8/31/06 Clinton Power Station - Mid-Cycle Performance Review and Inspection Plan
ML062430315
Person / Time
Site: Clinton 
(NPF-062)
Issue date: 08/31/2006
From: Ring M
Division Reactor Projects III
To: Crane C
Exelon Generation Co
References
Download: ML062430315 (7)


Text

August 31, 2006 Mr. Christopher M. Crane President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

CLINTON POWER STATION

Dear Mr. Crane:

On August 7, 2006, the NRC staff completed its performance review of the Clinton Power Station for the first half of the calendar year 2006 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous 12 months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked Exempt from Public Disclosure in Accordance with 10 CFR 2.390 will include the physical protection review and resultant inspection plan.

Plant performance for the most recent quarter at Clinton Power Station was within the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.

The enclosed inspection plan details the inspections, less those related to physical protection scheduled through March 31, 2008. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.

Additionally, inspections by the resident inspectors are planned to complete Temporary Instruction (TI) 2515-169, Mitigating Systems Performance Index (MSPI) Verification, prior to the end of calendar year 2006. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's

document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (630) 829-9703 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Mark A. Ring, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket No. 50-461 License No. NPF-62

Enclosure:

Clinton Power Station Inspection/Activity Plan DISTRIBUTION:

See next page

document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (630) 829-9703 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Mark A. Ring, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket No. 50-461 License No. NPF-62

Enclosure:

Clinton Power Station Inspection/Activity Plan DISTRIBUTION:

See next page DOCUMENT NAME:G:\\Branch TSS\\ALL MOC\\midcycle 2005 to 2006\\clinton\\Clinton MOC Letter 2006.wpd X Publicly Available G Non-Publicly Available G Sensitive X Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII E

RIII RIII RIII NAME MRing:sls DATE 08/16/2006 OFFICIAL RECORD COPY

C. Crane cc w/encl:

Site Vice President - Clinton Power Station Plant Manager - Clinton Power Station Regulatory Assurance Manager - Clinton Power Station Chief Operating Officer Senior Vice President - Nuclear Services Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Manager Licensing - Clinton Power Station Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency State Liaison Officer, State of Illinois Chairman, Illinois Commerce Commission Clinton Police Department Mayor of Clinton Mayor of Weldon DeWitt County Board Chairman DeWitt County Sheriff EMA Coordinator, DeWitt County Mayor of Wapella McLean County Board Chairman McLean County Sheriff EMA Coordinator, McLean County Piatt County Board Chairman Piatt County Sheriff EMA Coordinator, Piatt County Macon County Board Chairman Macon County Sheriff EMA Coordinator, Macon County INPO

C. Crane ADAMS Distribution:

TEB DXC1 KNJ RidsNrrDirslpab JLC1 GEG KGO RML2 SRI Clinton DRSIII DRPIII PLB1 TXN ROPreports@nrc.gov (inspection reports, final SDP letters, any letter with an IR number)

Clinton Inspection / Activity Plan 09/01/2006 - 03/31/2008 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/30/2006 12:56:41 Report 22 2

TI

- 2515/169 MSPI VERIFICATION Safety Issues 08/01/2006 10/31/2006 1

2515/169 IP Mitigating Systems Performance Index Verification 1

7112101

- RADIOLOGICAL ACCESS & POST OUTAGE ALARA Baseline Inspections 08/28/2006 09/01/2006 1

7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 08/28/2006 09/01/2006 1

7112102 IP ALARA Planning and Controls Baseline Inspections 08/28/2006 09/01/2006 1

71151 IP Performance Indicator Verification 2

M50.59

- MOD 50.59 INSPECTION Baseline Inspections 11/06/2006 12/01/2006 1

7111102 IP Evaluation of Changes, Tests, or Experiments Baseline Inspections 11/06/2006 12/01/2006 1

7111117B IP Permanent Plant Modifications 1

7112201

- RADIOLOGICAL EFFLUENTS Baseline Inspections 12/11/2006 12/15/2006 1

7112201 IP Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems Baseline Inspections 12/11/2006 12/15/2006 1

71151 IP Performance Indicator Verification 1

ME

- MAINTENANCE RULE INSPECTION Baseline Inspections 01/15/2007 01/19/2007 1

7111112B IP Maintenance Effectiveness 5

PI&R

- PROBLEM IDENITFICATION AND RESOLUTION Baseline Inspections 03/05/2007 03/23/2007 1

71152B IP Identification and Resolution of Problems 2

7112103

- RADIOLOGICAL INSTRUMENTATION Baseline Inspections 04/09/2007 04/13/2007 1

7112103 IP Radiation Monitoring Instrumentation and Protective Equipment 2

FY 2007

- CLINTON INIT PREP 07/2007 Not Applicable 07/23/2007 07/27/2007 1

W90158 OL - INITIAL EXAM - CLINTON - JUL/AUG 2007 1

BI

- ACCESS CONTROL NON-OUTAGE Baseline Inspections 08/06/2007 08/10/2007 1

7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 08/06/2007 08/10/2007 1

71151-BI01 IP Reactor Coolant System Activity Baseline Inspections 08/06/2007 08/10/2007 1

71151-OR01 IP Occupational Exposure Control Effectiveness 1

EP BI

- BASELINE EP EXERCISE INSP Baseline Inspections 09/10/2007 09/14/2007 1

7111401 IP Exercise Evaluation Baseline Inspections 09/10/2007 09/14/2007 1

71151-EP01 IP Drill/Exercise Performance Baseline Inspections 09/10/2007 09/14/2007 1

71151-EP02 IP ERO Drill Participation Baseline Inspections 09/10/2007 09/14/2007 1

71151-EP03 IP Alert & Notification System 3

FY 2007

- CLINTON INIT EXAM 08/2007 Not Applicable 08/13/2007 08/24/2007 1

W90158 OL - INITIAL EXAM - CLINTON - JUL/AUG 2007 3

7112202

- TRANSPORTATION & RADWASTE Baseline Inspections 09/17/2007 09/21/2007 1

7112202 IP Radioactive Material Processing and Transportation 5

CDBI

- COMPONENT DESIGN BASES INSPECTION Baseline Inspections 10/15/2007 11/16/2007 1

7111121 IP Component Design Bases Inspection This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Clinton Inspection / Activity Plan 09/01/2006 - 03/31/2008 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/30/2006 12:56:41 Report 22 1

7112203

- REMP & RAD MTL CONTROL Baseline Inspections 11/05/2007 11/09/2007 1

7112203 IP Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P 2

71111.11

- LIC OPERATOR REQUAL PROGRAM EVALUATION Baseline Inspections 11/12/2007 11/16/2007 1

7111111B IP Licensed Operator Requalification Program 1

7112102

- ALARA INSPECTION Baseline Inspections 11/26/2007 11/30/2007 1

7112102 IP ALARA Planning and Controls Baseline Inspections 11/26/2007 11/30/2007 1

71151-PR01 IP RETS/ODCM Radiological Effluent 1

BI

- OUTAGE ACCESS CONTROL AND ALARA Baseline Inspections 01/21/2008 01/25/2008 1

7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 01/21/2008 01/25/2008 1

7112102 IP ALARA Planning and Controls 2

HEATSINK

- HEAT SINK INSPECTION Baseline Inspections 03/24/2008 03/28/2008 1

7111107B IP Heat Sink Performance This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.