Letter Sequence Approval |
---|
TAC:MD2361, Addition of LCO 3.0.8, Inoperability of Snubbers (Approved, Closed) |
|
MONTHYEARML0628502912006-10-18018 October 2006 Staff'S Review of CLIIP Amendment to Adopt TSTF-372 Project stage: Approval ML0703106272007-01-31031 January 2007 Technical Specifications, Issuance of Amendment 179 Inoperability of Snubbers Using the Consolidated Line Item Improvement Process Project stage: Approval ML0633201532007-01-31031 January 2007 License Amendment, Issuance of Amendment 179 Inoperability of Snubbers Using the Consolidated Line Item Improvement Process Project stage: Approval 2006-10-18
[Table View] |
|
---|
Category:Technical Specifications
MONTHYEARML23353A1712024-01-18018 January 2024 Issuance of Amendment No. 237 to Clarify Support System Requirements for the Residual Heat Removal System and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 ML23347A1212024-01-11011 January 2024 Issuance of Amendment No. 236 to Adopt TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Volume Values to Licensee Control EPID L-2023-LLA-0046) ML23228A0252023-09-25025 September 2023 Issuance of Amendment No. 234 to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML23166B0882023-09-20020 September 2023 Issuance of Amendment No. 233 for Adoption of Alternative Source Term and Revision of Technical Specifications ML23052A0462023-02-21021 February 2023 Enclosure 4 - Revised Technical Specifications (Retyped Version) ML23052A0452023-02-21021 February 2023 Enclosure 3 - Revised Technical Specifications (Red Line Version) ML23067A1692022-12-29029 December 2022 Technical Specifications, Chapter 3.4, Reactor Coolant System ML23067A1602022-12-29029 December 2022 Technical Specifications, Chapter 3.6, Containment Systems ML23067A1612022-12-29029 December 2022 Technical Specifications, Chapter 1, Use and Application ML23067A1622022-12-29029 December 2022 Technical Specifications, Chapter 3.1, Reactivity Control Systems ML23067A1642022-12-29029 December 2022 Technical Specifications, Chapter 5, Administrative Controls ML23067A1652022-12-29029 December 2022 Technical Specifications, Chapter 3.8, Electrical Power System ML23067A1672022-12-29029 December 2022 Technical Specifications, List of Effective Pages ML23067A1582022-12-29029 December 2022 Technical Specifications, Chapter 3.5, Emergency Core Cooling Systems (ECCS) ML23067A1682022-12-29029 December 2022 Technical Specifications, Chapter 4, Design Features ML23067A1702022-12-29029 December 2022 Technical Specifications, Chapter 3.9, Refueling Operations ML23067A1562022-12-29029 December 2022 Technical Specifications, Chapter 3.7, Plant Systems ML23067A1572022-12-29029 December 2022 Technical Specifications, Chapter 3.3, Instrumentation ML23067A1632022-12-29029 December 2022 Technical Specifications, Chapter 2, Safety Limits (Sls) ML23067A1592022-12-29029 December 2022 Technical Specifications, Chapter 3, Limiting Condition for Operation (LCO) and Surveillance Requirement (SR) Applicability ML23067A1662022-12-29029 December 2022 Technical Specifications, Table of Contents ML23067A1712022-12-29029 December 2022 Technical Specifications, Chapter 3.2, Power Distribution Limits ML22301A0072022-12-0202 December 2022 Issuance of Amendment No. 229 to Revise Technical Specifications to Adopt TSTF-505, Revision 2, and TSTF-439, Revision 2 ML22334A2572022-11-30030 November 2022 Proposed Technical Specification TOC Page (Markup) ML22334A2602022-11-30030 November 2022 Revised Technical Specification Pages (Clean Pages) ML22334A2592022-11-30030 November 2022 Revised Technical Specification Pages (Markup) ML22334A2582022-11-30030 November 2022 Proposed Technical Specification TOC Page (Clean Page) ML22285A1182022-10-12012 October 2022 Attachment 1 to Enclosure 1: Marked-Up Existing Technical Specifications ML22285A1192022-10-12012 October 2022 Attachment 2 to Enclosure 1: Revised Clean Technical Specifications ML22251A3452022-09-0808 September 2022 Attachment 2: Retyped TS Pages for TS 3.6.8 ML22251A3442022-09-0808 September 2022 Attachment 1: Marked-Up TS Pages for TS 3.6.8 ULNRC-06744, Revised Technical Specification Pages2022-08-0404 August 2022 Revised Technical Specification Pages ML22181B1322022-06-30030 June 2022 Attachment 2 - Replacement for Attachment 2, Proposed Technical Specification Changes (Mark-up), of ULNRC-06688 ML22181B1332022-06-30030 June 2022 Attachment 3 - Replacement for Attachment 3, Revised Technical Specification Pages, of ULNRC-06688, as Corrected in ULNRC-06702 ML22153A1772022-06-0202 June 2022 Attachment 1 - Marked-Up Existing Technical Specifications ML22153A1782022-06-0202 June 2022 Attachment 2 - Revised Clean Technical Specifications ML21343A0972021-12-0909 December 2021 Attachment 3: Revised Technical Specifications Pages ML21343A0962021-12-0909 December 2021 Attachment 2: Proposed Technical Specifications Changes (Mark-Up) ML21335A4562021-12-0101 December 2021 Enclosure 4: Retyped Technical Specification Pages ML21335A4552021-12-0101 December 2021 Enclosure 3: Proposed Technical Specification Changes (Mark-Up) ULNRC-06702, Enclosureplacement Version of Attachment 3 to ULNRC-06688, Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-5052021-11-24024 November 2021 Enclosureplacement Version of Attachment 3 to ULNRC-06688, Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505 ML21194A2842021-06-22022 June 2021 Technical Specification, Chapter 3.7, Plant Systems ML21194A2912021-06-22022 June 2021 Technical Specification, Chapter 3.9, Refueling Operations ML21194A2902021-06-22022 June 2021 Technical Specification, Chapter 4.0, Design Features ML21194A2892021-06-22022 June 2021 Technical Specification, List of Effective Pages ML21194A2882021-06-22022 June 2021 Technical Specification, Table of Contents ML21194A2872021-06-22022 June 2021 Technical Specification, Chapter 3.8, Electrical Power Systems ML21194A2852021-06-22022 June 2021 Technical Specification, Chapter 3.6, Containment Systems ML21194A2862021-06-22022 June 2021 Technical Specification, Chapter 5.0, Administrative Controls ML21194A2832021-06-22022 June 2021 Technical Specification, Chapter 3.2, Power Distribution Limits 2024-01-18
[Table view] |
Text
(4) UE, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use in amounts as required any byproduct, source of special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5) UE, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.
C. This license shall be deemed to contain and is subject to the conditions specified in the Commission's regulations set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1) Maximum Power Level UE is authorized to operate the facility at reactor core power levels not in excess of 3565 megawatts thermal (100% power) in accordance with the conditions specified herein.
(2) Technical Specifications and Environmental Protection Plan*
The Technical Specifications contained in Appendix A, as revised through Amendment No. 179 and the Environmental Protection Plan contained in Appendix B, are hereby incorporated in the license.
The licensee shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
(3) Environmental Qualification (Section 3.11. SSER #3)**
Deleted per Amendment No. 169 Amendments 133, 134, &135 were effective as of April 30,2000 however these amendments were implemented on April 1,2000.
The parentheticIa notation following the title of many license conditions denotes the section of the Safety Evaluation Report and/or its supplements wherein the license condition Is discussed.
Amendment 179
LCO Applicability 3.0 3.0 LIMITING CONDITION FOR OPERATION (LCO) APPLICABILITY LCO 3.0.1 LCOs shall be met during the MODES or other specified conditions in the Applicability, except as provided in LCO 3.0.2, LCO 3.0.7, and LCO 3.0.8. I LCO 3.0.2 Upon discovery of a failure to meet an LCO, the Required Actions of the associated Conditions shall be met, except as provided in LCO 3.0.5 and LCO 3.0.6.
Ifthe LCO is met or is no longer applicable prior to expiration of the specified Completion Time(s), completion of the Required Action(s) is not required unless otherwise stated.
LCO 3.0.3 When an'LCO is not met and the associated ACTIONS are not met, an associated ACTION is not provided, or if directed by the associated ACTIONS, the unit shall be placed in a MODE or other specified condition in which the LCO is not applicable. Action shall be initiated within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> to place the unit, as applicable, In:
- a. MODE 3 within 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br />;
- b. MODE 4 within 13 hours1.50463e-4 days <br />0.00361 hours <br />2.149471e-5 weeks <br />4.9465e-6 months <br />; and
- c. MODE 5 within 37 hours4.282407e-4 days <br />0.0103 hours <br />6.117725e-5 weeks <br />1.40785e-5 months <br />.
Exceptions to this Specification are stated in the individual Specifications.
Where corrective measures are completed that permit operation in accordance with the LCO or ACTIONS, completion of the actions required by LCO 3.0.3 is not required.
LCO 3.0.3 is only applicable in MODES 1, 2,3, and 4 (continued)
CALLAWAY PLANT 3.0-1 Amendment 179
LCO Applicability 3.0 3.0 LCO APPLICABI~LY (continued)
LCO 3.0.7 Test Exception LCO 3.1.8 allows specified Technical Specification (TS) requirements to be changed to permit performance of special tests and operations. Unless otherwise specified, all other TS requirements remain unchanged. Compliance with a Test Exception LCO is optional. When a Test Exception LCO is desired to be met but is not met, the ACTIONS of the Test Exception LCO shall be met. When a Test Exception LCO is not desired to be met, entry into a MODE or other specified condition in the Applicability shall be made in accordance with the other applicable Specifications.
LCO 3.0.8 When one or more required snubbers are unable to perform their associated support function(s), any affected supported LCO(s) are not required to be declared not met solely for this reason if risk is assessed and managed, and:
- a. the snubbers not able to perform their associated support function(s) are associated with only one train or subsystem of a multiple train or subsystem supported system or are associated with a single train or subsystem supported system and are able to perform their associated support function within 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />s: or
- b. the snubbers not able to perform their associated support function(s) are associated with more than one train or subsystem of a multiple train or subsystem-supported system and are able to perform their associated support function within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
At the end of the specified period the required snubbers must be able to perform their associated support function(s), or the affected supported system LCO(s) shall be declared not met.
CALLAWAY PLANT 3.0-3 Amendment 179