July 11, 2006 MEMORANDUM TO: Stacey L. Rosenberg, Chief Special Projects Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation FROM:
Michelle C. Honcharik, Project Manager /RA/
Special Projects Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation
SUBJECT:
SUMMARY
OF MAY 23, 2006, OPEN MEETING WITH BOILING WATER REACTOR OWNERS' GROUP REGARDING PROPOSED TOPICAL REPORT SUBMITTALS FOR RISK-INFORMED TECHNICAL SPECIFICATION INITIATIVES 4a AND 6 (TAC NO. MC1445)
On May 23, 2006, a Category 2 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of the Boiling Water Reactor Owners' Group (BWROG) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss two proposed topical report submittals related to risk-informed technical specification (RITS) initiatives 4a and 6 for multiple systems completion time (CT) and allowed outage time extensions. A list of attendees is enclosed. See Agencywide Documents Access and Management (ADAMS) Accession No. ML061810166 for the meeting slides.
A prior pre-submittal meeting was held on October 28, 2004. Due to the time elapsed and NRC staff changes since then, a second meeting was deemed necessary. The October 28, 2004, meeting summary dated December 13, 2004, is available in ADAMS at Accession No. ML043210050; the meeting slide presentation is available in ADAMS at Accession No. ML043140156.
The BWROG reviewed the background and need for the topical reports and revisions made since the October 2004 meeting. The RITS initiative 4a and 6 reports were summarized. The BWROG also discussed the risk-informed approach, the risk impact measures and acceptance criteria, the system evaluation, and risk results. The BWROG stated that the systems being considered have no direct effect on core damage frequency or large early release frequency; the primary effect of the unavailability is on design basis. The proposed changes are:
initiative 4a - change the CT for one subsystem inoperable from 7 days to either 15 or 30 days and initiative 6 - change the CT for explicit technical specification limiting condition of operation 3.0.3 entry from 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> to either 1 or 7 days. The BWROG explained that the benefits of these proposed changes are to: avoid unnecessary unscheduled plant shutdowns, minimize plant transitions, and provide for increased flexibility in scheduling and performing maintenance and surveillance activities.
The BWROG also reviewed the NRC staff comments received from the October 2004 meeting and provided the responses and actions being taken to address them in the meeting slides.
The BWROG stated that it plans to submit both topical reports to the NRC for review in August 2006. Technical Specification Task Force (TSTF) travelers will be submitted once the review of the topical reports has commenced. The NRC staff suggested the TSTF travelers be submitted after any responses to NRC staff requests for additional information regarding the topical reports are submitted.
Members of the public were not in attendance.
Project No. 691
Enclosure:
List of Attendees cc w/encl: See next page
The BWROG stated that it plans to submit both topical reports to the NRC for review in August 2006. Technical Specification Task Force (TSTF) travelers will be submitted once the review of the topical reports has commenced. The NRC staff suggested the TSTF travelers be submitted after any responses to NRC staff requests for additional information regarding the topical reports are submitted.
Members of the public were not in attendance.
Project No. 691
Enclosure:
List of Attendees cc w/encl: See next page DISTRIBUTION:
PUBLIC PSPB Reading File RidsNrrDpr RidsNrrDprPspb RidsNrrLADBaxley RidsAcrsAcnwMailCenter RidsNrrPMMHoncharik RidsOgcMailCenter SAlexander AHowe (Andrew)
MStutzke TTjader SLaur TKobetz LMrowca DShum MRubin RJasinski MEETING NOTICE ACCESSION NO.: ML061280610 SLIDES ACCESSION NO.: ML061810166 PKG NO. : ML061800038 Meeting Summary: ML061800035 NRC-001 OFFICE PSPBP/PM PSPB/LA PSPB/BC NAME MHoncharik DBaxley SRosenberg DATE 7/10/06 7/7/06 7/11/06 OFFICIAL RECORD COPY
BWR Owners Group Project No. 691 cc:
Mr. Randy C. Bunt Vice Chairman, BWROG Southern Nuclear Operating Company Bin B057 P.O. Box 1295 Birmingham, AL 35201 Mr. J. A. Gray, Jr.
Regulatory Response Group Vice Chairman BWR Owners Group Entergy Nuclear Northeast 440 Hamilton Avenue Mail Stop 12C White Plains, NY 10601-5029 Mr. H. Lewis Sumner Executive Chairman, BWROG Southern Nuclear Company 40 Inverness Center Parkway P.O. Box 1295 Birmingham, AL 35242 Mr. Thomas G. Hurst GE Energy M/C A-16 3901 Castle Hayne Road Wilmington, NC 28401 Mr. Amir Shahkarami Executive Vice Chairman, BWROG Exelon Cornerstone II at Cantera 4300 Winfield Road Warrenville, IL 60555 Mr. William A. Eaton Entergy P.O. Box 31995 Jackson, MS 39286 Mr. Al Wrape PPL Mail Code GENPL4 Two North Ninth Street Allentown, PA 18101 Mr. Richard Libra DTE Energy - Fermi 2 M/C 280 OBA 6400 North Dixie Highway Newport, MI 48166 Mr. James F. Klapproth GE Energy M/C A-16 3901 Castle Hayne Road Wilmington, NC 28401 Mr. Kenneth Putnam Regulatory Response Group Chairman BWR Owners Group Nuclear Management Company Duane Arnold Energy Center 3277 DAEC Road Palo, IA 52324 Mr. Tim E. Abney GE Energy M/C A-16 3901 Castle Hayne Road Wilmington, NC 28401 Mr. Joseph E. Conen, Chairman BWR Owners Group DTE Energy-Fermie 2 200 TAC 6400 N. Dixie Highway Newport, MI 48166
ATTENDEES MEETING WITH THE BOILING WATER REACTOR OWNERS GROUP (BWROG)
MAY 23, 2006 BWROG F. Emerson S. Visweswaran T. Carrier NEI B. Bradley NRC M. Honcharik R. Tjader S. Laur A. Howe J. Peralta T. Kobetz D. Shum