Orders Approving Application Regarding Proposed Corporate Merger
ML061630448
Person / Time
Site: Salem, Saint Lucie, Seabrook, Turkey Point  NextEra Energy icon.png
Issue date: 08/03/2006
From: Moroney B
Plant Licensing Branch III-2
To: Stall J
Florida Power & Light Co
Moroney B, NRR/DORL, 415-3974
Shared Package
ML061640017 List:
References
TAC MC9651, TAC MC9652, TAC MC9653, TAC MC9654, TAC MC9655, TAC MC9656
Download: ML061630448 (8)


Text

August 3, 2006 Mr. J. A. Stall Senior Vice President, Nuclear and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, Florida 33408-0420

SUBJECT:

ST. LUCIE NUCLEAR PLANT, UNIT NOS. 1 AND 2, TURKEY POINT NUCLEAR PLANT, UNIT NOS. 3 AND 4, SEABROOK STATION, UNIT NO. 1, AND DUANE ARNOLD ENERGY CENTER - ORDERS APPROVING APPLICATION REGARDING PROPOSED CORPORATE MERGER (TAC NOS. MC9651, MC9652, MC9653, MC9654, MC9655 AND MC9656)

Dear Mr. Stall:

The U.S. Nuclear Regulatory Commission (NRC) staff has completed its review of the application dated January 20, 2006, filed by Florida Power and Light Company, FPL Energy Seabrook, LLC, and FPL Energy Duane Arnold, LLC. The application, pursuant to Section 50.80 of Title 10 of the Code of Federal Regulations, sought approval of the proposed indirect transfer of the operating licenses as held by the foregoing licensees for St. Lucie Nuclear Plant, Units 1 and 2, Turkey Point Nuclear Plant, Units 3 and 4, Seabrook Nuclear Station, Unit 1, and the Duane Arnold Energy Center to the extent effected by the proposed merger of FPL Group, Inc., and Constellation Energy Group, Inc. The enclosed Orders (Enclosure 1) approve the proposed indirect license transfers. The Orders will be placed in the NRC public document room (PDR), added to the Agencywide Documents Access and Management System Publicly Available Records System (ADAMS PARS) Library and will be forwarded to the Office of the Federal Register for publication. is the NRC staffs safety evaluation (SE) related to the preceding actions. Your January 20, 2006, submittal provided certain confidential commercial information relating to the Seabrook and Duane Arnold plants, which you requested to be withheld from public disclosure pursuant to 10 CFR 2.390(a)(4) and 10 CFR 9.17(a)(4). You letter included an affidavit in support of this request. The NRC staff reviewed your request and determined that the information sought to be withheld did contain proprietary commercial information. Since some of this information is discussed in the SE, Enclosure 2 will be withheld from public disclosure. is a nonproprietary version of the SE that will be placed in the NRC PDR and added to the ADAMS PARS Library.

J. Stall If you have any questions regarding this matter, please contact me at (301) 415-3974.

Sincerely,

/RA/

Brendan T. Moroney, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-250, 50-251, 50-331, 50-335, 50-389 and 50-443

Enclosures:

1. Orders
2. Safety Evaluation (Proprietary version)
3. Safety Evaluation (Nonproprietary version) cc w/encls 1 and 3: See next page

J. Stall If you have any questions regarding this matter, please contact me at (301) 415-3974.

Sincerely,

/RA/

Brendan T. Moroney, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-250, 50-251, 50-331, 50-335, 50-389 and 50-443

Enclosures:

1. Orders
2. Safety Evaluation (Proprietary version)
3. Safety Evaluation (Nonproprietary version) cc w/encls 1 and 3: See next page DISTRIBUTION:

PUBLIC LPL1-1 R/F LPL2-2 R/F LPL3-1 R/F RidsNrrOd RidsNrrAdro RidsNrrDorl RidsNrrDorlLpl1-1 RidsNrrDorlLpl2-2 RidsNrrDorlLpl3-1 RidsNrrPMBMoroney RidsNrrPMEMiller RidsNrrPMDSpaulding RidsNrrLABClayton RdsNrrLATHarris RidsNrrLACRaynor RidsOgcRp RidsAcrsAcnwMailCenter RidsOpaMailCenter RidsRgn1MailCenter RisRegion2MailCenter RidsRegion3MailCenter RidsSecyMailCenter RidsNrrDprPfpb RidsEdoMailCenter M. Dusaniwskyj, NRR S. Uttal, OGC Package: ML061640017 Letter: ML061630448 Orders: ML061640044 Proprietary SE: ML061640059 Nonproprietary SE: ML061640067 OFFICE LPL2-2/PM LPL2-2/LA PFPB/BC(A)

OGC DORL/D NAME BMoroney BClayton BWetzel SUttal CHaney DATE 07/24/06 07/24/06 06/21/06 07/28/06 08/03/06 OFFICIAL RECORD COPY

Page 1 of 3 Florida Power and Light Company ST. LUCIE PLANT FPL Energy Seabrook, LLC TURKEY POINT PLANT FPL Energy Duane Arnold, LLC SEABROOK STATION, UNIT NO. 1 DUANE ARNOLD ENERGY CENTER cc:

Mr. William E. Webster Vice President, Nuclear Operations Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Senior Resident Inspector St. Lucie Plant U.S. Nuclear Regulatory Commission P.O. Box 6090 Jensen Beach, Florida 34957 Craig Fugate, Director Division of Emergency Preparedness Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 M. S. Ross, Managing Attorney Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Marjan Mashhadi, Senior Attorney Florida Power & Light Company 801 Pennsylvania Avenue, NW., # 220 Washington, DC 20004 Terry O. Jones, Site Vice President Turkey Point Nuclear Plant Florida Power and Light Company 9760 SW. 344th Street Florida City, FL 33035 Douglas Anderson County Administrator St. Lucie County 2300 Virginia Avenue Ft. Pierce, Florida 34982 Mr. Christopher R. Costanzo Plant General Manager St. Lucie Nuclear Plant 6351 South Ocean Drive Jensen Beach, Florida 34957 Walter Parker, Licensing Manager Turkey Point Nuclear Plant 9760 SW. 344th Street Florida City, FL 33035 Mr. William A. Passetti, Chief Department of Health Bureau of Radiation Control 2020 Capital Circle, SE, Bin # C21 Tallahassee, Florida 32399-1741 Mr. Gordon L. Johnston Site Vice President St. Lucie Nuclear Plant 6351 South Ocean Drive Jensen Beach, Florida 34957 Attorney General Department of Legal Affairs The Capitol Tallahassee, Florida 32304 Senior Resident Inspector Turkey Point Nuclear Plant U.S. Nuclear Regulatory Commission 9762 SW. 344th Street Florida City, Florida 33035 Michael O. Pearce Plant General Manager Turkey Point Nuclear Plant Florida Power and Light Company 9760 SW. 344th Street Florida City, FL 33035 County Manager Miami-Dade County 111 Northwest 1 Street, 29th Floor Miami, Florida 33128 Mr. Terry L. Patterson Licensing Manager St. Lucie Nuclear Plant 6351 South Ocean Drive Jensen Beach, Florida 34957

Page 2 of 3 Florida Power and Light Company ST. LUCIE PLANT FPL Energy Seabrook, LLC TURKEY POINT PLANT FPL Energy Duane Arnold, LLC SEABROOK STATION, UNIT NO. 1 DUANE ARNOLD ENERGY CENTER cc:

Mark Warner, Vice President Nuclear Operations Support Florida Power and Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. Rajiv S. Kundalkar Vice President - Nuclear Engineering Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. J. Kammel Radiological Emergency Planning Administrator Department of Public Safety 6000 Southeast Tower Drive Stuart, Florida 34997 Mr. Peter Brann Assistant Attorney General State House, Station #6 Augusta, ME 04333 Gene St. Pierre, Site Vice President Seabrook Station FPL Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874 Resident Inspector U.S. Nuclear Regulatory Commission Seabrook Nuclear Power Station P.O. Box 1149 Seabrook, NH 03874 Town of Exeter 10 Front Street Exeter, NH 03823 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Office of the Attorney General One Ashburton Place, 20th Floor Boston, MA 02108 Board of Selectmen Town of Amesbury Town Hall Amesbury, MA 01913 Ms. Deborah Bell Federal Emergency Management Agency Region I J. W. McCormack P.O. &

Courthouse Building, Room 401 Boston, MA 02109 Mr. Tom Crimmins Polestar Applied Technology One First Street, Suite 4 Los Altos, CA 94019 Mr. Stephen McGrail, Director ATTN: James Muckerheide Massachusetts Emergency Management Agency 400 Worcester Road Framingham, MA 01702-5399 Philip T. McLaughlin, Attorney General Steven M. Houran, Deputy Attorney General 33 Capitol Street Concord, NH 03301 Mr. Bruce Cheney, Director New Hampshire Office of Emergency Management State Office Park South 107 Pleasant Street Concord, NH 03301

Page 3 of 3 Florida Power and Light Company ST. LUCIE PLANT FPL Energy Seabrook, LLC TURKEY POINT PLANT FPL Energy Duane Arnold, LLC SEABROOK STATION, UNIT NO. 1 DUANE ARNOLD ENERGY CENTER cc:

Mr. Michael Kiley Station Director Seabrook Station FPL Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874 James M. Peschel Regulatory Programs Manager Seabrook Station FPL Energy Seabrook, LLC PO Box 300 Seabrook, NH 03874 Mr. R. E. Helfrich Senior Attorney Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. W. E. Webster Vice President, Nuclear Operations Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 John Bjorseth Site Director Duane Arnold Energy Center 3277 DAEC Road Palo, IA 52324 Steven R. Catron Manager, Regulatory Affairs Duane Arnold Energy Center 3277 DAEC Road Palo, IA 52324 U. S. Nuclear Regulatory Commission Resident Inspectors Office Rural Route #1 Palo, IA 52324 Regional Administrator, Region III U.S. Nuclear Regulatory Commission Suite 210 2443 Warrenville Road Lisle, IL 60532-4351 Mr. D. A. Curtland Plant Manager Duane Arnold Energy Center 3277 DAEC Rd.

Palo, IA 52324-9785 Daniel McGhee Utilities Division Iowa Department of Commerce Lucas Office Buildings, 5th floor Des Moines, IA 50319 Chairman, Linn County Board of Supervisors 930 1st Street SW Cedar Rapids, IA 52404 Mr. Gary Van Middlesworth Vice President Duane Arnold Energy Center 3277 DAEC Road Palo, IA 52324-9785