November 14, 2006 Mr. David A. Christian Senior Vice President and Chief Nuclear Officer Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
SUBJECT:
PUBLIC MEETING TO DISCUSS MITIGATING SYSTEMS CORNERSTONE ACTIVITIES FOR THE KEWAUNEE POWER STATION
Dear Mr. Christian:
This letter refers to the public meeting conducted on October 25, 2006, at the West Kewaunee Township Town Hall in Kewaunee, Wisconsin. The meeting was held to review the degraded Mitigating Systems Cornerstone over the last four quarters and findings from the Nuclear Regulatory Commission (NRC) Inspection Procedure (IP) 95002 inspection at the Kewaunee Power Station.
Mr. Patrick Louden, Chief, Branch 5, Division of Reactor Projects, in the NRC Region III Office, opened the meeting with introductions of the NRC officials and then turned the meeting over to Julio Lara, Chief, Engineering Branch 3, Division of Reactor Safety, to discuss the findings from the IP 95002 inspection. The summary of the NRC discussion and IP 95002 inspection findings are outlined in the attached presentation slides.
After the NRC presentation, Ms. Leslie Hartz, Site Vice-President, Kewaunee, responded by stating that the improvements at Kewaunee were only the beginning of many longer-term site-wide improvements. You then stated that Dominions objective is to get and keep Kewaunee in the Licensee Response Column of the NRC Action Matrix. Your desire was for the plant to self-identify and correct deficiencies rather than having the NRC identify the deficiencies or provide additional regulatory oversight. You further stated that achieving excellence is a goal, but not at the expense of safety.
Mr. James Caldwell, the Region III Regional Administrator, concluded the meeting with an acknowledgment of Kewaunee wanting to continue to focus on improving plant performance.
A listing of principal Dominion and NRC meeting attendees and a copy of the handout provided by the NRC at the meeting are enclosed as Enclosures 1 and 2, respectively, to this letter.
D. Christian In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's document system (ADAMS), and is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If you have any questions regarding this meeting, please contact me at (630) 829-9627.
Sincerely, Patrick L. Louden, Chief Branch 5 Division of Reactor Project Docket No. 50-305 License No. DPR-43
Enclosures:
- 1. Public Meeting Attendees
- 2. NRC presentation slides cc w/encls:
L. Hartz, Site Vice President C. Funderburk, Director, Nuclear Licensing and Operations Support T. Breene, Manager, Nuclear Licensing L. Cuoco, Esq., Senior Counsel D. Zellner, Chairman, Town of Carlton J. Kitsembel, Public Service Commission of Wisconsin State Liaison Officer, State of Wisconsin
D. Christian In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's document system (ADAMS), and is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If you have any questions regarding this meeting, please contact me at (630) 829-9627.
Sincerely, Patrick L. Louden, Chief Branch 5 Division of Reactor Project Docket No. 50-305 License No. DPR-43
Enclosures:
- 1. Public Meeting Attendees
- 2. NRC presentation slides cc w/encls:
L. Hartz, Site Vice President C. Funderburk, Director, Nuclear Licensing and Operations Support T. Breene, Manager, Nuclear Licensing L. Cuoco, Esq., Senior Counsel D. Zellner, Chairman, Town of Carlton J. Kitsembel, Public Service Commission of Wisconsin State Liaison Officer, State of Wisconsin DOCUMENT NAME:C:\\FileNet\\ML063180262.wpd G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME JBartleman:dtp
- MAK for PLouden DATE 11/14/2006 11/14/2006 OFFICIAL RECORD COPY
D. Christian DISTRIBUTION:
TEB JFS2 RidsNrrDirsIrib GEG KGO GLS SXB3 DRPIII DRSIII PLB1 TXN PUBLIC MEETING PRINCIPAL ATTENDEES October 25, 2006 Dominion David Christian Dominion Senior Vice President and Chief Nuclear Officer Leslie Hartz Site Vice President, Kewaunee Kevin Davison Director of Operations and Maintenance, Kewaunee Lori Armstrong Director of Engineering, Kewaunee Tom Webb Director of Safety and Licensing, Kewaunee Paul Phelps Manager of Design Engineering, Kewaunee Russell Schaefer Manager of Nuclear Oversight, Kewaunee Jerry Riste Licensing, Kewaunee Nuclear Regulatory Commission James Caldwell Regional Administrator, Region III Patrick Louden Chief, Branch 5, Division of Reactor Projects Julio Lara Chief, Engineering Branch 3, Division of Reactor Safety Stephen Burton Senior Resident Inspector, Kewaunee Rob Krsek Senior Resident Inspector, Point Beach John Bartleman Reactor Engineer, Division of Reactor Projects Kevin Barclay Reactor Engineer, Division of Reactor Projects Public No members of the public showed up to the meeting.