February 8, 2007 Mr. Michael R. Kansler President Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601
SUBJECT:
PILGRIM NUCLEAR POWER STATION - PROPOSED AMENDMENT RE:
HIGH-PRESSURE COOLANT INJECTION (HPCI) AND REACTOR CORE ISOLATION COOLING (RCIC) SURVEILLANCE REQUIREMENTS (TAC NO.
MD2476)
Dear Mr. Kansler:
By letter dated June 30, 2006 (Agencywide Documents Access and Management System Accession No. ML061870469), Entergy Nuclear Operations, Inc. submitted a request to amend the operating license for the Pilgrim Nuclear Power Station by revising the Technical Specification (TS) Surveillance requirements (SRs) for the HPCI and RCIC system. Specifically you requested to modify the test frequency of the HPCI and RCIC systems in Pilgrim TS SR 4.5.C.1.d and SR 4.5.D.1.d, to require the current specified flow rate test be performed only following maintenance activities that could have affected system flow rate performance.
The purpose of this letter is to provide the results of the Nuclear Regulatory Commission (NRC) staff's acceptance review of your application. The acceptance review determines whether or not there is sufficient detail to allow the NRC staff to proceed with a comprehensive technical review. The review also ensures that the application adequately characterizes the regulatory requirements and licensing basis of the plant.
The NRC staff has reviewed your application and has determined that your request would not conform to NRC requirements. Specifically, it does not conform to the framework as outlined in the Final Commission Policy Statement on Technical Specification Improvements for Nuclear Power Reactors, dated July 22, 1993 (58 FR 39132). This policy statement was subsequently codified by changes to Section 36 of Part 50 of Title 10 of the Code of Federal Regulations (10 CFR 50.36) (see also 60 FR 36953, July 16, 1995). In addition, the application does not provide technical information in sufficient detail to enable the NRC staff to make an assessment in regards to the increased or decreased probabilities of system in-operability or the increased consequences to overall plant risk as a result of not performing the TS SRs as prescribed by your custom TSs or the Standard Technical Specifications for Boiling Water Reactors NUREG-1433, Revision 3, June 2004.
During a conference call on September 21, 2006, the NRC staff informed you that we would not accept your amendment application for review because it does not meet the requirements of 10 CFR 50.36 as stated above, Therefore we are closing TAC No. MD2476 effective on the date of this letter.
If you have any questions, please contact Mr. James J. Shea, at (301) 415-1388.
Sincerely,
/RA/
James J. Shea, Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-293 cc: See next page
ML063470397 OFFICE LPLI-1/PM LPLI-1/LA ITSB/BC LPLI-1/BC(A)
NAME JShea SLittle TKobetz JBoska DATE 12/14/06 12/18/06 12/19/06 2/08/07
Pilgrim Nuclear Power Station cc:
Regional Administrator, Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1415 Senior Resident Inspector U. S. Nuclear Regulatory Commission Pilgrim Nuclear Power Station Post Office Box 867 Plymouth, MA 02360 Chairman, Board of Selectmen 11 Lincoln Street Plymouth, MA 02360 Chairman Nuclear Matters Committee Town Hall 11 Lincoln Street Plymouth, MA 02360 Chairman, Duxbury Board of Selectmen Town Hall 878 Tremont Street Duxbury, MA 02332 Office of the Commissioner Massachusetts Department of Environmental Protection One Winter Street Boston, MA 02108 Office of the Attorney General One Ashburton Place 20th Floor Boston, MA 02108 MA Department of Public Health Radiation Control Program Schrafft Center, Suite 1M2A 529 Main Street Charlestown, MA 02129 Secretary of Public Safety Executive Office of Public Safety One Ashburton Place Boston, MA 02108 Director, Massachusetts Emergency Management Agency Attn: James Muckerheide 400 Worcester Road Framingham, MA 01702-5399 Mr. William D. Meinert Nuclear Engineer Massachusetts Municipal Wholesale Electric Company P.O. Box 426 Ludlow, MA 01056-0426 Mr. Kevin H. Bronson General Manager, Plant Operations Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 Mr. Michael A. Balduzzi Site Vice President Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 Mr. Stephen J. Bethay Director, Nuclear Safety Assurance Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 Mr. Bryan S. Ford Manager, Licensing Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508
Pilgrim Nuclear Power Station cc:
/
Mr. Gary J. Taylor Chief Executive Officer Entergy Operations 1340 Echelon Parkway Jackson, MS 39213 Mr. John T. Herron Sr. VP and Chief Operating Officer Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Oscar Limpias Vice President, Engineering Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Christopher Schwarz Vice President, Operations Support Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Michael Kansler President Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. John F. McCann Director, Nuclear Safety Assurance Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Ms. Charlene D. Faison Manager, Licensing Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Michael J. Colomb Director of Oversight Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Assistant General Counsel Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Ms. Stacey Lousteau Treasury Department Entergy Services, Inc.
639 Loyola Avenue New Orleans, LA 70113 Mr. James Sniezek 5486 Nithsdale Drive Salisbury, MD 21801-2490 Mr. Michael D. Lyster 5931 Barclay Lane Naples, FL 34110-7306 Mr. Garrett D. Edwards 814 Waverly Road Kennett Square, PA 19348