October 20, 2006 Mr. James Scarola, Vice President Brunswick Steam Electric Plant Carolina Power & Light Company Post Office Box 10429 Southport, North Carolina 28461
SUBJECT:
BRUNSWICK STEAM ELECTRIC PLANT, UNITS 1 AND 2 - NRC RECEIPT OF RESPONSE TO GENERIC LETTER 2003-01 CONTROL ROOM HABITABILITY (TAC NOS. MB9779 AND MB9780)
Dear Mr. Scarola:
The Nuclear Regulatory Commission (NRC) acknowledges the receipt of your responses to Generic Letter (GL) 2003-01, Control Room Habitability, in letters dated August 11, 2003 (Agencywide Document and Access Management System (ADAMS) Accession No. ML032310430), December 9, 2003 (ML033500350), and July 29, 2004 (ML042170286).
This letter provides a status of your response and describes any additional information that may be necessary to consider your response to GL 2003-01 complete.
The GL requested that you confirm that your control room meet its design bases (e.g., General Design Criteria (GDC) 1, 3, 4, 5, and 19, draft GDC, or principal design criteria), with special attention to: (1) Determination of the most limiting unfiltered and/or filtered inleakage into the control room and comparison to values used in your design bases for meeting control room operator dose limits from accidents (Item 1(a)), (2) Determination that the most limiting unfiltered inleakage is incorporated into your hazardous chemical assessments, and (3) Determination that reactor control capability is maintained in the control room or at the alternate shutdown location in the event of smoke (Item 1(b)). The GL further requested information on any compensatory measures in use to demonstrate control room habitability (CRH), and plans to retire them (Item 2).
You reported the results of American Society for Testing and Materials, ASTM E741, tracer gas tests for the Brunswick Steam Electric Plant (BSEP), Units 1 and 2, control room. For BSEP, you determined that the tested value for inleakages into the control room envelope (CRE) is 762 +/- 42 cubic feet per minute (cfm) for toxic gas and 869 (+/- 146) cfm for radiation protection, which is less than the values of 2000 cfm (toxic gas mode) and 10,000 cfm (radiation protection mode) that were assumed in the design basis analysis for CRH.
You also provided information that adequately supported a conclusion that reactor control capability is maintained from either the control room or the alternate shutdown panel in the event of smoke.
J. Scarola October 20, 2006 The GL further requested that you assess your technical specifications to determine if they verify the integrity of the CRE, including ongoing verification of the inleakage assumed in the design basis analysis for CRH, and in light of the demonstrated inadequacy of a delta () P measurement to alone provide such verification (GL Item 1(c)). As permitted by the GL, you provided a schedule for revising the surveillance requirement in the TS to reference an acceptable surveillance methodology. In your December 9, 2003, response you indicated that you will submit a license amendment request to revise your TS utilizing TSTF-448 within 6 months of the approval of TSTF-448 by the NRC.
The information you provided also supported the fact that there are no compensatory measures in place to demonstrate control room habitability.
The information you provided also supported the conclusion that you are committed to meet the intent of the GDC regarding control room habitability, which is documented in your Safety Evaluation.
Your commitment to submit a license amendment request based on Technical Specification Task Force (TSTF) Traveler TSTF-448, following our formal review and approval, is acceptable for purposes of closing out your response to GL 2003-01. The NRC staff will monitor submittal of the license amendment request and interact with you as necessary during the amendment process.
If you have any questions regarding this correspondence, please contact me.
Sincerely,
/RA/
Brenda Mozafari, Senior Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-325 and 50-324 cc: See next page
J. Scarola October 20, 2006 The GL further requested that you assess your technical specifications to determine if they verify the integrity of the CRE, including ongoing verification of the inleakage assumed in the design basis analysis for CRH, and in light of the demonstrated inadequacy of a delta () P measurement to alone provide such verification (GL Item 1(c)). As permitted by the GL, you provided a schedule for revising the surveillance requirement in the TS to reference an acceptable surveillance methodology. In your December 9, 2003, response you indicated that you will submit a license amendment request to revise your TS utilizing TSTF-448 within 6 months of the approval of TSTF-448 by the NRC.
The information you provided also supported the fact that there are no compensatory measures in place to demonstrate control room habitability.
The information you provided also supported the conclusion that you are committed to meet the intent of the GDC regarding control room habitability, which is documented in your Safety Evaluation.
Your commitment to submit a license amendment request based on Technical Specification Task Force (TSTF) Traveler TSTF-448, following our formal review and approval, is acceptable for purposes of closing out your response to GL 2003-01. The NRC staff will monitor submittal of the license amendment request and interact with you as necessary during the amendment process.
If you have any questions regarding this correspondence, please contact me.
Sincerely,
/RA/
Brenda Mozafari, Senior Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-325 and 50-324 cc: See next page DISTRIBUTION:
PUBLIC LPL2-2 r/f JRobinson RidsNrrDorlLPL2-2 RidsNrrLABClayton RidsNrrDssScvb RidsNrrPMBMozafari RidsOgcRp RidsNrrDprPgcb RidsAcrsAcnwMailCenter RidsRgn2MailCenter Accession Number: ML062500087 OFFICE LPL2-2/PM LPL2-2/LA SCVB/BC PGCB/BC LPL2-2/BC NAME BMozafari BClayton RDennig CJackson LRaghavan DATE 10/13/06 10/12/06 10/15/06 10/19/06 10/20/06 OFFICIAL RECORD COPY
Mr. James Scarola Brunswick Steam Electric Plant Carolina Power & Light Company Units 1 and 2 cc:
David T. Conley Associate General Counsel II -
Legal Department Progress Energy Service Company, LLC Post Office Box 1551 Raleigh, North Carolina 27602-1551 Mr. David R. Sandifer, Chairperson Brunswick County Board of Commissioners Post Office Box 249 Bolivia, North Carolina 28422 Resident Inspector U. S. Nuclear Regulatory Commission 8470 River Road Southport, North Carolina 28461 Mr. John H. ONeill, Jr.
Shaw, Pittman, Potts & Trowbridge 2300 N Street NW.
Washington, DC 20037-1128 Ms. Beverly Hall, Section Chief Division of Radiation Protection N.C. Department of Environment and Natural Resources 3825 Barrett Dr.
Raleigh, North Carolina 27609-7721 Mr. Ben Waldrep Plant General Manager Brunswick Steam Electric Plant Carolina Power & Light Company Post Office Box 10429 Southport, North Carolina 28461-0429 Public Service Commission State of South Carolina Post Office Drawer 11649 Columbia, South Carolina 29211 Ms. Margaret A. Force Assistant Attorney General State of North Carolina Post Office Box 629 Raleigh, North Carolina 27602 Mr. Robert P. Gruber Executive Director Public Staff - NCUC 4326 Mail Service Center Raleigh, North Carolina 27699-4326 Mr. T. P. Cleary Director - Site Operations Brunswick Steam Electric Plant Carolina Power & Light Company Post Office Box 10429 Southport, North Carolina 28461-0429 Mr. Norman R. Holden, Mayor City of Southport 201 East Moore Street Southport, North Carolina 28461 Mr. Warren Lee Emergency Management Director New Hanover County Department of Emergency Management Post Office Box 1525 Wilmington, North Carolina 28402-1525 Mr. Chris L. Burton, Manager Performance Evaluation and Regulatory Affairs PEB 7 Progress Energy Post Office Box 1551 Raleigh, North Carolina 27602-1551 Mr. Randy C. Ivey Manager - Support Services Brunswick Steam Electric Plant Carolina Power & Light Company Post Office Box 10429 Southport, North Carolina 28461