Period of Enforcement Discretion Extension for Arkansas Nuclear One, Units 1 and 2, During Implementation of National Fire Protection Association Standard 805
ML062020258
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 08/18/2006
From: Catherine Haney
Plant Licensing Branch III-2
To: Forbes J
Entergy Operations
Holland D, NRR/DORL, 415-1436
References
Download: ML062020258 (4)


Text

August 18, 2006 Mr. Jeffrey S. Forbes Site Vice President Arkansas Nuclear One Entergy Operations, Inc.

1448 S.R. 333 Russellville, AR 72802

SUBJECT:

PERIOD OF ENFORCEMENT DISCRETION DURING IMPLEMENTATION OF NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805, ARKANSAS NUCLEAR ONE, UNITS 1 AND 2.

Dear Mr. Forbes:

In a letter dated January 31, 2006 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML053500434), the U.S. Nuclear Regulatory Commission (NRC) acknowledged your letter of November 2, 2005 (ADAMS No. ML053140128), in which you stated that Entergy Operations, Inc. intended to adopt National Fire Protection Association (NFPA) Standard 805, NFPA 805, Performance-Based Standard for Fire Protection for Light-Water Reactor Electric Generating Plants, 2001 Edition, pursuant to Section 50.48(c) of Part 50 of Title 10 of the Code of Federal Regulations, at Arkansas Nuclear One, Units 1 and 2.

In your letter, you requested enforcement discretion for a period of 3 years for existing identified incidents of noncompliances, in accordance with the NRCs Interim Enforcement Policy. In the January 31, 2006, letter, the NRC granted a 2-year enforcement discretion period for Arkansas Nuclear One, Units 1 and 2. However, we noted that the NRC is considering your request for extended discretion and would contact you when we have reached a decision.

On the basis of a revision to the Enforcement Policy (71 Federal Register 19905), I am now informing you that your request for a 3-year enforcement discretion period is granted.

Therefore, the discretion period for Arkansas Nuclear One, Units 1 and 2, which began on December 31, 2005, will expire on December 31, 2008.

As you are aware, in order to receive enforcement discretion, you must: (a) evaluate the risk significance of all noncompliances to assure that they do not constitute Red (or Severity Level I) findings under the Reactor Oversight Program, (b) enter them into your corrective action program, and (c) implement and maintain appropriate compensatory measures until you complete your corrective actions, or until the NRC staff approves your license amendment request and issues its safety evaluation. You should refer to NRC Regulatory Issue Summary 2005-07, Compensatory Measures to Satisfy the Fire Protection Program Requirements, for additional NRC staff guidance on appropriate compensatory measures.

J. Forbes If you have any questions regarding this matter, please contact Drew Holland, Project Manager, at 301-415-1436 or DGH1@nrc.gov.

Sincerely,

\\RA\\

Catherine Haney, Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-313 and 50-368 cc: Those on the attached list

ML062020258 Office LPLIV:PM LPLIV:LA DRA/FPB:BC DRIS/IRIB:BC Name DHolland LFeizollahi SWeerakkody RGibbs Date 7/27/06 7/27/06 7/27/06 7/28/06 Office OE R-IV/DRS/EB2:BC LPLIV:BC DORL:D Name DSolorio LSmith DTerao CHaney Date 8/7/06 8/14/06 8/9/06 8/18/06

Letter to Mr. Jeffrey S. Forbes from Catherine Haney dated August 18. 2006

SUBJECT:

PERIOD OF ENFORCEMENT DISCRETION DURING IMPLEMENTATION OF NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805, ARKANSAS NUCLEAR ONE, UNITS 1 AND 2.

cc:

Senior Vice President

& Chief Operating Officer Entergy Operations, Inc.

P. O. Box 31995 Jackson, MS 39286-1995 Director, Division of Radiation Control and Emergency Management Arkansas Department of Health 4815 West Markham Street, Slot 30 Little Rock, AR 72205-3867 Winston & Strawn 1700 K Street, N.W.

Washington, DC 20006-3817 Senior Resident Inspector U.S. Nuclear Regulatory Commission P. O. Box 310 London, AR 72847 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 County Judge of Pope County Pope County Courthouse Russellville, AR 7280 Vice President, Operations Support Entergy Operations, Inc.

P. O. Box 31995 Jackson, MS 39286-1995 Wise, Carter, Child & Caraway P. O. Box 651 Jackson, MS 39205