ML061520375

From kanterella
Jump to navigation Jump to search
Summary of Meeting with Exelon Generation Company, LLC, Re GL 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design-Basis Accidents at Pressurized-Water Reactors
ML061520375
Person / Time
Site: Byron, Braidwood  Constellation icon.png
Issue date: 06/13/2006
From: Robert Kuntz
Plant Licensing Branch III-2
To:
Exelon Generation Co
Kuntz, Robert , NRR/DLPM, 415-3733
References
GL-04-002
Download: ML061520375 (6)


Text

June 13, 2006 LICENSEE:

Exelon Generation Company, LLC FACILITY:

Braidwood Station, Unit No. 2 and Byron Station, Unit No. 1

SUBJECT:

SUMMARY

OF MAY 16, 2006, MEETING WITH EXELON GENERATION COMPANY, LLC, TO DISCUSS GENERIC LETTER 2004-02, POTENTIAL IMPACT OF DEBRIS BLOCKAGE ON EMERGENCY RECIRCULATION DURING DESIGN-BASIS ACCIDENTS AT PRESSURIZED-WATER REACTORS On May 16, 2006, a Category 1 public meeting was held between the Nuclear Regulatory Commission (NRC) staff and representatives of Exelon Generation Company, LLC (the licensee), at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss the licensees proposal to delay two modifications identified as part of their response to Generic Letter (GL) 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors. A list of attendees is provided as Enclosure 1.

The licensee presented information (Agencywide Documents Access and Management System Accession No. ML061390034) on planned modifications as they pertain to GL 2004-02, as well as a time line that the modifications are scheduled to be completed for Bryon Station, Unit Nos. 1 and 2, and Braidwood Station, Unit Nos. 1 and 2. GL 2004-02, Requested Information section, request 2.(b) states in part that, All actions should be completed by December 31, 2007. In the licensees presentation it was stated that all modifications would be completed as per the guidelines in GL 2004-02 for Braidwood Station, Unit No. 1, and Byron Station, Unit No. 2. However, the licensee stated that due to on-going testing and evaluation that two of the modifications planned could not be completed for Braidwood Station, Unit No. 2, and Byron Station, Unit No. 1 until the spring 2008 planned outages for each unit. Therefore, the licensee is planning to submit a request for an extension to the requirements of GL 2004-02.

The NRC staff queried the licensee about several issues. The NRC staff asked the licensee if it were at all feasible to complete all of the modifications at the four units in accordance with the guidance given in GL 2004-02. The licensee stated that it was possible, but would not be preferable because the modifications would have to be complete without the desired analyses completed. The NRC staff also asked the licensee when they would be submitting their request for extension, and when they need a response from the NRC. The licensee state that they would submit their request within 2 weeks of the meeting, and that they would like the NRC to respond as quickly as possible so they can procure the necessary parts, and begin the required testing.

Members of the public were not in attendance and no public feedback was received.

Please direct any inquiries to Robert Kuntz at 301-415-3733 or rfk@nrc.gov.

/RA/

Robert F. Kuntz, Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. STN 50-457 and STN 50-454

Enclosure:

List of Attendees cc w/encl: See next page Please direct any inquiries to Robert Kuntz at 301-415-3733 or rfk@nrc.gov.

/RA/

Robert F. Kuntz, Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. STN 50-457 and STN 50-454

Enclosure:

List of Attendees cc w/encl: See next page Distribution:

PUBLIC LPL3-2 R/F RidsNrrDorlLpl3-2 RidsNrrPMRKuntz RidsNrrLADClarke RidsOgcRp RidsAcrsAcnwMailCenter R. Jasinski, NRR J.Dixon-Herrity, EDO RIII RidsRgn3MailCenter RidsNrrDss RidsNrrPMMChawla L. Whitney, NRR T. Hafera, NRR J. Hopkins, NRR R. McNally, NRR S. Unikewicz, NRR ADAMS Accession Number: ML061520375 OFFICE LPL3-2/PM LPL3-2/LA LPL3-2/BC NAME RKuntz:mw DClarke DCollins DATE 6/12/06 6/12/06 6/13/06 OFFICIAL RECORD COPY

Byron/Braidwood Stations cc:

Dwain W. Alexander, Project Manager Westinghouse Electric Corporation Energy Systems Business Unit Post Office Box 355 Pittsburgh, PA 15230-0355 Joseph Gallo Gallo & Ross 1025 Connecticut Ave., NW, Suite 1014 Washington, DC 20036 Howard A. Learner Environmental Law and Policy Center of the Midwest 35 East Wacker Dr., Suite 1300 Chicago, IL 60601-2110 U.S. Nuclear Regulatory Commission Byron Resident Inspectors Office 4448 N. German Church Road Byron, IL 61010-9750 Regional Administrator, Region III U.S. Nuclear Regulatory Commission Suite 210 2443 Warrenville Road Lisle, IL 60532-4351 Ms. Lorraine Creek RR 1, Box 182 Manteno, IL 60950 Chairman, Ogle County Board Post Office Box 357 Oregon, IL 61061 Mrs. Phillip B. Johnson 1907 Stratford Lane Rockford, IL 61107 George L. Edgar Morgan, Lewis and Bockius 1800 M Street, NW Washington, DC 20036-5869 Attorney General 500 S. Second Street Springfield, IL 62701 Illinois Emergency Management Agency Division of Disaster Assistance &

Preparedness 110 East Adams Street Springfield, IL 62701-1109 Byron Station Plant Manager Exelon Generation Company, LLC 4450 N. German Church Road Byron, IL 61010-9794 Site Vice President - Byron Exelon Generation Company, LLC 4450 N. German Church Road Byron, IL 61010-9794 U.S. Nuclear Regulatory Commission Braidwood Resident Inspectors Office 35100 S. Rt. 53, Suite 79 Braceville, IL 60407 County Executive Will County Office Building 302 N. Chicago Street Joliet, IL 60432 Braidwood Station Plant Manager Exelon Generation Company, LLC 35100 S. Rt. 53, Suite 84 Braceville, IL 60407-9619 Ms. Bridget Little Rorem Appleseed Coordinator 117 N. Linden Street Essex, IL 60935

Byron/Braidwood Stations Document Control Desk - Licensing Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Site Vice President - Braidwood Exelon Generation Company, LLC 35100 S. Rt. 53, Suite 84 Braceville, IL 60407-9619 Senior Vice President of Operations Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Director - Licensing and Regulatory Affairs Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Regulatory Assurance Manager - Braidwood Exelon Generation Company, LLC 35100 S. Rt. 53, Suite 84 Braceville, IL 60407-9619 Regulatory Assurance Manager - Byron Exelon Generation Company, LLC 4450 N. German Church Road Byron, IL 61010-9794 Assistant General Counsel Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348 Vice President - Licensing and Regulatory Affairs Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Manager Licensing - Braidwood, Byron and LaSalle Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555

Enclosure LIST OF ATTENDEES MEETING WITH EXELON GENERATION COMPANY, LLC TO DISCUSS GENERIC LETTER 2004-02 MAY 16, 2006 NRC Exelon T. Martin B. Rash D. Collins J. Bauer R. Kuntz B. Davenport M. Chawla D. Walker L. Whitney J. Panici T. Hafera D. Brush J. Hopkins*

R. McNally Sargent & Lundy S. Unikewicz I. Garza

  • Attended only part of the meeting.