Summary of 12/16/2005, Meeting with FPL Energy Seabrook, LLC to Discuss Measurement Uncertainty Recapture Power Uprate License Amendment Request (Tac MC8434)
ML060030107
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 01/11/2006
From: Geoffrey Miller
Plant Licensing Branch III-2
To:
Florida Power & Light Energy Seabrook
Miller G, NRR/DLPM, 415-2481
Shared Package
ML060030110 List:
References
TAC MC8434
Download: ML060030107 (3)


Text

January 11, 2006 LICENSEE: FPL ENERGY SEABROOK, LLC.

FACILITY: SEABROOK STATION UNIT NO. 1

SUBJECT:

SUMMARY

OF DECEMBER 16, 2005, MEETING WITH FPL ENERGY SEABROOK, LLC TO DISCUSS MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE LICENSE AMENDMENT REQUEST (TAC NO. MC8434)

On December 16, 2005, the Nuclear Regulatory Commission (NRC) staff held a meeting with FPL Energy Seabrook, LLC (FPLE) to discuss a license amendment request (LAR) submitted for the Seabrook Station, Unit No. 1 (Seabrook). Specifically, the meeting was held to discuss the list of topical areas of concern sent to FPLE by letter dated November 30, 2005. The LAR for Seabrook requested approval of a measurement uncertainty recapture (MUR) power uprate based on use of the Caldon, Inc. (Caldon) LEFM CheckPlusTM System. FPLE was supported in this meeting by representatives from Caldon. This document provides a summary of the meeting. It should be noted that the latter half of this meeting was to be closed to public participation due to the discussion of information proprietary to Caldon, however no members of the public were in attendance.

G. Edward Miller, Office of Nuclear Reactor Regulation, opened the meeting with a synopsis of the current status of the Seabrook LAR. Additionally, opening remarks were provided by Steve Hale, FPLE, and Cal Hastings, Caldon. The presentation slides used jointly by FPLE and Caldon are included as Enclosure 1, and the list of meeting attendees is included as , to this document. Following the opening statements, Herb Estrada of Caldon began the presentation with the basics of operation for the Caldon ultrasonic flow meter (UFM).

Following the discussion of the basics of operation of the Caldon UFM, each of the topical areas from the November 30, 2005, letter were discussed in series. The NRC staff engaged FPLE and Caldon with questions and comments throughout the presentation. At the conclusion of the meeting, areas for further discussion, resolved topics, and action items were reviewed.

Following a review of the days discussion, the meeting was adjourned. For any inquires concerning this meeting, I can be reached at (301) 415-2481, or gxm@nrc.gov.

/RA/

G. Edward Miller, Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443

Enclosures:

1. FPLE Slides
2. List of Attendees

Following a review of the days discussion, the meeting was adjourned. For any inquires concerning this meeting, I can be reached at (301) 415-2481, or gxm@nrc.gov.

/RA/

G. Edward Miller, Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443

Enclosures:

1. FPLE Slides
2. List of Attendees DISTRIBUTION:

PUBLIC CHaney JNakoski JBurns LPLI-2 Reading CHolden EHackett RTaylor ACRS DRoberts WLyon RHardies OGC VNerses YOrechwa IAhmed TMensah GMiller PKrohn, RGN-I TAlexion CRaynor Package Accession No.: ML060030110 Meeting Summary Accession No.: ML060030107 OFFICE NRR/LPLI-2/PE NRR/LPLI-2/LA NRR/LPLI-2/BC NAME GMiller: CM CRaynor DRoberts DATE 1/4/06 1/4/06 1/11/06 OFFICIAL RECORD COPY