MONTHYEARML0619904872006-07-0606 July 2006 Technical Specifications Change 06-04, Monitoring of Control or Shutdown Rod Position by an Alternate Means. Project stage: Request ML0631205752006-12-11011 December 2006 License Amendment, Issuance of Amendment Regarding Alternate Rod Position Monitoring Method (TAC Nos. MD2514 and MD2515) (TS-06-04) Project stage: Approval ML0634804802006-12-11011 December 2006 Technical Specifications, Issuance of Amendment Regarding Alternate Rod Position Monitoring Method Project stage: Approval ML0703002092007-02-0606 February 2007 Corrected Technical Specification Page for Amendment No. 304 Regarding Alternate Rod Position Monitoring Method (TS-06-04) Project stage: Other L-2007-175, Rod Position Indication Systems2007-11-12012 November 2007 Rod Position Indication Systems Project stage: Other 2006-07-06
[Table View] |
|
---|
Category:Letter
MONTHYEARML24032A0202024-01-31031 January 2024 NPDES Biocide/Corrosion Treatment Plan Annual Report, Cy 2023 ML23319A2452024-01-29029 January 2024 Issuance of Amendment Nos. 366 and 360; 164 and 71 Regarding the Adoption of TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions ML24018A0142024-01-17017 January 2024 Engine Systems, Inc., Report No. 10CFR21-0137, Rev. 1, 56913-EN 56913 ML24011A3182024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), October 2023 ML24011A3172024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), September 2023 ML24011A3202024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), December 2023 ML24011A3162024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), August 2023 ML24011A3192024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), November 2023 IR 05000327/20234422024-01-11011 January 2024 95001 Supplemental Inspection Report 05000327/2023442 and 05000328/2023442 and Follow-Up Assessment Letter ML24010A2132024-01-10010 January 2024 CFR 21.21 Final Report Regarding Siemens Medium Voltage Circuit Breakers ML24018A0952024-01-0404 January 2024 Engine Systems, Inc., 10CFR21 Reporting of Defects and Non-Compliance Report No. 10CFR21-0137, Rev. 0 ML24004A0332024-01-0303 January 2024 Interim Report of a Deviation or Failure to Comply Crompton Instruments Type 077 Ammeter ML24004A0402024-01-0303 January 2024 Response to NRCs November 8, 2023, Request for Additional Information - Related to Independent Spent Fuel Storage Installation CNL-23-068, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNL-23-036, Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08)2023-12-18018 December 2023 Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) ML23346A1222023-12-12012 December 2023 Annual Non-Radiological Environmental Operating Report - 2023 IR 05000327/20234202023-11-28028 November 2023 Security Baseline Inspection Report 05000327/2023420 and 05000328/2023420 CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23324A4362023-11-0909 November 2023 Exam Corporate Notification Letter Aka 210-day Letter ML23307A0822023-11-0808 November 2023 Request for Additional Information August 4, 2022, Exemption Request for Deviating from the Conditions of Certificate of Compliance No. 1032, Amendment No. 3, Related to Sequoyah Nuclear Plant Independent Spent Fuel Storage Installation IR 05000327/20230032023-11-0303 November 2023 Integrated Inspection Report 05000327/2023003 and 05000328/2023003 ML23306A1592023-11-0202 November 2023 Enforcement Action EA-22-129 Inspection Readiness Notification ML23292A0792023-10-19019 October 2023 Tennessee Valley Authority - Emergency Plan Implementing Procedure Revision, Includes EPIP-5, Revision 58, General Emergency IR 05000327/20230112023-10-16016 October 2023 Triennial Fire Protection Inspection Report 05000327/2023011 and 05000328/2023011 ML23285A0882023-10-12012 October 2023 Submittal of Sequoyah Nuclear Plant, Units 1 and 2, Submittal of Updated Final Safety Analysis Report Amendment 31 ML23284A4252023-10-11011 October 2023 10 CFR 50.59 and 10 CFR 72.48 Changes, Tests, and Experiments Summary Report; Commitment Summary Report; and Update to the Fire Protection Report ML23283A2792023-10-10010 October 2023 Revisions to the Sequoyah Nuclear Plant Units 1 and 2 Technical Requirements Manual ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23277A0462023-10-0404 October 2023 Revisions to the Sequoyah Nuclear Plant Units 1 and 2 Technical Specification Bases ML23275A0272023-09-29029 September 2023 Submittal of Discharge Monitoring Report (DMR) Quality Assurance Study 43 Final Report 2023 ML23271A1662023-09-28028 September 2023 Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2) CNL-23-059, Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-2023-09-20020 September 2023 Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision IR 05000327/20234032023-09-14014 September 2023 Cyber Security Inspection Report 05000327/2023403 and 05000328/2023403 (Cover Letter) ML23257A0062023-09-14014 September 2023 Enforcement Action EA-22-129 Inspection Postponement Request ML23254A2192023-09-11011 September 2023 Emergency Plan Implementing Procedure Revisions ML23254A0652023-09-0707 September 2023 Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2) CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000327/20230052023-08-29029 August 2023 Updated Inspection Plan for Sequoyah Nuclear Plant, Units 1 and 2 - Report 05000327/2023005 and 05000328/2023005 ML23233A0122023-08-17017 August 2023 Unit 1 Cycle 25 Refueling Outage - 90-Day Inservice Inspection Summary Report - Supplement ML23233A0142023-08-15015 August 2023 Discharge Monitoring Report (Dmr), July 2023 ML23215A1212023-08-0303 August 2023 301 Exam Administrative Items (2B) Normal Release ML23215A1572023-08-0303 August 2023 Enforcement Action EA-22-129 Inspection Readiness Notification CNL-23-028, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06)2023-08-0202 August 2023 Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06) ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information 2024-01-04
[Table view] |
Text
February 6, 2007 Mr. Karl W. Singer Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
SUBJECT:
SEQUOYAH NUCLEAR PLANT, UNIT 2 - CORRECTED TECHNICAL SPECIFICATION PAGE FOR AMENDMENT NO. 304 REGARDING ALTERNATE ROD POSITION MONITORING METHOD (TAC NO. MD2515)
(TS-06-04)
Dear Mr. Singer:
The U.S. Nuclear Regulatory Commission issued Amendment No. 304 to Facility Operating License No. DPR-79 for the Sequoyah Nuclear Plant, Unit 2, on December 11, 2006, in response to your application dated July 6, 2006. This amendment revised Action a of Technical Specification (TS) Limiting Condition for Operation (LCO) 3.1.3.2, Position Indication Systems -
Operating, to allow use of an alternate means other than the movable incore detectors to monitor the position of a control or shutdown rod should problems occur with the analog rod position indication system.
Subsequent to issuance, it was discovered that the word or had been omitted at the end of LCO Action a.2.c on page 3/4 1-17 of the Unit 2 TSs. Enclosed is a corrected TS Page.
Please replace the page issued on December 11, 2006, with the enclosed. This merely corrects an administrative error and does not affect the technical content of Amendment No. 304 and its associated safety evaluation.
Sincerely,
/RA/
Brendan T. Moroney, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-328
Enclosure:
Corrected TS Page 3/4 1-17 cc w/enclosure: See next page
ML070300209 NRR-058 Package: ML070300184 Tech Spec: ML070390365 OFFICE LPL2-2/PM LPL2-2/LA LPL2-2/BC (A)
NAME BMoroney RSola MChernoff DATE 2/6/07 2/5/07 2/6/07 Mr. Karl W. Singer SEQUOYAH NUCLEAR PLANT Tennessee Valley Authority cc:
Mr. Ashok S. Bhatnagar, Senior Vice President Mr. Randy Douet, Site Vice President Nuclear Operations Sequoyah Nuclear Plant Tennessee Valley Authority Tennessee Valley Authority 6A Lookout Place P.O. Box 2000 1101 Market Street Soddy Daisy, TN 37384-2000 Chattanooga, TN 37402-2801 Mr. Glenn W. Morris, Manager Mr. Preston D. Swafford, Senior Vice President Licensing and Industry Affairs Nuclear Support Sequoyah Nuclear Plant Tennessee Valley Authority Tennessee Valley Authority 6A Lookout Place P.O. Box 2000 1101 Market Street Soddy Daisy, TN 37384-2000 Chattanooga, TN 37402-2801 Mr. David A. Kulisek, Plant Manager Mr. Larry S. Bryant, Vice President Sequoyah Nuclear Plant Nuclear Engineering & Technical Services Tennessee Valley Authority Tennessee Valley Authority P.O. Box 2000 6A Lookout Place Soddy Daisy, TN 37384-2000 1101 Market Street Chattanooga, TN 37402-2801 Senior Resident Inspector Sequoyah Nuclear Plant General Counsel U.S. Nuclear Regulatory Commission Tennessee Valley Authority 2600 Igou Ferry Road 6A West Tower Soddy Daisy, TN 37379 400 West Summit Hill Drive Knoxville, TN 37902 Mr. Lawrence E. Nanney, Director Division of Radiological Health Mr. John C. Fornicola, Manager Dept. of Environment & Conservation Nuclear Assurance Third Floor, L and C Annex Tennessee Valley Authority 401 Church Street 6A Lookout Place Nashville, TN 37243-1532 1101 Market Street Chattanooga, TN 37402-2801 County Mayor Hamilton County Courthouse Ms. Beth A. Wetzel, Manager Chattanooga, TN 37402-2801 Corporate Nuclear Licensing and Industry Affairs Ms. Ann P. Harris Tennessee Valley Authority 341 Swing Loop Road 4X Blue Ridge Rockwood, TN 37854 1101 Market Street Chattanooga, TN 37402-2801 Mr. Robert H. Bryan, Jr., General Manager Licensing and Industry Affairs Tennessee Valley Authority 4X Blue Ridge 1101 Market Street Chattanooga, TN 37402-2801