December 20, 2006 Tennessee Valley Authority ATTN:
Mr. Karl W. Singer Chief Nuclear Officer and Executive Vice President 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
SUBJECT:
MEETING
SUMMARY
- CATEGORY 1 PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY (TVA) - BROWNS FERRY UNIT 1 RECOVERY STATUS
Dear Mr. Singer:
This refers to the public meeting conducted at Calhoun Community College located near Decatur, Alabama on December 18, 2006. The purpose of the meeting was to discuss the Browns Ferry Unit 1 (BF1) Restart Project status. Discussions during this meeting included the following topics: Unit 1 overview and schedule, returning systems to service, regulatory status, fire protection Appendix R, cable separations, nuclear assurance, Browns Ferry Nuclear (BFN) operational readiness, and restart readiness. Enclosure 1 contains a list of attendees. contains the Inspection Plan and Schedule Report. Enclosure 3 contains the presentation material used by your staff to discuss the status of the Browns Ferry Unit 1 Restart Project.
TVA also discussed Unit 1 fuel load status including upcoming significant milestones and delays in system turnovers. As a result of the meeting, the NRC will continue to conduct inspections to ensure that all measures applicable to restart readiness are in place prior to restart. Prior to conducting the Operational Readiness Assessment Team (ORAT) inspection, the NRC will review TVAs response to the NRCs prerequisite letter dated October 25, 2006 (ML062980431). The NRC plans to monitor recovery progress and inspect accordingly to maintain and ensure public health and safety throughout the Unit 1 recovery process.
Documents associated with the NRC oversight of the BF1 Recovery can be found at on the NRCs website at http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/bf1-recovery.html.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Should you have any questions concerning these meetings, please contact me at (404) 562-4501.
Sincerely,
/RA/
Joseph W. Shea, Director Division of Reactor Safety, Region II
2 TVA Docket No.: 50-259 License No.: DPR-33
Enclosures:
- 1. List of Attendees
- 2. Inspection Plan and Schedule Report
- 3. TVA Presentation Handout - Browns Ferry Nuclear Plant - Unit 1 Restart cc w/encls: (See page 3)
_Package: ML063560078 Doc: ML06350087 OFFICE RII:DRP SIGNATURE NAME TNazario DATE 12/ /2006 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO YES NO
3 TVA cc w/encls.:
Ashok S. Bhatnagar Senior Vice President Nuclear Operations Tennessee Valley Authority Electronic Mail Distribution Larry S. Bryant, Vice President Nuclear Engineering &
Technical Services Tennessee Valley Authority Electronic Mail Distribution Brian O'Grady Site Vice President Browns Ferry Nuclear Plant Tennessee Valley Authority Electronic Mail Distribution Preston D. Swafford Senior Vice President Nuclear Support Tennessee Valley Authority Electronic Mail Distribution General Counsel Tennessee Valley Authority Electronic Mail Distribution John C. Fornicola, General Manager Nuclear Assurance Tennessee Valley Authority Electronic Mail Distribution Bruce M. Aukland, Plant Manager Browns Ferry Nuclear Plant Tennessee Valley Authority Electronic Mail Distribution Robert H. Bryan, Jr., General Manager Licensing & Industry Affairs Tennessee Valley Authority Electronic Mail Distribution William D. Crouch, Manager Licensing and Industry Affairs Browns Ferry Nuclear Plant Tennessee Valley Authority Electronic Mail Distribution Beth A. Wetzel, Manager Corporate Nuclear Licensing and Industry Affairs Tennessee Valley Authority 4X Blue Ridge 1101 Market Street Chattanooga, TN 37402-2801 State Health Officer Alabama Dept. of Public Health RSA Tower - Administration Suite 1552 P. O. Box 303017 Montgomery, AL 36130-3017 Chairman Limestone County Commission 310 West Washington Street Athens, AL 35611 Masoud Bajestani, Vice President Browns Ferry Unit 1 Restart Browns Ferry Nuclear Plant Tennessee Valley Authority P. O. Box 2000 Decatur, AL 35609 Robert G. Jones, General Manager Browns Ferry Site Operations Browns Ferry Nuclear Plant Tennessee Valley Authority P. O. Box 2000 Decatur, AL 35609 Distribution w/encl: (See page 4)
TVA Meeting Summary to Karl W. Singer from Joseph W. Shea dated December 20, 2006.
SUBJECT:
MEETING
SUMMARY
- CATEGORY 1 PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY (TVA) - BROWNS FERRY UNIT 1 RECOVERY STATUS Distribution w/encl:
J. Boska, NRR E. Brown, NRR L. Raghavan, NRR C. Evans L. Slack, RII EICS L. Mellen, RII OE Mail RIDSNRRDIRS PUBLIC List of Attendees NRC/TVA Unit 1 Restart Management Meeting Nuclear Regulatory Commission W. Bearden, Senior Resident Inspector BF Unit 1, Branch 6, DRP E. Christnot, Resident Inspector BF Unit 1, Branch 6, DRP K. Clark, Senior Public Affairs Officer-Region II C. Haney, Director of DORL, NRR M. Lesser, Office of Regional Administrator-Region II T. Nazario, Project Engineer, Branch 6, DRP L. Raghavan, Branch Chief, DORL, NRR T. Ross, Senior Resident Inspector BF Units 2 and 3, Branch 6, DRP J. Shea, Director, Division of Reactor Safety (DRS)
C. Stancil, Resident Inspector BF Unit 1, Branch 6, DRP R. Trojanowski, State Liaison Officer-Region II M. Widmann, Chief, Branch 6, DRP Browns Ferry (TVA)
M. Bajestani, Vice President Unit 1 Restart R. Baron, Unit 1 Nuclear Assurance Manager D. Burrell, Electrical Engineering Manager-Unit 1 Restart W. Crouch, Site Licensing & Industry Affairs Manager J. McCarthy, Unit 1 Licensing T. McGrath, Senior Project Manager, Operational Readiness R. Moll, Recovery System Engineering Manager Public K. Bouma, Birmingham News S. Black, Limestone EMA M. Blakely, Limestone County Sheriffs Office J. Cassidy, Huntsville-Madison County EMA H. Frost, Law County EMA G. Grabryan, Flo-Land EMA R. King, Limestone County Sheriffs Office D. Kyle, City of Decatur B. Lawson, Huntsville Times R. Little, Alabama EMA W. Pace, Manager, Alabama Valley Relations, TVA C. Paschenko, Decatur Daily J. Price, Alabama EMA M. Robinson, Alabama EMA J. Sandlin, Scottsboro EPB M. Senf, Flo-Land EMA T. Vinson, Law County EMA