6/7/06 - R T Ridenoure Ltr. Omaha Public Power Dist, Re Fort Calhoun Station, Unit No. 1 - Pending 10 CFR 72.7 Exemption Request for Loading Spent Fuel in Dry-Shielded Canisters, Dockets 72-54, 50-285
ML061560394
Person / Time
Site: Fort Calhoun  Omaha Public Power District icon.png
Issue date: 06/07/2006
From: Strosnider J
Office of Nuclear Material Safety and Safeguards
To: Ridenoure R
Omaha Public Power District
Sebrosky J, NRC/NMSS 301-415-1132
References
Download: ML061560394 (4)


Text

June 7, 2006 Mr. R. T. Ridenoure Vice President - Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.

Post Office Box 550 Fort Calhoun, NE 68023-0550

SUBJECT:

FORT CALHOUN STATION, UNIT NO. 1 - PENDING 10 CFR 72.7 EXEMPTION REQUEST FOR LOADING SPENT FUEL IN DRY-SHIELDED CANISTERS

Dear Mr. Ridenoure:

I am writing to document our understanding of your plans to seek regulatory approval from the U.S. Nuclear Regulatory Commission (NRC) for a proposed exemption under provisions of 10 CFR 72.7. If approved, an exemption would allow you to load spent nuclear fuel in four dry shielded canisters using a light weight transfer cask design. You first discussed this matter with the NRC on February 27, 2006, when you advised that Omaha Public Power District (OPPD) planned to use the Standardized NUHOMS 32PT dry shielded canisters with a Transnuclear light weight transfer cask at the Fort Calhoun Station (FCS). We understand the important role that this cask loading campaign plays in completing your upcoming outage.

Over the past two months there have been significant interactions between NRC and OPPD staff, management, and contractors related to cask loading because of the need for FCS to examine options to accommodate its 75 ton capacity crane. In a public meeting, on May 24, 2006, your staff discussed a draft exemption request which you intend to submit to support the use of the light weight transfer cask. In telephone discussions with NRC management on June 1 and 2, 2006, you indicated that you intend to submit the exemption request on or about June 9, 2006. You indicated that the scope of your exemption request will be limited to loading four dry shielded canisters with a heat load of approximately 10-12 kilowatts per canister. In our June 2 discussion and during previous conversations with NRC management, we explained the importance of NRCs exemption review process elements and that exemption processing typically takes several months. In response, you committed to submit a complete, high quality exemption request, covering the scope described above. Although we intend to give high priority to this review, a high quality submittal is essential for the NRC to complete its technical review of the proposed exemption. After we complete our acceptance review of your submittal, we will establish a schedule.

R. Ridenoure 2

We trust this letter affirms, for you, our understanding of your plans, and reflects our staffs interactions on this matter. If you have any questions about this matter, please call me at (301) 415-7800, or Mr. Bill Brach, Director, Spent Fuel Project Office, at (301) 415-8500.

Sincerely,

/RA By M. Federline Acting For/

Jack R. Strosnider, Director Office of Nuclear Material Safety and Safeguards Docket Nos: 72-54, 50-285 cc: Service List

R. Ridenoure 2

We trust this letter affirms, for you, our understanding of your plans, and reflects our staffs interactions on this matter. If you have any questions about this matter, please call me at (301) 415-7800, or Mr. Bill Brach, Director, Spent Fuel Project Office, at (301) 415-8500.

Sincerely,

/RA By M. Federline Acting For/

Jack R. Strosnider, Director Office of Nuclear Material Safety and Safeguards Docket Nos: 72-54, 50-285 cc: Service List DISTRIBUTION:

NMSS r/f SBaggett AWang, NRR DMcIntyre, OPA RidsNmssSfpoSlid RidsNmssOd ML061560394 OFC:

SFPO E

Tech Ed SFPO C

SFPO OGC NAME:

JSebrosky EKraus (by fax)

EZiegler RNelson Ejensen (NLO)

DATE:

06/06/06 06/05/06 06/06/06 06/06/06 06/06/06 OFC:

SFPO E

SFPO NMSS NAME:

WRuland EWBrach WRuland for JRStrosnider MFederline for DATE:

06/06/06 06/06/06 06/07/06 C = COVER E = COVER & ENCLOSURE N = NO COPY OFFICIAL RECORD COPY

Ft. Calhoun Station, Unit 1 Service List cc:

Winston & Strawn ATTN: James R. Curtiss, Esq.

1700 K Street, N.W.

Washington, DC 20006-3817 Chairman Washington County Board of Supervisors P.O. Box 466 Blair, NE 68008 Mr. John Hanna, Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 310 Fort Calhoun, NE 68023 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005 Ms. Julia Schmitt, Manager Radiation Control Program Nebraska Health & Human Services R & L Public Health Assurance 301 Centennial Mall, South P.O. Box 95007 Lincoln, NE 68509-5007 Mr. David J. Bannister, Manager Fort Calhoun Station Omaha Public Power District Fort Calhoun Station FC-1-1 Plant P.O. Box 550 Fort Calhoun, NE 68023-0550 Mr. Joe L. McManis Manager - Nuclear Licensing Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550 Fort Calhoun, NE 68023-0550 Mr. Daniel K. McGhee Bureau of Radiological Health Iowa Department of Public Health Lucas State Office Building, 5th Floor 321 East 12th Street Des Moines, IA 50319