August 10, 2006 Mr. Gene F. St. Pierre, Site Vice President c/o James M. Peschel Seabrook Station PO Box 300 Seabrook, NH 03874
SUBJECT:
SEABROOK STATION, UNIT NO. 1 - CORRECTION OF AMENDMENT NO. 110, MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE (TAC NO. MC8434)
Dear Mr. St. Pierre:
On May 22, 2006, the Nuclear Regulatory Commission staff issued the subject amendment in response to your application transmitted by letter dated September 22, 2005. The amendment revised the Seabrook Station, Unit No. 1 (Seabrook) Technical Specifications (TSs).
Specifically, the amendment revised the Seabrook TSs to allow implementation of a 1.7 percent measurement uncertainty recapture power uprate.
Subsequent to the issuance, your staff identified errors in the associated safety evaluation. An errata sheet indicating the pages to be replaced, as well as the affected pages are enclosed.
We apologize for any inconvenience.
Sincerely,
/RA/
G. Edward Miller, Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443
Enclosures:
As stated cc w/encls: See next page
August 10, 2006 Mr. Gene F. St. Pierre, Site Vice President c/o James M. Peschel Seabrook Station PO Box 300 Seabrook, NH 03874
SUBJECT:
SEABROOK STATION, UNIT NO. 1 - CORRECTION OF AMENDMENT NO. 110, MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE (TAC NO. MC8434)
Dear Mr. St. Pierre:
On May 22, 2006, the Nuclear Regulatory Commission staff issued the subject amendment in response to your application transmitted by letter dated September 22, 2005. The amendment revised the Seabrook Station, Unit No. 1 (Seabrook) Technical Specifications (TSs).
Specifically, the amendment revised the Seabrook TSs to allow implementation of a 1.7 percent measurement uncertainty recapture power uprate.
Subsequent to the issuance, your staff identified errors in the associated safety evaluation. An errata sheet indicating the pages to be replaced, as well as the affected pages are enclosed.
We apologize for any inconvenience.
Sincerely,
/RA/
G. Edward Miller, Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443
Enclosures:
As stated cc w/encls: See next page DISTRIBUTION:
RidsNrrDorlLpl1-2 RidsOgcRp RidsRgn1MailCenter PUBLIC RidsNrrPMGMiller RidsAcrsAcnwMailCenter LPL1-2 R/F RidsNrrLACRaynor RidsNrrDorl GHill (2)
Package Accession Number: ML061910322 Amendment Accession Number: ML061910324 Tech Specs. Accession Number: ML062220236 OFFICE LPL1-2/PM LPL1-2/LA LPL1-2/BC (A)
NAME GEMiller:rsa CRaynor BPoole DATE 8/10/06 8/9/06 8/10/06 OFFICIAL RECORD COPY
Seabrook Station, Unit No. 1 cc:
Mr. J. A. Stall Senior Vice President, Nuclear and Chief Nuclear Officer Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. Peter Brann Assistant Attorney General State House, Station #6 Augusta, ME 04333 Resident Inspector U.S. Nuclear Regulatory Commission Seabrook Nuclear Power Station P.O. Box 1149 Seabrook, NH 03874 Town of Exeter 10 Front Street Exeter, NH 03823 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Office of the Attorney General One Ashburton Place, 20th Floor Boston, MA 02108 Board of Selectmen Town of Amesbury Town Hall Amesbury, MA 01913 Ms. Deborah Bell Federal Emergency Management Agency Region I J.W. McCormack P.O. &
Courthouse Building, Room 401 Boston, MA 02109 Mr. Tom Crimmins Polestar Applied Technology One First Street, Suite 4 Los Altos, CA 94019 Mr. Stephen McGrail, Director ATTN: James Muckerheide Massachusetts Emergency Management Agency 400 Worcester Road Framingham, MA 01702-5399 Philip T. McLaughlin, Attorney General Steven M. Houran, Deputy Attorney General 33 Capitol Street Concord, NH 03301 Mr. Bruce Cheney, Director New Hampshire Office of Emergency Management State Office Park South 107 Pleasant Street Concord, NH 03301 Mr. M. S. Ross, Managing Attorney Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. Rajiv S. Kundalkar Vice President - Nuclear Engineering Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 James M. Peschel Regulatory Programs Manager Seabrook Station FPL Energy Seabrook, LLC PO Box 300 Seabrook, NH 03874 Marjan Mashhadi Senior Attorney Florida Power & Light Company 801 Pennsylvania Ave., NW Suite 220 Washington, DC 20004
Seabrook Station, Unit No. 1 cc:
Mark Warner Vice President, Nuclear Operations Support Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420
CORRECTION TO LICENSE AMENDMENT NO. 110 SAFETY EVALUATION FACILITY OPERATING LICENSE NO. NPF-86 DOCKET NO. 50-443 Please replace the following pages of the Safety Evaluation associated with amendment No. 110 to Facility Operating License No. NPF-86 with the attached revised pages. The revised pages contain marginal lines indicating the areas of change.
Remove Insert 2
2 5
5 6
6 8
8 10 10 11 11 23 23 29 29