Public Meeting Summary, to Discuss the Byron Units 1 & 2 End-of-Cycle Plant Performance Assessment
ML061100289
Person / Time
Site: Byron  Constellation icon.png
Issue date: 04/19/2006
From: Richard Skokowski
NRC/RGN-III/DRP/RPB3
To:
References
Download: ML061100289 (5)


Text

April 19, 2006 LICENSEE:

Exelon Generation Company, LLC FACILITY:

Byron Station, Units 1 and 2

SUBJECT:

SUMMARY

OF THE APRIL 10, 2006, PUBLIC MEETING TO DISCUSS THE BYRON UNITS 1 AND 2 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On April 10, 2006, the Nuclear Regulatory Commission (NRC) held a public meeting at the Byron Station Training Center in Byron, IL. The meeting was between NRC Region III management and Exelon Generation Company management to discuss the NRCs assessment of Byron Unit 1 and 2s safety performance for the period from January 1 through December 31, 2005. The meeting notice and NRC presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML060860486 and ML061090493, respectively. A list of principal NRC and licensee meeting participants can be found in the attached Enclosure.

The NRC began the meeting with an overview of the NRCs Reactor Oversight Program (ROP),

national ROP results, and the Action Matrix in general. This was followed by a discussion of the NRCs assessment of Byron Unit 1 and 2s performance in calendar year 2005, which was documented in the March 2, 2006, end-of-cycle assessment letter, as ML060610443. As part of this regulatory performance meeting, Exelon briefly responded to the NRCs assessment. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials and Exelon representatives.

Sincerely,

/RA by Mark A. Wilk for/

Richard A. Skokowski, Chief Projects Branch 3 Division of Reactor Projects Docket Nos. 50-454; 50-455 License Nos. NPF-37; NPF-66

Enclosure:

As Stated See Attached Distribution

DOCUMENT NAME: E:\\Filenet\\ML061100289.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII NAME MWilk:dtp RSkokowski

  • MAW for DATE 04/19/06 04/19/06 OFFICIAL RECORD COPY

Exelon Generation Company, LLC cc w/encl:

Site Vice President - Byron Station Plant Manager - Byron Station Regulatory Assurance Manager - Byron Station Chief Operating Officer Senior Vice President - Nuclear Services Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing Manager Licensing - Braidwood and Byron Senior Counsel, Nuclear Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency State Liaison Officer, State of Illinois State Liaison Officer, State of Wisconsin Chairman, Illinois Commerce Commission B. Quigley, Byron Station

Exelon Generation Company, LLC ADAMS Distribution:

DXC1 JBH1 RidsNrrDirsIrib GEG KGO BLB1 DRPIII DRSIII PLB1 JRK1

Enclosure Meeting Participants NRC R. Skokowski, Chief, Branch 3, Division of Reactor Projects R. Kuntz, Program Manager, NRR B. Bartlett, Senior Resident Inspector, Byron R. Ng, Resident Inspector, Byron Exelon Generation Company D. Hoots, Site Vice President M. Snow, Plant Manager J. Bauer, Corporate Licensing B. Kouba, Nuclear Oversight Manager B. Kartheiser, Public Affairs Other members of licensee staff Local Officials M. Lewis, Fire Chief, Byron Fire Department Media V. Wells, Ogle County Newspapers Public R. and H. Johnson, Byron residents B. Meyer, Professional Reactor Operator Society