Category:Letter type:L
MONTHYEARL-23-267, Submittal of Discharge Monitoring Report (Npdes), Permit No. PA00256152023-12-18018 December 2023 Submittal of Discharge Monitoring Report (Npdes), Permit No. PA0025615 L-23-229, Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports2023-11-29029 November 2023 Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports L-23-247, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-11-17017 November 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-23-227, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 20232023-10-20020 October 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 2023 L-23-208, Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA00256152023-09-14014 September 2023 Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA0025615 L-23-167, Twenty-Third Refueling Outage Inservice Inspection Summary Report2023-09-13013 September 2023 Twenty-Third Refueling Outage Inservice Inspection Summary Report L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-179, Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA00256152023-07-18018 July 2023 Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA0025615 L-23-165, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-06-26026 June 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-23-139, Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report2023-06-13013 June 2023 Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report L-23-055, Submittal of the Updated Final Safety Analysis Report, Revision 342023-05-23023 May 2023 Submittal of the Updated Final Safety Analysis Report, Revision 34 L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report L-23-137, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-05-18018 May 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-23-125, Cycle 24 Core Operating Limits Report2023-05-17017 May 2023 Cycle 24 Core Operating Limits Report L-23-132, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-10010 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations L-23-129, Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations2023-05-0505 May 2023 Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations L-23-115, Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological2023-04-27027 April 2023 Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological L-23-126, Discharge Monitoring Report (Npdes), Permit No. PA00256152023-04-22022 April 2023 Discharge Monitoring Report (Npdes), Permit No. PA0025615 L-23-053, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-04-14014 April 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-061, Submittal of the Decommissioning Funding Status Reports2023-03-31031 March 2023 Submittal of the Decommissioning Funding Status Reports L-23-058, 180-Day Steam Generator Tube Inspection Report2023-03-27027 March 2023 180-Day Steam Generator Tube Inspection Report L-23-066, Annual Notification of Property Insurance Coverage2023-03-21021 March 2023 Annual Notification of Property Insurance Coverage L-23-036, Report of Facility Changes, Tests and Experiments2023-03-13013 March 2023 Report of Facility Changes, Tests and Experiments L-23-086, Response to Request for Additional Information for Emergency License Amendment Request for Technical Specification 3.5.2 Regarding One-Time Action for Valve Leak Repair2023-03-0404 March 2023 Response to Request for Additional Information for Emergency License Amendment Request for Technical Specification 3.5.2 Regarding One-Time Action for Valve Leak Repair L-23-087, Supplement to Emergency License Amendment Request for Technical Specification 3.5.2 Regarding One-Time Action for Valve Leak Repair (L-2023-LLA-0027)2023-03-0404 March 2023 Supplement to Emergency License Amendment Request for Technical Specification 3.5.2 Regarding One-Time Action for Valve Leak Repair (L-2023-LLA-0027) L-23-073, Emergency License Amendment Request for Technical Specification 3.5.2 Regarding One-Time Action for Valve Leak Repair2023-03-0101 March 2023 Emergency License Amendment Request for Technical Specification 3.5.2 Regarding One-Time Action for Valve Leak Repair L-23-016, Twenty-Eighth Refueling Outage Inservice Inspection Summary Report2023-02-21021 February 2023 Twenty-Eighth Refueling Outage Inservice Inspection Summary Report L-23-064, Discharge Monitoring Report, (NPDES) Permit No. PA00256152023-02-21021 February 2023 Discharge Monitoring Report, (NPDES) Permit No. PA0025615 L-23-057, Energy Harbor Nuclear Corp Retrospective Premium Guarantee2023-02-20020 February 2023 Energy Harbor Nuclear Corp Retrospective Premium Guarantee L-22-193, Request for Exemption from Specific Provisions in 10 CFR 50 Appendix H2023-02-14014 February 2023 Request for Exemption from Specific Provisions in 10 CFR 50 Appendix H L-22-286, Supplement to Request for an Amendment to Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time2023-02-14014 February 2023 Supplement to Request for an Amendment to Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time L-23-032, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Second Half of 20222023-01-23023 January 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Second Half of 2022 L-22-281, Discharge Monitoring Report (NPDES) Permit No. PA00256152022-12-16016 December 2022 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-22-246, Response to Request for Additional Information Regarding a Request to Consolidate Fuel Decay Time Technical Specifications to New LCO2022-12-0707 December 2022 Response to Request for Additional Information Regarding a Request to Consolidate Fuel Decay Time Technical Specifications to New LCO L-22-217, Submittal of Discharge Monitoring Report (NPDES) Permit No. PA00256152022-11-21021 November 2022 Submittal of Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-22-226, Emergency Preparedness Plan2022-11-0404 November 2022 Emergency Preparedness Plan L-22-222, Cycle 29-1 Core Operating Limits Report2022-10-31031 October 2022 Cycle 29-1 Core Operating Limits Report L-22-228, Independent Spent Fuel Storage Installation Changes, Tests, and Experiments2022-10-26026 October 2022 Independent Spent Fuel Storage Installation Changes, Tests, and Experiments L-22-200, Response to Request for Additional Information Regarding a 180-Day Steam Generator Tube Inspection Report Fall 2021 Refueling Outage2022-10-21021 October 2022 Response to Request for Additional Information Regarding a 180-Day Steam Generator Tube Inspection Report Fall 2021 Refueling Outage L-22-232, Withdrawal of a License Amendment Request Associated with Fire Protection Program Changes2022-10-21021 October 2022 Withdrawal of a License Amendment Request Associated with Fire Protection Program Changes L-22-238, Submittal of Discharge Monitoring Report (NPDES) Permit No. PA00256152022-10-20020 October 2022 Submittal of Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-22-227, Revised August 2022 Outfall 003 & 004 NPDES Discharge Monitoring Report (Dmr), Revised Daily Effluent Monitoring Report Forms for Outfalls 003 & 004 and Corrective Action Letter from Eurofins2022-10-0303 October 2022 Revised August 2022 Outfall 003 & 004 NPDES Discharge Monitoring Report (Dmr), Revised Daily Effluent Monitoring Report Forms for Outfalls 003 & 004 and Corrective Action Letter from Eurofins L-22-219, Submittal of Discharge Monitoring Report (NPDES) Permit No. PA00256152022-09-26026 September 2022 Submittal of Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-22-204, Submittal of Evacuation Time Estimates2022-09-0707 September 2022 Submittal of Evacuation Time Estimates L-22-137, Request for Fire Protection Program Changes2022-09-0606 September 2022 Request for Fire Protection Program Changes L-21-238, License Amendment Request for Addition of Analytical Methodology to the Core Operating Limits Report for a Full Spectrum Loss of Coolant Accident2022-08-31031 August 2022 License Amendment Request for Addition of Analytical Methodology to the Core Operating Limits Report for a Full Spectrum Loss of Coolant Accident L-22-188, Response to Request for Additional Information Regarding Steam Generator Inspection Report- Fall 2021 Refueling Outage2022-08-22022 August 2022 Response to Request for Additional Information Regarding Steam Generator Inspection Report- Fall 2021 Refueling Outage L-22-191, Spent Fuel Storage Cask Registration2022-08-17017 August 2022 Spent Fuel Storage Cask Registration 2023-09-14
[Table view] |
Text
FENOC FirstEnergyNuclearOperatingCompany James H. Lash 724-682-5234 Site Vice President Fax: 724-643-8069 December 21, 2006 L-06-171 ATTN: Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC 20555-0001
Subject:
Beaver Valley Power Station, Unit 1 BV-1 Docket No. 50-334, License No. DPR-66 Revised Commitment Date Relevant to FirstEnergy Nuclear Operating Company Correspondence to the NRC, Dated September 29, 2006 On September 13, 2004, the NRC issued Generic Letter 2004-02 relating to debris blockage on emergency recirculation during design basis accidents. FirstEnergy Nuclear Operating Company (FENOC) submitted the initial response in letter L-05-146, dated September 6, 2005. Subsequently, FENOC provided a supplemental response to the NRC by letter L-06-020, dated April 3, 2006. Contained within letter L-06-020, FENOC made commitments regarding specific implementation actions supporting FENOC's
,response to the Generic Letter.
Due to vendor activities with other utilities, the completion date for prototype testing of the proposed BVPS-1 strainer design (L-06-020 Commitment Number 2) was rescheduled for December 31, 2006. The revised commitment schedule was communicated to the NRC in letter L-06-145, dated September 29, 2006.
Due to ongoing schedule delays, an evaluation is being performed to ascertain the potential impact and benefits of alternate strainer designs and manufacturers. Ultimately, this evaluation and potential change in vendors will further delay prototype testing.
FENOC is submitting a revised commitment to complete the prototype testing prior to strainer installation. Because the strainer prototype testing is included in the design activities, no specific completion date is provided. Currently, BVPS-1 strainer installation is scheduled for the fall 2007 (IR18) refueling outage. The revised commitment does not reflect a change to the final completion due date for the remaining items related to Generic Letter 2004-02.
4 Beaver Valley Power Station, Unit 1 Revised Commitment Date L-06-171 Page 2 Regulatory commitments submitted with this letter are listed in the attachment. If there are any questions or if additional information is required, please contact Henry L. Hegrat, Supervisor - Fleet Licensing at (330) 315-6944.
Sincerely, H. Lash Attachment - Regulatory Commitment cc: Mr. T. G. Colburn, NRR Senior Project Manager Mr. P. C. Cataldo, NRC Senior Resident Inspector Mr. S. J. Collins, NRC Region I Administrator Mr. D. A. Allard, Director BRP/DEP Mr. L. E. Ryan (BRP/DEP)
Attachment to FENOC Letter L-06-171 Page 1 of 1 REGULATORY COMMITMENT The following list identifies those actions committed to by FirstEnergy Nuclear Operating Company (FENOC) for Beaver Valley Power Station (BVPS) Unit No. 1 in this document. Any other actions discussed in the submittal represent intended or planned actions by FENOC. They are described only as information and are not regulatory commitments. Please notify Mr. Henry L. Hegrat, Supervisor - Fleet Licensing at (330) 315-6944 of any questions regarding this document or associated regulatory commitments.
Commitment Due Date
- 1. Prototype testing of proposed BVPS- 1 strainer Prior to strainer installation design. during fall 2007 refuel outage (1R18).
Text
FENOC FirstEnergyNuclearOperatingCompany James H. Lash 724-682-5234 Site Vice President Fax: 724-643-8069 December 21, 2006 L-06-171 ATTN: Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC 20555-0001
Subject:
Beaver Valley Power Station, Unit 1 BV-1 Docket No. 50-334, License No. DPR-66 Revised Commitment Date Relevant to FirstEnergy Nuclear Operating Company Correspondence to the NRC, Dated September 29, 2006 On September 13, 2004, the NRC issued Generic Letter 2004-02 relating to debris blockage on emergency recirculation during design basis accidents. FirstEnergy Nuclear Operating Company (FENOC) submitted the initial response in letter L-05-146, dated September 6, 2005. Subsequently, FENOC provided a supplemental response to the NRC by letter L-06-020, dated April 3, 2006. Contained within letter L-06-020, FENOC made commitments regarding specific implementation actions supporting FENOC's
,response to the Generic Letter.
Due to vendor activities with other utilities, the completion date for prototype testing of the proposed BVPS-1 strainer design (L-06-020 Commitment Number 2) was rescheduled for December 31, 2006. The revised commitment schedule was communicated to the NRC in letter L-06-145, dated September 29, 2006.
Due to ongoing schedule delays, an evaluation is being performed to ascertain the potential impact and benefits of alternate strainer designs and manufacturers. Ultimately, this evaluation and potential change in vendors will further delay prototype testing.
FENOC is submitting a revised commitment to complete the prototype testing prior to strainer installation. Because the strainer prototype testing is included in the design activities, no specific completion date is provided. Currently, BVPS-1 strainer installation is scheduled for the fall 2007 (IR18) refueling outage. The revised commitment does not reflect a change to the final completion due date for the remaining items related to Generic Letter 2004-02.
4 Beaver Valley Power Station, Unit 1 Revised Commitment Date L-06-171 Page 2 Regulatory commitments submitted with this letter are listed in the attachment. If there are any questions or if additional information is required, please contact Henry L. Hegrat, Supervisor - Fleet Licensing at (330) 315-6944.
Sincerely, H. Lash Attachment - Regulatory Commitment cc: Mr. T. G. Colburn, NRR Senior Project Manager Mr. P. C. Cataldo, NRC Senior Resident Inspector Mr. S. J. Collins, NRC Region I Administrator Mr. D. A. Allard, Director BRP/DEP Mr. L. E. Ryan (BRP/DEP)
Attachment to FENOC Letter L-06-171 Page 1 of 1 REGULATORY COMMITMENT The following list identifies those actions committed to by FirstEnergy Nuclear Operating Company (FENOC) for Beaver Valley Power Station (BVPS) Unit No. 1 in this document. Any other actions discussed in the submittal represent intended or planned actions by FENOC. They are described only as information and are not regulatory commitments. Please notify Mr. Henry L. Hegrat, Supervisor - Fleet Licensing at (330) 315-6944 of any questions regarding this document or associated regulatory commitments.
Commitment Due Date
- 1. Prototype testing of proposed BVPS- 1 strainer Prior to strainer installation design. during fall 2007 refuel outage (1R18).