MONTHYEARML23325A2132023-12-18018 December 2023 Cover Letter for Final Model SE of TSTF-591, Revise Risk Informed Completion Time (RICT) Program ML23262B2292023-09-21021 September 2023 Cover Letter Transmitting Final SE of TSTF-591, Revision 0, Revise Risk-Informed Completion Time (RICT) Program ML23124A2212023-09-11011 September 2023 Cover Letter for Final SEs of TSTF-589, Eliminate Automatic Diesel Generator (DG) Start During Shutdown ML23206A1242023-07-31031 July 2023 TSTF-584 Cover Letter for Final SE ML23205A2342023-07-0606 July 2023 Draft TSTF-601, 'Extend Shield Building Completion Time After Refueling' ML23012A2812023-03-13013 March 2023 Draft SEs of TSTF-584, Eliminate Automatic RWCU System Isolation on SLC Initiation ML23059A3342023-02-28028 February 2023 TSTF-576 Open Issues Letter ML23010A2592023-01-11011 January 2023 Request for Additional Information Traveler TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML22272A5542022-10-0707 October 2022 Request for Additional Information Traveler TSTF-591, Revise Risk Informed Completion Time (RICT) Program TSTF-22-07, Transmittal of TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements2022-07-19019 July 2022 Transmittal of TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML22193A2372022-07-12012 July 2022 Request for Additional Information TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown TSTF-22-06, Technical Specifications Task Force - Request for a Workshop to Discuss the Interaction of Natural Phenomena Protection Design Features and Operability2022-07-0808 July 2022 Technical Specifications Task Force - Request for a Workshop to Discuss the Interaction of Natural Phenomena Protection Design Features and Operability ML22110A1712022-04-26026 April 2022 Acceptance for Review Regarding Traveler Tstf-584, Rev 0, Eliminate Automatic RWCU System Isolation on SLC Initiation TSTF-22-04, Technical Specifications Task Force - Transmittal of TSTF-591, Revision 0, Revise Risk Informed Completion Time (RICT) Program2022-03-22022 March 2022 Technical Specifications Task Force - Transmittal of TSTF-591, Revision 0, Revise Risk Informed Completion Time (RICT) Program ML21188A2782021-07-11011 July 2021 Cover Letter Transmitting Final SEs of CLIIP TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR (Residual Heat Removal) Shutdown Cooling TSTF-21-03, TSTF Response to NRC Questions on TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements and Submittal of Revision 12021-06-23023 June 2021 TSTF Response to NRC Questions on TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements and Submittal of Revision 1 ML21054A2512021-05-26026 May 2021 Cover Letter Transmitting Draft SEs of CLIIP TSTF-580, RHR Shutdown Cooling System - Hot Shutdown ML21106A2452021-04-20020 April 2021 Cover Letter Transmitting Final Model SE of TSTF 554, Revision 1, Revise Reactor Coolant Leakage Requirements ML21098A2422021-04-14014 April 2021 Cover Letter for Final SEs of TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML21068A4012021-03-24024 March 2021 Cover Letter for Draft SEs TSTF 577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections TSTF-21-01, Transmittal of TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2021-01-26026 January 2021 Transmittal of TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML20322A3612020-12-18018 December 2020 TSTF-554 Cover Letter for Final SE ML20308A6562020-11-0606 November 2020 Request for Additional Information Traveler TSTF-577, Revision 0, Revised Frequencies for Steam Generator Tube Inspections ML20168A3962020-10-30030 October 2020 Cover Letter Transmitting Draft SE of TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements ML20265A1152020-10-0909 October 2020 Cover Letter Transmitting Model SE of TSTF-582 and TSTF-583-T ML20133J8832020-07-29029 July 2020 Letter Transmitting Draft SE of Traveler TSTF-582, Revision 0, RPV WIC Enhancements TSTF-20-04, Technical Specifications Task Force - Transmittal of TSTF-577, Revision 0, Revised Frequencies for Steam Generator Tube Inspections2020-06-0808 June 2020 Technical Specifications Task Force - Transmittal of TSTF-577, Revision 0, Revised Frequencies for Steam Generator Tube Inspections ML20133J8152020-05-13013 May 2020 Letter Transmitting Revised Final SE of Traveler TSTF-564, Revision 2, Safety Limit MCPR, Using the Consolidated Line Item Improvement Process ML20132A1832020-05-11011 May 2020 Request for Additional Information TSTF-576, Revision 0, Revised Safety/Relief Valve Requirement TSTF-20-01, Transmittal of TSTF-IG-20-02, Guidance on Evaluating One-Time Surveillance Frequency Changes Under the Surveillance Frequency Control Program (TSTF-425M SFCP)2020-04-0909 April 2020 Transmittal of TSTF-IG-20-02, Guidance on Evaluating One-Time Surveillance Frequency Changes Under the Surveillance Frequency Control Program (TSTF-425M SFCP) TSTF-19-14, Technical Specifications Task Force - TSTF Response to NRC Questions on TSTF-582, RPV WIC Enhancements2020-02-12012 February 2020 Technical Specifications Task Force - TSTF Response to NRC Questions on TSTF-582, RPV WIC Enhancements TSTF-19-11, TSTF Response to NRC Questions on TSTF-554, Revise Reactor Coolant Leakage Requirements2020-01-16016 January 2020 TSTF Response to NRC Questions on TSTF-554, Revise Reactor Coolant Leakage Requirements ML19325C4362019-12-17017 December 2019 Cover Letter Transmitting Final SEs of Traveler TSTF-568, Revision 2, Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2 TSTF-19-09, Technical Specifications Task Force - Transmittal of TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements2019-12-13013 December 2019 Technical Specifications Task Force - Transmittal of TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements ML19323E9282019-12-10010 December 2019 Cover Letter Transmitting Final SEs of Traveler TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position TSTF-19-13, Technical Specifications Task Force - Updated TSTF Membership and Distribution2019-12-0303 December 2019 Technical Specifications Task Force - Updated TSTF Membership and Distribution TSTF-19-12, TSTF Comments on Draft Safety Evaluations for Traveler TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position.2019-11-0505 November 2019 TSTF Comments on Draft Safety Evaluations for Traveler TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position. TSTF-19-10, Transmittal of Errata Changes to TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2019-08-28028 August 2019 Transmittal of Errata Changes to TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML19176A1892019-08-14014 August 2019 Cover Letter Transmitting Final Safety Evaluations of Traveler TSTF-569, Revision 2, Revise Response Time Testing Definition TSTF-19-03, Request for Fee Exemption for TSTF-554, Revision 0, Revise Reactor Coolant Leakage Requirements - Letter2019-07-0808 July 2019 Request for Fee Exemption for TSTF-554, Revision 0, Revise Reactor Coolant Leakage Requirements - Letter TSTF-19-08, Draft of Traveler TSTF-582, Revision 0, RPV WIC Enhancements.2019-07-0303 July 2019 Draft of Traveler TSTF-582, Revision 0, RPV WIC Enhancements. TSTF-19-06, TSTF Comments on Draft Safety Evaluations for Traveler TSTF-569, Revision 1, Revise Response Time Testing Definition2019-06-25025 June 2019 TSTF Comments on Draft Safety Evaluations for Traveler TSTF-569, Revision 1, Revise Response Time Testing Definition TSTF-19-07, TSTF Handout for October 16, 2019, Meeting: Elimination of Commitment to Adopt TSTF-4932019-06-18018 June 2019 TSTF Handout for October 16, 2019, Meeting: Elimination of Commitment to Adopt TSTF-493 TSTF-19-05, Transmittal of TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2019-06-18018 June 2019 Transmittal of TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML19017A2222019-05-29029 May 2019 Letter Transmitting Draft Safety Evaluations of Technical Specifications Task Force Traveler TSTF-569, Revision 1, Revise Response Time Testing Definition ML19028A2852019-02-21021 February 2019 Final SEs of TSTF-566, Revision 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems (Transmittal Letter) TSTF-19-01, TSTF Comments on Draft Safety Evaluations for Traveler TSTF-566, Revision 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems2019-01-17017 January 2019 TSTF Comments on Draft Safety Evaluations for Traveler TSTF-566, Revision 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems ML19007A2252019-01-15015 January 2019 Letter Transmitting Final SEs of Traveler TSTF-557, Revision 1, Spent Fuel Storage Rack Neutron Absorber Monitoring Program. ML18284A3772018-12-31031 December 2018 Incorporation of Technical Specifications Task Force (TSTF) Traveler TSTF-565, Revision 1, Revise the LCO 3.0.2 and LCO 3.0.3 Bases, Into the Next Revision of the Standard Technical Specifications TSTF-18-13, TSTF Comments on Draft Safety Evaluation for Traveler TSTF-557, Revision 1, Spent Fuel Storage Rack Neutron Absorber Monitoring Program.2018-12-20020 December 2018 TSTF Comments on Draft Safety Evaluation for Traveler TSTF-557, Revision 1, Spent Fuel Storage Rack Neutron Absorber Monitoring Program. 2023-09-21
[Table view] |
Text
November 16, 2006 Technical Specifications Task Force (TSTF) 11921 Rockville Pike, Suite 100 Rockville, MD 20852
SUBJECT:
Establishment of Milestone Schedule for TSTF Travelers (Docket No. PROJ0753)
Dear Members of the TSTF:
As discussed during our August 17, 2006, public meeting, a schedule has been established by NRC for completing the review of all in-process TSTF travelers.1 NRC reviewed the schedule with your representative, Mr. Brian Mann, on November 16, 2006. This letter and the enclosed table establish a schedule for completion of TSTF traveler reviews. This schedule updates and supercedes any previously-submitted schedules.
Should circumstances lead to schedule slippage, the causing party should promptly inform the other in writing and coordinate with the impacted party to re-establish and publish an appropriately revised schedule. This is of particular importance in connection with TSTF response to NRC staff requests for additional information as failure to provide a timely responsive reply, in accordance with the agreed schedule, or to successfully negotiate a revised schedule, may result in termination of the NRC review process.
Early completion of any activity will not necessitate schedule revision. However, the NRC will endeavor to complete tasks early. The current revision of the Open TSTF Traveler Milestone schedule will be published and accessible via the NRC public web at Home > Nuclear Reactors
> Operating Reactors > Licensing > Technical Specifications > Open TSTF Travelers.
1 As new TSTF travelers are opened and active travelers are closed on an ongoing basis, it should be recognized that recent changes may not appear in this schedule.
TSTF Technical Specifications Branch project leads are listed for each TSTF traveler. Please contact these individuals in coordinating activities specific to their review. Ross Telson may also be contacted at (301) 415-2256 or rdt@nrc.gov in the event one of these individuals is unavailable or should you have questions or need further information in connection with the TSTF traveler review process.
Sincerely,
/RA/
Timothy J. Kobetz, Chief Technical Specifications Branch Division of Inspection and Regional Support Office of Nuclear Reactor Regulation
Enclosure:
As stated cc: P. Infanger, PWROG/B&W B. Woods, PWROG/CE W. Sparkman, PWROG/W M. Crowthers, BWROG D. Hoffman, EXCEL B. Mann, EXCEL
TSTF Technical Specifications Branch project leads are listed for each TSTF traveler. Please contact these individuals in coordinating activities specific to their review. Ross Telson may also be contacted at (301) 415-2256 or rdt@nrc.gov in the event one of these individuals is unavailable or should you have questions or need further information in connection with the TSTF traveler review process.
Sincerely,
/RA/
Timothy J. Kobetz, Chief Technical Specifications Branch Division of Inspection and Regional Support Office of Nuclear Reactor Regulation Enclosure cc: P. Infanger, PWROG/B&W B. Woods, PWROG/CE W. Sparkman, PWROG/W M. Crowthers, BWROG D. Hoffman, EXCEL B. Mann, EXCEL DISTRIBUTION:
ITSB r/f ITSB Staff RidsNrrAdro RidsNrrDirsItsb ADAMS ACCESSION NO: ML063170404-pkg, ML0629803970-ltr; ML063200386-enc.
OFFICE ITSB:DIRS BC:ITSB:DIRS NAME RDTelson TJKobetz DATE 11/16/2006 11/16/06 OFFICIAL RECORD COPY
In-process TSTF Traveler Schedule Milestones & Explanation Milestone Dates Meaning (Milestone dates in the attached spreadsheet may be interpreted as follows)
Application (a) This is the date the application was received by the NRC. The document processing center (DPC) will typically place the document into ADAMS within a few days of receipt. For electronic submittals, the DPC confirms, via email, both receipt and placement into ADAMS.
RAI Issued (c) This is the projected (actual) date a Request for Additional Information (RAI) letter will be (is) available to- or delivered to TSTF. If a copy of the signed RAI will be (is) emailed or faxed, it is this date. Otherwise, it is the date at which the RAI letter will become (is) publically available in ADAMS, permitting public access (typically the signature date plus six (6) days).
RAI Resp. (d) This is the projected (actual) date when TSTFs RAI response letter will be (is) available to technical staff. If a copy of the signed RAI response letter (will be) is emailed or faxed to the TSTF lead, it is this date.
Otherwise, it is the date at which the RAI response letter becomes available in ADAMS, permitting staff access (typically three days following receipt by the DPC).
Fed Reg NFC (e)
- For TSTFs processed in accordance with the Consolidated Line Item Improvement Program (CLIIPd), this is the projected (actual) date that both the model application (Model LAR) and safety evaluation (Model SE) will become (are) Noticed in the Federal Register for public comment.
This milestone is N/A for non-CLIIPd TSTFs which are not typically Noticed to the Federal Register for public comment Fed Reg NOA (f)
- For TSTFs processed in accordance with the Consolidated Line Item Improvement Program (CLIIPd), this is the projected (actual) date that both the model application (Model LAR) and safety evaluation (Model SE) will become (are) Advertised in the Federal Register as Available for Industry Adoption.
For non-CLIIPd TSTFs, there is no Fed Reg NOA. In this instance, this milestone reflects the earlier of the following dates: (i) The date at which the letter approving the TSTF will become (is) publically available in ADAMS (typically 6 days after being signed) or (ii) the date the signed letter will be (is) faxed or emailed to TSTF.