MONTHYEAR0CAN062302, Submittal of Revision 22 of the ANO Fire Hazards Analysis2023-06-20020 June 2023 Submittal of Revision 22 of the ANO Fire Hazards Analysis 0CAN102102, Units 1 and 210 CFR 50.71(e) Report Revision 20 of the ANO Fire Hazards Analysis2021-10-0606 October 2021 Units 1 and 210 CFR 50.71(e) Report Revision 20 of the ANO Fire Hazards Analysis ML17191B1332017-06-0707 June 2017 Redacted Fire Hazards Analysis, Revision 17 1CAN111501, Second Set of Round 2 Responses to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-8052015-11-0404 November 2015 Second Set of Round 2 Responses to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-805 1CAN081501, 120-Day Response to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-8052015-08-12012 August 2015 120-Day Response to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-805 1CAN071501, Arkansas, Unit 1 - 90-Day Response to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-8052015-07-21021 July 2015 Arkansas, Unit 1 - 90-Day Response to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-805 1CAN051501, Response to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-8052015-05-19019 May 2015 Response to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-805 2CAN121404, Arkansas, Unit 2 - Adoption of National Fire Protection Association Standard NFPA-805, License Amendment Request Supplemental2014-12-0909 December 2014 Arkansas, Unit 2 - Adoption of National Fire Protection Association Standard NFPA-805, License Amendment Request Supplemental 2CAN081401, Response to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-8052014-08-0707 August 2014 Response to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-805 1CAN011401, License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)2014-01-29029 January 2014 License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition) 2CAN121302, Response to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-8052013-12-0404 December 2013 Response to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-805 0CAN110502, Letter of Intent to Adopt NFPA 805 - Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition, Arkansas Nuclear One - Units 1 and 22005-11-0202 November 2005 Letter of Intent to Adopt NFPA 805 - Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition, Arkansas Nuclear One - Units 1 and 2 2023-06-20
[Table view] Category:Letter type:
MONTHYEAR2CAN012401, U.S. Additional Protocol2024-01-17017 January 2024 U.S. Additional Protocol 2CAN012403, Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42024-01-11011 January 2024 Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN012401, Registration of Cask Use2024-01-10010 January 2024 Registration of Cask Use 1CAN122301, Responses to Request for Additional Information for Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISl-037)2023-12-14014 December 2023 Responses to Request for Additional Information for Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISl-037) 2CAN112302, Submittal of Amendment 31 to Safety Analysis Report2023-11-16016 November 2023 Submittal of Amendment 31 to Safety Analysis Report 0CAN102303, Registration of Cask Use2023-10-24024 October 2023 Registration of Cask Use 0CAN102302, (ANO) Emergency Plan Revision 49 and Emergency Plan On-Shift Staffing Analysis Revision 32023-10-11011 October 2023 (ANO) Emergency Plan Revision 49 and Emergency Plan On-Shift Staffing Analysis Revision 3 0CAN102301, Evacuation Time Estimate (ETE) Study2023-10-0404 October 2023 Evacuation Time Estimate (ETE) Study 1CAN092301, Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-09-21021 September 2023 Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN092302, Supplement to Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002)2023-09-14014 September 2023 Supplement to Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002) 2CAN092301, Reply to a Notice of Violation2023-09-0808 September 2023 Reply to a Notice of Violation 0CAN092301, Emergency Plan Implementing Procedure Revision2023-09-0505 September 2023 Emergency Plan Implementing Procedure Revision 0CAN082301, Units 1 and 2 - Changes to the Quality Assurance Program Approval Form for Radioactive Material Package No. 03412023-08-17017 August 2023 Units 1 and 2 - Changes to the Quality Assurance Program Approval Form for Radioactive Material Package No. 0341 2CAN082301, Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 2, Twenty-Ninth Refueling Outage (2R29)2023-08-10010 August 2023 Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 2, Twenty-Ninth Refueling Outage (2R29) 0CAN072301, Registration of Cask Use2023-07-18018 July 2023 Registration of Cask Use 1CAN062304, Supplement Related to License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation2023-06-29029 June 2023 Supplement Related to License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation 0CAN062301, Status of Actions to Return to Compliance2023-06-26026 June 2023 Status of Actions to Return to Compliance 0CAN062302, Submittal of Revision 22 of the ANO Fire Hazards Analysis2023-06-20020 June 2023 Submittal of Revision 22 of the ANO Fire Hazards Analysis 1CAN062301, Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISI-037)2023-06-0808 June 2023 Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISI-037) 0CAN052303, Annual 10 CFR 50.46 Report for Calendar Year 20222023-05-24024 May 2023 Annual 10 CFR 50.46 Report for Calendar Year 2022 0CAN052302, Emergency Plan Rev. 482023-05-11011 May 2023 Emergency Plan Rev. 48 0CAN052301, Units 1 and 2 - Annual Radiological Environmental Operating Report for 20222023-05-0909 May 2023 Units 1 and 2 - Annual Radiological Environmental Operating Report for 2022 2CAN052301, Cycle 30 Core Operating Limits Report (COLR)2023-05-0303 May 2023 Cycle 30 Core Operating Limits Report (COLR) 0CAN042302, Annual Occupational Radiation Exposure Report for 20222023-04-27027 April 2023 Annual Occupational Radiation Exposure Report for 2022 0CAN042301, Radioactive Effluent Release Report for 20222023-04-14014 April 2023 Radioactive Effluent Release Report for 2022 2CAN042301, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-04-0505 April 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 1CAN032301, License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure2023-03-30030 March 2023 License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure 2CAN032303, Responses to Request for Additional Information Concerning the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-03-29029 March 2023 Responses to Request for Additional Information Concerning the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 2CAN032304, Supplement to the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-03-29029 March 2023 Supplement to the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 2CAN032305, 03 Post Examination Analysis2023-03-23023 March 2023 03 Post Examination Analysis 1CAN032302, Inspection Summary Report for the Thirtieth Refueling Outage (1R30)2023-03-20020 March 2023 Inspection Summary Report for the Thirtieth Refueling Outage (1R30) 1CAN012301, Responses to Request for Additional Information for Request for Relief ANO1-ISI-0352023-01-30030 January 2023 Responses to Request for Additional Information for Request for Relief ANO1-ISI-035 2CAN012303, U.S. Additional Protocol2023-01-23023 January 2023 U.S. Additional Protocol 2CAN012302, Relief Request ANO2-RR-23-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-01-20020 January 2023 Relief Request ANO2-RR-23-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 1CAN122201, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42022-12-22022 December 2022 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN122202, Registration of Cask Use2022-12-21021 December 2022 Registration of Cask Use 0CAN122201, Reply to a Notice of Violation; EA-22-0992022-12-0808 December 2022 Reply to a Notice of Violation; EA-22-099 0CAN112201, Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002)2022-11-10010 November 2022 Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002) 1CAN102202, Application to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation2022-10-31031 October 2022 Application to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation 1CAN102203, Cycle 31 Core Operating Limits Report2022-10-24024 October 2022 Cycle 31 Core Operating Limits Report 1CAN102201, Supplement to Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations2022-10-13013 October 2022 Supplement to Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations 0CAN092201, Supplement to License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements2022-09-29029 September 2022 Supplement to License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements 1CAN092201, Supplement to Request for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fifth 10-Year Interval, First Period2022-09-0808 September 2022 Supplement to Request for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fifth 10-Year Interval, First Period 0CAN082201, License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements2022-08-30030 August 2022 License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements 1CAN082201, Request for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fifth 10-Year Interval, First Period2022-08-24024 August 2022 Request for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fifth 10-Year Interval, First Period 2CAN072201, Response to Request for Additional Information Requests for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fourth 10-Year Interval, Second and Third Periods2022-07-20020 July 2022 Response to Request for Additional Information Requests for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fourth 10-Year Interval, Second and Third Periods 0CAN072201, Registration of Cask Use2022-07-14014 July 2022 Registration of Cask Use 0CAN062202, Registration of Cask Use2022-06-0909 June 2022 Registration of Cask Use 1CAN062201, Response to the Request for Additional Information Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations2022-06-0202 June 2022 Response to the Request for Additional Information Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations 1CAN052201, Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Augmented Examination Requirements ANO1-ISI-0352022-05-31031 May 2022 Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Augmented Examination Requirements ANO1-ISI-035 2024-01-17
[Table view] |
Text
Entergy Operations, Inc.
1448S.R.333 17-6E ergyRussellville, ARl72802 Tel 479-858-4888 Jeffrey S. Forbes Vice Presideni Operations AIO OCAN110502 November 2, 2005 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Letter of Intent to Adopt NFPA 805 - Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Arkansas Nuclear One - Units 1 and 2 Docket Nos. 50-313 and 50-368 License Nos. DPR-51 and NPF-6
Dear Sir or Madam:
This letter serves to inform you that Entergy Operations, Inc. (Entergy) intends to adopt NFPA 805 (Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition) in accordance with IOCFR50.48(c) for Arkansas Nuclear One, Units 1 and 2.
The transition to the performance-based standard will commence during the first quarter, 2006, and will take approximately 36 months to fully implement. The schedule is subject to change depending on the extent of any physical plant modifications and/or changes to the fire protection program determined necessary to comply with NFPA 805. An updated schedule will accompany the License Amendment Request required under I OCFR50.48(c)(3)(i).
The NFPA 805 transition process will proceed in three phases:
Phase 1-Preliminary assessment of the Fire Protection Program (Complete)
- Technical and regulatory assessments performed to determine the feasibility and practicality of performing the transition.
Phase 2-Reviews and Engineering Analysis
- Nuclear Safety Performance Criteria Transition review
- Non-Power Operational Mode Transition review 71kO(6
OCAN 10502 Page 2 of 3
- Radiological Release Transition review
- License Amendment Requests Phase 3-Implementation
. Monitoring The process will be considered complete upon receipt of the approved license amendment authorizing the transition to NFPA 805.
The NRC Interim Enforcement Policy (69FR33684, June 16, 2004) provides guidelines for enforcement discretion for identified non-compliances. Those non-compliances must be entered into the licensee's Corrective Action Program, must not be associated with findings that the Reactor Oversight Process Significance Determination Process would evaluate as Red, or would not be categorized as Severity Level 1, and appropriate compensatory measures have been taken. As outlined in the Enforcement Policy, enforcement discretion begins with the licensee's letter of intent.
For the reasons stated below, Entergy requests an extension of the enforcement discretion window to three years for each of the ANO units.
- Wrthin Entergy, and the nuclear industry in general, there are a limited number of experts in the areas of Electrical Engineering (circuit analysis), System Engineering, and Appendix R Safe Shutdown needed to support reconstitution of the Appendix R design basis and the transition to NFPA 805.
- The ANO units are dissimilar in that Unit-1 is a B&W plant and Unit-2 is a CE plant.
Therefore, separate analyses and evaluations must be performed for each unit. For efficiency and consistency, Entergy plans on conducting the evaluations in series utilizing the same resources. Even if sufficient personnel were available to perform the Appendix R Reconstitution Project and NFPA 805 transition in parallel, there would be added burden to maintain the analysis consistency and quality. For this reason we estimate the total project duration to be approximately 36 months.
- Entergy believes that the risk of extension of the enforcement discretion window is low since all issues have either been assessed as low risk or corrective actions taken.
Based on the fact that the ANO units are dissimilar and that they will be the first two units to transition to NFPA 805 in NRC Region IV, Entergy believes there is much to be learned from the transition. Therefore, Entergy proposes that Arkansas Nuclear One, Units I and 2, be considered pilot plants for the initial implementation of performance based fire protection using NFPA 805. As part of this pilot process, Entergy requests all licensing and review fees be waived for the License Amendment Requests for both ANO units. Entergy believes that our participation in the pilot process will benefit the NRC significantly through the experience gained throughout the NRC observation process, especially considering the dissimilarity of the ANO units. The experience gained by the NRC and Entergy in
OCAN1 10502 Page 3 of 3 developing, submitting, and reviewing the Transition Report will allow the development of valid industry templates for future licensees undergoing transition. The knowledge and experience gained during the observation process will provide valuable input into the NRC inspection guidance for transition. In addition, waiver of the licensing fees will somewhat offset the expense and burden of orchestrating the on-site observation process.
Commitments made in this submittal are documented in the attachment. Should you have any questions regarding this submittal, contact Richard Scheide at 479-858-4618.
- Sihr6ely, JSF/rhs Attachment cc: Dr. Bruce S. Mallett Regional Administrator U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Mr. Drew Holland Mail Stop 0-7 D1 Washington, DC 20555-0001
Attachment to OCAN1 00507 List of Regulatory Commitments A_
Attachment to OCAN1 00507 List of Regulatory Commitments The following table identifies those actions committed to by Entergy in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments.
TYPE SCHEDULED ONE- One) COMPLETION TIME CONTINUING DATE COMMITMENT ACTION COMPLIANCE (If Required)
ANO-1 and ANO-2 will transition the X March 31, 2009 Fire Protection Program to comply with NFPA 805