ML061590112
| ML061590112 | |
| Person / Time | |
|---|---|
| Site: | Point Beach |
| Issue date: | 06/06/2006 |
| From: | Ann Marie Stone NRC/RGN-III/DRS/EB2 |
| To: | Koehl D Nuclear Management Co |
| References | |
| IR-06-006 | |
| Download: ML061590112 (9) | |
See also: IR 05000266/2006006
Text
June 6,2006
Mr. Dennis L. Koehl
Site Vice President
Point Beach Nuclear Plant
Nuclear Management Company, LLC
6590 Nuclear Road
Two Rivers, WI 54241-9516
SUBJECT:
- INFORMATION
REQUEST FOR AN NRC BIENNIAL BASELINE COMPONENT DESIGN BASES
INSPECTION (CDBI) 05000266/2006006 (DRS); 05000301/2006006 (DRS)
Dear Mr. Koehl:
On August 14, 2006, the NRC will begin a biennial baseline Component Design Bases
Inspection (CDBI) at the
. A team of seven inspectors will
perform this 4-week inspection. This inspection will be performed in accordance with revised
NRC Baseline Inspection Procedure (IP) 71111.21 and replaces the biennial Safety System
Design and Performance Capability inspection.
The CDBI inspection focuses on components which have high risk and low design margins.
The components to be reviewed during this baseline inspection will be identified during an
in-office preparation week prior to the first week of on-site inspection. In addition, a number of
risk significant operator actions and operating experience issues, associated with the
component samples, will also be selected for review.
The inspection will include 4 weeks of on-site inspection. This will include one to two weeks of
on-site information gathering. The inspection team will consist of six NRC inspectors, of which
five will focus on engineering and one on operations. The current inspection schedule is as
follows:
On-site weeks: August 14, 2006, August 28, 2006, September 11, 2006, and
September 25.
The team will be preparing for the inspection mainly during the weeks of August 14 and 21, 2006,
as discussed in the attached enclosure. A Region III Senior Reactor Analyst will accompany the
inspection team during the week of August 14, 2006, to review probabilistic risk assessment data
and assist in identifying risk significant components, which will be reviewed during the inspection.
Experience with previous baseline design inspections of similar depth and length has shown that
these type of inspections are extremely resource intensive, both for the NRC inspectors and the
licensee staff. In order to minimize the inspection impact on the site and to ensure a productive
inspection for both parties, we have enclosed a request for information needed for the inspection.
D. Koehl
-2-
It is important that all of these documents are up to date and complete in order to minimize the
number of additional documents requested during the preparation and/or the on-site portions of
the inspection. The information request has been divided as follows:
The first group lists information necessary for a productive inspection preparation. This
information should be available to the Regional Office by no later than July 28, 2006, or sooner.
The second group of documents requested are those items necessary for the teams in-office
(August 21, 2006) preparation activities. During the in-office preparation week, the team may
identify additional information needed. This information should be available by August 28, 2006
(on-site week). The last group lists information necessary to aid the inspection team in tracking
issues identified as a result of the inspection. It is requested that this information be provided to
the lead inspector as the information is generated during the inspection.
The lead inspector for this inspection is Mr. Robert Daley. We understand that our regulatory
affairs contact for this inspection is Ms. Fritzi Flenji of your organization. In order to facilitate the
inspection, we request that a contact individual be assigned to each inspector to ensure
information requests, questions, and concerns are addressed in a timely manner. If there are
any questions about the inspection or the material requested in the Enclosure, please contact the
lead inspector at (630) 829-9749 or via e-mail at RCD@nrc.gov.
In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter and
its enclosure will be available electronically for public inspection in the NRC Public
Document Room or from the Publicly Available Records (PARS) component of NRC's document
system (ADAMS). ADAMS is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Ann Marie Stone, Chief
Engineering Branch 2
Division of Reactor Safety
Docket Nos. 50-266; 50-301
Enclosure:
Component Design Bases Inspection (CDBI) Document Request
See Attached Distribution
D. Koehl
-3-
cc w/encl:
F. Kuester, President and Chief
Executive Officer, We Generation
D. Cooper, Senior Vice President, Group Operations
J. McCarthy, Site Director of Operations
D. Weaver, Nuclear Asset Manager
Plant Manager
Regulatory Affairs Manager
Training Manager
Site Assessment Manager
Site Engineering Director
Emergency Planning Manager
J. Rogoff, Vice President, Counsel & Secretary
K. Duveneck, Town Chairman
Town of Two Creeks
Chairperson
Public Service Commission of Wisconsin
J. Kitsembel, Electric Division
Public Service Commission of Wisconsin
State Liaison Officer
D. Koehl
-2-
It is important that all of these documents are up to date and complete in order to minimize the
number of additional documents requested during the preparation and/or the on-site portions of
the inspection. The information request has been divided as follows:
The first group lists information necessary for a productive inspection preparation. This
information should be available to the Regional Office by no later than July 28, 2006, or sooner.
The second group of documents requested are those items necessary for the teams in-office
(August 21, 2006) preparation activities. During the in-office preparation week, the team may
identify additional information needed. This information should be available by August 28, 2006
(on-site week). The last group lists information necessary to aid the inspection team in tracking
issues identified as a result of the inspection. It is requested that this information be provided to
the lead inspector as the information is generated during the inspection.
The lead inspector for this inspection is Mr. Robert Daley. We understand that our regulatory
affairs contact for this inspection is Ms. Fritzi Flenji of your organization. In order to facilitate the
inspection, we request that a contact individual be assigned to each inspector to ensure
information requests, questions, and concerns are addressed in a timely manner. If there are
any questions about the inspection or the material requested in the Enclosure, please contact
the lead inspector at (630) 829-9749 or via e-mail at RCD@nrc.gov.
In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter and
its enclosure will be available electronically for public inspection in the NRC Public
Document Room or from the Publicly Available Records (PARS) component of NRC's document
system (ADAMS). ADAMS is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Ann Marie Stone, Chief
Engineering Branch 2
Division of Reactor Safety
Docket No. 50-254; 50-265
Enclosure:
Component Design Bases Inspection (CDBI) Document Request
See Attached Distribution
DOCUMENT NAME:E:\\Filenet\\ML061590112.wpd
G Publicly Available
G Non-Publicly Available
G Sensitive
G Non-Sensitive
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
OFFICE RIII
RIII
RIII
RIII
NAME
RDaley: ls
PLouden
AMStone
DATE
06/06/06
06/06/06
06/06/06
OFFICIAL RECORD COPY
D. Koehl
-3-
ADAMS Distribution:
DXC1
MXB
RidsNrrDirsIrib
GEG
KGO
KKB
CAA1
DRPIII
DRSIII
PLB1
JRK1
INFORMATION REQUEST FOR
COMPONENT DESIGN BASES INSPECTION (CDBI)
Enclosure
1
Inspection Report: 05000266/2006006; 05000301/2006006 (DRS)
Information Gathering/
Inspection Dates:
August 14, 2006
Inspection Dates:
August 28, 2006, September 11, 2006, and September 25, 2006
Inspection Procedure:
IP 71111.21, Component Design Bases Inspection
Lead Inspector:
Robert Daley, Lead Inspector
(708) 829-9749
RCD@nrc.gov
I.
Information Requested Prior to the On-site Information Gathering/Inspection Week
(by July 28, 2006, or sooner)
The following information is requested by July 28, 2006, or sooner, to facilitate inspection
preparation. If you have any questions regarding this information, please call the team
leader as soon as possible. (Information in lists should contain enough information to
be easily understood by the inspection team.)
1.
Risk ranking of top 100 components from your site specific probabilistic safety
analysis (PSA) sorted by Risk Achievement Worth (RAW). Include values for
Birnbaum Importance, Risk Reduction Worth (RRW), and Fussell-Veseley (FV)
(as applicable).
2.
Provide a list of the top 500 cut-sets from your PSA.
3.
Risk ranking of operator actions from your site specific PSA sorted by RAW.
Provide copies of your human reliability worksheets for these items.
4.
If you have an External Events or Fire PSA Model, provide the information
requested in Items 1 and 2 for external events and fire.
5.
Any pre-existing evaluation or list of components and associated calculations with
low design margins, (i.e., pumps closest to the design limit for flow or pressure,
diesel generator close to design required output, heat exchangers close to rated
design heat removal etc.).
6.
List of high risk Maintenance Rule systems/components based on engineering or
expert panel judgement.
7.
A list of operating experience evaluations for the last 3 years.
8.
A list of emergency and/or off-normal operating procedure changes in the last
5 years.
INFORMATION REQUEST FOR
COMPONENT DESIGN BASES INSPECTION (CDBI)
Enclosure
2
9.
A list of maintenance work orders involving repetitive failures in the last 5 years
for the top 100 components. For the purposes of this request, repetitive failure
would be 3 or more failures of the same component or sub-component in the
last 5 years.
10.
A list of Condition Reports related to any of the top 100 components in the last
3 years.
11.
A list of trend codes used for trending corrective action documents.
12.
A list of modifications sorted by component identified in item 1.
13.
List of and Information on any common cause failure of components experienced
in the last 5 years at your facility.
14.
A list of the design calculations which provide the design margin information for
components included in item 1.
15.
List of Root Cause and/or Apparent Cause Evaluations associated with
component failures or design issues initiated/completed in the last 5 years.
16.
List of MOVs in the MOV program, design margin and risk ranking.
17.
List of AOVs in the AOV program, design margin and risk ranking.
18.
SSCs in the maintenance rule (a)(1) category.
19.
Site Top Ten issues list.
20.
Provide list of PRA assumptions regarding operator actions and the associated
procedures.
21.
A copy of any internal/external self-assessments and associated corrective action
documents generated in preparation for the inspection.
22.
A copy of engineering/operations related audits completed in the last 2 years.
23.
Current management and engineering organizational chart.
INFORMATION REQUEST FOR
COMPONENT DESIGN BASES INSPECTION (CDBI)
Enclosure
3
II.
Information Requested (for the approximate 30 selected components) to be
Available Either during the 1st On-site Inspection Week (August 14, 2006) or by
August 22, 2006. NOTE: Most of this information should be provided as
components are selected during the first on-site preparation week
(August 14, 2006)
1.
List of condition reports (corrective action documents) associated with each of the
selected components for the last 5 years.
2.
The corrective maintenance history associated with each of the selected
components for the last 2 years.
3.
Copies of calculations associated with each of the selected components, excluding
data files. Please review the calculations and also provide copies of referenced
material (such as drawings, engineering requests, vendor letters).
4.
Copies of operability evaluations associated with each of the selected components
and plans for restoring operability, if applicable.
5.
Copies of selected operator work-around evaluations associated with each of the
selected components and plans for resolution, if applicable.
6.
Copies of any open temporary modifications associated with each of the selected
components, if applicable.
7.
Trend data on the selected electrical/mechanical components performance for last
three years (For example, pumps performance including in-service testing, other
vibration monitoring, oil sample results, etc., as applicable).
III.
Additional Information to be Provided on August 28, 2006 On-site (for final 15 - 18
selected components)
Requests for additional information based upon the results of preparation during the week
of August 21, 2006 will also be provided during that same week. The lead inspector will
normally provide these list(s).
IV.
Information Requested to be provided throughout the inspection
24.
Copies of any corrective action documents generated as a result of the teams
questions or queries during this inspection.
25.
Copies of the list of questions submitted by the team members and the
status/resolution of the information requested (provide daily during the inspection to
each team member).
INFORMATION REQUEST FOR
COMPONENT DESIGN BASES INSPECTION (CDBI)
Enclosure
4
26.
Reference materials (make available during all on-site weeks). NOTE: At least
one volume should be in paper format (i.e., not electronic):
a.
Technical Specifications
i.
Technical Specifications;
ii.
Technical Specification Bases;
iii.
Technical Requirements Manual; and
iv.
CTS (Old Technical Specifications if ITS has been implemented).
b.
Updated Final Safety Analysis Report
c.
Quality Assurance Plan
4.
Copies of these documents do not need to be solely available to the team as long
as the inspectors have easy and unrestrained access to them.
a.
Original FSAR Volumes;
b.
Original SER and Supplements (for Original FSAR);
c.
FSAR Question and Answers;
d.
Vendor Manuals;
e.
General set of plant drawings;
f.
Procurement documents for components selected (verify retrievable);
g.
Plant procedures (normal, abnormal, emergency, surveillance, etc.); and
h.
IPE/PRA report.
If you have questions regarding the information requested, please contact the lead inspector.