GV 100% COMPLETE F'ROMINTERNAL AND EXTERNALRFOZl x-222 El.ll X-223 t El.ll Torus Pendmtion GV 100Yo I COMPLETE FROMIZXTERNALRFOZl X-224A & B INSULATION PREVENTING INSPECTIONFROM EXTERNAL, INTERNAL,UNDER WATER THIS WIU BE RESCHEDULED WHEN DIVERS ARE IN TORUS OR TORUS HAS BEEN DRAMED ALONG WITlI THE UNDERWATER SURFACES.

1.11 TolusPenetrsdion GV 100% COMPLETE FROMEXTERNAL W 0 2 1 (UNIIER WATER)

X-225 EL12 VT-3 100% COMPLETE FROMEXTERNALRFCBl(UNDER WATER)

El.ll Torus Peaetration GV 100% COMPLETE FROMEXTERNALRFOZI (UNDER WATER)

X-226A & B E1.12 VT-3 100% COMPLETE FROMEXTERNALRFOZI (UNDERWATER)

EL11 Torus Penetmtion GV 100% COMPLETE FROMEXTERNALRFo21 (UNDER WATER)

X-227 E1.12 1I VT-3 I 100% I COMPLETE FROMEXTERNAL RFml (UNDER WATER)

I I EL11 TorusPenQtation GV 100% COMPETED FROM EXTERIOR RFOZ1 (NOTACCESSIBLE FROM X-228 INTERIOR)

EL11 Torus Pen&ation GV 100% COMPLETED FROMEXTERIOR RFO21 (NOT ACCESSIBLE FROM X-229 INTERIOR)

EL11 Toms P e n d o n GV 100% COMPLEED FROMEXTERIORRF021 X-230

&G COMFTZTED FROM DITEPJOR RFOZ1 (B,D,F &H ARE EL11 TorusPenetraton GV 100YO UNDER WATER FROM INTERNAL)

X-231A-H B,D,F,G& H COMPLETED FROM EXTERNAL RFCB 1 RESCHEDULE A,C, & E FOR RFO22(wmpleced pre RFO 22)

ASME SECTION M EXAM.CATEGORY: E-A 100% COMPLETEDFROMINTERNALRF021 238 to elevation 251 EXTERNAL INACCESSIBLE BY DESIGN quadrant ato 90 100% COMPLETED FROMIh'TEN'JAL. RFo21 I I I EXTERNAL INACCESSIBLE BY DESIGN I I I EL11 I Dnwellelevation I GV I 100% COMPLETED FROMINTERNAZ, RF021 2 6 to elevation 251 EXTERNAL INACCESSIBLE BY DESIGN quadrant 90to I80 COMPLETEDFROMl[NTERNALRFO21 EXTERNAL lNACCESSIBLE BY DESIGN EL11 Drywellelevation GV lODO/o COMPLETED FROM INTERNALRFOZ1 238to elevation 251 EXTERNAL INACCESSIBLE BY DESIGN quadrant 180to 270 d e w

t I

E1.12 VT-3 loo?? . COMPLETED FROM INTERNAL RF021 8 ExTERNAtINACCESsI8LEBY DESIGN EL11 Drywell elevatim GV 100% COMPLETED FROM NEFCNAL RFO2l 238to eIevation 251 EXTIERNALINACCESSIBLEBY DESIGN quadrant 270 to 360 E1.12 degFees VT-3 100% OOMPLETEDFROMINTERNALRF021 EXTERNAL INACCESSIBLEBY DESIGN EL11 Drywellelevation GV 100?4 COMPLETED FROMEVIERNAL. RFO21 251 to elevation 269 EXTERNAL INACCESSIBLEBY DESIGN qu.adtimt 0 to 90 E1.12 degrees VT-3 100% COMPUTED FROM INTEF3VA.L RFO21 EXTERN& INACCESSIBLEBY DESIGN El.ll Drywell elevation GV 100% COMPLETED FROMINTERNALRF021 251 to elevation269 EXTERNALINACCESSIBLEBY DESIGN quadnmt90to180 degreg I

El. I1 Drywell elevation GV 10% COMPLETED FROMIlvTmNAL RFo21 251 to elevation269 EXTERNAL INACCESSIBLEBY DESIGN quadrant 3.80to 2'70 degrees EL11 DryweU elevation GV 100% COMPLETED FROMINTERNALRF021 251 to elevation 269 EXTERNALINACCESSIBLEBY DESIGN quadrant 270 to 360 aegrees EL11 Drywell elevation GV 1OO?! COh4PLETED FROM INTERNAL RF021 269 to elevation321 ECIERNAL. INACCESSIBLE BY DESIGN quaoh.antoto90 degrees E1.11 Drywell dwation GV COMF'LETEDFROMINTERNALR.F021 269 to elevation 321 ECI'EXWAL INACCESSIBLEBY DESIGN q u a b t 90 to 180 degrees E1.11 DrywelI elevation GV 100% COMPLETEDIXOMrmTERNALFSOZ1 269 to elevation 321 EXERNAL INACCBSIBLEBY DESIGN quadrant 180 to 270 kees ~

ELI1 Drywell elevation GV 100% COMPIETED FROM INTERNAL RFO21 269 to ekv&cro 321 EXTERNALINACCESSIBLE BY DESIGN quadrant 270 to 360 degrees El.11 Drywen Head GV 100% COMPLETED M021 interior surfacesand Drywen flanges El.ll Drywell Head GV 100% COMPLETED RFOZ1

~orsurfsces CONTAINME r SURFACES (DRYWELL PENETRATIONS)

EL11 DryweUPenetratim GV 100% COMPLETED INTERNAL AND EXTERNAL RF021 x-1 PORTIONS OF THEEXTERNAL AREA ARE INACCESSIBLE FROM DIRECT vzSUAJ+EXAMINATION BY DESIGN EL1 I DrywellPeoetration GV 100% COMPLETED INTERNAL AND EXTERNAL F S 0 2 1 x-2 PORTIQNS OF THE EXTERNAL AREA AKE INACCESSIBLE FROM DIRECT VISUAL EXAMINATiON BY DESIGN

El.ll Drywell Penetration GV 100% COMPLETEDINTERNALANDEXTERNALRF021 El.ll Drywell Penetrativn GV 100% COMPETED INTERNALRFO21 X-SA THRU X-5H EXTERNAL TO BE COMPLETED BEFORE OR DURING RF022(completedpreRFO 22)

I E1.12 VT-3 COMPIETED FROM THE INTERNAL SURFACE RFO21 I

GV 100% WMF'LETED FROMINTERIORRFO21 RESCHEDULEEXIERIOR BEFORE OR DURING RF022(oompleted pre RFO 22)

El.ll DrywellPenetratiGil GV 1OPh COMPLETED FROM INTERNAL RFO21 X-7A EXTERNALTO BE SCHEDULED BEFORE OR DURING RFO22(completed RFO 22)

GV El.ll 1 Drywell Penetr;aica x-7c GV El.ll Dryweu Penetration GV COMPLETED FROM LNTERN MCI'ERNAL TO BE SCHEDULED BEFORE OR DURING GV E1.12 VT-3 EL11 Drywell Penetration GV X-9A El.ll 1 DryWellPmetration X-9B GV 100% COMPLETED FROMMTERNAZ.RF021 EXTERNALTO 3E SCHISDULED BEFORE OR DURING RFOn(camp1eted RFO 22)

I El .11 1 DrywelI Penetration x-10 GV RE3CSDUL.E FOR W022 (completed RFO 22) External surface insulated restridingaccess for GV Exam. N d internal surface has I

El.ll Drywen PenetTation GV RESCHEDULE FOR R Fm (completed RFO 22) External d a c e El.ll Drywdl Penetration GV FROM INTERNAL RF021 (INACCESSIBLEAREA x-12

.. . . . .. . ....-. . 8 . . ___ ..-. ._. - . . -.- - - . . . . . - - ... ... - - . ... . ... ... . .. - - .... . .... .. ...

8 El.11 Drywell Penetration COMPLETEDF'ROMINTE~ALRF021 X-13A RNAL TO BE SCHEDULEDBEFORE OR DURING RF022 El.ll Drywell Penetralicm COMPLETED FROM INTEIZNAL RF021 X-13B RNAL TO BE SCHEDULEDBEFORG OR DURING RFO22 El.ll DrywellPenetration X-14 El.11 DrywellPenecration x-15 EL11 Drywell Peneb.ation GV 100% THIS FZNETRATION IS NOT ACCESSIBLEFOR GV EXAM OF X-16A INTERNALSURFACE. (completed RFO 22)

El.11 DrywellPtnetraticm GV 100% TRIS PENETRATIONIS NOT ACCESSIBLE FOR GVEXAM OF x-16B INTERNAL SURFACE.(completedRFO 22)

El.ll Drywell Pmctratian GV 100% COMPLETED FROMINTERNALRFO21 X-17 EXERNALTO BE SCKEDUI.ED BEFORE OR DURING W 0 2 2 (compleled pre RFO 22)

El.ll Drywell Penetration GV 1004/0 COMPLETED lXOMINTERNAL W021 X-18 EXTERNAL TO BE SCHEDULED BEFORE OR DURING W 0 2 2 (completed pre RFO 22)

I I El.11 Drywell Penetration GV 100% COMPLETED FROMMTERNALRFO21 x-19 EXTERNAL TO BE SCHEDULEDBEFORE OR DUfUNG -022 (completedRM)22)

I I I

EL11 Drywell Penetration GV 100?%3 WWIETED FROM INTERNAL RFO21 x-20 EXTERNALM BE SCHEDULEDBEFORE OR DURING RFcn2(completcd pre RFO 22)

I EL21 Drywen PmeEratia GV lOOo! COMPLETEDFROM lNTJ5RNAL RF021 x-21 EXIXRNAL TO BE SCHEDULEDBEFORE, OR DURING RFO22(completed pre RFO 22) t Dryweu Pennetration GV 100% COMPLETED FROM INTERNALRFOZl x-22 EXIZRNM. TO BE SCHEDULED BEFORE OR DURING RF022(completedpre RFO 22)

ELI1 Drywell Penetraticn av 100% INSuLATlON PREVENTS ACCESS FOR GV EXAM FROM X-23 INTERNAL SURFACE. (completed RFO 22)

EL11 Drywell Penetratiar GV 100% LNSULATIONPREVENTS ACCESS FOR GV EXAM FROM X-24 INTERNAL SURFACE(completed RFO 22)

I El.11 Drywell Pentztration GV 100% COMPLETED FROM INTERNAL RFozl X-25 EXTERNALTO BE SCHEDULED BEFORE OR DURING I(Foz2(compIeted pre RFO 22)

EL11 Drywell Penetration GV 100% COMPLETED FROMTNTERNALRFcnl X-26 EXTERNAL TO BE SCHEDULEDBEFORE OR DURING Eo22

( c o m p l d pre RFO 22)

+

E1.12 VT-3 100% COMPLETED FROM INTERNAL RFm1 I

EL11 Drywell Penetration GV loo?? COMPLETED FROM WIXWAL RFO21 X-27 EXTERNAL. TO BE SCHEDULED BEFORE OR DURING RF022 (completed RFO 22)

~ ~

El.ll DryWeUPeretratica GV 100% COMPLETED FROM INTERNALRF021 X-28 EXTERNAL TO BE SCHEDULED BEFORE OR DURING RF022

~compleledRFO 22)

EL11 RESCHEDULE FOR RF022 INTERNAL SURFACE NOT SAFELY ACCESSIBLE FOR GV EXAMINATION (completed RFO 22)

El.ll DrywdlPenebatioo GV 100% COMPLETEDFROM INTERNALRFOZl X-30 EXTERNALTO BE S C B D W D BEFORE OR DUIUNG RF022 (completed pre RFO 22)

EL12 VT-3 100% COMPLETED FROM INTERNAL RFOZl El.ll DrywetlPenetratim GV 100% COMPLETED FROMINTERNALRF021 X-31 EXTEFWAL TO BE SCHEDULED BEFORE OR DURING RFo22 (completedpre RFO 22)

EL12 VT-3 looOm COMPLETED FROM INTERNAL RF021 El.ll DrywellPemtration GV 100% COhPLETI3DFROMMTERNALRF021 X-32 EXTERNAL TO BE SCHEDULEDBEFORE OR DURING RFOZ2

~complaedpre RFO 22)

I------

El. 12 100% COMPUTED FROMINTERNALRF021 El.ll 100% COMPLETED FROMINTERNALRF021 EXTERNAL TO BE SCHJ3DULED BEFORE OR DURING R W 2 2 (completed pre RFO 22)

EL11 Drywell Peoctratian 100% RESCHEDULEFOR RF022 (completedpre RFO 22) x-34 EL11 DrywellPeneCration GV 100% COMPIETEDFROMINTERi'JALANDE2CIXRNALRFOZl X-35A THIS PENETRATIONIS PARTIALLY ACCESSIBLE FORGV

~~

EL12 El.11 EEzq-?

X-35B 100%

100%

Wh4PUTED FROM INTERNfi RFO21 COMPLETEDFROM INTERNAL AND EXTEWAL W021 THIS PENETRATION IS PARTIALLY ACC?3SIBLEFOR GV EXAM EL12 100% COh4FTEIBD FROM rmTERNALRF021 El.ll hyweIi Pme?ratioa GV 100% COMPLETED FROM INTERNALAND EXIERNAL RF021 x-35c THISPENETRATION IS PARTIALLY ACCESSIBLE FOR GV EXAM E1.12 VT-3 100% COMPLETED FROM INTERNAL.RF021 I

I-EL11 100% COMPLETED FROM XNTERNAL AND EXTERNAL RFO21 X-35D THIS PIPJETRATION IS PARTIALLY ACCESSIBLE FOR G V EXAM Drywdppenetratim f VT-3 100% COWLETED FROM INTERNAL. RF021 100% COMPLETED FROM INTERNAL AND EXXERNALRFO21 THiS PENETRATIONIS PARTIALLY ACCESSIBLE FOR OV EXAM

E1.12 VT-3 100% COMPLETED FROMINTERNALRFOZl ELXI Drywen Penetration GV 100% COMPLETED FROM IMERNAL W02I X-36 EXTERNALTO BE SCHEDULED BEFORE OR DURING RF022 (completedpre RFO 22)THIS PENETRATION IS NOT SAFELY ACCESSIBLE FOR GVEXAU El.11 Drywell Penetration GV 100% COMPLETEDFROMINTERNALRFOZX X-37A EXTERNAL TO BE SCHEDUUD BEFORE OR DURING RFO22 (oompl&edpreRFO 22) THIS PENETRATION IS NOT ACCESSIBLE FOR GV EXAM DUE TO PROXIMITY OF PIPES M EACH OTHER AND THE MINIMAL CLEARANCES BETWEEN THE CRD PPING AND THE mmmm SLEEVES.

EL11 Drywen Penetration GV 100% COMPLETED FROM INTERNAL. RF07.1 x-3% EXTERNAL TO BE SCHEDULED BEFORE OR DURINGRFOZZ (completed pre RFO 22) THIS Pl3EXIU'MON IS NOT ACCESSBLE FOR GV EXAM DUE TO PROXIMITY OF PIPES TO EACH OTHER AND THE MINIMAL CLEARANCES BETWEEN THE CIU) PIPING AND THE CONCRETE SLEEVES.

El.11 Drywell PenetIatiOn GV 100% COMPLETED FROM INTERNAL RFOZI x-37c EXTERNAL TO BE SCHEDULED BEFORE OR DURING -022 (aomplaed pre RFO 22) THIS PENETRATION IS NOT ACCESSIBLE FOR GV EXAM DUE TO PROXWKY OF PIPES TO EACH OTHER AND THE MINIMALCLEARANCES BETWEZN THE CRD PIPING AM)THE CONCRETE SLEEVES.

El.ll Drywell Penetration GV 100% COMPETED FROMINTEWAL RFOZl x-37D EXTEF?XALTO BE SCHENJIED BEFORE OR DURING RFO22 (compietedpre RFO 22)THIS PENETRATION IS NOT ACCESSIBLE FOR GV EXAM DUE TO PROXIMITY OF PIPES TO EACH OTHER AM) THEMINIMALCLEARANCESBETWEENTHE CRD PIPING AND THECONCRETE S?XEVES.

EL11 Drywell Penetraticn GV 100% COMPtETEDFROMINTEWALRF021 X-38A EXTERNAL.TO BE SCHEDULED BEFORE OR DURING RFo22 (completed pre RFO 22) THISPENETRATION IS NOT ACCESSIBG FOR GV EXAM DUE TO PROXIMITY OF PIPES TO EACH OTHER AND THEMINIMAL CLEARANCES BETWEENTHE CIiD PIPING AND THE CONCRETE S W V E S .

EL11 Drywell Penetration GV 100% COMPLETED FROM INTERNALRFOZl X-3833 EXTERNALTOBESCHEDULEDBEFOREORDURINGRFO22

  • (completedpre RFO 22) THIS PENJXRATKONIS NOT ACCESSIBLE FOR GV EXAM DUE TO PROXIMITY OF PEES TO EACH OTHEfz AND THE MlNLMAL CLEARANCESBETWEEN THE CRD PIPING AND THE CONCRETE SLEEVES.

EL11 Drywell Peaetration GV 100% COM.PLETED FROM INTERNAL RF021 X-38C EXTERNAL TO BE SCHEDULED BEFORE OR DURING RF022 (completed pre RFO 22)THIS PENETRATION IS NOT ACCESSIBE FOR GV EXAM DUE TO PROXIMITY OF PIPES TO EACH OTHER AND THE MIMMAL CLEARANCES BETWEEN THE CRD PIPINO AND THECONCRETE SLEEVES.

El.ll Drywen Penetration GV 10o?h COMPLETED FROM INTERNALRFO21 X-38D EXTERNAL TO BE SCHEDULED BEFORE OR D W G RF-2 (completed pre RFO 22) THIS PENETRATION IS NOT ACCXLSSIBa FOR GV EXAM DUE TO PROXIh4IlY OF PIPES TO EACH OTHER AND THE CLEARANCES BETWEEN THE CRD PIPING AND THE CONCRETE SLEEVES.

EL11 Drywell Penetration GV 100% ~~LEIEDFROMINTERNALRFO21 X-39A EXTERNAL TO BE SCHEDULED BEFORE OR DURING RF022 (completed pre RFO 22) THIS PENETRATION IS INACCESSIBLE FOR GV EXAM OF EXTERNAL SURFACES RUE TO INSULATION

I EI.ll DrpdlPenetrrdion GV 100% COMPLETED FROMINTE~ALRFOZI X-39B EXTERNAL TO BE SCIXEDUWD BEFORE OR DURING WO22 (completed pre RFO 22)

El.ll Di3w811Penetratim GV 1W/o COMPLETED FROM iN'I'ERNAL RFO21 X4OA EXTERNAL TO BE SCHEDULED BEFORE OR DURING RFOn (compIetedpre RFO 22) THIS PENETRATION IS NOT SAFELY ACCESSlBLE FOR GVEXAM OF EXTERNAL SURFACE El.11 GV 1W/o COMPLETED FROM INTERNAL, RF021 EXTERNALTO BE SCHEDULED BEFORE ORDURING RF022 (cnnpletedpreRFO 22) THIS PENETRATION IS NOT SAFELY ACCESSIBLE FOR GV EXAM OF EXTERNAL SURFACE ELI 1 1

DrYc9.4 P0l&ion GV 100?? COMPIJXED FROMrmTERNAL W021 x4oc EXTERNAT.TO BE SCHEDULED BEFORE OR DURING RF022 (completed pre RFO 22)THIS PENETRATION IS NOT SAFELY

~

ACCESSIBLE FOR GV EXAM OF EXIERNJ~LSURFACE EL11 GV 100% COMPLETED FROMINTERIVALRFO21 EXTERNALTO 3 E SCHEDULED BEFORE OR DURING RFO22 (completedpre RM, 22) THIS PENETRATION IS NOT SAFELY ACCESSIBLE FOR GV E X A M OF EXIXFtNAL SURFACE I

EI.11 100% RE23mDUT-E FOR RFOn (oompl&ed RFO 22) THE, INTEWAL SURFACE OF THlS PENETRATION IS NOT SAFELY ACCESSIBLE FOR GV EXAh4 El.ll DrywellPeneh-dtion x-42 I GV 101)0/0 COMPLETED FROM INTERNALRF021 EXTERNALTO BE SCHEDULED BEFORE OR DWUNG RF022 (completedpre RFO 22)

E1.11 Drywell Penetration GV 100% COMPLETED FROM INTERNAL RFO21 x-43 EXTERNAL TO BE SCHEDULEDBEFORE OR DURING RF022 (completed RFO 22) THE EXTERNAL SURFACE OF THIS PENETRATION IS NOT SAFELY ACCESSIBZ FOR GV EXAM El.ll DrYwellPcmiration GV 100% COMPLETED FROM INTERNfi RFO21 X-44 EXTERNAL TO BE SCHJDUJJDBEFORE OR DURING RF022 (complaed RFO 22) THE EXTERNAL SURFACE OF THIS PENETRATIONIS NOT SAFELY ACCESSIBLE FOR GV EXAM El.ll DryweITPeaetraticu GV 100% COMPLETED FROM INTERNALRFO2I x-45 EXTERNAL TO BE SCHEDULED BEFORE OR DURING RF022 (completed pre RFO 22)

El.ll Drywell Peuehticm GV 1OWh COMPLETED FROM INTERNALRFO21 X-46 EXTERNALTO BE SCHEDULED BEFORIE OR DURING RF022 (completed RFO 22) THE EXTERNAL SURFACE OF THIS PENETIUTION IS NOT SAFELY ACCESSIBLE FOR GVEXAM EL11 r)rywenPenetration GV 100% RESCHEDULE FOR WO22(comptBed RFO 22) TJX INTERNAL, x-47 SURFACE OF THIS PENETRATION IS NOT SAFELY ACCESSIBLE FOR GV EXAM EL11 100YO COMPLETED FROMINTERNALEGO21 EXTERNAL TO BE SCzfEDUlLED BEFORE OR D m G EGO22 (completed pre RFO 22)

EL11 ~dPe.nebatim GV 100% COMPLETED FROM INTERNAL,RFO21 x-49 EXrEF3W.LTO BE SCHEDULED W O R E OR DURPJG E 0 2 2 (completed pm RFO 22)

El.ll DrywedlPenetration GV loo?/. COMPLETED FROMINTERNALRFOzl x-so EXTEWAL TO BE SCHEDULED BEFORE OR DURING RF022 (completedpre RFO 22)

+

El.11 DryWellPenetration GV 100% COMl'uETEf) FROM INTERNAL RFO21 (INACCESSIBLE AREA X-104B IDENTIFIED)

EXTERNALTO BE SCHEDULED BEFORE OR DURINGRFOZO (completedpre RFO 22)

CQMPLETEI) FROMINTERNAL RFO21 (INACCESSIBLEAREA IDrnED}

1 1 1 1 EXTERNAL, TO BE SCHEDULED BEFORE OR DURING RMn2 (cOmplBedpreRFO22) 51.11 DrywellPenetrdon GV 100% COMPLEJXDFROMINTERNALRFO2I (INACCESSIBLE AREA X-105A IDENTIFED)

EXTERNAL TO BE SCHEDULED BEFORE OR DURING W22 (completed pie RFO 22)

COWLIZTEI)FROM INTERNAL RFO21 (INACCESSIBLEAREA IDZTl-EED)

EXTERNALTO BE SCHEDULED BEFORE OR DURING RFO22 (oompleted pre RFO 22)

I E1.ll 100% COMPLETED FROM INTERNAL W021 (3NACCESSLl3LIEAREA

)

D I

I.3LTERNAL TO BE SCHEDULED BEFORE OR DURING RFm2 (COmplBed prc RFO 22)

COh4PLETJ5D FROM INTEIUUL RFO21 (INACCESSIBLEAREA IDENTIFIED)

~RNALTOBESCEIEDULEDBEFOREORDURINOIRF022 (oomplBedpreRFO22)

COMPLETEDFROM INl'XRNALRFo511 EXTERNALTO BE SCHEDULED BEFORE OR DURING RF022 (comgleted pre RFO 22)

EI.11 Drywell Penetration 100% COMPLETEDFROM~~&RF~l X-107 EXERNAL. TO BE SCHEDULED BEFORE OR DURING RFOn (completedpreRFOZ2) t F SEALS, GASKETS, JDMO TURE B W R S ASME SECTIONXI EXAM. CATEGORY E-D IS1 EXam YO REMARKS SECTION XI IDENTIFICATION COMPLETE ITEM NO. TO DATE E5.30 iNTERIOR VT-3 100% INSPECTIONCOMPLETED RFO21 MOISTURE DTSCREPANCES WERE IDENTIFIED AND DISPOSIITON FOR BARRIER THIS ITEM IS WITH MECHANICAL DESIGN ENGINEERING jLRlNG .UGMENTED ASME CLASS MC ASME SECTION XI E M N CATEGORY: E-C I

ASME SECTIONXI IS1 EXam YO REhRARKs m IDENTIFICATlON COMPLET NUMBER NO./DESCRIPTION E TO DATE Drywell Interior E4.11 Surfaceatthe VT-I 100% Tbe area identified for augrtlentedexam of the Drywell surface at the Moishue B a n k rno- barrier interfaceshall be &om containmentplate weld joint Interface l~OfX-5BtothecoatainmentplateweldjoirdrigbtOfpenetratiOnX-5E and emthe concrete metal i n d c e up 1 foot. Complete RF022

T E4.12 Drywell rntexior Volumetlic 100% TheareaidmtSedforaugmeutedexamoftheDrywd1surfaceatthe Slnfsce at the moisture barrier i n t d c e shall be from Containment plate weld joint Moisture Barrier left ofX-5Bt~thecoatainmentplateweldjoiatrigfRofpm~onX-Intdace 5E and ~ I X I the concrete metal interfsceup 1 foot. Complete RFO22 CONTAINMENTPRESSURE RETAINMGBOLTING ASME SECTIONXI EXAM. CATEGORY: E-G Asm Is1 Exam  %

SECTION XI IDENTEICATION COMPLETE ITEM NO. NO./DESCRTPTION TO DATE E8.10 TORUS MANWAY VT-1 1OW? RESCHEDULE FOKW022 (completedRFO 22)

FLANGE BOLTING PENETRATION 200A -

ES.10 TORUS MANWAY VT-I 100% RESCHEDULE FOR RF022 (completed W O 22)

FLANGE BOLTING PJiMXRATION 200B E8.10 V16-19-5A-F VT-1 100% W022 INSTALLEB E8.10 VT-x. 100% RF022 REMOVED

Vermont Yankee DataSheetNo: g'?k-O -.Q!o Visual Examination Report Form Work Order No.: ou-YO37 VT-1, Containment Surfaces (IWE)

ProcedureNoRev.: j?&= 80 p.5 /r?EL4 1

- # /

Visual Aids Illumination Level Check Method I

Photo I I

Sketch I Xntermediate I

a/#

/

&/A c

IDirect I None B None htermediare OJ-7 A,

& .u c

/&

1Remote Attached Attached Final "1 7f j % 9  : 15 A/y 5-/-0/

df qef'" .4"eJ cue* r/2'53' &'e 993-0 iemote Examination Conditionfiquipment Remarks P

Evaluation Required?

~ ~ $NO e s V W F 8045.02 NE 8045 Rev. 1 Page 1 of I

Work Order Number: 0 0 -0O'sb~7- 000 Thickness Calibration Data Sheet .

Instrument Instrument Make: ? &

a q P&L< instrument Model: 2 6 DL Ph3 Instrument SM: '9.329'3s7 Instrument Display: CRT { ) Digital (/ Horizontal Linearity Performed?: Yes ( ) No (\d Calibration Block Serial Number: E k / - 1 , 64 /-2 Calibration Block Material: $k Product Form: wrykf Block Temperature: 7 5 OF Thicknesses: ,860 - T . 001 M&TE Used?: Yes ( } No (4 M&TE Description I WN: k.

Calibration Times initial Calibration: O g O O Check: ./ 3 oc Check 14 Check: N/A Check ~h/

Final: 1630 Sketch and Examination Results:

fee pfiy Examiner:

Reviewer:

5A56d PA -6 Level: 21=

Date: 5$ Io 6 0 I

Date: S l 8 f o ~ Yes ( J y ,

Form Number:

No ( )

Cog. Engineer. &?$&d 4 Date: ~ / ~ ~ / b WNEF8053.0'l~

U Page 1 of 1 Date:&WW' NE 8053 Original

  • NI[:HX3%4425 LPC#l .

Experience Hours Credit:

Work Order Number: m-oaSo37-oao Thickness Calibration Data Sheet lnstrument Instrument Make: PAlvA M-#ICs Instrument Model: 2 6 0 C PL k 5 Instrument SM: 9 3 1 2 9'307 Instrument Display: CRT ( ) Digitat (4 Horizontal Linearity Performed?: Yes ( )

~ ~~

No (#

IC 1-1. Calibration Mock SeriaINumber: E/C 1-2 Calibration Block Material: CAR SPEE C Product Form: W e6 U 6 ) 17 Block Temperature: 75 OF Thicknesses: 0.f506", u I ~ W ' , ~ ~ s o o " Z, . O O ~ ~ zI ,s n i '1, 3,ea$

M&T Used?: Yes ( ) No (4 M&TE Description/W:

. . .' Calibration Times InitialCalibration: 0 0 0 0 Check: hf/A Check: NIA Ch-: &/A Check dIi4 Final: 1osn Sketch and Examination Results: s EE Q A E  ;

Reviewer: Date: s"d0.0 f Form Number:

Cog. Engineer. Date: 5/41 /o t WNEF8053.01 I &y#**k 6+wt Page 1of 1 ANII: . /W /

& Date: fl-KH*/ NE 8053 Original LPC#l -

Experience Hours Credit:

FB c

Q. .

(3

[

c cn a ..

3 3w

Vermont Yankee Visual Examination Report Form Work Order No.: 00- 37 VT-1, Containment Surfaces @WE)

Procedure No/Rev.: /vE 80 y 5 ,&EVI /

, Page 1 of 6 Date: .5-9-0/

Component 3Remote Attached I =Attached I Final f6/%. I ?,dU,4?42 1 / Remarks iemote Examination ConditionsEquipment 5 3 uc/E: 943-82 Recordable NIA RemarkslObservations I

Evaluation Required?

VYNEk 8045.02 NE 8045 Rev. 1 Page 1 of 1

Vermont Yankee Visual Examination Reference Data Sheet No: 8o'j?c- O/2 O / 9 Level: z Date: H-y-O/

>miner: c'/R Level: .J/A Date: 4h f/) I / b hviewer: Date: 4 - c Lviewer:

A " Date: L h WNEF-8045.04 NE 8045 Original Page 1 of 1 Lpc # I

miner:

Level: &- Date:

viewer:

Date: w-viewer:

Date: J/c6 Date: 5-//--4/

VYNEE 8045.04 NE 8045 Original Page I of 1 LPC #I

EVALUATION OF DATA PROWED BY VT-1, CONTAINMENT SURFACES (IWE)

DATA SHEETNO: 8045-01-019 During RFO 21 IWEexaminationsit was discoveredthat the Joint Seal at tbe concrete to steel interface on the 238' level of the containmenthad failed and there was evidence of corrosion in areas of the seal. As a malt a portion of the circamferenceof the seal interface area was declared as augmented. The joint seal itselfwas also s c w e d for replacement during RFO-22.

At the start of RFO-22 the examinersperformed the requiredVT-1examinationsof the augmented area at thejoint seal to determine if any changes had occurred chningthe last operating cycle. The results ofthat examination meal no changes identified in the augmented area After the VT-1 exminationswere complete the processbegan for the joint seal replacement. A band of paint was removed from the concrete loor up the steel c o n t a i n t approximately 6" wide for the fizll ciKnU33ference. The recessed area for the joint seal was also cleaned m preparationfor the new seat installation. At this point a VT-3 examinationswas performedwhich identified a band of pitting that Covered much of the 360-degreecircumference. A more detailed VT-1was ordered by the Responsrwe Engineer to detail this area prior to paidseal hstiUion.

Thisjoint seal area was identified as an issue in the early 1990's. (ER-99-1594deals with the issues fiom the 1990's resolution). lo 1993 the joint seal area was cleaoed and painted so as to form a paintjoint seal at the concrete to seal interface. The areas identified during the EO-21 examinations were areas thatwere experiencing evidence of Oormsion and paint loss in tbis painteajoint area. Some of the paint was still intact and providhg protection for the steel it was covering.

The new areas of pitting inthe area of the joint seal are as a result of the coatingremovalto white metal in this area. This area was not previously identified during RFO-21 because it was an old area of pitting that had been coveredby the 1993 coating and had not experienced any further degradation. As a result ofthe coatings being completely removed from thisjoint area,this VT-1 examhation was able to map this region without the impedance of any obstruction.

The areas of pitthg are isolated to the general area of the joint seal interface between the concrete and the stel. The pitting subsides as it move up or down out of the joint seal area. This was evident when a portion of the steel surface was exposed as a result of the removal ofa concrete chip. The imcler d a c e area exposed was approximately !3" wide.and 3" &ep in a crescent shape. The worst case pitting is isolated to aband in the joint seal area from approximately %" wide to approximately 1" wide and is described in the report as areas w i 6 general wastage and connected pining AU corrosionidentified within this report is bounded by evaluation VYM 99/139, Based on this evaluation ail areas are well withinthe required design base metal thicknesses and are for continued operation as is.

/tA-!bKonnell IWE Responsible Engineer May 11,2001

Vermont Yankee Work Order No.:C)O -ms037-0cll _ _

LkJC Procedure No/Rev.:rYifBd 97 +ud. 1 Visual Examination Report Form for VT-3 Moisture Barriers, Gaskets and Seals (1.WE) Page I .of f Date: 5-f./-a/

~~

Visual Aids t Illumination Level Check Photo/Sketch 0 Magnifier I Light Source (Describe] Date F/dS&AW7-

$/+o/ =None Mirror Other:,&W?&iST E4 4!/@

NO. e/2rs3 ~~ --

&We +i3-ez Intermediate & + 0 Attached W Illumination Cardmumber. v)% 5-/9*/

Remarks Evaluation Required?

OYes I No qeviewer: Date r / / d o /

Y 3eviewer: Date Date FA/$@./

I WNEF 8047.08 NE 8047 Original Page 1 of 1

/3/

Data Sheet No: 2?M Work Order No,: 00 -LsOs~37-c80 Vermont Yankee Visual Examination Report Form for VT-3 Procedure NoiRev.: &~8Uf?7&0. 0 Evaluation Level Date 5-9-01 Required?

OYes @No Examiner: Level d(k Date  %

?M $u. &/hJ Reviewer:

WNEF 8047.07 NE 8047 Original Page 1 of 1

Vermont Yankee Procedure Nomev.: A!& 8 . ~ 7 / . b ~ d d Visual Examination Report Form for General Visual (IWE) Page I of 1 Date: &/6& -I Component Examiner: Level Date Reviewer: Date Reviewer: Date /e!&&

ANII:

1 1 W d Date &fd 60 v

VYNEF 8047.06 NE 8047 Original Page 3 of 1

Data Sheet No: Z W - CLQ- 3$4/

Vermont Yankee work Order NO.: 00 - o SO35 Procedure NolRev.: go9 ?/&9dd.

Visual Examination Report Form fur General Visual (IWE) Page- / of 1 Date: /4//6./09 ./

Component Component ID: % R ~ A BAVb

  • s- B s**tem:&+a*nl

. c AlCAnc Drawing NolRev.: sf& - 42 4% Location:

b 1 I Visual Aids Photo Sketch Method 0 Binoculars mane mane d e c t U Mirror D Attached U Attached 0 Remote d g h t Source 1 Examination Location Description/Remarks Remote Examination ConditionslEquipment Remarks i

Ex amin er: Level Date Date Dale /&4/&

Date (of?@

VYNEF 8047.06 NE 8047 Original Page 1 of 1

Vermont Yankee Procedure NolRev.: AIE 20 v ~AA.P.JPC Visual Examination Report Form for General Visual (IWE) Page 1 of 1 Date:Je//6/0Q 9 Component f i 5 p C . J -

Examiner: L e v e l & y j d h W Date ffh,h&

Examiner: Level Date Reviewer: Date Date <.& /.7

/

Date to-[?+

VYNEF 8047.b6 NE 8047 Original Page f of 1

e Data Sheet No:

6- 6 t J Work Order No.: 00 - 0 SO 35 Vermont Yankee Procedure NolRev.: 90 7/o/l;BNdd..

Visual Examination Report Form for General Visual (IWE) Page / of I ~ate:J0./6/0~ .-

. Y System:_Cl4u?La#J MCr J+

lrawing No/Rev.: sf& ..4.2- ' &/ 3 Location: RK &I.!

Visual Aids Photo Sketch Method 3 Binoculars @%one -one 6 e c t 7 Mirror 0 Attached 0 Attached 0 Remote d g h t Source Examination Location Description/Rernarks Remote Examination ConditionslEquipment Remarks 3 6" Scale &&;dRs;d is h M Gidkrk..

3 Other t4oM AJ a/+x;AO,c # 4u*q %I

- ~ -

%mination Results, Details and Comments:

Examiner: ~ Level Date Reviewer: Date VYNEF 8047.06 NE 8047 Original Page 1 of I

Work Order No.: 00 - 0 503s Vermont Yankee Procedure NolRev.: fd ~7/$&'9dd Visual Examination Report Form for Genera! Visual (IWE) Page I of / Date: / o / / G / ~ o 3 Component il Drawing NoIRev,: &20 - * ' Ad 620;~w~b Location: 4 &kd*.+~

Visual Aids Photo Sketch I VMethod 0 Binoculars G6L-Ie @&ne direct 0 Mirror 0 Attached . 0 Attached 0 Remote d g h t Source Examination Location DescriptionEiemarks Remote Examination ConditionslEquipment Remarks D 6" Scale &&L;$P &'Z cpc*, 8 8

'Uh D Other PLAtk&&.&J x 2 3 1 A,c, +E 1

Examination Results, DetaiIs and Comments:

II Examiner: Level Date Reviewer: Date VYNEF 8047.06 NE 8047 Original Page 1 of 1

e Data Sheet No: z d e - Ad- 3 5?

Work Order No.: 00 - 0%?3.$

Vermont Yankee Procedure NolRev.: &84~ 7 / & ! ; 9 4 & ~

Visual Examination Report Form fur General Visual (IWE) Page - / of 1 Date: /0//6/00 ./

Component 3rawing NolRev.: 3 2 a e ' Location: A ~ du#

W Visual Aids Photo Sketch Method I J Binoculars 6 o n e &ne h r e c t 3 Mirror D Attached CJ Attached 0 Remote idight Source Examination Location Oescription/Remarks Remote Examination ConditionslEquipment Remarks 7 6" Scale Ejafar*uPcs,nXoc*, bC 9 4 3 Other P*dcd;&J x> Ob A 3.1)

Examiner: Level Date Date Date /?&/oa Date !04?*

VYNEF 8047.06 NE 8047 Original Page 1 of 1

Data Sheet No:

Visual Examination Report Form Work Order No.: Ob - 0056 3500 VT-1, Bolting (WE)

ProcedureNoiRev.: wq5 &/o Page I of f Date: q/q*or II _ .

Ii 1 Component Component ID: V tb-14-5;4 System: Pc A C Photo/Sketch Method 8 Examination Bolting Components Examined done direct &Place dolting 0 Washers 1I Attached 0 Remote

- Removed Visual Aids 17 Bushings 17 Flange Surface 1 Magnifying Glass

&ilTor l5dight Source (Describe): pt%JcRf3 u &df Remote Examination ConditionsLimitations:

Examiner: + Level:= Date: 41 0 0 Yes Examiner: Level: *Date: Q IA Reviewer: Date: g/fh/

Reviewer: Date:

ANII: Date: 9-a u-o/

VYNEF 8045.03 NE 8045 Original Page 1 of 1

I Vermont Yankee I DataSheetNo: 6OQ3 c

-. c Oz.

Visual Examination Report Form Work Order No.: 00 00 5&35-00 ProcedureNoiRev.: NE 8ac(5r r(-b VT-1, Bolting @WE)

Page 1 of I Date: 4./9-0r Component Component ID: J lb-19-5B system: Pc A C r

DrawingNoRev.: 6 -19 117 s

' .I GI63 I

Boltinghgth @/A II

" Bolting Diameter: dA I' Phato/Sketch Method Examination Illumination Level Check direct 6 Place dolting 0 Washers Date

-0 Attached ~

1 Remote 1 0Removed El Bushings 0 Flange Surface ~

Initial 12=w 444d' Visual Aids Intermediate d/A dh%

Erosion /- I I Wear Jc Evidence of Leakage Other (Explain) c I 4 A I 44 I / +

Examiner: . Level:= Date: q*49 0 (

0 Yes Examiner: 44 Level: &Date: EJ /&

Reviewer: Date: #/&A/

1 Reviewer: Date:

VYNEF 8045.03 NE 8045 Original Page 1 of 1

1 Vermont Yankee I DataSheetNo: (Jib-(4-S Work Order No.: Ob 00 56 35-00

6) @%r-&/- a3 Visual Examination Report Form VT-1, BoIting (rwE)

FrocedureNoRev.: mq5 Page I of f Date: d*/?*Ol I

Component Component ID: VIb-fq-SC System: PCAC RemarkdObservations LooseNissing cl 4 4 4 A Thread Engagement 4 Thread Damage J Galling J ~

\ ~ ~~

Coating Degradation J I BenVTwisted J I I Physical Damage / I I Fractured Parts / I f Gouges .J Crack.s/I,inears J Corrosion / I I /

Erosion / f J 1 \

Evidence o f Leakage 4 Other (Emlaid . I W A @/A / +

Examiner: eve^: EDate: 3 (9 0\

,- Yes Examiner: L e v e l 4 A Date: 4 4 Reviewer: Date: {&$/$I Reviewer: Date:

ANII: Date: v-@/

VYNEF 8045.03 NE 8045 Original Page 1 of 1

Vermont Yankee Data Sheet No: &qs-oj- oq Work Order No.: 60 . 00 56 35-00 Visual Examination Report Form VT-1, Bolting (WE)

ProcedureNo/Rev.: At e/.

Page I of f Date: 4'/4 .d 1 r 1

.I 463 Bolting Length: c3/A " Bolting Diameter: "CIA Other (Explain) I I Examiner: Level: =Date: 3* f 9 0 Yes Examiner: Level: a

& Date: Jlh Reviewer: Date: Vh~ldi Reviewer: Date:

ANII: Date: +2 Wd/

VYNEF 8045.03 NE 8045 Original Page 1 of 1

Vermont Yankee Visual Examination Report Form v-1Bolting

, ow]E)

Cornponent Component ID: J lb cf 5-E System: WAC r

Drawing No/Rev.: 4 -14 I I 7 5 . I C!63 Bolting Length: @/& " Bolting Diameter: dA 11 PhotolSketch Method Examination BoIting Components Examined Illumination Level Check

&One direct d n Place rrB0lting E t Washers 0 Attached 0 Remote 0 Removed 0 Bushings 0 Flange Surface Initial Erosion WKW Evidence of Leakage Other Exthin) a Yes WNEF 8045.03 NE 8045 Original Page 7 of 1

Vermont Yankee Data Sheet No: -5 O b Visual Examination Report Form Work Order No.: 00 - 00 50 35-00 ProcedureNolRev.: N E W q 5 e/o VT-I, Bolting @WE)

Page 4 of I Date: 4 (4 *bI Component System: Pc A t umination Card/No.:

e D Yes VYNEF 8045.03 NE 3045 Original Page f of 1

Vermont Yankee I Data Sheet No:

Work Order No.: -

4 . do L / / U r - 00C7 Visual Examination Report Form ProcedureNoRev.: #&- 95 &U- /

VT-1, Bolting @WE)

Page / of / Date: 5-

/I Commnent I None Direct 0 In PIace iB Bolting Washers 0 Attached Remote H Removed Bushings = Flange Surface

/

0 Magnifying Glass Illumination Card/No.: Intermediate &?+ a/ #

CI Mirror Light Source (Describe): /%?Sxby& Find? $j$&,+~~p?&.&7-0/

Remote Examination ConditionsiLimitation: 8 OYes INo Date: d" O /

VYNEF 8045.03 NE 8045 Original Page 1 of 7

Work Order No.:

Visual Examination Report Form Procedure No/Rev.:

VT-1, Bolting @WE) Page / of /

Component

-/9 -5 9 System: ZGWS J7ZWS Bolting Length* dII Bolting Diameter: 7'50 "

PhotoISketch Method Examination BoIting Components Examined Illumination Level Check Bl None H Direct In Place Bolting LI Washers 0 Attached 0 Remote Removed Initial Visual Aids 0 Magnifying Glass Illumination CardMo.: Vy8

- Mirror Light Source (Describe): /%+s&&>&

c Remote Examination ConditionsKimitations:

Lightmeter Sht 15 3 U

Evaluation Required?

Level: Z D a t e : yd@/

UYes #No Level: &Date: EI/A f

Date: S7dd /

Reviewer: ../A Date:

H ANII; m Date: s-&-# o !

WNEF 8045.03 NE 8045 Original Page 1 of 1

Data Sheet No: zdg- 6 J- 398 Work Order No.: 00- 00 5 6 35 Vermont Yankee Procedure NolRev.: /?? 7 b 2 d,/O .

Visual Examination Report Form for Genera! Visual (IWE) Page I of / Date: '//L/af I

-~ ~

Component Visual Aids Photo Sketch Method

@I Binoculars B None @ None si] Direct &AH&

0 Mirror D Attached 17 Attached Remote

@ Light Source Examination Location DescriptionIRemarks Remote Examination ConditionslEquipment Remarks

[7 6" Scale Examiner: d/A Level I.'/A Date 4&

Reviewer: d/. Date (/A 1 Reviewer: dlA Date 1"/!

I

, ANII: Date

/-3/-o/

VYNEF 8047.06 NE 8047 Original Page 1 of 1 i

c Data Sheet NO: Li7 -01 . 0 31 Work Order No.: 00 - 50 3'7 Vermont Yankee Procedure NolRev.: 8OJ7 40 .

Visual Examination Report Form for General Visual (1WE) Page, 1 of 9 Date:af 8

--- ~ ~

Component Drawing NolRev.: 620 2 00 Location: W ~ C L Visual Aids Photo Sketch Method 0 Binoculars PQ None 0 Mirror 0 Attached Light Source Examination Location Descrjption/Remasks Remote Examination ConditionsEquipmsnt Remarks 0 6" Scale  %+4eter ~4 r CFC eC Reviewer: - Pfi 5ate ANII: Date &-Z-O/

W N E F 8047.06 NE 8047 Original Page 1 of 1

I

INSERVICE DISCREPANCY REPORT (IDR)

IDR #: Q2-07 Date : 5/2/2001, Component: Location: prvwe11 Performed By: Date :

Disposition/Repair:

IS1 Program Coordinator: Date :

R e p a i r Effort:

Reference Document:

Repair Completion D a t e :

Service Induced: YES - NO -BY : Dale :

Sample Expansion Required: YES -. NO BY: -Date:

Sample Expansion:

IS1 Program Coordinator: Date :

Reinspection Required: YES NO -BY :

Subsequent Inspection Required: YES - NO -BY :

IS1 Supervisor Notified:

IS1 Program Coordinator: Date:

. Reinspection Completed Satisfactorily:

IS1 Supervisor: Date :

IDR Closed:

ISI Program coordinator: Date:

VYAPF 4027.01 AP 4027 Rev. 4 +

Page 1 of 1

r 1 Data Sheet No: - 6 360 Work Order Na.:&

Vermont Yankee Procedure NofRev.: pp 702d'/U Visual Examination Report Form for General Visual (IWE) page I of 1 Date: !//&,/oI r r Component I Component ID: X- 5 4 fir% $'I4 system: 31 2 ~

- 3( c1

~/t Drawing NolRev.: 5 9 m - +f tocation: 4.r+4&d& --sUk.4AU Visual Aids Photo I Sketch Method

@ Binoculars I None p Direct 6444 -6 0 Mirror 0 Attached I3 Attached 0 Remote Light Source Examination Location Descriptionmemarks Remote' Exammation ConditionsEquipment Remarks 0 6" Scale B n y W

  • M pede b C & + l . t P - 4 yb 0 Other -a)4,C1O,&,F, 6--t ci Examination Results, Details and Comments:

WNEF 8047.06 NE 8047 Orighnal Page 1 of 1 f

Examiner: &

i

e DataSheetNo: soq7- o / - O g q Work Order No.: Odfl.55 3 6 Vermont Yankee 96 (/7 R o Procedure ~ o / ~ e v . :

Visual Examination Report Form for General Visual (IWE) Page / of / Date:&/* /

Component Component ID: X- 7 A +e',675

/ system: 4 4 cM I

Drawing NolRev.: xf&b Location: A- TL&I Visual Aids Photo Sketch Method I3 Binoculars f l None None @Direct U Mirror 0 Attached 0 Attached IJ Remote tight Source Examination Location Description/Remarks Remote Examination ConditionslEquipment Remarks 0 6" Scale . E*:dkdrJ gj&r.vd IJ Other . bE$dJcLk 4 Pwet 5 Jl-4 Examination Results, Details and Comments:

A.s"/h6C &..s e)o)+cl.;&c- Je b h wc .TAJ4 3 &dm. G l c'st,

  • a&#.

Examiner: Level Examiner: Level Reviewer: Date Y

Reviewer: Date w%

VYNEF 8047.06 NE 8047 Original Page 1 of 1

Visual Aids Photo Sketch Method 7 Binoculars p None E?None Direct &A Lr o , t 3 Mirror 0 Attached 0 Attached 0 Remote 8 Light Source Examination Location DescriptionlRemarks Remote Examination ConditionslEquipment Remarks 7 6 Scale b&pcu P4J.G u t a -

Examiner: E~/A Level nl/~ Date &/A Reviewer: /3/A Date *rA Reviewer:. #/A Date d1A ANII:  !/-by& Date /-2(&f CII VYNEF S0$7.06 NE 8047 Original Page I of 1 i

Data Sheet NO: 8047 - 01 B 43 Work Order No.: 00- 503 6 Vermont Yankee Procedure Nomev.: 84q7 40 Visual Examination Report Form for General Visual (IWE) Page / of 1 Date:d3lb/D J I---- Component I Component ID:

Drawing Nomev.:

X -9 & A SFLO .

.: System:

Location:

3 4dcLc ~

7 u ~ d c L .

Viual Aids Photo Sketch Method Binoculars None @ None JO Direct 6 ~ 0 ~ 4 Minor 0 Attached 0 Attached 0 Remote

.IExaminer: Level IReviewer:

Y N/A Date N/A VYNEF 8047.0.6 NE 8047 Original Page 1 of 1

Work Order No.: n0 c b S S ~?

Vermont Yankee Procedure NolRev.: b0 f? k b Visual Examination Report Form for General Visual (IWE) Page 1 of / Date: #&/

~~

Component I

kaminer: Level Date ixarniner: Level 4 Date .l//p .

kviewet: Date %c&

leviewer: Date .//A VY NEF 8047.09 NE8047 Original Page 1 of I

Vermont Yankee Procedure No/Rev.: Po47 R 0 Visual Examination Report Form for General Visual (IWE) Page / of I Date: +!,+IO{

Component Examiner:

3eviewer:

Y Level Date 7,

./ 36 C r /

Date Nh Reviewer: 4 4 Date ANII: Date r-#W VYNEF 8047.0.6 NE 8047 Original Page 1 of 1

Work Order No.: 60 00 - 50 3 5 Vermont Yankee Procedure NoIRev.: PP 7 6 aY%

Visual Examination Report Form for General Visual (IWE) Page  ! of / DaTe: @fd t Visual Aids Photo Sketch Method 3 Binoculars None $9None @ Direct b a d0 QC C 3 Mirror U Attached D Attached 0 Remote

~

$ Light Source Examination Location Descriptjon/Remarks Remote Examination ConditionsEquipment Remarks 3 6" Scale Oq hku, P.wLrlydc'M "/A 3 Other X-1>

Examination Results, Details and Comments:

Examiner: rl/d Level Date @4 Reviewer: .'/A Date /J/A Reviewer:

  • 1J/R Date Nh ANN: Date VYNEF 8047.06 NE 8047 Original Page 1 of 1 i

Vermont Yankee Procedure NolRev.: f/ 76 2 f h  ;

Visual Examination Reoort Form for General Visual '[IWE) Page of / Date:  !/lr/bf I Component Visual Aids Photo I Sketch I Method 0 Binoculars 9 Nene 13 Mirror D Attached 0 Attached [J Remote

$t Light Source Examination Location Description/Remarks Remati Examination ConditionsiEquipment Remarks c3 6" Scale 0 Other WNEF 8041.06 NE 8047 Original Page 1 of I i.

Work Order No.: 00 ST Vermont Yankee Visual Examination Report Form for General Visual (IWE)

Component Drawing NolRev.: Location:& &/A& &I Visual Aids I Photo I Sketch I Method 0 Binoculars 0 Mirror Light Source II W None El Attached I ab None 0 Attached Examination Location Descrip&n/Remarks I@ Direct 0 Remote

&EJY&

1 Remote. Examination ConditionsAquipment Remarks 0 6' Scale Examination Results, Details and'Comments:

Examiner: Level Examiner: Date dh VYNEF 8047.06 NE 8047 Original Page I of 1

Data Sheet No: C J - 38 Work Order No.: 00- Od so hs Vermont Yankee Procedure NofRev.: Pf 9 b 4 ,

Visual Examination Report Form for General Visual (IWE) Page I of I Date:_kICL?6 1 I Visual Aids Photo Sketch Method 0 Binoculars l,R None @ None @ Direct 6- ZY aC 0 Mirror U Attached U Attached 5 Remote Pp Light Source Examination Location Description/Remarks Remote Examination Conditionskquipment Remarks 0 6 Scale BFpuY fid&u46h VA 0 Other X-IbA VYNEF 8047.06 NE 8047 Original Page 1 of 1 i

Vermont Yankee Procedure NolRev.: 90 q7 Ro Visual Examination Report Form for Generat Visual (IWEI Page - 1 of - I Date: 5///0/

Component

omponent IO: Y-IGB -; System: ~&/Lc Xawing No/Rev.: 59- q/ Location: RX Visual Aids Phot0 Sketch I Method 7 Binoculars a None @ None $Direct trd+t&

3 Mirror CI Attached 0 Attached 0 Remote 8 Light Source Examination Location Descrbtionmemarks I Remote Examination ConditionsKquipment Remarks J 6" Scale Examiner: Levei Ni& Date IJ/A Reviewer: - Date 1 s7r/d I ,

VYNEF 8047.06 NE 8047 Original Page I of 1

e Data Sheet No: - 380 Work Order No.: -

06 ob 503s Vermont Yankee Procedure NolRev.: P L7ol,t'/o.

Visual Examination Report Form for General Visual (1WE) Page / of f Date: f//G /O/ t

~

Component Zornponent ID: X-17 System: D r ~ rkJ4 fl 3rawing NoJRev.: 5?W - t// Location: K ~ - f ; a r N ~5- lu: z .

Visuai Aids 0 Binoculars I

~

Photo r Sketch I Method 3 Mirror 0 Attached 0 Attached 0 Remote 9 tight Source Examination Location OescriptionlRemarks Remote Examination Cooditions/Equipment Remarks 3 6" Scate c'd rt VA Examiner: d/h Level Date p//n Reviewer: N/A Date /?/A Reviewer:' dA Date </A ANII: / - Date I-?/*(

VYNEF 8047.06 NE 8047 Original Page 1 of 1

\

r Data Sheet No: 06 - 4 v - 3W Work Order No.: 0 0 - 0 0 50'35 Vermont Yankee Procedure NoiRev.: @ 7 d 3. /o .

Visual Examination Report Form for General Visual (IWE) Page. t! of I Date;  :/16b/ i Visual Aids Photo Sketch Method 3 Binoculars @None *  !@None ,$$ Direct k d a P u-&

7 Mirror 0 Attached 0 Attached ICI Remote 8 Light Source Examination Location DescriptionlRemarks Remote ExaminationConditionslEquipment Remarks 7 6"Scale Examiner: AI/A Levef /?/R Date Nhd Reviewer: N/!! Date hr/p Reviewer: ' Date dh VYNEF 8047.06 NE 8047 Original Page 1 of 1 i

e Data Sheet NO: Z W - 6J- 378 Work Order No.: 60 40 s o 3s Vermont Yankee Procedure NolRev.: pfl 7O A V h ,

Visual Examination Report Form for General Visual (IWE) Page i of 1 Date: !11&!0/ /

Visual Aids Photo Sketch Method 13 Binoculars @ None D3 None @ Direct r-L D Mirror 0 Attached 0 Attached 0 Remote Light Source Examination Location Oescription/Remarks Remote Examination ConditionsiEquiprnent Remarks El 6 Scale b q w 4 fi&Cd,& &/A 0 Other x- i 4 V

Examiner: d1.k Level &/A Date M Reviewer: */A Date n11~

Reviewer: &/A Date If Date /-sI-of P

VYNEF 8047.06 NE 8047 Original Page Iof 1, t

Vermont Yankee Procedure NolFtev.:JC) $7 Ro Visual Examination Report Form for General Visual (I WE) Page / of 1 Date:<A,/O/

Component Component ID: x- 19 System: 3 / t L t k )et54

/

Drawing NolRev.: L Visual Aids photo Sketch Method Q Binoculars P N m pb None PDirect 6.tc~4 0 Mirror 0 Attached t3 Attached D Remote pLight Source Examination Location Descriptionmemarks Remote Examination ConditbnslEquipment Remarks U 6 n Scale c

b5;P Examiner: Level a* Date s///o1 Examiner: Level &/A Date *I//A Reviewer:A D a t e Reviewer: - +/A Date 131~

Date &-d- "',2/

VYNEF 6047.M NE BO47 Original Page I of 1

Visual Examination Report Form for General Visual (!WE) page [ of 1 Date: {//&/O/ I Component VYNEF 8047.06 NE 8047 Original Page 1 of 1 I

I Data Sheet No: zMo' 37 b Work Order No.: 40- 00 S O 3 s Vermont Yankee Procedure NolRev.: PP704o Visual Examination Report Form for General Visual (IWE) Page I of f Date: / / / 6 / 0 / I Component Component ID: x - a1 System: D / ~~ z 3 4 Drawing NdRev.: <9 20 4/ Location: AX-& PA/& S"&*.

r VisuaI Aids Photo Sketch Method

@Binoculars @Nons 4 None Direct t * & e ~

  • L 0 Mirror El Attached 0 Attached 0 Remote p l i g h t Source Examination Location DescriptionlRemarks Remote Examination ConditionslEquipment Remarks 6" Scale -yuC.CQ &u*M*.- qb Other - x-At Examination Results, Details and Comments:

25.F4-m.r H . c 62 4:s PLdPJ.Ih. 4 - X & S L iLL45.t A 3 , j0U (6 ry t a n 8 1 U h V S- , 5 h , w e , f ? d:C_ lQz"df&;L w #%

hlo 4*4?,-)Uto /u *&-e&& 5 y & &e

. 5*#,t &h, Examiner: &/A Level &/A Date #/A Reviewer: N/A Date 3h Reviewer: MIA Date $/A Date /-3td/

i M N E F 8047.06 NE 8047 Original Page 1 of 1 t

Vermont Yankee Visual Examination Report Form for General Visual (IWE) Page ! of- Date: !//6h/ I Component esults, Details and Comments:

Reviewer: A/A Reviewer: - d//3 Date&

Date /- 5 w U

WNEF 8047.06 .

NE 8047 Original Page 1 of 1 I

e Data Sheet NO: - - 037 SO#? O /

Work Order No.: 00 - 5037

  • Vermont Yankee Procedure Nomev.: 804'7 LQ Visual Examination Report Form for General Visual (IWE) Page / of Date: 5//6/

I Component Examiner: Level Date </~/OI Examiner: d/A)

Reviewer: Date /d 1

,Reviewer:

W N E F 8047.06 NE 8047 Original Page 1 a i 1

Work Order No.: 00- 0 0 fi 3 Vermont ~ i n i t e e Pcocdwa Nomev.: PP 702 9 /z, '

' Visual Examination Report Form for General Visual (1WE) Page of / ~ a t e : a / t Component Component IO: x-A?, System: -isnu d

  • l / i Drswing NolRev.: 5 7 2-3 -41 Location: &1;-kn NlLp & L i c e 0 Visual Aids Photo Sketch Method Binocdars E?None None Direct e&L 0 Mirror Cip tight Source D 6" Scale I

Reviewer: E3!A Date! Ni Reviewer: - '/A ate  ?/A WNG SDls"l.06 NE 8047 original Page 1 of 1 i

r Data Sheet No:

Work Order No.: 00 *5a 3'7 Vermont Yankee Procedure NolRev.: %q? 44%

Visual Examination Report Form for General Visual (IWEI Component

ornponeot ID: j(++ system: 3qd d Irawing NolRev.: -#a - #/ Location:

Visual Aids Photo Sketch Method 3 Binoculars p None None $ Direct 6wyroCe 3 Mirror 0 Attacbed D Attached D Remote YLight Source Examination Location Description/Remarks Remote Examination ConditionsEquipment Remarks 3 6" Scale 3 Other Z G h P d SJP-fPL NIA

xamination Results, Details and Comments:

Ixaminer: -4 4 Level Date &/A '

W N E F 8047.06 NE 8047 Original Page 1 of 1

I e Data Sheet No: D e - 6i/- 37%

Work Order No.: -

0 0 00 SO 3s I

f Vermont Yankee Visual Examination Report Form for General Visual ([WE)

Component Procedure ~ o m v . :

Page 4 of.- l PP 7 d Aq/Q Date:-j//e/o I Component IO: X-A4 System: -4 Drawing NofRev.: 5 9 P-D-CfI tocation: ~ X - L r 5tu ~ A~ d P

Visual Aids Photo Sketch Method Sinoculars pB None @ None @Direct 6~ It&

0 Mirrar 0 Attached 0 Attached 0 Remote

)?f tight Source Examination Location DescriptiodRemarks Remote Examination ConditionslEquipment Remarks ci 6" Scale Examiner; '/A Level .'/R Date A h Reviewer: flh Date 'h Reviewer:

Date d/!

II I

WNEF 8047.06 NE 8047 Original Page 1 of I i

Data Sheet NO: ZM 6 q w 39 8 7 Work Order No.: ba- 00 50 3s Vermont Yankee Procedure Nomev.: Pf 7o W / O Visual Examination Report Form for Generat Visual ( I WE] Page / of^-.

f Date: Vf6-hf I j

Component Component fD: L System: D/t~t -4 MNEF 8047.06 NE 8047 Original Page 1 of 1

Vermont Yankee Procedure NolRev.: #?? 742.9 /fl .

Visual Examination Report Form for General Visual (IWEj Component Component ID: - X - ~b System: 3 r~

Drawing NolRev.: .$?a> r q/ Location: 4 d ~ d d . -d. S A &6cd Visual Aids Photo Sketch i Method D Binoculars WNone l%r None Mirror a Attached D Attached n Remote Light Source 1 Examination Location DescfiptionlRemarks Remote Examination CondltionslEquiprnent Remarks 0 6" Scale 0 Other I Examination Results. Details and Comments:

c Examiner: '/A Level 4b Date IJ/A Reviewer: "/A Date 'h Reviewer:r. N/A Date 4~

VYNEF 8047.06 NE 8047 original Page 1 of 1 i

t Data Sheet No: goq 7-@/ - 8s Work Order No.: 80 - 503.6 Vermont Yankee Procedure No/Rev.: Rd g7 kb .

Visual Examination Report Form for General Visual (IWE) Page / of I Date: SfYb t r-

~ ~~~

Component Visual Aids Photo Sketch 0 Binoculars None @ None Direct L e j d 0 Mirror 0 Attached 0 Attached 0 Remote Light Source Examination Location DescriptionlRemarks Remote Examination ConditionslEquipment Remarks Q 6 Scale EfwcbQ 6&4hccL 0 Other b434 &.e-Level

/.rp 67 Date //A/

Examiner: Level Date  %%

Date d<h/

Reviewer: Date 4 4 Date J=5--+

I VYNEF 8047.06 N E 8047 Original Page 1 of 1 i

Vermont Yankee Procedure NclXev.: pp 7 d 2 d O .

Visual Examination Report Form for General Visual (IWE) Page I of 1 Date: !/'b,/nL 4 Component

mponeot ID: x- aS 1

Visual Aids Photo Sketch Method 8, Direct 6 4 + 4 Y

  • L 3 Binoculars pNm8 P o n e 9 Mirror 0 Attached 0 Attached 0 Remote a Light source Examination Location DesuiptionlRemarks Remote Examination ConditionslEquipment Remarks 3 6" Scale 39-4 P&cJru..c;h */A 3 Other x- 2-93 3amination Results, Details and Comments:

Examiner: Levat rJh Date A'lA qeviewer: 'h Date 44 VYN& 8047.06 NE 8047 Ofi&@l Page 1 of 1 i

Vermont Yankee procedure Nomev.: // 7&2Lf./o .

Visual Examination Report Farm for General Visual (IWE)

__ ~~

Component Zornponent tD: -

>rawing Nomev.: .<q to L(/fl Visual Aids I Photo I Skttch I Method 3 Binoculars @ None None p Direct 45*~u*L 3 Mirror 0 Attached 0 Attached Cl Remote 8 Light Source Examination Location Oescriptionjflernarkg Remote' Examinah CunditionslEquipment Remarks 3 6" Scale c1 Other x- ac9

&amination Results, Detals and Comments:

M N E f 8047,OS NE 8047 Orighal Page 1 of 1

t Data Sheet No: m g

  • Gc/-37r 9

Work Order No.: 0 0 -00se35 Vermont Yankee Procedure NolRev.: f?p762 c/./o.

Visual Examination ReDort Form for Visual Aids Photo Sketch Method 0 Binoculars p None )X None Direct &J*P a-L D Mirror U Attached 0 Attached 10 Remote Light Source Examination Location DescriptionlRemarks Remote Examination ConditionslEquipment Remarks 0 6" Scale

\

VYNEF 8067.06 NE 8047 Original Page 1 of 1 I

Vermont Yankee Procedure NolRev.: pp 26A$/0 '

Visuat Examination Report Form for General Visual (IWE) p a g e ~ o f I Date: :I/&/.

Component Component IO: c System: 3rt~LJCY Drawing NdRev.: -5733 - 5v Location: ba 3 u n . & t u c, Visual Aids Photo Sketch Method 0 Binoculars Q None 8 None @ Direct 6e h clbvc Mirror 0 Attached 0 Attached D Remota

@ light Swrce Examination Location Descriptionlftemarks Remote Examination CondifionslEquipment Remarks 0 6* Scale 3yjd.lrCQ P 4wC-cd;~ #/A I

WNEk 8047.06 NE 8047 Ofigind Page 7 of 1  ;

VYNS 804'7.06 NE 8047 Original Page 1 of 1 i

Work Order No.: ob DO 5035 Vermont Yankee Procedure NolRev.: pp 70 Wli7 .

Visua! Examination Report Form for General Visual (IWE)I Page / of / Date: !//.fh/ J Component Visual Aids Photo Sketch Method 3 Binoculars p None RNone FDirect 6 3 Mirror 0 Attached 0 Attached 0 Remote id Light Source Examination Location DescriptionfRemarks Remotd Examina?ian ConditionsiEquipment Remarks 3 6 ScaIe 0%Y u/ Y 94 N e f Pa-4 ;3 b J &/A 3 Other x- 33 VYNEk 8047.06 NE 8047 Original Page 1 of 1 I

I Vermont Yankee Procedure NolRev.: -@

Visual Examination Report Form for Page f

. of-. / Date: !/.L,/o/ r General Visual (IWE)

Component 1 Reviewer: Nh Date Iv/p VYNEF 8047.06 NE 8047 original Page 1 of 1 i

I Vermont Yankee Visual Examination General Visual (IWE)Form for Report Work Order No.:

Procedure NolRev.:

Page 'of 40 5 6 8oq? Ro 33 Date: s f i / U ( 1 Component I Sketch ID Attached I Remote VYNEF 8047.06 NE8047 Original Page 1 of 1

Vermont Yankee Procedure NolRev.: f P 7b R + / D .

Visual Examination Report Form for General Visual (IWE) Page of / Date: I//c./D/ I r--- ~

~ ~- ~

Component

~~

1 Component ID:

Drawing NolRev.:

X - 39 A + E 0- + I System:

Location:

3- CU, G ~ + ~sdA4EP.d AA a Visual Aids Photo Sketch Method 0 Binoculars Q None @ None Direct 6~

I3 Mirror U Attached 0 Attached 0 Remote Light Source Examination Location Descript;on,JRernarks Remote Examination ConditionslEquipment Remarks 0 6" Scale hhlueu P&AJ&+f& : b L s N]4 0 Other I X-39tAcB I, Examination Results, Details and Comments:

Examiner: #/A Level N h Date  %

Reviewer: #/A Date 4 Reviewer:

  • Date '%

VYNEF 0047.06 NE 8047 Original Page 1 of 1 i

Work Order No.: B d rr 5 0 3b Vermont Yankee Procedure NolRev.: db q? & a Visual Examination Report Form for General Visual (IWE) Page /of l Date: .C/<lo Component Component ID: &Y/ .: System: 39d d Drawing No/Rev.:

Visual Aids 593-0 -vi Photo I

Location:

Sketch I

a & L & u1 Method

-Id8*d -

0 Binoculars @ None B Norie $&.Direct 60~s-po~

0 Minor U Attached 0 Attached 0 Remote Light Source Examination Location Description/Remarks Remote Examination ConditiondEquiprnent Remarks 6 Scale G*+ef #d &*LCk&

0 osm b F > k ) c N psh)4, Examination Results, Details andcomrnents:

Examiner: IcI/A Level wr/A Date #/A Reviewer:

Y Date ri1Io1 Reviewer: * */A Date &!A ANI1: Date xg-o/

W N E F 8047.06 NE BO47 Original Page 1 of 1

Data Sheet No: z'c- 6Y- 3tz Work Order No.: 06 - 00 50 &

Vermont Yankee Procedure NolRev.: pp 7b > ~ / O Visual Examination Report Form for General Visual ~ I W E ) page I of 1 Date: )*//</&I P

Component Component ID: y-4L System: %A+ A* ~4 Drawing NolRev.: 5 7 Lc3 - L/I Location: ~ x . f - u d3 " 4 / R t E 5 Visual Aids Photo Sketch Method D Binoculars None None $' Direct b a d 4

' 0 Mirror 0 Attached 0 Attached I3 Remote fl Light Source Location Descriptionmemarks Remote' Examination ConditionslEquipmentRemarks E%eminsr?~an 0 6" Scale 1

Other )c- 5%. 1 Examination Results, Details and Comments:

I -,

Reviewer: "'/A Date Nh VYNEF 8047.06 NE 8047 drighal Page 1 of 1 i

Vermont Yankee I Visual Examination Report Foirm for Page .

f of f General Visual (1WE)

Component K- q.3 System: 3fp4 Component ID:

Drawing NolRev.: 5Tzo - Location: /ai%&&-AJ:I$++ (r -

Visual Aids Photo Sketch Method 0 Binoculars None @ None a Direct &

0 Attached D Remote 0 Attached W N E F 0047.06 N E a047 qriginal Page 1 of 1 i

Work Order No.: 0 0 - 0 4 5 0 3c Vermont Yankee Visual Examination Report Form for Procedure NotRev.: PP 70A${/O General Visual (IWE) Page I of I ~atet-1 Visuai Aids Phbto Sketch I Method D Binoculars FN- None $5 Direct 0 Mirror 0 Attached 0 Attached 0 Remote

-~ ~~

Light Source Examination Location DescriptionlRernarks Remote Examination ConditionslEquipment Remarks 0 S* Scale 3fi~""Lc P<&- (cw;0n/

V WNEF 8047.06 NE 8047 Original Page 1 of 1 i

I Work Order No.: 00 " 3 6' Vermont Yankee Procedure No/Rev.: 86 f 7 RO Visual Examination Report Form for General Visual (IWE) Page of I ate: c/.j.

Component Component ID: x47 .: system: >AS d 4 Drawing No/Rev.: sqw d f( Location: ut /de Visual Aids Photo Sketch Method 0 Binoculars f$ None None 9 Direct &A+&

0 Mirror 0 Attached C3 Attached D Remote

$ Light Source Examination Location DasctiptionlRemarks Remote Examination ConditionslEquiprnent Remark:

0 6" Scale GfW#uaQ &&&.ch "ish Examiner: Level */A. Date ~h Reviewer:

Reviewer: Date &h

-&ANII: g e Date X-A-Qf WNEF 8047.06 NE 8047 Original Page 1 of 1

Vermont Yankee Visual Examination Report Form for General Visual (IWE)

Procedure No/Rev.:

Page __ 1 of I

  • Date: !//&l'~ I

-~ - ~

Component Visual Aids Photo Sketch Method Binoculars Pp None p None Rirect 6*~ P c **

L 3 Mirror 0 Attached 17 Attached C l Remote R Light Source Examination Location Desctiption/Remarks Remote Examination ConditionslEquipment Remarks 7 6" Scale acc) 3& k*efr&&q l?ac*gcu I d

  • A:J L h Examiner: @/A Reviewer: Nh Date ~h4 Reviewer:- dJA I Date IJ/A ANI!: 1 J Date /-5/d V

WNEF 8047.06 NE 8047 Qn'gina1 Page 1 of 1 I

Data Sheet No: xu6- 386 Work Order No.: 00 %t SU 35 Vermont Yankee Procedure NolRev.: pp 7 Visual Examination Report Form for General Visual (]WE) Page I of I Date: !ii.?iil Component

omponent ID
x- 5-0 Visual Aids Photo Sketch Method 7 Binoculars  !) I None None )gl Direct 6.- a PaL 3 Mirror 0 Attached 0 Anached Remote rb Liaht Source Examination Location DescriDtion/Rernarks I Remote Examination CondkionslEquipment Remarks Reviewer: J/A Date VYNEF 8047.06 NE 8047 Original Page 1 of 1 i

I Data Sheet .N

.O work Order No.: 00 -00 5 0 3 5 Vermont Yankee Visual Examination Report Form for procedure NofRev.: PP 7azSI /A General Visual (IWE) Page of / -Date:  !//s/o[

Component W N E F 8047.06 NE 8047 Original Page 1 of 1

Vermont Yankee Procedure NoIRev.: @p 7 0 t f 10 .

Visual Examination Report Form for General Visual (IWE) Page I of I Date: ?/iS-/o! I

~~

Component hmponent ID: x-SL .* System: 3 i ~ h yd 4 -

Srawing No/Rev.: 59 xb - 4[ ' Location: & f- ARL 5A&-P Visual Aids Photo Sketch Method Binoculars 03 None @ None ,L3 Direct p0-C 0 Mirror 0 Attached D Attached 10 Remote

$ t i g h t Source Examination Location DescriptionlRemarks Remote. Examination ConditionsIEquipment Remarks D 6" Scale # oh) WA Examiner: tW Level 44 Date di!A Reviewer: Date dh Reviewer: - al4 Date '/A VYNEF 8047.06 NE 8047 Original Page 1 of 1 1

Vermont Yankee Visual Examination Report Form for General Visual (IWE)

Component

omponent ID: k-/o/ A,&r

.k,3 b System: CJCC LL Visual Aids Photo Sketch Method ql None Qb None 3 Binocufars Direct ~*AJI+*L 8 Minor 113 Attached 10 Attached 10 Remote 9 Light Source Remote Examination ConditionsEquiprnent Remarks 3 6" Scale f Other I '

Examiner; d!A Level J!h Date,&.

Reviewer: &!A Date d!A Reviewer: Date 4/,,

Bate  !/?la/ f, WNEF 8047.06 NE 8047 brlginal Page 1 of 1

a Data Sheet No: Z d E - .

3?9 r'

Work Order No.: c 9056 35 Vermont Yankee Procedure NO/REV.: PPI 4 & / 0 Visual Examination Report Form for General Visual (!WE) Page ot 1 Date:  ?//c/o/ t 1 t

I Component iD: x- /QO A! 6,c Component System: 'zs hL1 d 4 4

A Drawing NolRev.: <9 w - qi Location: EK+L/w~/G S u /r- Cfi c d Visual Aids Photo I Sketch Method 1 fa Direct &,A~P+ I 0 Remote marks Remote Examination ConditionslEquipment Remarks W N E F 8047.06 NE 8047 briginal .

Page 1 of 1 i

n Data Sheet No: - &Uc 391 I

Work Order No.: 00-00 5035 Vermont Yankee Procedure NolRev.: pp 702-$

Visual Examination Report Form for General Visual (IWE) Page f of 1 Date: ? j l ~ i / u i I Component hmponent ID:  %-lo?, System: Jc 1/1 I\

Visual Aids Photo Sketch Method 3 Binoculars &None 8 None 0 Direct N u t p**GsQ, 3 Mirror 0 Attached CI Attached 1o Remote 91 Light Source Examination location DescriptionlRemarks Remote-Examination ConditionslEquipment Remarks 7 6" Scale

"//t

-~ _ _

%amination Results, Details and Comments:

VVNEF 8047.06 NE 8047 Original Page 1 of 1

a Data Sheet No:

Vermont Yankee Visual Examination Report Form for General Visual (IWE) page 1 of t ate: !hdrh/

Component P

WNEF 0047.06 NE 8047 brigha!

Page 1 of f

r Data Sheet No: z u c o GLJ-387 Work Order No.: O U - ~ S ' O ~ S Vermont Yankee Procedure NolRev.: @p 76 ;?"? 1 0 .

Visual Examination Report Form for General Visual [IWE) Page t of I Date: i / i i / d / t Component

omponent io: X- J o(P System: 3 1 0 ~w LI

( .

Visual Aids Photo Sketch Method 3 Binoculars 9 None PpNone FDirect GWa t-*b

%.Mirror 0 Attached 0 Attached U Remote Light Source Examination Location Description/Remarks ' Remote Examination Conditions/EquipmentRemarks 0 6" Scale afip4.z P*,,*~rJQ;ord N/A Examiner: ~h Level NA Date *h Reviewer:. */A Date #/A Reviewer: @/A Date iJ/A ANII: I If Date ldT/*/

il WNEF 8047.06 NE 8047 Original Page 1 of I  !

I Work Order No.: 00-00 5 0 3s Vermont Yankee Procedure NolRev.: flP 70 3-q /a '

Visual Examination Report Farm for General Visual (IWE) p a g e l o f Date: 1/ic,,&

1 Component Visual Aids Photo Sketch Method 0 Binoculars None fFNone 9 Direct &*a ~ fCi U Attached 0 Attached Remote Examinatian Location Oescr$tion/Remarks Remote' Examination ConditionslEquiprnent Remarks 0 6" Scale 4 4 D Other x- 107 L .

VYNEF 8047.06 NE 8047 Original Page 1 of 1

Vermont Yankee I Visual Examination Report Form VT-1, Containment Surfaces (IWE) work Order NO.: bU* iL4 /7 DO ProcedureNoRev.: d& fb6 /k h1

. Page 1 of 2 Date: 534/

Remote Examination ConditiondEquiprnent Remarks Other (Explain)

Exminer: Level: 4 Date: EvaIuation Required?

Examiner: 4 Level: dh Date:

Reviewer:

Date: c/~L/ ayes d o Reviewer: /.I& me: aI/A ANII: H Date: s-Y-01 VYNEF 8045.02 NE 8045 Rev. 1 Page 1 of 1

Vermont Yankee Reference Data Sheet No:

Visual Examination Page 2 of Date: fA_/dl/o 1 r r Supplemental Report Form Component Zomponent ZD: )'2064 System: %w.3 f'

baminer: ."/R Level: ..fR Date: 4 ieviewer: 4 Date: sydk/

teviewer: 4 4 Date: 4k Date:  %/

VYNEF. 8045.04 NE 8045 Original Page 1 of 1 tpc #I

Vermont Yankee Data Sheet No: gocds- 6 01 3 Work Order No.: 00 -a0 46 1 7 4 0 0 Visual Examination Report Form Procedure NoRev.: Nk"g)oi/F -/ REV0 /

VT-1, Bolting OWE)

Page I of 1 Date: S- 3-o/

Bolting Length: 4 % ,' " Bolting Diameter:

PhotolSketch Method Examination Bolting Components Examined Ihmiaation Level Check dNone EfDirect I3 In Place dolting 0 Washers Visual Aids Intermediate c

_ _ _ _ _ ~ ~

0 Magnifying GIass Milmination c a r c ~ ~ o . : Y Y8 Intermediate /vA.

0 Mirror d i g h t Source (Describe):

Remote Examination ConditionslLimitations:

&& r c c /

w Final 223 /-./e 5h/$

NA Lightmeter SM: 8/2/53 Evaluation Required?

ayes 0%0 1Examiner: Level: .lkDate: &/A l WNEF 8045.03 N E 8045 Original Page 1 of 1

Vermont Yankee Data Sheet No: go fLs4c3 1 o/s" Visual Examination Report Form Work Order No.: U U - OU 96 s*.-0 4 0 Procedure NoRev.: 46 86 95 /e@. 0 VT-1, Bolting (rwE) page / of / Date: S - s n o /

VYNEF 8045.03 NE 8045 Original Page 1 of 1

Vermont Yankee gDataShmNo.zz Work Order No.: d d -dd 94/P-* CJ00 Visual Examination Report Form ProcedureNo/Rev.: N E ~ 9.5 o /pF& /

VT-1, Bolting (WE)

Page / of / Date: 5-3-a1 II Component CH/JC&-~ /'

Drawing NoRev.: 9 -62.o.L Meuuo

  • Bolting Length: ya" " Bolting Diameter:

I I I1 Ph otolSketch Method Examination BoltingComponents Examined ntumination Level Check II None Direct 0 In Place M Bolting 0 Washers Attached 0 Remote Removed 0 Bushings Flange Surface

__F I

Visual Aids Magnifying Glass w Illumination carmo.: @

0 Mirror 1Light Source (Describe): ,/=)%dL+~ f Remote Examination Conditionskimitations: #

/v/A- Lightmeter W. r/z/53 Evaluation Required?

OYes EN0 WNEF 8045.03 NE 8045 Original Page 1 of 1

WNEF 8047.06 NE 8047 Original Page Iof 1 i

Vermont Yankee Procedure NolRev.: /f 7oaq/b Visual Examination Report Form for General Visual (IWE) Page t of I Date: ~//tLol r Component Visual Aids Photo Sketch Method Binoculars ITP None @? None 9, Direct b*&*raC a Mirror D Attached [7 Attached 0 Remote

@ LightISource Examination Location DescriptionlRemarks 1 Remote Examination ConditionsEquipment Remarks VYNEF 8047.06 NE 8047 Original Page 1 of 1

Work Order No.: 0 0 - 00 5 0 35 Vermont Yankee Procedure NolRev.: PP 70 a'// O .

Visual Examination Report Form for General Visual (IWE) Page of / Date: I/IG/O / I I

Component System: Tu/Lv Q Visual Aids 1I Photo II Sketch I Method 0 Binoculars None @ None I@

1 Direct &IrFo-C 0 Mirror d)f Light Source Examination Location DescriptionlRemarks Remote Examination ConditionslEquiprnentRemarks

, 0 6" Scale 7'4 A W ' P*wa..hA:6&S v4

' 5 Other k-3 G+kk j Examination Results, Details and Comments:

VYNEF 8047.06 NE 8047 Original Page 1 of 1

Data Sheet No: b70 47 I e

0 32-Work Order No.: 06 - S O3 7 Vermont Yankee procedure Nomev.: %f7 40 Visual Examination Report Form for General Visual ([WE) Page - / of 1 Date: 5/..t/0[

t ComDonent Drawing NOlReV.: 59%-

Visual Aids Photo Sketch Method 0 Binoculars YNone @ None 09 Direct GJ-&

Mirror 0 Attached 10 Attached 10 Remote

~ ~

Light Source 1 Examination Location DescriptioniRemarks Remote Examination ConditionslEquipment Remarks 0 6" Scale Cl Other Examination Results, Details and Comments:

I Examiner:

Examiner: &&

Level@,

Level A+ 3 Date Date 5r/t/o A.&

/

Reviewer: Date <h&

Reviewer: - Date @

I ANII: &gH& Date d=t?&.

VYNEF 8047.06 NE 8047 Original Page 1 of 1

INSERVICE DISCREPANCY REPORT (IDR)

IDR #: lL!,AB Date : 5/2/2002 X-207A -

I Component: Location: Drvwell Performed By: Date:

Disposition/Repair:

IS1 Program Coordinator: Date :

Repair Effort:

Reference Document:

Repair Completion D a t e :

Service Induced: YES - NO -BY: Date:

Sample Ekpansion Required: YES - NO BY: Date:

Sample Expansion:

IS1 Program Coordinator: Date :

Reinspection Required: YES - NO BY:

Subsequent Inspection R e q u i r e d : YES - NO BY:

IS1 Supervisor Notified:

IS1 Program Coordinator: Date:

Reinspection Completed Satisfactorily:

IS1 Supervisor: Date:

IDR Closed:

ISI Program coordinator: Date :

WAPF 4027.01 AP 4027 Rev. 4

  • Page I of 1