Response to GL 2006-03 - Potentially Nonconforming Hemyc and MT Fire Barrier Configurations
ML063000065
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 11/27/2006
From: Williams J
Plant Licensing Branch III-2
To: Crane C
Exelon Generation Co
Williams J, NRR/DLPM/LPD1, 415-1470
References
GL-06-003, TAC MD1575, TAC MD1576
Download: ML063000065 (4)


Text

November 27, 2006 Mr. Christopher M. Crane, President and Chief Nuclear Officer Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 - NRC RECEIPT OF RESPONSE TO GENERIC LETTER 2006-03, POTENTIALLY NONCONFORMING HEMYC AND MT FIRE BARRIER CONFIGURATIONS (TAC NOS. MD1575 AND MD1576)

Dear Mr. Crane:

The Nuclear Regulatory Commission (NRC) acknowledges the receipt of your June 6, 2006, response to Generic Letter (GL) 2006-03, Potentially Nonconforming Hemyc and MT Fire Barrier Configurations for the Dresden Nuclear Power Station, Units 2 and 3 (Dresden). Under oath or affirmation, you stated that Dresden does not rely on either the Hemyc or MT fire barrier system and provided documentation with regard to other 1 or 3-hour fire barrier material that separates redundant safe shutdown trains. These trains are located within the same fire area, and are designed and installed in accordance with current NRC guidance. Based on your response, the basis for stating that this other fire barrier has been designed and installed in accordance with NRC guidance should be maintained on site, and will be subject to inspection during the normal NRC inspection process. The NRC staffs review of your response to GL 2006-03 is complete.

If you have any questions regarding this topic, please contact me at (301)415-1470 or jfw1@nrc.gov.

Sincerely,

/RA/

Joseph F. Williams, Senior Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-237 and 50-249 cc: See next page

Mr. Christopher M. Crane, President November 27, 2006 and Chief Nuclear Officer Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 - NRC RECEIPT OF RESPONSE TO GENERIC LETTER 2006-03, POTENTIALLY NONCONFORMING HEMYC AND MT FIRE BARRIER CONFIGURATIONS (TAC NOS. MD1575 AND MD1576)

Dear Mr. Crane:

The Nuclear Regulatory Commission (NRC) acknowledges the receipt of your June 6, 2006, response to Generic Letter (GL) 2006-03, Potentially Nonconforming Hemyc and MT Fire Barrier Configurations for the Dresden Nuclear Power Station, Units 2 and 3 (Dresden). Under oath or affirmation, you stated that Dresden does not rely on either the Hemyc or MT fire barrier system and provided documentation with regard to other 1 or 3-hour fire barrier material that separates redundant safe shutdown trains. These trains are located within the same fire area, and are designed and installed in accordance with current NRC guidance. Based on your response, the basis for stating that this other fire barrier has been designed and installed in accordance with NRC guidance should be maintained on site, and will be subject to inspection during the normal NRC inspection process. The NRC staffs review of your response to GL 2006-03 is complete.

If you have any questions regarding this topic, please contact me at (301)415-1470 or jfw1@nrc.gov.

Sincerely,

/RA/

Joseph F. Williams, Senior Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-237 and 50-249 cc: See next page Distribution:

PUBLIC RidsOgcRp LPL3-2 R/F RidsAcrsAcnwMailCenter RidsNrrDorlLPL3-2 RidsRgn3MailCenter RidsNrrLADClarke RidsNrrDorlDpr RidsNrrPMJWilliams RidsNrrDraAfpb Accession Number: ML063000065 NRR-106 OFFICE LPL3-2/PM LPL3-2/LA AFPB/BC LPL3-2/BC NAME JWilliams:mw DClarke SWeerakkody DCollins DATE 11/13/2006 11/13/2006 11/17/2006 11/27/2006 OFFICIAL RECORD COPY

Dresden Nuclear Power Units 2 and 3 cc:

Site Vice President - Dresden Exelon Generation Company, LLC 6500 N. Dresden Road Morris, IL 60450-9765 Plant Manager - Dresden Nuclear Power Station Exelon Generation Company, LLC 6500 N. Dresden Road Morris, IL 60450-9765 Manager Regulatory Assurance - Dresden Exelon Generation Company, LLC 6500 N. Dresden Road Morris, IL 60450-9765 U.S. Nuclear Regulatory Commission Dresden Resident Inspectors Office 6500 N. Dresden Road Morris, IL 60450-9766 Chairman Grundy County Board Administration Building 1320 Union Street Morris, IL 60450 Regional Administrator, Region III U.S. Nuclear Regulatory Commission Suite 210 2443 Warrenville Road Lisle, IL 60532-4351 Illinois Emergency Management Agency Division of Disaster Assistance &

Preparedness 110 East Adams Street Springfield, IL 62701-1109 Document Control Desk - Licensing Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Senior Vice President - Midwest Operations Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Vice President - Regulatory & Legal Affairs Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Assistant General Counsel Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348 Manager Licensing - Dresden Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555